School Building Committee
Regular MeetingLowell, MA · January 18, 2023
Minutes
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
School Building Committee Meeting
Meeting Minutes
Date: January 18th, 2023
Time: 6:00 PM
Location: Zoom / Virtual Participation
School Building Committee Members Present:
Michael Vaughn (Chief Procurement Officer), Dr. Joel Boyd (Superintendent of Schools), Richard
Underwood (Operations and Maintenance Director), Michael Fiato (Head of School), Conor Baldwin
(CFO), Mark Byrne (DPW Commissioner), David Peaslee (Captain LPD), William Samaras (Former
Mayor of Lowell), Edward Kennedy (MA Senator), Rodney Elliot (State Representative), Maryann
Manzi (LPD), Jay Mason (Lowell Sustainability Council-Architect), Maria Sheehy
City Staff Present:
Shawn Machado (Assistant City Manager), Paul St. Cyr (DPW Commissioner), Austin Ball (Deputy CFO)
Perkins Eastman Consultants Present:
Joe Drown, Robin Greenberg
Skanska Consultants Present:
Jim Dowd
Suffolk Construction Consultants Present:
Pannha San Chung
The order of business was as follows:
I. Attendance/Roll Call
Meeting called to order at 6:03 PM by S. Machado on behalf of Manager Golden and asked to accept
and place on file remote / zoom participation, roll call showed 13 present.
S. Machado opened the meeting and welcomed those in attendance and asked the body to take a look
at last month’s meeting minutes and accept the minutes.
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
II. City of Lowell
Motion to accept and place on file the minutes from December 14th SBC meeting, by W. Samaras and
seconded by Dr. Boyd.
III. Suffolk/Skanska/PE Presentation:
Phase 2 – Construction Update
Pannah – Biggest milestone was that structural steel has begun at the Freshman Academy, have also
started underground MEP’s. Have completed concrete foundation at Building F and the North
Connector. Have also completed micropiles at the bridge on the east side. In February will continue
with steel and will begin concrete foundation in Building D. In March, will begin concrete slabs for
Building D/F.
Showed photos of foundation wall of Building F and North Connector as well as steel columns. The
milestone for steel in Building D is February 22nd.
IV. Suffolk - MBE/WBE and Workforce Progress
Pannah – Maintained the number of female workforce and minority workforce from the previous
meeting. Suffolk is meeting with subcontractors to try to increase female workforce.
V. Perkins Eastman – Designer Update
Robin / Joe - Informed the body and public as of now there is no update in this section.
VI. Skanska - Budget Update
Jim- The overall budget is $381,967,231. $20.1 million remaining in construction contingency which
is a number being tracked since the GMP was finalized. $597k has been spent in the construction
management contingency and have not used any money in the owner’s contingency budget. The
invoice for December was for $6.7 million that was sent to the city before the meeting. Currently
processing change orders as they come in and on a good track.
VII. Skanska – Next Steps
Jim- Waiting to hear back from MSBA to update overall budget, which was submitted to them by the city in
November. Steel has been proceeding nicely and will continue too.
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
Questions / Comments:
W. Samaras – Has the weather helped since we haven’t gotten any major snowfall?
Jim – Yes, the weather has been helpful in keeping the project on track.
W. Samaras – How was it decided that only two toilets would be in the woman’s locker room in the
new gym?
Jim – Aware of that issue and I’ll turn it over to Joe from Perkins Eastman for a detailed explanation.
Joe – Toilets are designed for the entire project and once it is complete there will be multiple toilets
on the second floor. The design was constructed because the population is much larger on the second
floor than the first, once Phase 2 is completed more toilets will become available. The structure does
meet the building code requirements.
W. Samaras – So once Phase 2 is completed you will have access to more laboratories?
Joe – Yes, that is correct.
W. Samaras – Are there urinals and toilets in the men’s room?
Joe – Yes there are.
W. Samaras – Can anything be done at this point in time for this particular area?
Joe – Not as of this current time, once Phase 2 gets closer to completion they will have access to more
toilets.
E. Kennedy – How many more fixtures will be on the second floor?
Joe – 5 more fixtures for both males and females.
E. Kennedy – The population was perceived to be higher on the second floor rather than the first?
Joe – Yes, looked at the population of students and deemed that the second floor would be utilized
more frequently than the first.
E. Kennedy – Back in 2016/2017, there was a vision report to configure the buildings, do you think it
would be beneficial to review that report?
Joe – Absolutely, we can certainly go back and review any and all notes.
E. Kennedy – Was the vision report incorporated into the construction of this project?
Joe – Yes, it was.
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852 P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager
E. Kennedy – Are you guys doing any other high school projects with the MSBA and if so how
many?
Joe – Yes, they’re two of them currently.
E. Kennedy – Asked if Perkins has had conversations with the MSBA regarding the overruns?
Joe – Yes, currently speaking with the MSBA about it and the MSBA is reviewing whether or not
they should increase the dollars per sq foot.
E. Kennedy – Will the MSBA look back retroactively if they do increase?
Joe – We have asked the MSBA this question and haven’t received a clear indication yet.
Robin – The MSBA did vote to adjust the cost per sq foot in design.
Jim – Skanska has done a roundtable with other OPM’s and the MSBA regarding this.
S. Machado – Any other questions? None at this time.
Motion to adjourn by C. Baldwin, 2nd by W. Samaras.
Meeting adjourned at 6:31 PM
Agenda
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager/ SBC Chair
School Building Committee Meeting
Meeting Agenda
Date: January 18, 2023
Time: 6:00 PM
Location: Via remote participation - Zoom
I. City – Accept Communication/ Remote Participation (Zoom)
a. Communication Remote / Zoom Participation: Meetings Will Be Held via Zoom Using Remote
Participation As Follows: Members Of The Public May View The Meeting Via LTC.Org (On-Line;
Live Streaming; Or Local Cable Channel 99). Those Wishing To Speak Regarding A Specific Agenda
Item Shall Register To Speak In Advance Of The Meeting By Sending Email To City Manager’s
Office With A Phone Number To Call So That You May Be Issued Zoom Link To The Meeting. Email
Address Is ABALL@LOWELLMA.GOV. If No Access to Email You May Contact City Manager’s
Office At 978-674-4402. All Request Must Be Done Before 4:00 PM On The Day Of Meeting. For
Zoom - HTTPS://SUPPORT.ZOOM.US/HC/EN-US/ARTICLES/201362193-JOINING-A-MEETING
II. City - Accept Minutes of December 14, 2022 Meeting
III. Suffolk/Skanska/PE - Presentation
a. Phase 2 – Construction Update
IV. Suffolk - MBE/WBE and Workforce Progress
V. Perkins Eastman – Designer Update
VI. Skanska - Budget Update
VII. City/Skanska – Meeting Schedule
VIII. Adjourn