City Council Meeting
Regular MeetingMarshall, MN · September 14, 2021
Minutes
CITY OF MARSHALL
CITY COUNCIL MEETING
MINUTES
Tuesday, September 14, 2021
The regular meeting of the Common Council of the City of Marshall was held September 14, 2021, at City Hall,
344 West Main Street. The meeting was called to order at 5:30 P.M. by Mayor Robert Byrnes. In addition to
Byrnes the following members were in attendance: Craig Schafer, Steve Meister, Don Edblom, John DeCramer,
Russ Labat and James Lozinski. Absent: None. Staff present included: Sharon Hanson, City Administrator;
Dennis Simpson, City Attorney; Jason Anderson, Director of Public Works/ City Engineer; Annette Storm,
Director of Administrative Services; Jim Marshall; Director of Public Safety; and Kyle Box, City Clerk.
The Pledge of Allegiance was recited at this time.
There was a general consensus to operate under the current agenda.
MMUA Award
The CEO of Minnesota Municipal Utilities Association Jack Kegel and Marshall Municipal Utilities General
Manager David Sch provided the MMUA Community Services Award to Councilmember John DeCramer in
recognition of long and outstanding service to his community and his support to municipal utilities.
Consider approval of the minutes from the regular meeting held on August 24, and from a work session held
on August 25, 2021.
Motion made by Councilmember Lozinski, Seconded by Councilmember Labat That the minutes from the
regular meeting held on August 24, and from a work session held on August 25, 2021, be approved as filed
with each member and that the reading of the same be waived. Voting Yea: Mayor Byrnes, Councilmember
Schafer, Councilmember Meister, Councilmember Edblom, Councilmember DeCramer, Councilmember Labat,
Councilmember Lozinski. The motion Carried. 7-0
Project Z75/SAP 139-124-004: South 4th Street Reconstruction Project --1) Public Hearing on Assessment;
2) Consider Resolution Adopting Assessment.
This project consisted of the following: reconstruction and utility replacement on South 4 th Street from the
intersection of Elaine Avenue and South 4th Street to the intersection of Country Club Drive and South 4 th
Street. Utility work included sanitary sewer, watermain, and storm sewer replacement. This project also
included new curb and gutter, new 5-ft. sidewalk on the west side of the street, driveway aprons, water
services, and sewer services to the right-of-way.
The following is a breakdown of the proposed project funding. The costs shown below include 16% for
engineering and administrative costs, for a total project cost of $2,968,379.94. The following is a proposed
breakdown of the project funding:
Wastewater Fund $594,332
MMU $784,329
Surface Water Management Utility $731,750
Mn/DOT $135,038
City Participation (MSAS) $514,578
Assessed to Property Owners $343,391
Total Project Amount $2,968,380
City Council Meeting September 14, 2021 Minutes
Page 2 of 14
Per the current Fee Schedule, the assessment interest rate is calculated using the most recent bond interest
rate and adding 2% for administrative costs.
The 2020 GO Bond interest rate was 0.84% plus 2% results in a 2.84% assessment interest rate. The term of
the assessment repayment is proposed by staff to be 8 years. The City has no formal written policy on the
term but has followed an administrative past practice to generally match the assessment repayment to the
bond repayment term assuming a typical reconstruction project with assessments reaching near the maximum
of the residential assessment rate. If the assessment is substantially higher in cases such as commercial
assessments the term may be appropriate to increase. Alternatively, on smaller assessment projects
consideration could be made to shorten the assessment term. One other item to note is that if additional
principal is paid each year the interest is recalculated annually to address the payments. Therefore, there is no
penalty for individuals to repay on a more accelerated schedule if they so choose.
Director of Public Works/ City Engineer Jason Anderson provided the background information on the agenda
item.
Jordan Carstensen, 801 4th St. South, discussed how the project effected his property specific to his driveway.
Mr. Carstensen commented that there are water drainage issues with the driveway that was poured and that
he will need to replace the driveway apron and the remainder of the driveway in order to correct the work
that has been done with the information that was provided by the city.
Linda McGrath, 401 Kathryn Ave, commented that she never received a letter about the project and was
surprised about the amount she received for her assessment. Ms. McGrath commented that the amount being
assessed is a lot for a property owner to pay. Ms. McGrath’s daughter, who now lives in the house described
that they previously had water issues and now their basement bathroom is no longer usable.
City Attorney Dennis Simpson discussed the differed option requires for the property needs to be the
homestead of the property owner.
Director of Public Works/ City Engineer commented that the sanitary sewer line was not replaced at this
property and that every property owner effected did receive a letter at the beginning on the project.
Councilmember Lozinski commented on the look back period regarding surrounding assessments.
Councilmember Meister clarified that notices were sent out to property owners.
Councilmember Labat clarified that both public informational meetings were held at MMU.
