Planning Board
Regular MeetingLowell, MA · June 6, 2022
Minutes
City of Lowell - Planning Board
Planning Board Meeting Minutes
Monday, June 6 6:30 p.m.
City Council Chambers, 2nd Floor, City Hall
City of Lowell, 375 Merrimack Street, Lowell, MA
Remote Participation Optional via Zoom
Note: These minutes are not completed verbatim. For a recording of the meeting, visit www.ltc.org
Members Present
Chairman Linnehan
Member Frechette
Member Lockhart
Member Cheng
Members Absent
Member Gallivan
Member Malavich
Others Present
Peter Cutrumbes, Assistant Planner
A quorum of the Board was present. Chairman Linnehan called the meeting to order at 6:34 P.M.
I. Minutes for Approval
May 16, 2022 Minutes
G. Frechette motioned to accept the minutes, and C. Cheng seconded. The vote was unanimous, (4-0).
The minutes were approved.
II. Other Business
Tree Planting Plan – Greening the Gateway Cities
The City of Lowell has applied to the Commonwealth’s Greening the Gateway Cities program for FY2023.
The Lowell Planning Board is required to approve the proposed tree planting plan in this application.
On Behalf:
Jess Wilson, Design Planner for the City of Lowell
J. Wilson presented the project. This project is an application for funds to plant trees in the Highlands
and Acre neighborhoods, particularly in several parks and LHA properties. It is a $20,000 grant. The
application requires the submittal of a tree planting plan. The City would like to focus on planting trees
on Broadway Street, Chelmsford Street, and Westford Street. There are also planned tree plantings for
Koumantzelis Park, Armory Park, Durkin Park, and Clemente Park. There is a plan to plant trees at three
LHA properties: Harold Hartwell, Francis Gatehouse, and City View Towers. The program also allows the
City to fund trees on private developments. 13 projects approved by land use boards have decided to
accept these trees. J. Wilson says the plan was kept generic in order to keep the potential sites where
trees can be planted as expansive as possible.
Discussion:
G. Frechette discussed how important he believes this program is. In particular, he stated that softening
the urban landscape is very important for establishing a sense of place. There were no further
comments from Planning Board members.
Motion:
T. Linnehan motioned to approve the tree planting plan, and R. Lockhart seconded. The vote was
unanimous (4-0). The tree planting plan was approved.
III. New Business
Public Shade Tree Hearing – 171.1 South Street (South Common) 01852
In accordance with MGL Ch. 87.5 and Chapter 260 of the Lowell Code of Ordinances, the Lowell Planning
Board will hold a public hearing to hear all interested persons regarding the proposed removal of five (5)
public shade trees at 171.1 South Street (South Common). The proposed tree removal is necessary in
order to complete planned improvements to the park. A total of twenty five (25) trees are proposed for
replacement.
On Behalf:
Jess Wilson, Design Planner for the City of Lowell.
J. Wilson summarized the proposed tree removal, which is part of a $600,000 redesign of South
Common. This redesign focuses on irrigating the fields, adding landscaping, and improving handicap
accessibility from the parking lot. The trees need to be removed in order to put in the new ADA
accessible walkway. 25 trees in other parts of the park will be planted, with 10 being planted during this
phase. 10 trees with calipers of 2.5-3.5 inches will be replaced.
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
C. Cheng asked if the 10 trees will be planted in the same area they are removed. J. Wilson said they will
not, as they will be planted around the track area to provide shade.
Motion:
G. Frechette motioned to approve the tree removal, and R. Lockhart seconded. The vote was unanimous
(4-0). The tree removal was approved.
Site Plan Review – 100 Phoenix Ave 01852
Advanced Cultivators LLC has applied to the Lowell Planning Board for Site Plan Review approval to
construct a marijuana cultivation facility on site. This property is located in the Light Industrial (LI) zoning
district. The proposal requires Site Plan Review approval pursuant to Section 7.10 and Section 11.4 from
the Lowell Planning Board.
