CALL TO ORDER A meeting of the Lake Quality Commission (LQC) was held on October 16, 2024 in
the Emergency Operations Center at the Maple Grove Government Center, 12800
Arbor Lakes Parkway, Maple Grove.
Chairperson Fahrenbruch called the meeting to order at 6:30 p.m.
Commissioners Present:
Becky Fahrenbruch – Chair - Eagle Lake
Brennon O’Callaghan, Vice Chair – Fish Lake
Nancy Bergstrand – Weaver Lake
Joe Ruegsegger – At Large
Steve Lane – Cedar Island Lake
Commissioners Absent:
George Schneider – Rice Lake
Sharon Martin-Kotula – Edward Lake
Others Present:
Kristy Janigo, City Council Liaison
Derek Asche, City of Maple Grove
Mark Lahtinen, City of Maple Grove
Hente Braam, Rice Lake
Pete Cangialosi, City of Maple Grove resident
APPROVAL OF Minutes of the April 17, 2024 LQC meeting were presented.
MINUTES
MOTION TO APPROVE by Ruegsegger, second by O’Callaghan. With all in favor the
motion was APPROVED.
AREA REPORTS Mark Lahtinen – Most lakes are currently 3-6” low.
Rice Lake, Hente Braam – Carp removal project was completed and conversation is
turning to another drawdown. Zebra Mussels were discovered in July. The U of M
was on the lake to collect sediment cores. The lake is level is low.
Weaver Lake, Nancy Bergstrand – Docks and boats are slowly leaving the lake.
Council Liaison Kristy Janigo – Rush Creek Stream Restoration contract was
awarded by the City Council and Councilmember Janigo recently spoke at the WLIA
meeting.
Eagle Lake, Becky Fahrenbruch – Good summer on the lake. Water level is low and
docks are being removed. Attended the Metro Blooms shoreline restoration
workshop with several residents.
Cedar Island Lake, Steve Lane – The year started off with cleaner water followed by
1-2 months of filamentous algae. It is estimated the lake had 3.0 – 3.5 feet of
water clarity in 2024.
Brennon O’Callaghan, Fish Lake – Good activity on the lake this summer. FLARA
completed their channel dredging project and their goose removal project.
Joe Ruegsegger, At Large – Fish lake is quieting down with some boats and docks
still in place. Attended Metro Blooms shoreline restoration workshop with several
residents.
Derek Asche, Water Resources Engineer – Alum treatment of Eagle and Pike lakes
is on schedule.
INDIVIDUAL LAKE Asche presented an individual lake improvement grant request from Mr. Tim
IMPROVEMENT Johnson on Eagle Lake. The project consists of shoreline repair by replacing a timber
PROJECT retaining wall with fieldstone boulders. After discussion, LQC recommended staff
APPLICATION - develop a priority system for individual project applications.
JOHNSON
MOTION TO APPROVE by Fahrenbruch, second by Bergstrand. With all in favor the
motion was APPROVED.
LAKE Asche introduced the lake regulations item noting that the City has received
REGULATIONS & numerous concerns from lakeshore owners regarding the various regulations on
2025 WORK PLAN area lakes. Concerns include but are not limited to no-wake times, impact of waves
on shoreline from wake surfing boats, and enforcement of existing regulations.
City code on lake regulations was initially established in 1984 with updates in 2005
and 2009. Lake use changes over time and Asche noted that periodic review of lake
regulations has been done in the past.
After discussion, LQC suggested lake regulation updates should start in January 2025
in case there is a need for updates prior to the 2025 boating season.
MOTION TO APPROVE by O’Callaghan, second by Fahrenbruch. With all in favor
the motion was APPROVED.
INFORMATIONAL Asche reported that street sweeping had been completed citywide. The sweeping
ITEMS took 414 hours and picked-up over 400 cubic yards of material.
FUTURE November 20, 2024
MEETING:
ADJOURNMENT Meeting adjourned at 7:23 pm.