School Building Committee
Regular MeetingLowell, MA · April 6, 2017
Minutes
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Kevin J. Murphy
City Manager
Michael McGovern
Assistant City Manager
School Building Committee MSBA Meeting
Meeting Minutes
Date: April 6, 2017
Time: 10:00AM
Location: Mayor’s Conference Room
1. - Attendance
Attendees: Kevin Murphy, Conor Baldwin, Maryann Ballotta, David Beati, Rodney Elliott, Steve
Gendron, Robert Healy, Edward Kennedy, Salah Khelfaoui, Brian Martin, Jay Mason, William
Samaras, Richard Underwood and Mike Vaughn.
Roll call 14 SBC members present.
Also in attendance: Mike McGovern and Rodney Conley.
From Skanska: Jim Dowd, Mary Ann Williams and Dale Caldwell.
From Perkins Eastman: Robert Bell, Joe Drown, and Alicia Caritano.
2. / 3. - Building Option Plan Refinement /
Progress on Classroom Availability Discussion with ELT (inform phasing)
R. Bell began discussing the organizational concept for the educational plan. The diagram
highlights rooms for community use in yellow and administration in red. The design would
include having an administrative heart with a location towards the front of the school. The
diagrams illustrate course groupings such as arts, humanities, science and math.
He began discussing the Cawley site first as it is a new construction that may be easier to
visually see the groupings. R. Bell noted the common zone (gym/cafeteria/library) as well as the
distinct academic wing for general, science, and special education class rooms. The presentation
continued to illustrate what the floor plan may look like at this stage of the feasibility study.
Freshman classrooms are grouped on the first floor by the cafeteria, gym and pool. The media
center is located on the second floor of the plans, along with the upper level of the field house.
Art classes are proposed to be located on the fourth floor, with north facing windows. All floor
and classroom plans are diagrams based on studies, components may change. E. Kennedy asked
about the MSBA memorandum, approximately 18 pages that noted the Cawley site did not have
enough labs or classrooms. K. Murphy noted that the MSBA sent comments to the City on April
5th, and that the Manager’s Office will distribute the document in the afternoon to the School
Building Committee and the public. R. Bell noted that the design firm ran into a similar situation
at the Boston Arts Academy. The comments for the PDP submission is a systematic check list
used by the MSBA that some items requested may not fit into the criteria. The science class
rooms commented on included the freshman “wet” class rooms that are a different size than the
sophomore – senior science labs. These freshman class rooms just need more of an explanation
to reasoning for classroom size variance. R. Bell noted that the PSR report will be more in depth
on which spaces are planned to be larger than the MSBA normally approves; such as the
auditorium and pool. E. Kennedy asked the design team to explain why the lab numbers are
undersized. R. Bell noted that the MSBA standard class room is an average of 23 students;
having 24 student average class size would add eight class rooms to the total design. E. Kennedy
inquired to the groundwater study. M. Williams noted that the team will further investigate and
address the issue in the next submission. J. Dowd noted that the Civil Engineer will investigate
the storm water management. E. Kennedy asked if the team implied that there were more or
better reasons for eliminating the Wang site. He continued that it was believed the traffic would
not be sufficient in the area, which could be the same case for Cawley. E. Kennedy also brought
up the comment from the MSBA regarding a point scoring system for the site selection. M.
Williams noted that the Wang site could not fit the projected size and parking that the Cawley
site could. She continued that this is just a point of clarification that the MSBA is requesting. D.
Beati asked how the MSBA makes determination when the OPM and the City do not know
where the water level is. W. Samaras asked for clarification for the classroom size, specifically
how large the Lord building classrooms currently are. R. Bell noted that the current classrooms
are 850 sq. ft., while the draft plans at Cawley have classrooms that are 900 sq. ft. W. Samaras
also inquired to a comment on making the Cawley site five to six stories. He noted that acquiring
land is the City’s responsibility, and that a confined campus may not be ideal. R. Bell stated that
the suggestion came up at various meetings and public review. He continued that it was a area of
research that will be pursued to ensure that every stone is turned over, even if only for academic
purposes. W. Samaras commented that the draft plan seems more urban than suburban with the
number of floors.