On Behalf:
Attorney William Martin, Applicant’s Representative
W. Martin spoke on behalf of the applicant, Advanced Cultivators LLC. The principals, Rich Borges and
Steve Ramirez, were also in attendance. Additionally, the engineer, Brian Geaudreau, and the property
owner, Frank Fedeira, were present. W. Martin said that the proposed cultivation center is 12,000
square feet. The applicant believes it will be low-impact to the area, and proposes roughly 10 employees
at the outset.
The project has received all necessary approvals from LPD, LFD, and Solid Waste and Recycling.
W. Martin said that the current parking spaces are half a foot short on width and go up to the property
line, violating the zoning ordinance. However, the parking area has existed as is for approximately 20
years, and thus the applicant does not believe they need to change.
Finally, W. Martin said that the applicant believes there will be 3-6 deliveries a week.
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
T. Linnehan asked about recycling being included as a condition, and W. Martin said they accept that
condition.
G. Frechette asked about odor mitigation, as this has been an issue at other sites. He expressed that he
feels the site is not as large of an issue due to its industrial location, but that he is concerned with the
issue regardless. W. Martin said they are fairly confident in the odor mitigation system. R. Borges then
spoke on the odor mitigation system. R. Borges said there will be negative pressure in the cultivation
rooms to keep odor locked inside. Any air that makes it into the attic or venting system will be run
through an electrostatic filter before it goes outside. The mechanical engineer for the project felt
confident in the system, with roughly 98% of odor being mitigated. R. Borges said they are open to extra
measures regardless. T. Linnehan said they always try to put an odor plan in place so that way the City
has jurisdiction to enforce odor issues, rather than just the Commonwealth.
G. Frechette said he thinks the parking plan may be okay as presented and would defer to fellow Board
members on allowing it. Board members suggested no issues.
R. Lockhart asked why the design memo says that “within cultivation spaces” no odor control is needed
because of how the air moves. He is seeking clarification. R. Borges said the cultivation rooms
themselves are a closed loop, and that no air moves through them due to the negative pressure system.
The ductwork in those rooms have air filtration because that is the only way any air may escape the
room.
R. Lockhart asked if impervious areas will be increasing, and W. Martin said the total amount will stay
the same.
C. Cheng said that fellow members have addressed his concerns, and that he would also like to see a
little more documentation on odor mitigation.
T. Linnehan confirmed with W. Martin that they need a Stormwater Permit.
T. Linnehan did not have a problem with the way the parking is laid out.
Motion:
G. Frechette motioned to accept the Site Plan review with the following conditions, and R. Lockhart
seconded.
● Applicant will submit a detailed odor mitigation plan satisfactory to DPD
● Applicant shall agree to work with the City to mitigate any future odor issues
● Applicant will have an onsite recycling program
● Applicant will need a Stormwater Permit and final approval from the City Engineer dept.
The vote was unanimous (4-0). The Site Plan was accepted.
G. Frechette motioned to issue a Special Permit for the use with the following conditions, and R.
Lockhart seconded.
● Applicant will submit a detailed odor mitigation plan satisfactory to DPD
● Applicant shall agree to work with the City to mitigate any future odor issues that may be
required
● Applicant will have an onsite recycling program
● Applicant will need Stormwater Permit and final approval from City Engineer dept.
The vote was unanimous (4-0). The Special Permit was granted.
Special Permit – 251 Clark Road 01852
Leo Garneau has applied to the Lowell Planning Board for Special Permit approval to construct a new
single-family home on the property at 251 Clark Road. The subject property is located in the Suburban
Single Family (SSF) zoning district. The project requires Special Permit approval from the Lowell Planning
Board pursuant to Section 5.1.1(7) to reduce the minimum frontage required by 15 feet.
