Historic District Commission
Regular MeetingManistee, MI · July 27, 2009
Minutes
HISTORIC DISTRICT COMMISSION
Council Chambers, City Hall
70 Maple Street
Manistee, MI 49660
SPECIAL MEETING MINUTES
July 27, 2009
A Special Meeting of the Manistee City Historic District Commission was held on Monday, July 27, 2009
at 4:00 p.m. in the Council Chambers, City Hall, 70 Maple Street, Manistee, Michigan.
Meeting was called to order at 4:00 p.m. by Chair Kracht.
ROLL CALL:
Members Present: Dave Carlson, Maria DeRee, Teena Kracht, Nathaniel Neider, John Perschbacher
Members Absent: T. Efaxiadis, (excused), Vacancy
Others: Kevin Mulvihill (Abonmarche), Elbert Purdom (369 River Street), Vanessa Buhs,
Travis Alden (Main Street/DDA Director), Jon Rose (Community Development),
and Denise Blakeslee (Planning & Zoning)
APPROVAL OF AGENDA:
MOTION by Dave Carlson, seconded by Maria DeRee that the Agenda for the July 27, 2009 Special
Meeting be approved.
With a voice vote this motion passed unanimously.
APPROVAL OF MINUTES:
MOTION by Nathaniel Neider, seconded by Dave Carlson that the Minutes of the July 13, 2009 Special
Meeting be approved.
With a voice vote this motion passed unanimously.
NEW BUSINESS:
Elbert Purdom - Big Bear Investments, 369 River Street
Chair Kracht called a Special Meeting for the Commission to discuss the project at 369 River Street.
City of Manistee Historic District Commission
Special Meeting Minutes of July 27, 2009
Page 2
It was called to staff’s attention that the contractor was adding brick to the building at 369 River Street. The
addition of new brick over existing brick was not disclosed to the Commission during the application
process. It was shown on the construction drawings, but these were not submitted with the application to
the Historic District Commission.
It was also noted that the brick on the second, and third story has been patched not following the Secretary
of the Interior’s Guidelines.
These issues resulted in a suggest to stop the work and a phone call to Robb McKay, State Preservation
Office. Mr. McKay recommended that the applicant remove the patches and follow the guidelines in
Preservation Brief #1 Assessing Cleaning and Water-Repellent Treatments for Historic Masonry Buildings
and Preservation Brief #2 Repointing Mortar Joints in Historic Masonry Buildings. Copies were given to
the applicant.
Mr. McKay, State Preservation Office said that there are two ways to address the inclusion of new brick to
the front of the building covering the piers that were revealed during demolition process.
< First the Historic District Commission could require the brick be removed and a new plan be
submitted for approval. This results in a hardship for the owner and delay to the completion of a
significant improvement to our downtown.
< Second would be for the Historic District Commission to not issue a Certificate of Compliance when
the project is completed. Instead a Notice to Proceed can be issued that allows the project to be
completed but does not indicate compliance.
This stays on file and states that a project was done that did not meet the requirements of the
Secretary of the Interior Guidelines, but did not result in irreversible damage to the integrity of the
building.
Kevin Mulvihill, Abonmarche - Mr. Mulvihill is the Architect for the project. Mr. Mulvihill explained
that the building originally had an EFIS system attached to the first floor. There was no documentation that
could be found on how the building originally looked. This resulted in having to drill holes into the EFIS
system to try to determine what was behind it. Remodeling to the lower portion of the building was done
in 1986 that altered the floor level and gave the building a continuous plane.
The brick on the side piers has had spalling and were damaged. Anchor points were drilled into the brick
when the EFIS system was added to the building. The brick that is being added to the side piers and new
brick base will provide a continuous plane for the first floor of the building.
The building design was to cover the historical column. Until demolition took place they did not know if
it was a metal post or decorative column. The plans were to maintain a cohesive line of the building. If the
piers did not have the brick on them then the building would be stepped back on the ends and changes would
need to be made to insure waterproofing.
City of Manistee Historic District Commission
Special Meeting Minutes of July 27, 2009
Page 3
Mr. Mulvihill spoke with the Contractor who said that the brick restoration will be brought into compliance.
Jon Rose, Community Development Director - Mr. Rose spoke of his conversation with Mr. McKay and
how a Notice to Proceed can be issued instead of Certificate of Compliance. This would allow the project
to continue but indicates that compliance with the Secretary of the Interior’s Standards for Restoration was
not met. This does not stop the Building Inspector from issuing a Certificate of Occupancy.
Elbert Purdom, 369 River Street - Mr. Purdom said that he wants Historical Tax Credits for this project
and wants a Certificate of Compliance.