R. Bell continued with the review of the Full Renovation option. This includes the Freshman
Academy but excludes the Steam plant. He noted it may be more difficult to visually see the
clustering of course subjects, but ensured the committee that it is possible to achieve the desired
results. He commented on the central location of the cafeteria as well as the auditorium. R. Bell
also noted the location of the general administrative area as well as the art and music area. The
1922 building would contain the math and sciences as well as humanities. The administration
would also have locations on both sides of the bridge to disburse teachers and adult presence
throughout the building. The upper level would contain robotics and engineering. The Lord
building would be renovated to have a new main entry with the cafeteria at the center of the
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Kevin J. Murphy
City Manager
Michael McGovern
Assistant City Manager
building. The main administration and culinary class rooms would be located nearby. R. Bell
also commented on the reconfiguration of the field house. R. Bell stated that the full renovation
meets the same program as the new construction at the Cawley site. M. Vaughn asked if the
estimate budget included an allowance to create space includes reconfiguring the walls in the
existing buildings; in which R. Bell replied yes. R. Bell commented on the multipurpose room
adjacent to the field house on the first level. He also mentioned the third floor having a TV
studio center as well as the science labs.
R. Bell then continued to the Add / Renovation Option 2, which has a similar layout to the Full
Renovation. The dining area is split into two floors, with the Freshman having a separate floor
from upper classmen. There is an alternative possibility for the culinary program to move up a
floor and have the cafeteria entirely on one floor. The core science labs and math classrooms are
adjacent to each other. This option has a relocated library on the third floor. There would be
satellite media centers broken into zones such as reading and research.
R. Bell went on to discuss the Add/ Renovation Option 3, which also has a similar layout
including the same media center and library as the 1922 building in the Full Renovation. The
field house would be located on the adjacent property, allowing for the design of more green
space. The media center would be slit onto two levels with the option to swap one floor with the
cafeteria. The plans reevaluate the main stairwell to connect more spaces, bringing everything
together. D. Beati inquired about the exhibit plans, particular the brown areas in option three. R.
Bell commented that the parking and paving cross hatch areas in the downtown images are
diagrammatic; it is still too early to commit to any designs. D. Beati also asked about net zero
storm water policy if it would be under parking areas or any storage space. J. Drowd commented
that there are designs for wells, either vertical or horizontal, for storage tanks that can pump
water into the ground that will be absorbed overtime. J. Mason asked if two level space for the
media center would be connected in option three. R. Bell replied that the floor plans are a
concept design; everything can and may change as part of a larger puzzle. W. Samaras asked if
the team thought about taking down the Lord building with the expanded site as the logistics
seem to throw in more modules and time. R. Bell noted that while the options mature, it can be
determined if large portions of the building can be torn down. E. Kennedy referred to the MSBA
Comments, on page 14, the report states that the regarding past projects $28.5 million was used
in 1998; which may need to be paid back on a prorated basis if an alternative site is selected. N.
Williams stated that the standard for the MSBA is to go back 20 years; the team would look into
this. It is possible that if the Cawley site is selected, by the time work begins it may have
exceeded the 20 year period. E. Kennedy noted that the impact of the Full Renovation and
Cawley seem to be the focus of the study rather than options two and three. M. Williams noted
that the reason the addition/renovation options were not discussed as much is that the MSBA had
fewer questions on both options. D. Beati asked at this point, is the price estimate the same
regarding non-reimbursable items. M. Williams noted that the pool is one of the expected costs
that will not be reimbursed by the MSBA. K. Murphy noted that the infrastructure at the Cawley
site will be more than any infrastructure at the downtown site. D. Beati asked what was included.
M. Williams stated that anything that exceeds 8% of the building costs would be included; there
are not individual items at this time. M. McGovern noted that the cost estimates sent out in
December and January included around $15 million in infrastructure costs for utilities (water,
sewer, gas, and electricity). K. Murphy added that sidewalks would also be an additional cost. E.
Kennedy stated that the pool in the down town option as well was not included in the estimate.
He commented on the page 4 of the MSBA comments regarding a newly constructed pool. R.
Bell stated that the MSBA strongly worded this comment, and that when he spoke to them, they
agreed it would be non-reimbursable but would consider the pool. S. Gendron noted that Option
2 needed no modular, but may require an offsite athletics area. Option 3 does not require any
additional space for either modular class rooms or for physical education. S. Gendron asked if
there should be any safety concerns during construction in Option 3, or if the team would address
any issues that would arise. J. Drowd noted that the majority of work that the design team had
completed is addition/renovation projects; they have experience separating contractors from
school activities. R. Bell noted that the team would isolate portions at a time for construction to
limit impact. He also noted that B. Martin has worked with them to determine open spaces that
may help create vacancy and a buffer space. R. Bell stated that the goal is to portion off vertical
sections of the building and create 1 – 3 classroom buffer that may include temporary walls. J.