Motion made by Councilmember Schafer, Seconded by Councilmember Lozinski that the Council close the
public hearing on assessments for Project Z75/SAP 139- 124-004: South 4th Street Reconstruction Project.
Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember Meister, Councilmember Edblom,
Councilmember DeCramer, Councilmember Labat, Councilmember Lozinski. The motion Carried. 7-0
City Council Meeting September 14, 2021 Minutes
Page 3 of 14
Motion made by Councilmember Schafer, Seconded by Councilmember DeCramer that the Council adopt
RESOLUTION NUMBER 21-066, which is the “Resolution Adopting Assessment” for Project Z75/SAP 139-124-
004: South 4th Street Reconstruction Project. Voting Yea: Mayor Byrnes, Councilmember Schafer,
Councilmember Edblom, Councilmember DeCramer, Councilmember Lozinski. Voting Nay: Councilmember
Meister, Councilmember Labat. The motion Passed. 5-2
Project Z76: South 1st Street Reconstruction Project --1) Public Hearing on Assessment; 2) Consider Resolution
Adopting Assessment.
This project consisted of reconstruction and utility replacement on South 1st Street generally between
Southview Drive and George Street. Water, sanitary sewer, and storm sewer catch basins were replaced along
South 1st Street in this area. Sidewalk was added along the west side of the street to provide connection to
existing sidewalk north of the project area on South 1st Street and existing sidewalk at Southview Drive. This
project also included new curb and gutter, driveway aprons, and water services. In addition to the utility
replacement and street reconstruction on South 1st Street, sanitary sewer force main improvements were
made at the intersection of South 1st Street and DeSchepper Street.
The following is a breakdown of the proposed project funding. The costs shown below include 16% for
engineering and administrative costs, for a total project cost of $730,539.96. The following is a proposed
breakdown of the project funding:
Wastewater Fund $164,077
MMU $213,293
Surface Water Management Utility $73,850
City Participation (Ad Valorem) $170,292
Assessed to Property Owners $109,028
Total Project Amount $730,540
Per the current Fee Schedule, the assessment interest rate is calculated using the most recent bond interest
rate and adding 2% for administrative costs. The 2020 GO Bond interest rate was 0.84% plus 2% results in a
2.84% assessment interest rate.
The term of the assessment repayment is proposed by staff to be 8 years. The City has no formal written
policy on the term but has followed an administrative past practice to generally match the assessment
repayment to the bond repayment term assuming a typical reconstruction project with assessments reaching
near the maximum of the residential assessment rate. If the assessment is substantially higher in cases such as
commercial assessments the term may be appropriate to increase. Alternatively, on smaller assessment
projects consideration could be made to shorten the assessment term. One other item to note is that if
additional principal is paid each year the interest is recalculated annually to address the payments. Therefore,
there is no penalty for individuals to repay on a more accelerated schedule if they so choose.
Director of Public Works/ City Engineer Jason Anderson provided the background information on the agenda
item.
Ben Walker, 609 1st St. South, asked for clarification on how residents in the project area are assessed, why
residents receive different amounts, and if the maximum assessed amount is $5,700 for a property why are
some amounts more. Mr. Walker asked why residents of the previous project were asked to pay for 11% of
City Council Meeting September 14, 2021 Minutes
Page 4 of 14
the project while residents of this project are being asked to pay for 14.9% of the project. Mr. Walker
commented that this is a lot of money to ask of people.
Edward Carberry, 700 1st St. South, commented on the overall project and his opposition towards it. Mr.
Carberry commented on the grass that was planted and if he could replant wildflowers that were previously
there. Mr. Carberry asked for clarification of the cost breakdown and why it states $0 for sidewalk and if that
means it’s the responsibility of the property owner to pay those costs. Mr. Carberry also discussed the
maximum amount and asked for an explanation on why his is over the stated $5,700 amount. Mr. Carberry
also asked for clarification on how deferment works.
Councilmember Meister commented that the grass needs to be reworked and placed back in the condition it
was.
Director of Public Works/ City Engineer discussed how special assessments are calculated per property.
City Attorney Dennis Simpson discussed how the maximum special assessment amount was set by the district
court.
Director Anderson commented that he will follow through with the project manager to make sure the grass is
reseeded. Director Anderson also discussed on the precents assessed for each project and that every project is
different depending on state aid and utility involvement.
Mr. Walker followed up by asking if the city chooses to assess the amounts received by property owners.
Director Anderson commented that assessments are calculated by a formula approved by the council. Mr.
Walker asked if the amount was negotiable or not.
Director Anderson commented that the formula used for each project are the same but the total amounts for
each project will change depending on certain factors.
Councilmember Meister commented on special assessments and if the council should choose to switch over to
include project costs to ad valorem.
