School Building Committee
Regular MeetingLowell, MA · December 14, 2022
Minutes
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
School Building Committee Meeting
Meeting Minutes
Date: December 14th, 2022
Time: 6:00 PM
Location: Zoom / Virtual Particpation
School Building Committee Members Present:
Tom Golden, Jr. (City Manager, School Building Committee Chair), Michael Vaughn (Chief
Procurement Officer), Richard Underwood (Operations and Maintenance Director), Michael Fiato
(Head of School), Conor Baldwin (CFO), Mark Byrne (DPW Commissioner), William Samaras
(Former Mayor of Lowell), Edward Kennedy (MA Senator), Rodney Elliot (State Representative),
Maryann Manzi (LPD), Jay Mason (Community Member – Architect)
City Staff Present:
Shawn Machado (Assistant City Manager), Paul St. Cyr (DPW Commissioner), Austin Ball (Deputy CFO)
Perkins Eastman Consultants Present:
Joe Drown, Robin Greenberg
Skanska Consultants Present:
Jim Dowd
Suffolk Construction Consultants Present:
Rex Radloff
The order of business was as follows:
I. Attendance/Roll Call
Meeting called to order at 6:05 PM by T. Golden, Jr. and asked to accept and place on file remote /
zoom participation, roll call showed 11 present.
Manager Golden opened the meeting and welcomed those in attendance and asked the body to take a
look at last month’s meeting minutes and accept the minutes.
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
II. City of Lowell
Motion to accept and place on file the minutes from November 9th, 2022 SBC meeting, by W.
Samaras and seconded by M. Byrne.
III. Suffolk/Skanska/PE Presentation:
a. Phase 1 - Completion Update
Rex – Since last update, Suffolk has made progress with installing the butcher block benches, striping
inside the gym and currently working on finishing the punch list. At the beginning there were 1600
punch list items created and 1434 have been completed. Most of the remaining punch list is on the
outside of the building.
b. Phase 2 – Construction Update
Rex – Currently in the middle of construction with phase two. The rest of December will be
completing ground improvements and with continuing the concrete foundation. In January, steel will
begin to be installed and this will continue into the upcoming months. The concrete foundation will
be completed in January. RAP installation ongoing at night to not disturb the students. RAP is about
80% completed at this point and are drilled into the ground about 10-24 feet. After RAP installed the
next step is to go right into foundations. Visual shown on screen to indicate where all the RAP’s have
been installed and will be installed.
IV. Suffolk - MBE/WBE and Workforce Progress
Rex – The total work hours and total workers have increased in all categories from the previous
meeting, however percentages have remained the same.
V. Perkins Eastman – Designer Update
Robin / Joe - Informed the body and public as of now there is no update in this section.
VI. Skanska - Budget Update
Jim- The overall budget is $381,967,231. Currently going through change orders each month and
have spent, to date $102M and the MSBA has reimbursed the city $68M. Also, there is currently a
$6M request in to the MSBA for reimbursement.
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
Questions / Comments:
E. Kennedy – The striping has not been completed in the gym in time for the holiday basketball
tournament, was this a mistake?
Jim – No, due to the delay with the bleachers could not get all the lines painted. As a solution, we
have had the courts professionally taped.
E. Kennedy – Will the tape always be used?
Jim – No, we are just waiting until the summer and are currently in communication with the Athletic
Director regarding completing the line painting.
J. Mason – Was at the City Council meeting and saw an image of the roof of the high school with the
equipment on there, would like to know if there is going to be a professional study done to organize
the equipment on the roof?
Robin – At the gym all the equipment that is there is permanent. On the high roof the focus was
keeping all the equipment to the east and as compact as possible to maximize the ability for solar.
M. Fiato – Just want to thank the Skansa for being so responsive.
T. Golden – Any other questions? None at this time.
Motion to adjourn by W. Samaras, 2nd by E. Kennedy.
Meeting adjourned at 6:26 PM
Agenda
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager/ SBC Chair
School Building Committee Meeting
Meeting Agenda
Date: December 14, 2022
Time: 6:00 PM
Location: Via remote participation - Zoom
I. City – Accept Communication/ Remote Participation (Zoom)
a. Communication Remote / Zoom Participation: Meetings Will Be Held via Zoom Using Remote
Participation As Follows: Members Of The Public May View The Meeting Via LTC.Org (On-Line;
Live Streaming; Or Local Cable Channel 99). Those Wishing To Speak Regarding A Specific Agenda
Item Shall Register To Speak In Advance Of The Meeting By Sending Email To City Manager’s
Office With A Phone Number To Call So That You May Be Issued Zoom Link To The Meeting. Email
Address Is ABALL@LOWELLMA.GOV. If No Access To Email You May Contact City Manager’s
Office At 978-674-4402. All Request Must Be Done Before 4:00 PM On The Day Of Meeting. For
Zoom - HTTPS://SUPPORT.ZOOM.US/HC/EN-US/ARTICLES/201362193-JOINING-A-MEETING
II. City - Accept Minutes of November 9, 2022 Meeting
III. Suffolk/Skanska/PE - Presentation:
a. Phase 1 - Completion Update
b. Phase 2 – Construction Update
IV. Suffolk - MBE/WBE and Workforce Progress
V. Perkins Eastman – Designer Update
VI. Skanska - Budget Update
VII. Skanska - Next Steps