School Building Committee
Regular MeetingLowell, MA · April 30, 2018
Minutes
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Eileen Donoghue
City Manager
Michael McGovern
Assistant City Manager
Scho0ol Building Committee Meeting
Meeting Minutes
Date: April 30, 2018
Time: 6:30 PM
Location: City Council Chambers
I. - Attendance
Present: Eileen Donoghue, William Samaras, Conor Baldwin, Maryann Ballotta, Brian Barry,
Marianne Busteed, James Cook, David Cunningham, James Donison, Gary Frisch, Edward
Kennedy, Salah Khelfaoui, Connie Martin, Jay Mason, Rady Mom, Maria Sheehy, Richard
Underwood, Michael Vaughn.
Also in attendance:
City Councilors: John Leahy, Vesna Nuon, James Milinazzo, Rita Mercier, David
Conway, & Karen Cirillo
School Committee Members: Andre Descouteaux, Gerry Nutter and Jackie Doroghty
City: Mike McGovern, Mike Geary, and Heather Varney
Skanska: Maryann Williams, Dale Caldwell, Jim Dowd
Perkins Eastman: Joe Drown, Robert Bell, Alicia Caritano, Dawn Guarriello
Taverse Landscape Architects: Ashley Iannuccilli
City Manager E. Donoghue called the meeting to order at 6:30 PM.
II. - Update on Tasks Since Last SBC Meeting
A. Caritano discussed the overview of meetings on the LHS project since the March 2018
School Building Committee meeting. On April 4, 2018 the Sustainability meeting was held
consisting of a work shop for 22 people including the members of the School Department,
Skanska, Perkins Eastman, and their consultants, and the City. The group discussed sustainable
strategies for the new high school. A. Caritano noted that there was also a City Department
Head meeting on April 4, 2018 in which all relevant department managers were present to
discuss approvals needed and the timeline. The Security meeting on April 12, included a
workshop of 17 people to discuss security issues for all the options and current trends. A.
Caritano also mentioned the April 12, 2018 community meeting in which the open forum
provided a good amount of input. She stated that the team has updated the estimated EUI,
energy use intensity, for the design options to provide a relative comparison for each of the
options as compared to the existing buildings. The EUI for the existing buildings is 63
kBtu/SF-yr, Option 2A is 42.53, Option 3A is 41.98, and New A is 36.23. The energy update
serves as a benchmark for future study which will include lifecycle cost analysis.
III. - Design Option Overview and Cost Update
B. Bell provided an overview of the three design options. All options meet the Educational
program including relocating the Freshman Academy to provide a consolidated campus. Option
2A has a, limited green space and loading, windowless labs, and requires a temporary
gymnasium. Option 3A incorporates the adjacent land at 75 Arcand Drive which allows for a
larger entry plaza, an expanded footprint which includes lightwells in the 1980 building so that
there are no windowless labs, and additional greenspace and loading. Option 3A also requires no
temporary facilities, but requires Eminent Domain. New Option A, also takes the adjacent land
and requires Eminent Domain. However the footprint fills the site and has a limited entry plaza,
and green space. In addition, New Option A requires a temporary gymnasium and 24 temporary
classrooms. R. Bell noted that the presentation includes the pros and cons for each option in
additional to specific building specifications.
D. Guarriello discussed the massing of all the options. There were multiple meetings, during the
PSR where the Design Team explained the design options included the proposed plans and
phasing. She noted that the floor plans illustrated in the presentation are only for the main floor
so that the audience can get an idea of the layout. She also mentioned that the size of the new
gymnasium, locker room and fitness area is consistent among options 2A and 3A.
D. Guarriello discussed Option 3A, which includes the expanded site with more greenspace, new
bridges and light wells. She noted that the building is set back from the property line giving
students more space on the Father Morrissett Blvd. J. Mason inquired to the comparison of the
two courtyard sizes for Options 2A and 3A. A. Iannuccilli stated that 2A is approximately 3,600
square feet, and 3A is 15,000 square feet. D. Guarriello compared the square footage to the size
of four classrooms for 2A and sixteen classrooms for 3A. A. Ianunuccilli also compared the size
to the green space across the street from the high school by the parking garage which is 14,000
square feet.
D. Guarriello discussed New A, which is almost up to the property line at the street. She
mentioned that the design lets light into the classrooms as they are set up in bars. D. Guarriello
stated that the auditorium would be located in the windowless space.