Motion made by Councilmember Schafer, Seconded by Councilmember Lozinski that the Council close the
public hearing on assessments for Project Z76: South 1st Street Reconstruction Project. Voting Yea: Mayor
Byrnes, Councilmember Schafer, Councilmember Meister, Councilmember Edblom, Councilmember
DeCramer, Councilmember Labat, Councilmember Lozinski. The motion Carried. 7-0
Motion made by Councilmember DeCramer, Seconded by Councilmember Schafer that the Council adopt
RESOLUTION NUMBER 21-067, which is the “Resolution Adopting Assessment” for Project Z76: South 1st
Street Reconstruction Project. Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember Edblom,
Councilmember DeCramer, Councilmember Lozinski. Voting Nay: Councilmember Meister, Councilmember
Labat. The motion Passed. 5-2
Ice and Snow Removal and Weed Elimination from Private Property in the City of Marshall. 1) Conduct a
Public Hearing. 2) Consider a Resolution Adopting the Assessment.
City Council Meeting September 14, 2021 Minutes
Page 5 of 14
City shall conduct public hearing to consider approving of special assessment to be levied against City property
to allow for collection of costs incurred by the City to remove ice and snow and to mow lawns-eliminate
weeds on private property. Minnesota Statutes Chapter 429.101 does set forth the various types of City
charges that can be assessed against property taxes pursuant to the special assessment process. Minnesota
Statutes §429.101 subd. 1(1) indicates that snow, ice, or rubbish removal from sidewalks may be assessed
against property owners. §429.101 subd. 1(2) indicates that “weed elimination from streets or private
property” may be assessed against property owners.
The procedure by which those types of costs incurred by the City may be assessed against private property
owners is outlined in Minnesota Statute §429.061 and procedures further outlined in a Minnesota Court of
Appeals decision Sykes v. Rochester City Council Court of Appeals case A13-2421. The Sykes decision does
require full compliance with §429.061, when levying those costs as assessments against private property.
§429.061 does require public hearing to be held before those amounts can be assessed.
The City Council has previously passed a resolution declaring the costs to be assessed as required by
Minnesota Statute §429.061 and further that a second resolution has been passed calling for a public hearing
regarding those costs to be assessed. Notice of public hearing has been sent to property owners and has been
published in the Marshal Independent as required by Statute. Public hearing is to be held as scheduled.
The City has incurred the costs for ice and snow removal, lawn mowing and weed elimination as set forth in
the attached resolution. Approval of the resolution will allow for the City to recover its out-of-pocket costs.
Motion made by Councilmember Meister, Seconded by Councilmember Labat that the Council close the public
hearing on assessments for ice and snow removal and for weed elimination from private property in the City
of Marshall. Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember Meister, Councilmember
Edblom, Councilmember DeCramer. The motion Carried. 7-0
Motion made by Councilmember Meister, Seconded by Councilmember DeCramer that the Council adopt
Resolution Number 21-068, which is the “Resolution Adopting Assessment” for ice and snow removal and for
weed elimination from private property in the City of Marshall. Voting Yea: Mayor Byrnes, Councilmember
Schafer, Councilmember Meister, Councilmember Edblom, Councilmember DeCramer, Councilmember Labat,
Councilmember Lozinski. The motion Carried. 7-0
306 Athens Ave.– 1) Public Hearing regarding a home property tax abatement request 2) Consideration of a
resolution approving home property tax abatement.
On August 24, 2021, a public hearing was called for and to be held on September 14, 2021 regarding a home
property tax abatement request. Per M.S 469.1813 sub 5 The governing body of the political subdivision may
approve an abatement under sections 469.1812 to 469.1815 only after holding a public hearing on the
abatement. The property is located at 306 Athens Ave. with an estimated market value of $203,200 and with
the difference of improvement being $191,400.
The approximate amount of assistance is $1,056.00 a year or $2,112.00 over a maximum period of 2 years as a
Homestead.
City Council Meeting September 14, 2021 Minutes
Page 6 of 14
Motion made by Councilmember Schafer, Seconded by Councilmember DeCramer to close the public hearing.
Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember Meister, Councilmember Edblom,
Councilmember DeCramer, Councilmember Labat. Voting Abstaining: Councilmember Lozinski. The motion
Passed. 6-0-1
Motion made by Councilmember Schafer, Seconded by Councilmember DeCramer to approve Resolution
Number 21-069, a resolution approving home property tax abatement. Voting Yea: Mayor Byrnes,
Councilmember Schafer, Councilmember Meister, Councilmember Edblom, Councilmember DeCramer,
Councilmember Labat
Voting Abstaining: Councilmember Lozinski. The motion Passed. 6-0-1
Consider Approval of the Consent Agenda.
Motion made by Councilmember Schafer, Seconded by Councilmember Edblom.
Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember Meister, Councilmember Edblom,
Councilmember DeCramer, Councilmember Labat, Councilmember Lozinski
Approval of Resolution Number 21-070, a Resolution Accepting the Coronavirus Local Fiscal Recovery Funds
Approval of an amendment to the Personnel Policy Manual--Appendix B--Maximum Allowable
Reimbursement/Per Diem Rates
Approval for the Wastewater Treatment Facilities Improvement Project – 1) Consider Application for Payment
No. 26 to Magney Construction, Inc.; 2) Consider Payment of Invoice 0274632 to Bolton & Menk, Inc.
Approval for Project ST-022: Bruce Street Gravel Resurfacing Project – Consider Authorization to Receive
Quotes.
Approval for a Quit Claim Deed – Out lot B, Carr Subdivision I.
Approval of a Room Rental Policy.
Approval to authorize to declare vehicles as surplus property for the Marshall Police Department.
Approval of Resolution Number 21-071, a Resolution Authorizing Transfer of Funds from Fund 609 to Capital
Project Fund 401
Approval of Resolution Number 21-072, a Resolution Designating Uniform Election Dates and Polling
Locations.
Approval of Resolution Number 21-073 a Resolution Approving the MERIT Center Bonding Request
Approval of the bills/project payments
Project SWM-007: Independence Park Pond Forebay Expansion Project – Consider Authorization to Advertise
for Bids.
City Council Meeting September 14, 2021 Minutes
Page 7 of 14
The shared use trail system located in Independence Park has reached the end of its useful life and the City
would like to replace the majority of the park’s trail system, bringing it into compliance with the Americans
with Disabilities Act (ADA). A trails replacement project was awarded to A&C Excavating at the August 25,
2021, City Council Budget Work Session following Council action at the August 24, 2021 City Council meeting.
Further, City staff believes it would be prudent to complete an Independence Park Pond forebay expansion
project in coordination with the trail replacement project. The forebay expansion would create additional
pond storage volume in the park while also creating a ponding environment that promotes solids settlement
(stormwater treatment) within the forebay area with the goal of reducing future pond areas that will require
dredging. Coordinating this work with the trail replacement project helps to ensure that new trail is installed in
the proper location and investments into trail pavement and new culvert crossing are preserved.
At the August 10, 2021, City Council meeting the Council authorized staff to hire Bolton & Menk to complete
project plans for a pond forebay expansion project that will run concurrent with the park trails project that has
already been awarded.
Now, City staff is finalizing work with Bolton & Menk for final design plans for the forebay pond expansion
project. These plans are nearly completed, and staff is looking to prepare the contract for bid advertisement.
This memo is intended to introduce the project and authorize staff to advertise for bids. Staff is planning an
October 6th, 2021, bid opening date with an award recommendation to Council at the October 12th, 2021
meeting.
An estimated cost of $214,255 including contingency (10%) and engineering (16%) costs for this pond project.
The majority of project costs will be funded through the Surface Water Management Utility.
Motion made by Councilmember Schafer, Seconded by Councilmember DeCramer That the Council authorize
advertisement for bids for Project SWM-007: Independence Park Pond Forebay Expansion Project. Voting Yea:
Mayor Byrnes, Councilmember Schafer, Councilmember Edblom, Councilmember DeCramer. Voting Nay:
Councilmember Meister, Councilmember Labat, Councilmember Lozinski. The motion Passed. 4-3
Project Z87 - Diversion Channel Slope Repair and Sheet Piling Removal Project – Consider Award of Bid.
Motion made by Councilmember Lozinski, Seconded by Councilmember Schafer to remove from the table.
Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember Meister, Councilmember Edblom,
Councilmember DeCramer, Councilmember Labat, Councilmember Lozinski. The motion Carried. 7-0
This agenda item was tabled at the August 24, 2021, meeting to September 14, 2021 meeting. The following is
a summary of the unapproved minutes:
Motion made to award to R&G Construction Co. of Marshall, MN in the amount of $98,950.44 and
failed by a 3-3 vote.
Motion made to award to Towne & Country Excavating, LLC of Garvin, MN in the amount of $85,094.00
and failed by a 2-4 vote.
Motion made to table until the September 14, 2021, regular Council meeting and carried by a 6-0 vote.
The Redwood River Diversion Channel begins west of the Lyon County Public Works property at the diversion
structure east of County Road 7. Over the last several years, the channel bank has eroded significantly in
City Council Meeting September 14, 2021 Minutes
Page 8 of 14
several locations upstream of the drop structure north of Madrid Street. There are several locations where
sheet piling used for outfall installation was left in place. This sheet piling, along with numerous recent high-
water events, has contributed to the erosion of the diversion channel banks. The drainage ditches adjacent to
the diversion channel spill into the channel via flume channels. These flume channels have also exhibited
erosion and need repair.