On Behalf:
Attorney John Geary, Applicant’s Representative
J. Geary summarized the Special Permit request to reduce minimum frontage by 15 feet. J. Geary said
they have submitted a site plan, a landscaping plan, and a rendering of the property. He argued that this
application supports the City’s goal of increasing housing. J. Geary also argued that there are no adverse
impacts of the proposal for the neighborhood. He also believes that the house fits into the character of
the neighborhood. J. Geary said the soils were tested last week and proved suitable for a subsurface
retention system onsite. He also expressed that they will comply with all Engineering comments
regarding this project.
Speaking in Favor:
None
Speaking in Opposition:
Mitchell Guziekja, 255 Clark Road
M. Guziekja did not feel that squeezing a house on this property fits the character of the neighborhood
and that it will devalue his home.
Kevin Ahern, 40 O’Heir Way
K. Ahern asked if this project needs Zoning Board relief as well. T. Linnehan said no. K. Ahern said the
construction materials on a nearby site have caused issues with his neighbor’s retaining wall. He is
concerned that construction on this site could cause problems as well.
He expressed concerns about the retaining system, as his newly finished basement flooded a few years
ago. J. Geary addressed the retaining system questions from K. Ahern by saying the soils were tested
and that the system is designed specifically for the site. The engineer is working closely with the
Stormwater Team on this retention plan.
Karen Gray, 52 Ohare Way
K. Gray expressed concerned about water runoff from the property, as water from the site currently
runs off onto her driveway. Her driveway has cracked due to this. K. Gray asked the Board if there was
any other relief required. J. Geary said there is no other relief needed.
Discussion:
G. Frechette said that in the early 2000s the required frontage in the Suburban Single Family zone was
only 75 feet. After this, it was raised to 90 feet. This ability to lower frontage via special permit is to give
the Planning Board flexibility in determining how the house would sit on the lot. He summarized how
the house is compliant with the required dimensions under Section 5.1. G. Frechette said he would have
liked to see a layout of the surrounding lots in order to compare the sizing better.
J. Geary added that the homes in the vicinity of this property have 100 feet of frontage, but that closer
to the Tewksbury line they are closer to 75 feet. He also said the O’Heir Way subdivision next door all
have 75 feet of frontage, and so he feels they are consistent.
G. Frechette said that, visually, the project fits in with the neighborhood and that the retention system
will be a large improvement. R. Lockhart said a home fits very comfortably on this lot.
C. Cheng said he thinks the application meets the spirit of the special permit.
T. Linnehan inquired about the engineering department’s requests, which include contacting the
department before drainage, paving, water, and sewage work. J. Geary said he is happy to be in contact
with them and meet their requests. He said that the engineering department will have oversight of the
runoff as well, as there is a stormwater permit required here.
J. Geary says he believes it will increase the value of the surrounding homes.
Motion:
R. Lockhart motioned to issue the Special Permit with the following conditions, and C. Cheng seconded.
● The project must receive a Stormwater Permit
● The retention system will ensure all run off from the lot will be retained on site
● The applicant will be held to the design, size, scale, and landscaping plan as presented at the
hearing, with final approval by DPD.
The vote was unanimous (4-0). The Special Permit was granted.
IV. Continued Business
Site Plan Review and Special Permit: Saint Louis School 72-74 Boisvert Street and 253 W Sixth Street
01850
ZR Development Group LLC has applied to the Planning Board and Zoning Board of Appeals to redevelop
the existing St. Louis School building into nineteen (19) residences with twenty four (24) off-street
parking spaces. The application requires Site Plan Review under Section 11.4 to construct more than
three dwelling units and Special Permit approval for the conversion of an existing historic school under
Section 8.1. The application also requires Variance approval under Section 6.1 for relief from the off-
street parking requirement, Section 5.1 for relief from the land area per dwelling unit requirement and
usable open space requirement, and under Section 8.1.3(4) for relief from the minimum square footage
requirement and for any other relief required under the Lowell Zoning Ordinance.