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Eileen Donoghue
City Manager
Michael McGovern
Assistant City Manager
J. Drown noted that the team has been working on an updated cost estimate. He mentioned that
there are a few points to make note of including a schedule conflict which resulted in Perkins
Eastman bringing in new cost estimators, PM&C, and the project estimator staffing at
SKANSKA also changed. These staffing changes resulted in a “fresh set of eyes” on the project.
J. Drown noted that the space program changed as the swimming pool was removed, reducing
the size of the school. While refining the design Perkins Eastman has the opportunity to make
the design more efficient. J. Drown also noted that the cost estimates reconciled within 1% of
one another. By the end of the meeting, both estimators understood how other was viewing the
project, which was a very constructive important meeting. The estimated project cost is within
the MSBA average of $400-$500 / square foot construction.
J. Drown noted that the slide for reconciled revised PSR cost estimate includes projected costs
from Perkins on right and SKASNKA on left. He explained that the construction cost includes
the cost of the building and the site. The Project Budget includes the construction cost as well as
the other soft project costs such as Design Team, Operation Project Manager fees, and
construction contingencies etc. Option 2A construction cost is $ 262,135,000 with a project
budget of $333,040,000. Option 3A construction cost is $270,456,000 with a project budget of
$345,400,000. New A construction cost is $289,153,000 with a project budget of $361,624,000.
The city share for 2A is $124,282,000; for 3A is $135,960,000 and New A is $160,955,000.
W. Samaras inquired to the reimbursement cost, if the City would ever be able to obtain a higher
rate of reimbursement, how the city may begin conversations with the state on this topic. M.
Williams addressed this noting that the City may open discussions with the MSBA to consider
spaces that exceed the space summary guidelines if the argument about the scale of the school
and student population can be justified, and argue that the school does not fit with the average
model used as a guideline. B. Barry inquired if there was a different reimbursement rate for each
option. M. Williams noted that the team looked at the last set of responses from MSBA on the
comments for ineligible costs. It is a snapshot in time, the spaces consider ineligible cost for
reimbursements will need to be carried by the City, unless the MSBA does approve items for
reimbursement. She continued, noting that the guidelines are generally for schools with a
thousand students. This is an important part of why the size of school may fall outside the
guidelines. B. Barry asked why the construction costs go down so much. A. Caritano replied that
Option New A includes temporary classrooms, which are not required for any other option, and
constitute a large chunk of the cost. B. Barry inquired to why the gross numbers illustrated for
state reimbursement on Option 2A is $209,000,000, and Option New A reimbursement is
$8,000,000 less. J. Drown stated that there more factors than just if an item is ineligible or
eligible, they also need to be within the maximum $/sf for reimbursement in order to be
reimbursed. He noted that with Option New A, some of the limits were reached, making the
costs ineligible for reimbursement. R. Bell reinforced this noting that the design hit the cap on
the reimbursement; a building may be more expensive even if the footprint is smaller. D.
Guarriello stated that the differential between the reconciled revised PSR cost estimates has a
substantial amount of money that is ineligible as it relates to reimbursable $/ sf.
E. Kennedy followed up to W. Samaras’ notion that the City’s portion could go down and asked
what the team meant by being conservative. J. Drown stated that the city portion can go down,
but this is not known until the city enters into a conversation with the MSBA. E. Kennedy
inquired to why the portion may go down. J. Drown noted that the square footage is scaled down,
and more spaces become eligible with more money reimbursed by the MSBA.
E. Kennedy asked if there will be a negotiation. M. Williams replied that the team will not know
until final project budget scope when the City receives more feedback from the MSBA
submission, how the reimbursement will be reflected. E. Kennedy asked what the duration of
Schematic Design will be, and if it would be July 1. M. Williams stated that April 10, 2019 is
when the MSBA Board approval would be scheduled for Schematic Design. The team would
submit February of 2019. With the local appropriation, the state gives the city 120 days to
appropriate funding for the project by mid-august, which is reflected in the project schedule. E.