City Engineering staff has identified a project to repair the severely eroded channel bank locations, remove
sheet piling, and repair flume channels and storm water pipe outfalls. Staff originally budgeted $155,000 in
the 2021 Capital Budget to perform repairs in the diversion channel.
At the July 27, 2021, meeting the City Council authorized staff to advertise for bids.
On August 18, 2021, bids were received for the above-referenced project. At the bid opening, it was noted
that our electronic bidding system indicated that three bids were completed, and those three bids were read
aloud. It was noted that R & G Construction of Marshall was the apparent low bidder with a bid of $98,950.44.
Following the bid opening, City staff identified that a fourth bid was submitted on time, but the bidder had not
acknowledged the third and last project addendum that was issued. Because the final addendum was not
acknowledged, our electronic bidding program identified the bid as being incomplete. Upon investigation,
staff realized that Towne & Country Excavating’s proposal was completed and submitted on Friday, August
13th. The third addendum was issued on Monday, August 16th. The electronic bidding program sends an e-
mail notification that an addendum is issued, but Towne & Country did not check e-mail or otherwise failed to
acknowledge the most recent addendum. Therefore, the program turned Towne & Country’s “completed”
submittal into an “incomplete” submittal. Towne & Country’s proposal was for $85,094.00 and the contractor
has notified staff that Addendum No. 3 does not impact their submittal.
The purpose of Addendum No. 3 was to notify all bidders of an alternative method of completing a portion of
the contract work. Staff determined the need to issue Addendum No. 3 because staff had authorized one
contractor that they may utilize an alternative method to complete work and it was important to issue
notification of the alternative method to all plan holders to help ensure that contractors are aware of all
construction methods available to them to give the City of Marshall the best possible price.
City staff has conferred with City legal staff regarding this situation. As is common in municipal bid
advertisements, the City’s advertisements contain the language that the City reserves the right to reject all
bids or waive informalities or irregularities. There are several court rulings that have established that a bidder
who has deviated from the specifications may still be awarded a contract if the deviation was a nonmaterial
deviation. A general rule is that a deviation is material if it gives a bidder a substantial advantage or benefit
over other bidders. Conversely, non-material deviations are those that are technical irregularities that do not
injure other bidders.
Reviewing Addendum No. 3, it is not requiring any additional information from bidders, it is not changing the
scope of work that is required to be completed, it is not changing project quantities, it does not contain a new
proposal sheet, it does not change the nature of work to be completed, and by City staff’s determination, it is
largely non-material in nature because it is a question and answer type of project addendum.
City Council Meeting September 14, 2021 Minutes
Page 9 of 14
To make an award recommendation in this instance, the City Council will need to make the determination of
whether the failed acknowledgement of Addendum No. 3 constitutes a material deviation.
Motion made by Councilmember Lozinski, Seconded by Councilmember DeCramer that the Council declare
the failed acknowledgement of Addendum No. 3 to be non-material in nature and authorize award of the
project to Towne & Country Excavating, LLC of Garvin, MN in the amount of $85,094.00. Voting Yea:
Councilmember Edblom, Councilmember DeCramer, Councilmember Lozinski. Voting Nay: Mayor Byrnes,
Councilmember Schafer, Councilmember Meister, Councilmember Labat. The motion Failed. 3-4
Motion made by Councilmember Labat, Seconded by Councilmember Schafer that the Council declare the
failed acknowledgement of Addendum No. 3 to be material in nature, reject the non-conforming apparent low
bid and authorize award of the project to the second low bid received from R&G Construction Co. of Marshall,
MN in the amount of $98,950.44. Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember
Meister, Councilmember Labat. Voting Nay: Councilmember Edblom, Councilmember DeCramer,
Councilmember Lozinski. The motion Passed. 4-3
Consider Resolution Approving the changes for the 2022 Fee Schedule
There are proposed changes/updates for the 2022 Fee Schedule. The Ways & Means Committee reviewed the
changes to the Fee Schedule at their meeting on August 25,2021. Ways & Means Committee are
recommending further Council discussion and approval of the changes/updates to the 2022 Fee Schedule. Per
the request of the Ways & Means Committee, the Special Assessment For Street Reconstruction has been
flagged for further discussion. As well as an additional comparison of the difference in a 1% increase in
Wastewater rates has been included in the packet.
Motion made by Councilmember Labat, Seconded by Councilmember Lozinski Approve Resolution Number 21-
074, a resolution approving specific fees to be charged by the City of Marshall. Voting Yea: Mayor Byrnes,
Councilmember Schafer, Councilmember Meister, Councilmember Edblom, Councilmember DeCramer,
Councilmember Labat, Councilmember Lozinski. The motion Carried. 7-0
Consider approval to enter into a fleet management program with Enterprise Fleet Management.