On Behalf:
Attorney John Geary, Applicant’s Representative
J. Geary spoke on behalf of the project. He represented his client, ZR development. Jim Zorbas (Principal
of ZR Development), Mark Ohara (Engineer), and Gary Thomas/Kerry Owens (Design Team) were also in
attendance. J. Geary mentioned that this is a continued hearing for a Special Permit and a Site Plan
Approval.
J. Geary said that the Board had requested clarification of a few issues that came up at the last hearing.
He then summarized the changes they have made. J. Geary said that they had revised the site plan to
include angled parking spaces, in order to make traffic flow operate as designed (into the site via W 6th
and out via Boisvert St). The applicant also has agreed to screen the dumpster, per the Board’s request.
Additionally, the bike racks on the plan have been moved to the interior of the site to keep bikes safer.
The applicant has also added a strip of grass on the north side of the property into the plans. There will
now also be a transportation board in the interior of the building to provide train and bus schedules.
Most importantly, J. Geary said they had Jeffrey Dirk of Vannasse and Associates conduct an on street
parking study.
J. Geary then went on to summarize the study. He said that Vannasse broke the study into 3 zones near
the property. Zone 1 consists of the area from West 6th St. to Ennel St. and Boisvert St. The study found
14 on street spaces. Zone 2 runs from Beaulieu Street to West 6th St. to Victor St. The study found 28 on
street spaces. Zone 3 consists of the area from Boisvert St to West 6th St. to Victor St. The study found
33 on street spaces. This made a total of 75 on street spaces. The study found that the peak parked hour
was at 1:30 PM, during which on street parking was at 65% capacity. This meant that there were still 26
spaces left. The study found that 9 AM had the fewest cars parked on the street, with 51 on-street
spaces available. Ultimately, the study found that there is plenty of parking for residents and guests. J.
Geary said that the parking study did not include the parking spaces in front of the church property on
West 6th St.
Mark O’Hara then spoke. He said there is 4500 square feet of landscaping on the site, compared to the
all concrete site right now. This will decrease the amount of impervious surfaces, and in turn improve
the drainage system. M. O’Hara has been working with Gorden and City Engineer Ting Chang. The initial
sidewalk proposal was asphalt but the Engineer has requested concrete, to which the applicant was
amenable.
Gary Thomas, part of the Design Team from Northpoint Construction MGMT, then spoke. He said that,
architecturally, they tried to keep the building in its existing state. They have added 6 bike racks on the
plan. G. Thomas said there has been no significant changes compared to the last meeting.
Speaking in Favor:
None
Speaking in Opposition:
Maureen Kelleher, 37 Unsworth Street
M. Kelleher expressed that the project needs to be stepped back in size. She felt that 12 units would be
appropriate, as the parking lot has room for 24 cars and this would allow 2 cars per unit. M. Kelleher
said that renters don’t care as much about the neighborhood. She also said that the units are
undersized.
Additionally, she said the study is inaccurate, as it does not take into account people who leave in the
morning or who don’t get home until 7 oclock. She worried that cars will be parked all the way up to
intersections and make visibility bad.
Sandy McNamara, 78 Boisvert Street
She disagreed with the parking study. She has calculated spots herself. Her complaints included that the
study has spaces in front of fire department that aren’t allowed to be parked in, and that it also includes
things like bus stops. S. McNamara said she only calculated 8 spaces in Zone 1, not 14. She expressed
her opinion that the City should do a peer review of the parking study. She said she believes the City
needs housing but that the developers need to be fair to neighbors.
Karen Vashras, 63 Beaulieu Street
Ms. Vashras echoed similar concerns. She said there is a bus stop that was added in January that the
parking study lists as a spot. This limits the parking spaces shown on the plan. 7 AM - 7 PM is not a good
range for parking because people also park to drop kids at Greenhalge School.
