Date: August 6th, 2020
Time: 5:00 PM
Location: Virtual Meeting—Zoom
School Building Committee Members Present - Eileen Donoghue, Ed Kennedy, William
Samaras, Jeff Wilson, Jay Mason, Sokhary Chau, Connie Martin, Michael Fiato, Mike
Vaughn, Christine Clancy, Conor Baldwin, Jim Cook, Dianne Tradd, MaryAnn Ballotta
City Staff Present: Kara Keefe Mullin, Peter Cutrumbes, Phillip Geoffroy
Perkins Eastman Consultants Present: Robert Bell, Joe Drown, Robin Greenberg
Skanska Consultants Present: Maryann Williams, Jim Dowd
Suffolk Construction: Rex Radloff, Chris Walenten
Meeting called to order at 5:05 PM by E. Donoghue. Roll call showed 14 present.
E. Donoghue put forth a motion to appoint Michael Fiato, new Head of School at Lowell High School, to the
Committee. 2nd by Ed Kennedy.
M. Fiato introduced himself and discussed his excitement for the building of the new high school.
E. Donoghue introduced Councilor Chau and asked to begin the presentation of the design process, which
will focus on details that have taken place between the current date and the last meeting.
J. Drown began the presentation and provided a brief overview of what would be discussed.
R. Greenberg discussed the process for gathering input on the design plan. They have been focusing on
having user groups that include residents and staff. These groups have provided feedback. R. Greenberg also
continued by highlighting the fact that they still have virtual meetings with City authorities.
J. Dowd discussed the permitting process and says they have had no delays so far. The Conservation
Commission approved the project on 5/27. On 6/1, the Planning Board approved the Site Plan Review and on
7/20 approved the removal of trees along Father Morissette Blvd. J. Dowd said they submitted their permit to
NPS last week on how
the project interacts with the National Park. There is also a Certificate of Appropriateness hearing coming up
with the Lowell Historic Board. There will be a permit application for building demolition at 75 Arcand
Drive in the fall. All permitting is proceeding as planned.
R. Radloff introduced himself as the project manager from Suffolk. He spoke on the plan for maintaining
school operations and not interrupting downtown life while the job is happening. They are developing plans
for deliveries, student/staff exits and entrances, and safely diverting pedestrian and vehicular traffic. They
will be using barriers and covered walkways for entrance and exiting, will have police details, and there will
be additional signage. Their goal is to minimize presence outside of site.
J. Mason asked a question on idling. He asked if there will be a sequenced arrival of materials and removal of
debris from the site.
R. Radloff answered by saying drivers will only idle at Cawley Stadium. All deliveries arrive there and then
be moved to LHS site.
J Wilson asked about provisions for wheelchair access while the project is ongoing.
R. Radloff responded by saying every temporary measure will be ADA accessible.
J. Drown gave an update on the bidding process. He said they are 50% of way through construction
documents, which will be used for contractors to bid. He also discussed milestones they want to meet along
the way: they just completed 60% of cost estimate documents (and will be using two independent estimators),
the gymnasium early bid package will be going out 8/17, they will submit 60% of the cost estimate
documents to the MSBA in Sept and 90% in October, and the bid documents final submission will be in
February of 2021.
E. Kennedy asked about the construction schedule and when ground will actually be broken.
C. Walenten said the abatement and demolition of 75 Arcand Drive will be starting late October or early
November. The gym/fieldhouse will then be going up, and will be finished by April 2022. C. Walenten said
each phase will last roughly 18 months, and that demo is included as part of construction. Steel will be
“coming out of the ground” in March 2021, and the project will be done by April 2022.
C. Baldwin asked if the pandemic has affected costs of materials that are being procured.
C. Walenten said it hasn’t effected costs, but that they have seen delays. Some additional costs have come up
for sanitizing job sites.
Meeting adjourned by E. Donoghue at 5:33 P.M.
Agenda
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Eileen Donoghue
City Manager
Kara Keefe Mullin
Assistant City Manager
School Building Committee Meeting
Meeting Agenda
Date: August 6, 2020
Time: 5:00 PM
Location: Zoom/Remote Participation
Pursuant to Governor Baker’s Emergency Order modifying the State’s Open Meeting Law issued
March 12, 2020, meetings will be held using remote participation as follows. Members of the
public wishing to speak regarding a specific agenda item shall register to speak in advance by
sending an email to pgeoffroy@lowellma.gov indicating the agenda item and a
primary/secondary (backup) phone number to call so that you may be conferenced into the
meeting. If you have no access to email, you may contact call 978-674-4402 to register to speak.
I. Accept Minutes of February 24, 2020 Meeting
II. Appointment of New Members
III. Presentation of Design Progress
IV. Review Permitting Progress
V. Traffic Management Plan and Logistics
VI. Schedule Update
a. Early Bid Package and Mobilization
b. Phasing and Long Term Schedule
Next Steps/ Upcoming Meetings