Drowd commented on the use of HEPA filters. J. Drowd stated that the fieldhouse is almost a
separate project that would have construction duration of approximately 18 months. D. Beati
inquired about the infrastructure upgrades required for the new school, particularly for the
sidewalks around the site. K. Murphy stated that the bussing plan and traffic study will dictate
the sidewalks needed in accordance with accessibility requirements.
4. - Schedule Update
A. Caritano discussed the civil soil as well as storm and drain water investigation at the
existing high school. The Cawley site is in phase 1 of the investigation and is expected to be
completed at the end of April. Phase two is currently underway and the drilling is completed.
The geotechnical borings are also complete. The hazmat sampling results are being analyzed at
the lab. The structure work is being analyzed at the 1922 Building and the Freshman Academy.
The survey and flagging at the Cawley site is ongoing. The traffic study and student safety
walking to school is also ongoing.
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Kevin J. Murphy
City Manager
Michael McGovern
Assistant City Manager
D. Beati asked about the second phase of testing at the existing site, would the asbestos impact
the downtown cost for abatement. A. Caritano noted that the testing was done in PDP and the
estimate costs were included. D. Beati inquired to the $3.5 - $9 million cost of abatement. M.
McGovern noted that the cost is estimated to be $3.6 million. D. Beati also asked if the reports
substantiate the removal of hazmat matter. J. Drowd stated that contaminated material would be
removed during excavation. D. Beati asked if the SBC would be provided information prior to
the vote in May.
5. - Approval of Expenditures for Additional Investigations
K. Murphy noted that the CFO and Deputy CFO reviewed the amendment for additional
expenditures proposed by Perkins Eastman and Skanska for a traffic study. C. Baldwin noted that
the Finance team recommended the SBC approve the amendment as it is within the appropriated
budget. R. Healy motioned to approve, seconded by M. Vaughn. Roll call 13 yea, 6 absent; so
voted.
6. - Community Outreach
K. Murphy stated that the City arranged community outreach programs in Khmer and Spanish at
the CMAA and the Senior Center during March. M. Williams stated that there was significant
turnout and was well attended by the community members who asked questions and expressed
their concerns. The majority of questions were regarding the process, expense in construction as
well as student safety during construction. K. Murphy stated that additional community meetings
will be scheduled to keep the public informed once the City receives more information. J. Mason
asked if there would be an economic meeting. K. Murphy stated that there was a meeting on
April 5, 2017 that discussed the preliminary report. A more detailed report will be expected
within approximately a month. K. Murphy also commented on the City Council motions, which
will all be responded to prior to any final decision.
D. Beati inquired about the exhibits still showing parking downtown and asked if it may be
revised for the next plans that are produced. B. Martin asked if May 9, 2017 is still the targeted
date for a decision. M. Williams noted that the weather may affect the geotechnical and the
traffic study. K. Murphy stated that the Administration wants everyone to be comfortable with
the information prior to a decision; the information would not be distributed the day before. He
noted that if there is a need, the date will be modified.
7. - Website Development Update
R. Conley commented on the website development, which is estimated to roll out on April 20,
2017. The website will contain meeting minutes, agendas and related documents including the
MSBA PDP review comments. R. Underwood asked if it may be a good idea to revisit Option 5,
similar to Option 3, but the site would include taking the adjacent land. K. Murphy commented
that the SBC reviewed the options, and that option did not receive support. He stated that the
team will look into adding one more option with the MSBA, and potentially bringing the option
back for a vote.
8. - Next Steps
R. Healy motioned to adjourn, seconded by M. Vaughn.
Notes taken and certified by:
Agenda
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Kevin J. Murphy
School Building Committee Meeting City Manager
Michael McGovern
Assistant City Manager
What: School Building Committee Meeting
When: Thursday, April 6, 2017 at 10:00 a.m.
Where: Lowell City Hall,
375 Merrimack Street,
2nd Floor Mayor’s Reception Room,
Lowell, MA 01852
Purpose of the meeting:
Agenda Items – April 6, 2017
- Building Option Plan Refinement
o Full Renovation (Existing Site)
o New School Cawley
- Progress on Classroom Availability Discussions w/ ELT (informs phasing)
- Schedule Update
- Update on Additional Existing Condition Investigations
- Approval of Expenditures for Additional Investigations
- Community Outreach
Update on CBA and CMAA Meeting Last Week
Additional Community Meetings
- Website Development Update
- Next Steps
Get email alerts for Lowell
A daily email when new agendas and minutes are posted.