At the August 24, 2021, regular meeting Enterprise Fleet Management brough forward a proposal at the
request of council and staff to begin reviewing a fleet management program. After hearing the proposal
council requested that the program be reviewed by the Equipment Review Committee and the Ways and
Means Committee.
On September 9, 2021, both the Equipment Review and Ways and Means Committees met with staff and an
Enterprise representative to review the program. Both Committees unanimously approved the program to the
City Council for approval.
Included the in packet is an updated Fleet Planning Analysis. This analysis is a snapshot of our current fleet
under Enterprises recommended program. If the Council does approve the program Enterprise’s team will
begin to work with each department to determine their fleet needs. This will be an opportunity for staff to
analyze their own departments and vehicle needs and requirements.
City Council Meeting September 14, 2021 Minutes
Page 10 of 14
All final decisions within this program remain with the City. Enterprise will provide data driven information on
the best time to replace and cycle vehicles. If a vehicle is taken out of the cycle or kept longer then what is
recommended the numbers do change.
The City Attorney has reviewed the documents/ agreements provided by Enterprise.
Motion made by Councilmember Schafer, Seconded by Councilmember Lozinski to approve a fleet
management program with Enterprise Fleet Management. Voting Yea: Mayor Byrnes, Councilmember Schafer,
Councilmember Edblom, Councilmember DeCramer, Councilmember Labat, Councilmember Lozinski. Voting
Nay: Councilmember Meister. The motion Passed. 6-1
Preliminary Plat of Carr Subdivision III - Introduce Plat and Call for Public Hearing.
The final plat of Carr Subdivision I was approved by the City Council at its April 4, 2005, meeting. At the June
28, 2010, City Council meeting the plat was altered with the passing of Carr Subdivision II. Carr Subdivision II
consisted of a small portion of the southwest corner of Carr Subdivision I which included a portion of MnDOT
right-of way set aside for the future connection of Travis Road to MN 23. After discussions with MnDOT, the
City and Developer elected to eliminate the future access point to MN 23 and desired to alter the location of
Donald Drive and Travis Road.
Now, the developer wishes to combine and split lots to construct townhomes on the south side of Andrew
Street in a similar manner to those constructed on the north side. Because one of the lots is in Carr Subdivision
I and the other is in Carr Subdivision II, a platting process is required to adjust lot sizes for the construction of
townhomes. The area is zoned R-2 where townhomes are a permitted use. City staff has conferred with
Marshall Municipal Utilities regarding the placement of a new utility easement with this plat.
Attached please find a copy of the Preliminary Plat and the Engineer’s Report of Preliminary Plat Review.
Copies of the proposed subdivision have been sent to the local utility companies for their review and
comments.
The preliminary plat was presented at the Planning Commission meeting on September 8, 2021. Following
discussion, Schroeder made a motion, second by Muchlinski to recommend approval to City Council as
recommend by staff. Fox abstained from vote. All voted in favor.
Motion made by Councilmember Edblom, Seconded by Councilmember DeCramer that the Council call for
public hearing on the Preliminary Plat of Carr Subdivision III to be held at the September 28, 2021, City Council
meeting, as per the recommendation of the Planning Commission. Voting Yea: Mayor Byrnes, Councilmember
Schafer, Councilmember Meister, Councilmember Edblom, Councilmember DeCramer, Councilmember Labat,
Councilmember Lozinski. The motion Carried. 7-0
Approve Change Order-City Hall Project
The City Hall Committee has reviewed several times Change Order 14. There have been three versions with
the attached the final version. Chairman Lozinski had indicated his support to submit to City Council for their
consideration and approval this Change Order if significant progress has been made on remaining items for
City Hall. This past week, significant progress has been made.
City Council Meeting September 14, 2021 Minutes
Page 11 of 14
Motion made by Councilmember Lozinski, Seconded by Councilmember Schafer Approve Change Order 14 in
the amount of $11,969.00. Voting Yea: Mayor Byrnes, Councilmember Schafer, Councilmember Edblom,
Councilmember DeCramer, Councilmember Lozinski. Voting Nay: Councilmember Meister, Councilmember
Labat. The motion Passed. 5-2
Authorization to use excess Public Facilities Authority loan funds for select equipment repairs at the
Wastewater Facility.
The Wastewater Treatment Facility is just completing a large improvement project. The City used a Public
Facilities Authority (PFA) low interest loan to finance the project. The project will be finishing up about
$30,000 under budget, and we have a few items that need to be replaced in the very near future that were
not part of the original improvement project. City staff believes that this would be a good time to address
these items versus budgeting for them in the future to take advantage of the low interest rate offered by the
PFA loan. There are excess funds still available in the loan for qualifying small purchases associated with the
project.
