School Building Committee
Regular MeetingLowell, MA · September 17, 2020
Minutes
Office of the City Manager
City Hall ● 375 Merrimack Street ● Lowell, MA 01852
P: 978.674.4000 ● F: 978.970.4007
www.LowellMA.gov
Eileen Donoghue
City Manager
Kara Keefe Mullin
School Building Committee Meeting Assistant City Manager
Meeting Minutes
Date: September 17th, 2020
Time: 5:00 PM
Location: Virtual Meeting—Zoom
School Building Committee Members Present: Eileen Donoghue, John Leahy, Ed Kennedy,
Jeff Wilson, Jay Mason, Michael Fiato, Mike Vaughn, Conor Baldwin, Jim Cook, Dianne
Tradd, MaryAnn Ballotta, Maria Sheehy, Lt. Peaslee
City Staff Present: Kara Keefe Mullin, Peter Cutrumbes, Phillip Geoffroy, Sokhary Chau
Perkins Eastman Consultants Present: Dawn Guariello, Robert Bell, Joe Drown,
Robin Greenberg
Skanska Consultants Present: Maryann Williams, Jim Dowd
Suffolk Construction Staff Present: Rex Radloff, Chris Walenten
Meeting called to order at 5:04 PM by E. Donoghue. Roll call showed 13 members and 25 total present.
Motion to accept previous meeting minutes seconded by Ed Kennedy
M. Williams gave a brief presentation on cost estimates and reconciliation. Both companies plans were
reconciled within budget, and were within $546,000 of each other. With construction costs of $270 million,
these estimates were within 1/3 of 1% of each other. She stressed that the cost estimates are tracking in a very
positive way.
J. Drown addressed design questions from previous meetings, and gave a presentation with graphics showing
the work site. He also discussed some packages going out to bid early. Package 1A (75 Arcand Drive
Demolition) and Package 1B (Concrete foundations and steel for the gym) both went out to bid early. Both
these bids are tracking on budget. Currently, Perkins Eastman is 60% through construction documents.
Additionally, Mr. Drown shared that the City Council has approved the use of three items on this project: the
Master Radio Box from the Fire Department, the Access Control system at LHS, and the sidewalk street
lights in the area. He also gave a brief refresher on the construction phases.
C. Walenten discussed the Phase 1 work site logistics. During the third week of October, Suffolk is taking
over the site and putting up fencing. First activity is to abate 75 Arcand Drive, and then they advance to
demolition. The asphalt will be stripped and leveled off in December, with drill foundations being done in
January. The concrete foundations will be put down in February, and steel will come out of the ground in
March.
J. Drown informed the meeting that the next step tonight was to vote to authorize Skanska and Perkins
Eastman to submit the 60% construction documents to the MSBA.
E. Donoghue asked if there were any questions.
Lt. Peaslee asked if parking at the Mason Building will be restricted, as the Police Department uses the spots
closest to the fencing of the construction site.
C. Walenten answered that the lot will not be touched. The fence will only on be around 75 Arcand Drive.
J. Cook asked if the Mason Lot was ever in the plans for the project.
E. Donoghue answered no.
E. Kennedy asked about meeting hiring thresholds for residents and minorities.
E. Donoghue answered that packages haven’t gone out for labor yet, but that hiring goals are part of the
contract.
C. Walenten discussed what the vote is for, which is to submit supporting info, drawings, etc. to the MSBA.
They will send questions back if they have them, and the docs will be submitted on 9/25.
J. Cook asked how long it takes the MSBA to review the documents.
C. Walenten answered that they generally get the plans back in 2-4 weeks from submittal.
E. Kennedy proposed a vote to authorize Skanska and Perkins Eastman to submit 60% docs, seconded by Jim
Cook.
Unanimous vote.
E. Donoghue asked if we need to meet in October.
J. Drown highlighted the short-term time line for the project. Once bids are confirmed, they will get executed
as a contract with the early bid contractors. That work starts mid-October. Followed by that will be
completing the 90% construction documents and submitting them on December 11th. Completing the cost
estimates is targeted for October 30th-December 4th. Final bid documents submission is scheduled for
February 1st.
E. Donoghue asked if the next meeting of this group should be in advance of December submission.
J. Drown recommended the week preceding December 11th.
J. Leahy asked how the early stages of construction are going to impact Cobblestone’s outdoor seating due to
the pandemic.
C. Walenten answered that they don’t need the access road until the school opens.
E. Donoghue: Meeting adjourned 5:30 P.M. Moved by E. Kennedy, and seconded by J. Leahy
Agenda
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978.970.4000 • F: 978.970.4007
www.LowellMA.gov
Eileen M. Donoghue
City Manager
Kara Keefe Mullin
Assistant City Manager
School Building Committee Meeting
Meeting Agenda
Date: September 17. 2020
Time: 5:00 PM
Location: Zoom/Remote Participation
Pursuant to Governor Baker’s Emergency Order modifying the State’s Open Meeting Law issued
March 12, 2020, meetings will be held using remote participation as follows. Members of the
public wishing to speak regarding a specific agenda item shall register to speak in advance by
sending an email to mailto:pgeoffroy@lowellma.gov indicating the agenda item and a
primary/secondary (backup) phone number to call so that you may be conferenced into the
meeting. If you have no access to email, you may contact call 978-674-4402 to register to speak.
I. Accept Minutes of August 6, 2020 Meeting
II. Review Cost Estimates and Reconciliation Process
III. Address design questions from previous meeting
IV. Vote to authorize Skanska and Perkins Eastman to submit the 60% Construction
Documents package to the MSBA.
V. Next Steps/ Upcoming Meetings