School Building Committee
Regular MeetingLowell, MA · October 19, 2023
Minutes
The City of Lowell • Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978-674-4402 • F: 978-970-4007
www.Lowellma.gov
Thomas A. Golden, Jr.
City Manager
School Building Committee Meeting
Meeting Minutes
Date: October 19th, 2023
Time: 6:00 P.M
Location: Mayor’s Reception Room / Zoom
School Building Committee Members Present:
Mike Vaughn (Chief Procurement Officer), Liam Skinner (LPS Superintendent), Richard
Underwood (LHS Operations and Maintenance Director), Michael Fiato (Head of School), Conor
Baldwin (Chief Financial Officer), James Hall (LPS COO), David Peaslee (LPD Captain), William
Samaras (Former Mayor of Lowell), Edward Kennedy (State Senator), Rodney Elliot (State
Representative), Jay Mason (Lowell Sustainability Council – Architect), Maria Sheehy (Esq.),
Benjamin Opara, (Community Member), John Haley (Community Member), Paul St. Cyr (DPW
Commissioner)
City Staff Present:
Shawn Machado (Assistant City Manager), Austin Ball (Deputy CFO)
Perkins Eastman Consultants Present:
Joe Drown, Robin Greenberg
Skanska Consultants Present:
Jim Dowd
Suffolk Consultants Present:
Rex Radloff, Pannha San Chung
The order of business was as follows:
I. Attendance / Roll Call:
Meeting Called to order at 6:00 P.M by S. Machado and asked to accept and place on file remote
/ zoom participation, roll call showed 15 present.
City of Lowell:
S. Machado asked the committee to review the minutes from the last meeting and to make a
motion to place on file. Minutes passed by roll call, motion by E. Kennedy and 2nd by M.
Vaughn.
II. Suffolk:
Phase 2 – Construction Update
Pannha – Currently on Phase 2 milestones, in October began façade work at Building D, began
interior finishing in Building F and continued MEP overhead rough in Building D.
J. Mason – Any reason we are still showing gym in the plan?
Pannha – No, this is an old photo and we will update for next meeting.
In November we are looking to complete façade work in Building F, begin elevator work and
drywall work in Building D and lastly, begin the façade work on the South Bridge. Showed
progress photos from the past couple months.
S. Machado – Any questions? (None at this time)
III. Suffolk – MBE Workforce Update:
Pannha – Currently exceeding goal of the minority workforce, the goal is 15.3% and we are
currently at 24.4%. Project goal for female workforce is 6.9% and currently we are at 4.2%.
Lastly, the Lowell resident workforce is at 10.4%.
B. Opara – It seems these numbers are improving.
Pannha – That is correct, we are exceeding the minority workforce goal and with new trades that
are coming on, we hope to increase the number in the female workforce category.
IV. Perkins Eastman - Designer Update:
Joe – No update this month.
V. Skanska – Budget / Cash Flow Update
Jim - The total budget for the LHS project is $381.9 million dollars and the MSBA has
reimbursed the city $101 million to date. The main thing we are currently tracking is the
contingency line item, to date we have had 14 change orders totaling almost $3.4 million dollars
and we currently have $17.8 million remaining in construction contingency. This month’s billing
was $6.6 million and the total billing is $157 million.
Jim – Any questions?
J. Mason – Do you feel that the project is about 50% spent down?
Jim – Of the committed dollars we have spent about half, this is where we should be.
B. Opara – Do you think we are on track with our contingency numbers?
Jim – Yes, but it will tick up as we get further into the renovation phase of the project.
S. Machado – Any other questions? (None at this time).
Next Steps:
Jim – Suffolk will have a big push to get envelope enclosed in the next month and half with the
winter approaching as well as the brick façade. Actively working with the school administration
to limit impacts on the students.
C. Baldwin – As a follow up from our last SBC meeting the city sold a bond of $30 million with
an interest rate of just over 4%.
B. Opara – What was the projected interest rate at the beginning of the project?
C. Baldwin – 5%
L. Skinner – Can you please discuss and give us an update on elevators and air conditioning
within the project? Which phase will that be a part of?
Joe – Elevators are located within each portion of each phase. When the project is finished there
will be a total of 8 elevators. AC will be given to phase 1 and 2 once phase 2 is officially
completed.
M. Vaughn – Are the elevator companies having issues getting parts?
Pannha – As of now, we currently haven’t had any problems.
W. Samaras – Are we still on schedule with this project?
Pannha – Yes, we are still on schedule to complete phase 2 as well as on schedule to start phase
3 next summer. We are also on schedule for the entire completion of the project in 2026.
J. Mason – Is the electrical switch gear all set? We have seen long lead times for electrical
service equipment.
Jim – Yes, the Phase 2 switch gear resides in Phase 1 and the remaining phases are already in
storage.
M. Fiato – I’d like to recognize Jim and his team for their hard work and quick response if any
staff member runs into an issue or problem, Jim’s team is quick to respond and address the
problem. Do we have any update on the city hiring of the HVAC specialist?
S. Machado – Yes, we are very close to hiring an individual. The interviews have finished and an
offer letter was sent out.
M. Fiato – Will this position be just for the high school or all municipal buildings?
S. Machado – Mainly just the high school but will work on other buildings as needed.
S. Machado – Any other questions? (None at this time)
Motion to adjourn at 6:20 by B. Opara, 2nd by C. Baldwin, so moved.
Agenda
Office of the City Manager
City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978.674.4402 • F: 978.970.4007
www.LowellMA.gov
Thomas A. Golden, Jr.
City Manager/ SBC Chairman
Shawn Machado
Assistant City Manager
Lowell High School - Building Committee Meeting
Meeting Agenda
Date: Thursday, October 19, 2023
Time: 6:00 PM
Location: Mayor’s Reception Room (City Hall & via remote participation – Zoom)
Agenda
I. City – Accept Communication/ Remote Participation (Zoom)
II. Communication Remote / Zoom Participation: Meetings Will Be Held via Zoom
Using Remote Participation As Follows: Members Of The Public May View The Meeting Via LTC.Org
(On-Line; Live Streaming; Or Local Cable Channel 6). Those Wishing To Speak Regarding A Specific
Agenda Item Shall Register To Speak In Advance Of The Meeting By Sending Email To City Manager’s
Office With A Phone Number To Call So That You May Be Issued Zoom Link To The Meeting. Email
Address Is ABALL@LOWELLMA.GOV. If No Access to Email You May Contact City Manager’s Office At
978-674-4402. All Request Must Be Done Before 4:00 PM On The Day Of Meeting. For Zoom -
HTTPS://SUPPORT.ZOOM.US/HC/EN-US/ARTICLES/201362193-JOINING-A-MEETING
October 19, 2023
LHS School Building Committee Agenda
Page 2 of 2
III. City Manager – Welcome and Roll Call Vote
IV. City - Accept Minutes of August 24, 2023 Meeting
V. Suffolk/Skanska/Perkins Eastman – Presentation
a. Presentation: Phase 2 – Construction Update
VI. Suffolk - MBE/WBE and Workforce Progress
VII. Perkins Eastman – Designer Update
VIII. Skanska – OPM Update
a. Budget Update
b. Contingency Review
IX. Skanska - Next Steps
X. Adjournment