Regina Faticanti, 169 Bunker Hill Ave
R. Faticanti said there should be a plan for snow emergencies due to parking. She also expressed
concern that people may not actually follow the traffic patterns laid out on the site from the lot. She
asked for confirmation that the trees are planted close enough together so that cars cannot exit the lot
onto the Bunker Hill Avenue side.
Rodney Elliott, 15 Cresta Drive
R. Elliott said he is not a resident of the neighborhood but was concerned about parking after speaking
to residents. He said this was a common complaint that he saw on the Council. R. Elliott agreed with R.
Faticanti’s concerns about where the cars go during snow ban.
During this time, T. Linnehan clarified for all speakers that the parking relief will be from the Zoning
Board of Appeals, not from the Planning Board. T. Linnehan explained that what will be decided by the
Planning Board is a Site Plan Review and if the conversion of a historic school to a new use can take
place. T. Linnehan then asked J. Geary when the application is before the ZBA. J. Geary said June 13.
Attorney Ellen Wright, 92 Boisvert Street
E. Wright said she is disgusted by the parking report. Her son was hit by a car in this neighborhood while
biking and she believes increased on-street parking will make visibility for drivers even worse. She
echoed concerns about parking during snow emergencies.
Larry Hurdy, 88 Boisvert Street
L. Hurdy expressed concern that this project will make it to the ZBA. He also said that he thinks the
parking plan is not correct, and that it’s intentionally vague. He argued that potentially every household
at the site could have 4 vehicles. L. Hurdy echoed E. Wright’s comments that on street parking will
create safety issues for children biking and playing. Lastly, he said there may be new issues such as
sewer line upgrades if more people are using city services.
Discussion:
S. McNamara asked if a peer review for parking can be done by the Planning Board. T. Linnehan said he
thinks that it should be done by the ZBA, as it has jurisdiction over the parking relief.
M. Kelleher asked if the Planning Board is approving the number of units. T. Linnehan explained that any
proposal with more than 3 units has to come before the Board. T. Linnehan also said they have to
approve the conversion of an historic school’s use. All other requested relief (parking, land area per
dwelling unit, usable open space, and minimum square footage) would be coming from the Zoning
Board of Appeals.
J. Geary clarified to the residents in attendance that they are not asking for relief for 24 parking spaces,
only 14. He also defended Jeffrey Dirk’s parking study. J. Geary said F. Cigliano does not think that the
open space in the rear of the property should be taken away for parking. J. Geary also said that the size
of the units fit the market.
G. Frechette said that he appreciated community input on this project and S. McNamara’s on the ground
attempt to calculate parking spots. G. Frechette said he drove to the site and saw parking spaces. He
also said Jeffrey Dirk has done good parking study work in the past. G. Frechette did agree that the side
streets are congested parking wise. He argued that the smaller unit size indicates that less vehicles will
be there, as it attracts non-families or younger families.
G. Frechette also said the angled parking spaces will control the flow of traffic thru the site and will
ensure cars enter and exit where they are supposed to.
G. Frechette believes the landscaping plan will benefit the site, but also the neighborhood, by softening
the look. G. Frechette said they can condition that the snow has to be removed from the site. He also
said maybe there could be slightly fewer units, especially because the studios are so small.
C. Cheng asked if they could continue until after the ZBA makes their decision. He felt it is better to wait
to hear from them. T. Linnehan and R. Lockhart expressed agreement with this. T. Linnehan also felt
there should be less units.
Motion:
G. Frechette motioned to continue to the July 18 meeting, and R. Lockhart seconded. The vote was
unanimous (4-0). The project was continued to the July 18 meeting.
V. Notices
R. Lockhart reported on the May Historic Board meeting regarding 330 Jackson Street. He said there will
be a new parking garage adjacent to the Judicial Center, with 540 spaces. He also said that there will be
some minimum maintenance issues coming up to ensure properties downtown look good. Lastly, he also
mentioned that the historic sign program is still ongoing.