Jon Rose - Explained the difference between the Environmental Review that was conducted by the State
of Michigan for the MSHDA Grant -vs- the Tax Review that is done for a Historic Tax Credits. Because
the State had approved the Environmental Review for the Grant does not mean that it qualifies for Tax
Credits.
Elbert Prudom - Said that he wants Tax Credits for this project and wants to know what to do.
Commissioner Perschbacher said that he had worked on a possible solution. He had found postcards that
of the Bank Building that included a portion of this building. He has reviewed these postcards and from
that review wrote out the three options he discussed during the meeting for the Recording Secretary to
include in the minutes. The three options that are available and Option B may allow Tax Credits:
A. As owner proposes.
B. Piers to remain as exposed.
1. New added brick to be removed.
2. New added brick under windows - street level up- to be left and continued as
planned.
3. Piers to be patched - piers to have the new brick removed along with fasteners and
either paint removed or repainted.
C. Same as “B” but brick matching piers to be used instead of current new brick under windows
to street level.
Kevin Mulvihill - It was asked if the columns could be left exposed. Mr. Mulvihill said it would require
redesign and time is a factor. Changes to the plan would need to include design to make sure that the
building would be waterproof, the contractor is already on site and there are construction costs to be
considered.
Vanessa Buhs - Ms. Buhs is administering the MSHDA Grant for this project. She said this grant was
written and a Notice of Interest was done. They were unable to find pictures and evidence of what was
under the facade. Numerous times they came to the Commission and made exhaustive efforts to bring
information to the Commission. To bring in full construction drawings for each Commissioner would have
cost $3,000. The Commission never asked about the brick and the project received approval from the
Historic District Commission, State and Downtown Development Authority. They were never told the
project could be stopped. Who is going to pay the additional expenses?
City of Manistee Historic District Commission
Special Meeting Minutes of July 27, 2009
Page 4
Jon Rose - The Historic District Commission and the State only received a copy of the 8 ½ x 11 colored
rendering. The application and presentation to the Commission did not make any mention of new brick
being added over the old brick. The Commission did not receive construction drawings that detailed that
new brick was being added.
Kevin Mulvihill - said that they did not know what the columns would look like, they could have been a
metal beam or support post. They were not incorporated into the plan.
Vanessa Buhs - how are you suppose to incorporate an element if you do not know what it is?
Jon Rose - This is an issue that is dealt with all the time during Historic Preservation. When a new element
is discovered then the State or Historic District Commission are notified for direction on how to proceed.
The issue here is that if Mr. Purdom wants Historical Tax Credits then the State needs to be contacted with
how to proceed.
Mr. Rose also asked about the brick repair that was done on the back of the building and wanted to know
what type of mortar and repair was done.
Kevin Mulvihill - said that he would get a copy for file.
The Commission asked if Robb McKay could come here to review the building. Mr. Rose said that the
State has cut their Travel and Training Funds. Discussed if the Commission could pay to have him come
here. Mr. Rose said he did not believe they had and budgeted funds. Discussed if the DDA Design
Committee had any funding available.
Kevin Mulvihill - said that he would be willing to go to Lansing to meet with Mr. McKay to discuss the
project and a solution.
Elbert Purdom - said he would contact Robb Mc Kay about the Historical Tax Credits. He can live with
the delay but would like to keep the arches in the plan. He is very disheartened on how this project has gone
but he wants the Historical Tax Credits.
MOTION by Nathaniel Neider, seconded by Maria DeRee that this item be postponed and placed on the
August 6, 2009 agenda under Old Business.
With a voice vote this motion passed unanimously.
In the event that information is before the next meeting then Chair Kracht will schedule a Special Meeting.
OLD BUSINESS
None
City of Manistee Historic District Commission
Special Meeting Minutes of July 27, 2009
Page 5
PUBLIC COMMENTS AND COMMUNICATIONS CONCERNING ITEMS NOT ON THE
AGENDA
None
CORRESPONDENCE
None
STAFF REPORTS
None
The Next meeting of the Historic District Commission will be on Thursday, August 6, 2009 at 3:00 p.m.
in the Council Chambers, City Hall, 70 Maple Street.
ADJOURNMENT:
MOTION by Maria DeRee, seconded by Nathaniel Neider that the meeting be adjourned. Motion passed
unanimously.
MEETING ADJOURNED AT 5:30 P.M.
MANISTEE HISTORIC DISTRICT COMMISSION
__________________________________________
Denise J. Blakeslee, Recording Secretary
Get email alerts for Manistee
A daily email when new agendas and minutes are posted.