Wastewater Department staff have received quotes for additional repairs that total about $47,000. The items
are as follows: a roof top air conditioning unit for the Control Room, replacement of the Federal Pacific service
panel in the shop, replacement of a soft start controller for our sludge mixing pump, and update VFD controls
for our ATAD Digester. These items would be done outside of the contract with Magney Construction. We
have verified with MPCA that these items do qualify for the loan funds.
Motion made by Councilmember Schafer, Seconded by Councilmember Meister that the Council authorize the
additional equipment repairs of nearly $47,000 utilizing the low interest PFA loan. Voting Yea: Mayor Byrnes,
Councilmember Schafer, Councilmember Meister, Councilmember Edblom, Councilmember DeCramer,
Councilmember Labat, Councilmember Lozinski. The motion Carried. 7-0
Consider Resolution Adopting Preliminary Levy for 2022
At the August 25th work session, staff proposed a levy increase of $730,709 or 10.07%. The main contributing
factors for this increase are an increase levy item for street mill and overlays, increased salaries, an additional
street employee and heath care costs.
Staff have been directed by the Council to reduce this increase for the preliminary levy to 6.0- 7.0%. All cities
must adopt proposed budget by resolution and certify proposed tax levy to the county auditor on or before
September 30th.
Final levies may be lower than the proposed levy but may not exceed the proposed levy that is adopted in
September.
Staff is recommending a 2022 preliminary levy increase of $435,093 or 6.0%.
The proposed 2022 preliminary general fund budget currently has a deficit of 287,267.29. Of this amount
140,000 is planned use of reserves on one-time expenditures. The remaining amount is due to an additional
street employee and unknown health insurance costs – which are being budgeted at a 9% increase from 2021.
This amount will not be known until October 1st and will be adjusted for the final budget approval in
December.
City Council Meeting September 14, 2021 Minutes
Page 12 of 14
The City Council is required to hold a public meeting for the proposed levy and certify to the County Auditor
the date, location and start time at the same time the proposed levy is certified. Currently in the resolution
this date is being proposed Tuesday, December 14th at 6:00pm located at City Hall.
Motion made by Councilmember Schafer, Seconded by Councilmember DeCramer Approve Resolution
Number 21-075, a Resolution Adopting Preliminary Levy for 2022. Voting Yea: Mayor Byrnes, Councilmember
Schafer, Councilmember Meister, Councilmember Edblom, Councilmember DeCramer, Councilmember
Lozinski. Voting Nay: Councilmember Labat. The motion Passed. 6-1
Commission/Board Liaison Reports
Byrnes Southwest Regional Development Commission met and revised the personnel policy.
Schafer No Report
Meister No Report
Edblom Public Housing Commission met to welcome a new member and are finalizing summer projects.
Planning Commission met to begin the discussion on the Comprehensive Plan and the
importance of the Commissions involvement.
DeCramer Diversity, Equity, and Inclusion Commission continues to prepare for the Welcoming Week
event on September 18 at the YMCA. The Commission also has created a subcommittee to
handle communications that would be sent out to the community.
Labat Library Board met to review its reopening schedule at the Marshall and Lyon County branches.
The Friends of the Foundation raised $3,400 during a book sale during Sounds of Summer. Plum
Creek will select a new Director for the position prior to the end of the year.
Lozinski No Report
Councilmember Individual Items
Councilmember Lozinski commented that if he receives any anonymous letters that he does not read them,
and they are shredded. He requested that if a resident of Marshall wishes to speak with him that they are to
sign their letters.
Councilmember Labat commented on the striping of the lanes near Southview.
Councilmember Meister discussed a complaint he received regarding new installation of sidewalks. Member
Meister also discussed that it was reported to him that sidewalks are being taken out.
Mayor Byrnes commented on the 9/11 20th anniversary event and thanked Councilmember Schafer for
speaking at the anniversary event. Mayor Byrnes also discussed the initial results of the 2020 Census and
compared population and housing additions throughout Marshall’s three Wards.
City Council Meeting September 14, 2021 Minutes
Page 13 of 14
Mayor Byrnes also discussed the 13.7% sales tax increase from May 2020 to May 2021.
Councilmember Schafer commented on the 9/11 20th anniversary and thanked Public Safety Director Jim
Marshall and his staff for putting together the event.
City Administrator
City Administrator Sharon Hanson commented that she will step more into the EDA role while the currently
Director is on leave and provided an update on ongoing EDA projects. Administrator Hanson also discussed the
community survey and that it would be expanding into other parks and recreation projects, rather than just
the aquatic center.
Director of Public Works
Director of Public Works/ City Engineer Jason Anderson provided project updates happening throughout the
city including the Army Corps. of Engineer levy project, James/ Camden/ N. 1 st Street reconstruction project
and the State aid overlay project. The parks trail project will begin in the near future.
Director of Public Works/ City Engineer commented on the photos provided by Councilmember Meister and
that the project is not yet complete, and that additional grading work and seeding will still occur. Director
Anderson also address that some duplicated sidewalk ramp crossings were removed in uncontrolled
intersections.