G. Frechette provided an update from NMCOG. The organization has a new Executive Director, Jennifer
Raitt, coming onboard. G. Frechette also discussed the NMCOG traffic volume report and how the
organization had to alter their study methodology during COVID. He said traffic seems to be dispersing
more throughout the day now, as opposed to peak hours, due to hybrid or work from home jobs. He said
this relates to the Pawtucketville Market Basket traffic study, as the engineers will now stay out for the
whole day as opposed to peak hours.
VI. Further Comments from Planning Board Members
VII. Adjournment
C. Cheng motioned to adjourn, and R. Lockhart seconded. The vote was unanimous (4-0). The meeting
adjourned at 9 PM.
Agenda
City of Lowell - Planning Board
Planning Board Agenda
Monday, June 6, 2022 at 6:30 p.m.
This meeting will occur in-person with the option to join remotely. You can choose to
attend in-person in the Mayor’s Reception Room, 375 Merrimack Street, Lowell, MA 01852;
or you can choose to attend remotely by using one of the following four options to access
the meeting:
1. Join via your computer, tablet, or smartphone: https://lowellma.zoom.us/j/9410770919
2. Call 646-558-8656 and enter the MEETING ID: 941 077 0919
3. Watch LTC Channel 99
4. Watch online at: www.ltc.org/watch/channel-99
Review all application documents online at: www.lowellma.gov/1098/Planning-Board
I. Minutes for Approval
5/16/2022 Meeting Minutes
II. Other Business
Tree Planting Plan – Greening the Gateway Cities
The City of Lowell has applied to the Commonwealth’s Greening the Gateway Cities program for FY2023. The Lowell
Planning Board is required to approve the proposed tree planting plan in this application.
III. New Business
Public Shade Tree Hearing – 171.1 South Street (South Common) 01852
In accordance with MGL Ch. 87.5 and Chapter 260 of the Lowell Code of Ordinances, the Lowell Planning Board will
hold a public hearing to hear all interested persons regarding the proposed removal of five (5) public shade trees at
171.1 South Street (South Common). The proposed tree removal is necessary in order to complete planned
improvements to the park. A total of twenty five (25) trees are proposed for replacement.
Site Plan Review – 100 Phoenix Ave 01852
Advanced Cultivators LLC has applied to the Lowell Planning Board for Site Plan Review approval to construct a
marijuana cultivation facility on site. This property is located in the Light Industrial (LI) zoning district. The proposal
requires Site Plan Review approval pursuant to Section 7.10 and Section 11.4 from the Lowell Planning Board.
Special Permit – 251 Clark Road 01852
Leo Garneau has applied to the Lowell Planning Board for Special Permit approval to construct a new single-family
home on the property at 251 Clark Road. The subject property is located in the Suburban Single Family (SSF) zoning
district. The project requires Special Permit approval from the Lowell Planning Board pursuant to Section 5.1.1(7) to
reduce the minimum frontage required by 15 feet.
III. Continued Business
Site Plan Review and Special Permit: Saint Louis School 72-74 Boisvert Street and 253 W Sixth Street
01850
ZR Development Group LLC has applied to the Planning Board and Zoning Board of Appeals to redevelop the existing
St. Louis School building into nineteen (19) residences with twenty four (24) off-street parking spaces. The
application requires Site Plan Review under Section 11.4 to construct more than three dwelling units and Special
Permit approval for the conversion of an existing historic school under Section 8.1. The application also requires
Variance approval under Section 6.1 for relief from the off-street parking requirement, Section 5.1 for relief from the
land area per dwelling unit requirement and usable open space requirement, and under Section 8.1.3(4) for relief
from the minimum square footage requirement and for any other relief required under the Lowell Zoning
Ordinance.
IV. Notices
V. Further Comments from Planning Board Members
VI. Adjournment