School Building Committee Meeting
Meeting Minutes
Date: September 15, 2022
Time: 6:00 PM
Location: Mayor’s Reception Room
School Building Committee Members Present:
Tom Golden, Jr. (City Manager, School Building Committee Chair), Michael Vaughn (Chief
Procurement Officer), Dr. Joel Boyd (Superintendent of Schools), Richard Underwood (Operations
and Maintenance Director), Conor Baldwin (CFO), Mark Byrne (DPW Commissioner), David
Peaslee (Police Captain), William Samaras (Former Mayor of Lowell), John Leahy (City Councilor),
Rodney Elliot (State Representative), Maryann Manzi (LPD), Jay Mason (Community Member –
Architect), Erica Harvey (Teacher)
City Staff Present:
Shawn Machado (Assistant City Manager), Austin Ball (Deputy CFO)
Perkins Eastman Consultants Present:
Joe Drown, Robin Greenberg
Skanska Consultants Present:
Maryann Williams, Jim Dowd
Suffolk Construction Consultants Present:
Rex Radloff, Pat DeBennedetto
The order of business was as follows:
I. Attendance/Roll Call
Meeting called to order at 6:03 PM by CFO Baldwin on behalf of T. Golden, Jr. Roll call showed 13
present.
CFO Baldwin opened the meeting and welcomed those in attendance.
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
Mr. Mason - Asked question regarding how minutes of previous meetings work and why a question
about Solar Array System’s for the high school by Councilors Robinson and Gitschier was not
included.
II. City of Lowell
Motion to accept and place on file the minutes from June 2, 2022 SBC meeting, August 18, 2022
SBC meeting and the acceptance of a new member on the SBC committee John Haley by Mr.
Samaras and seconded by Mike Vaughn.
III. Suffolk/Skanska/PE Presentation:
a. Phase 1 - Completion Update
Rex - Certificate of occupancy was completed on 8/31 and are currently installing approx. 2,000
bleachers into gym. The concrete work is ongoing and final paving is set for later in October. His team
will start the process of their fall plantings and will complete the final punch list which will end Phase
1.
Council Leahy - Asked when the Tim Golden plaque will be coming in and also an update on the
weight room.
b. Phase 2 – Construction Update
Rex – Phase two work is ongoing with the removal and demolition of 80’s building. Bulk demolition
is ongoing and the field house has started to be removed. A new site work contractor will be coming
in and pre-excavation will begin. Concrete for Phase two will begin in October and carry through
November, steelwork will begin the end of December. During phase two an infiltration system will be
installed.
Mr. Byrne - With the demolition beginning have you run into any issues with Water and Sewer?
Mr. Mason - Asked about the trucks that are leaving with all the debris from the demolition and
whether or not that is being recycled. Also inquired about Leed certifications and if any are being
sought out.
c. Phase 2 – High School Campus Logistics
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
Rex – Indicated that some jersey barriers will be moved across the crosswalk on the boulevard for
safety. Noted that stair J will allow access into the building for students and faculty.
IV. Suffolk - MBE/WBE and Workforce Progress
Rex - Discussed MBE/WBE and Workforce progress to date some highlights include; the total
minority construction workforce is at 25.1%, the total female construction workforce is at 3.6% and
the total Lowell resident construction workforce is at 10.7%.
V. Perkins Eastman – Designer Update
Joe - Informed the body and public as of now there is no update in this section.
VI. Skanska - Budget Update
Jim- Reviewed project budget status to date. They’re $249,453 change orders to date which will come
out of the construction contingency. The construction contingency also has $504,139 pending in
change orders. As of today we have not used any funds from the owner’s contingency budget and
have no pending change orders. In the construction manager contingency they’re currently $141,094
approved change orders and $147,162 pending change orders. The total amount for the project spent
to date is $90.6M. The project is currently on budget.
VII. Skanska - Next Steps
Rex - The next steps is the field house will be coming down.
Questions / Comments:
Ms. Harvey – Asked about ADA ramps and compliance also spoke about how parking spots are being
blocked.
Mr. Samaras – Asked Jim to clarify the different types of contingency and why they’re three different
budget line items. Also inquired about how the contingency’s are approved.
Mr. Byrne – Inquired if some of the owner’s contingency could be used to make building
improvements like HVAC etc.
Mr. Vaughn – Questioned if the subcontractors from Phase 1 to Phase 2 were the same price or was
one section higher.
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
Mr. Underwood – Commented that since this was an aggressive plan it may have been a little rushed
and we may need to slow down and have a little better attention to detail.
Councilor Leahy – Asked if Superintendent or Operations Director had any other concerns.
Dr. Boyd – Informed Councilor that student safety is number 1 priority and that the City
Manager and Jim Dowd have been great in helping with this project.
Ms. Harvey – Informed the body and public that this project has been working well with
teachers and students.
Councilor Leahy – Inquired about security and asked if it was being staffed correctly.
Mr. Byrne – Wondered if we might be able to move demolition to later in the day and whether or not
the city’s ordinance will allow demolition at night.
Manager Golden – Informed the body / public if the ordinance needed to be changed they will
adjust it.
Motion to adjourn by CFO Baldwin, 2nd by W. Samaras.
Meeting adjourned at 6:39PM
Agenda
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978.674.4000 • F: 978.970.4007
www.LowellMA.gov
School Building Committee Meeting
Meeting Agenda
Date: September 15, 2022
Time: 6:00 PM
Location: City Hall Mayor’s Reception Room
MEETING AGENDA
1. Attendance/ Roll Call
2. City of Lowell
a. Vote – Accept new members – John Haley (Community Member)
b. Vote - Accept minutes of the June 2, 2022 SBC Mtg.
c. Vote - Accept minutes of the August 18, 2022 SBC Mtg.
3. Suffolk/Skanska/PE - Presentation:
a. Phase 1 - Completion Update
b. Phase 2 – Construction Update
c. Phase 2 – High School Campus Logistics
4. Suffolk - MBE/WBE and Workforce Progress
5. Perkins Eastman – Designer Update – No new Design Updates to Provide
6. Skanska - Budget Update
7. Skanska - Next Steps
8. Adjournment