City Attorney
City Attorney Dennis Simpson provided discussion that the MAHA agreement was reviewed the MAHA board
and will be brought back to the Council in the near future. The council approved the purchase of land at 800
North Hwy 59, Marshall is waiting on title and plat work to be completed. Broadmoor Valley abatement order
for four properties has been served.
Information Only
There were no questions on the information items.
Administrative Brief
There were no questions on the administrative brief.
Upcoming Meetings
There were no questions on the upcoming meetings.
City Council Meeting September 14, 2021 Minutes
Page 14 of 14
Adjourn
Motion made by Councilmember Meister, Seconded by Councilmember Lozinski to adjourn. Voting Yea:
Mayor Byrnes, Councilmember Schafer, Councilmember Meister, Councilmember Edblom, Councilmember
DeCramer, Councilmember Labat, Councilmember Lozinski. The motion Carried. 7-0
Mayor
Attest:
City Clerk
Agenda
CITY OF MARSHALL
City Council Meeting
Agenda
Tuesday, September 14, 2021 at 5:30 PM
City Hall, 344 West Main Street
OPENING ITEMS
1. MMUA Award
APPROVAL OF AGENDA
APPROVAL OF MINUTES
2. Consider approval of the minutes from the regular meeting held on August 24, and from a work session
held on August 25, 2021.
PUBLIC HEARING
3. Project Z75/SAP 139-124-004: South 4th Street Reconstruction Project --1) Public Hearing on
Assessment; 2) Consider Resolution Adopting Assessment.
4. Project Z76: South 1st Street Reconstruction Project --1) Public Hearing on Assessment; 2) Consider
Resolution Adopting Assessment.
5. Ice and Snow Removal and Weed Elimination from Private Property in the City of Marshall. 1) Conduct
a Public Hearing. 2) Consider a Resolution Adopting the Assessment.
6. 306 Athens Ave.– 1) Public Hearing regarding a home property tax abatement request 2) Consideration
of a resolution approving home property tax abatement.
CONSENT AGENDA
7. Consider Resolution Accepting the Coronavirus Local Fiscal Recovery Funds.
8. Consider approval of an amendment to the Personnel Policy Manual--Appendix B--Maximum Allowable
Reimbursement/Per Diem Rates.
9. Wastewater Treatment Facilities Improvement Project – 1) Consider Application for Payment No. 26
to Magney Construction, Inc.; 2) Consider Payment of Invoice 0274632 to Bolton & Menk, Inc.
10. Project ST-022: Bruce Street Gravel Resurfacing Project – Consider Authorization to Receive Quotes.
11. Project SWM-007: Independence Park Pond Forebay Expansion Project – Consider Authorization to
Advertise for Bids.
12. Quit Claim Deed – Outlot B, Carr Subdivision I.
13. Consider Approval of a Room Rental Policy.
14. Consider authorization to declare vehicles as surplus property for the Marshall Police Department.
15. Consider Resolution Authorizing Transfer of Funds from Fund 609 to Capital Project Fund 401.
16. Consider a Resolution Designating Uniform Election Dates and Polling Locations.
17. MERIT Center Bonding Request.
18. Consider approval of the bills/project payments.
APPROVAL OF ITEMS PULLED FROM CONSENT
TABLED ITEM
19. Project Z87 - Diversion Channel Slope Repair and Sheet Piling Removal Project – Consider Award of Bid.
NEW BUSINESS
20. Consider Resolution Approving the changes for the 2022 Fee Schedule.
21. Consider approval to enter into a fleet management program with Enterprise Fleet Management.
22. Preliminary Plat of Carr Subdivision III - Introduce Plat and Call for Public Hearing.
23. Approve Change Order-City Hall Project.
Disclaimer: These agendas have been prepared to provide information regarding an upcoming meeting of the
Common Council of the City of Marshall. This document does not claim to be complete and is subject to change.
City Council Meeting September 14, 2021 Agenda
Page 2 of 2
24. Authorization to use excess Public Facilities Authority loan funds for select equipment repairs at the
Wastewater Facility.
25. Consider Resolution Adopting Preliminary Levy for 2022.
COUNCIL REPORTS
26. Commission/Board Liaison Reports
27. Councilmember Individual Items
STAFF REPORTS
28. City Administrator
29. Director of Public Works
30. City Attorney
ADMINISTRATIVE REPORTS
31. Administrative Brief
INFORMATION ONLY
32. Information Only
MEETINGS
33. Upcoming Meetings
ADJOURN
Disclaimer: These agendas have been prepared to provide information regarding an upcoming meeting of the
Common Council of the City of Marshall. This document does not claim to be complete and is subject to change.
Get email alerts for Marshall
A daily email when new agendas and minutes are posted.