Kennedy asked if the loan order could be brought before the City Council in late spring, early
summer. M. Williams replied yes. D. Guarriello noted that the team would definitively know
when the OPM fills out the 3011 forms to determine the square footage ineligible. M. Williams
added that a caveat to this is that the funding agreement will not be signed until eminent domain
is complete, at which time the city would have to have complete control of the land. W. Samaras
inquired if there would be negotiation with the MSBA. R. Bell stated that the Irish Auditorium at
LHS is one of the spaces that may be ineligible currently. There may be an argument that making
the existing facility smaller may cost more, which makes it prudent to renovate the existing space
instead. J. Mason asked if at the end of schematic design, the City would have a number with the
MSBA that could change during the design element. M. Williams noted that when the OPM
submits form 3011 with the scope and budget, there may be some communication prior to the
agreement; but once the Scope and Budget Conference is held, that would be the final number
agreed upon with no more negotiations. D. Guarriello stated that the MSBA sets a total
maximum grant amount which may fluctuate during construction; the number can change when
change orders are deemed ineligible. She noted that at the end of schematic design, only 20% of
the design will be complete, but Perkins Eastman will be further along in the process than the
district and community may typically see for a project in Schematic Design. B. Barry asked if the
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Eileen Donoghue
City Manager
Michael McGovern
Assistant City Manager
gymnasium and Freshman Academy is the same size in options 2A and 3A. R. Bell noted that
the size is the same for all three options.
IV. - Community Forum
Two members of the community spoke. E. Donoghue noted that the City Manager’s Office is
tasked with updating the project website to make sure that it is up to date and accurate. She
mentioned that the office will work regularly with the consultants. M. Williams noted that the
project design for a phased occupied demolition and construction that will take 21 months after
the project is approved by the MSBA and the City. The start of the construction will begin
August 1, 2021. Option 2A would take 4 years plus a summer, 3A would take five years and the
New A would take 4 years.
B. Barry inquired if the extent of the rehabilitation is to gut the entire buildings or to keep much
of the existing structure. R. Bell stated that this could depend on the design once the team gets
into more detail. He explained that on a preliminary level, based on the wall thickness, the team
will make judgments to take out a whole wall rather than to make many holes in the wall. R. Bell
noted that the walls would not be recognizable. The idea is not to completely gut the buildings at
this point, but a substantial gut is likely. The walls, stairs, corridors may remain as shells, or may
be moved based on a number of variables. B. Barry inquired to if there would be all new systems
in the buildings or if existing electric and heating systems will remain. R. Bell noted that there
would be all new plumbing, heating and electric systems. J. Drown noted that the 1980 building
will be entirely redone with new systems, right down to the wire.
V. - Vote on Recommended Preferred Option to the City Council for the
PSR Submittal to the MSBA
E. Donoghue asked if there were any additional comments or concerns prior to the vote. B. Barry
stated that this was his first meeting but he has followed the project all along. He noted that the
SBC is charged with coming up with the best and most cost effective site to recommend to the
City Council. He stated that he does not think that any of three options before the committee at
the moment are the most effective, all have compromises in them. He mentioned that he sent a
communication regarding looking into South Common prior to being on the committee. E.
Kennedy motioned to vote to recommend a preferred option to the City Council.
City Manager Eileen Donoghue Option 3A
Mayor William Samaras Option 3A
Conor Baldwin Option 3A
Maryann Ballotta Option 3A
Brian Barry Option 2A
David Beati Absent
Head of School Marianne Busteed Option 3A
James Cook Option 3A
David Cunningham Option 3A
James Donison Option New A
Councilor Rodney Elliott Absent
Gary Frisch Option 3A
Robert Healy Absent
Councilor Edward Kennedy Option 3A
Superintendent Salah Khelfaoui Option 3A
School Committee Member Connie Martin Option 3A
Jay Mason Option 3A
State Representative Rady Mom Option 3A
Maria Sheehy Option 3A
Richard Underwood Option 3A
Michael Vaughn Option 3A
1 Option 2A, 16 Option 3A, 1 Option New A. The School Building Committee approves Option
3A as the recommended preferred option to the City Council. So voted.
E. Kennedy motioned to adjourn, seconded by M. Vaughn. Meeting adjourned 7:25 PM.
Notes taken and certified by:
Agenda
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4400 ● F: 978.970.4007
www.LowellMA.gov
Eileen Donoghue
City Manager
Mike McGovern
Assistant City Manager
School Building Committee Agenda
Monday April 30, 2018 6:30 PM
City Council Chambers
I. Update on Tasks Since Last SBC Meeting:
• City All Department Meeting
• Sustainability Meeting
• Security Meeting
• Energy Update
II. Overview of Design Options
III. Cost Update
IV. Community Forum
V. Vote on Recommended Preferred Option to the City Council for the PSR
Submittal to the MSBA
VI. Next Steps
Get email alerts for Lowell
A daily email when new agendas and minutes are posted.