Public Improvement & Transportation Committee
Regular MeetingMarshall, MN · June 10, 2025
Minutes
MINUTES
PUBLIC IMPROVEMENT/TRANSPORTATION COMMITTEE MEETING
JUNE 10, 2025
3:15 PM
MEMBERS PRESENT: Craig Schafer, James Lozinski, John Alcorn
MEMBERS ABSENT: None
STAFF PRESENT: Jason Anderson, Director of Public Works/City Engineer; Eric Hanson, Assistant City
Engineer; Geoff Stelter, Senior Engineering Specialist; E.J. Moberg, Director of
Administrative Services
OTHERS PRESENT: None
Call to Order
Schafer called the meeting to order at 3:26 pm.
1. Approval of Minutes
MOTION MADE BY Schafer to approve the minutes of the March 25, 2025 meeting as presented, SECOND BY Alcorn.
ALL VOTED IN FAVOR. THE MOTION PASSED 2:0.
Lozinski joined the meeting at 3:28 pm.
2. Project ST-014 (139-122-009/139-124-005): S 4th & Country Club Intersection Reconfiguration and
Reconstruction
The S 4th Street and Country Club Drive intersection currently operates under traffic signal control today. The traffic
signal was installed in 1983 and it is well out of compliance with current accessibility standards. The skew angle at
this intersection creates a safety hazard for both motorized travelers and pedestrians. Both S. 4th Street and Country
Club Drive are Municipal State Aid Street (MSAS) routes. The City of Marshall receives a significant amount of
funding for the maintenance and improvement of MSAS routes. With this funding, there is also a mandate from
MnDOT that engineering standards are complied with and MSAS rules are followed to both utilize the funds for
improvements and continue to draw “needs” that result in MSAS fund disbursement. With these considerations in
mind and understanding that an improvement needs to be made at this intersection to ensure compliance with
current standards, engineering staff received Council support to solicit proposals for an Intersection Control
Evaluation (ICE) at the January 26, 2021 meeting. At the February 23, 2021 meeting, the City selected Short Elliot
Hendrickson (SEH) to perform the ICE and generate the report. Following a July 6, 2021 PI/T meeting, the City
Council accepted the ICE report at their July 13, 2021 meeting and recommended drawing 3 or 5 for the intersection.
Following this Council meeting, city staff hosted adjacent property owners for an informational session on August 9,
2021 to present the proposed changes and seek input. This project is currently identified in our 2027 CIP. City
engineering staff has garnered two federal LRBP grants that total $824,000 for this project. Additional project
funding will come from the water, sewer, and stormwater utility for utility work on South 4 th Street, and MSAS
funding for all remaining costs. Prior conversations with Council and property owners have promoted Layout 5, and
staff believes that there was support for layout 5 back in 2021. With the project nearing, we’d like to re-confirm
layout 5 or hear input otherwise. Staff will likely request to hire a consultant to aid in project design and permitting
for this project, and with the federal standards and process, we’d like to begin work soon.
MOTION MADE BY LOZINSKI to recommend Layout 5 to the City Council, with a mini roundabout to the west and
a ¾-intersection to the east, SECOND BY ALCORN. ALL VOTED IN FAVOR. THE MOTION PASSED 3:0.
3. CIP Review
Projects are identified for reconstruction and placement into our CIP based primarily on utility replacement needs.
Additionally, street and sidewalk age are considered and factored into staff review. Included with the CIP is a list of
streets that are likely candidates for a mill and overlay surface treatment over the next 5 years. These are streets
PI/T – 06/10/2025
-1-
that staff believe will not require utility work within the next 10-15 years, but the age and condition of the street
warrants a surface replacement. Staff estimates that a typical street reconstruction costs roughly $2.75M/mile, and
this cost does not include storm sewer, water, street lighting, and sanitary sewer utilities. With all utilities, the cost
can push $5M/mile. The actual cost varies based on street size, street section, number and width of
driveways/sidewalk, size and quantity of utilities, etc. Additional treatments have a lesser cost. Mill and overlay
costs roughly $300,000/mile for a 1.5” treatment with edge milling and no ADA sidewalk work included. A chip seal
is roughly $40,000/mile on a typical Marshall street. These treatments are cost-effective measures to help sustain
our system, but you cannot chip seal and overlay forever. A typical bituminous street may last 20-25 years when
new and we may get away resurfacing the street 2 to 3 times over its life. But at some point, the bottom layer(s) of
bituminous will degrade to a point where it is no longer effective to overlay the street, and the surface will just not
last as long as it should. With over 80 miles of local streets, many with utilities beneath them, it is important that
we continue to make incremental investments in maintaining and replacing our critical assets.
Informational/input only-no formal voting action taken on this item.
Other Business
None.
Adjourn
Being no further business, MOTION BY LOZINSKI, SECOND BY SCHAFER to adjourn. ALL VOTED IN FAVOR. THE
MOTION PASSED 3:0. Meeting adjourned at 4:28 p.m.
Respectfully submitted,
Lona Rae Konold, Administrative Assistant
PI/T – 06/10/2025
-2-
Agenda
CITY OF MARSHALL
Public Improvement & Transportation
Committee
Agenda
Tuesday, June 10, 2025 at 3:15 PM
City Hall, 344 West Main Street
APPROVAL OF AGENDA
APPROVAL OF MINUTES
1. Consider Approval of the Minutes
NEW BUSINESS
2. Project ST-014 (139-122-009/139-124-005): S 4th & Country Club Intersection Reconfiguration and
Reconstruction
3. CIP Review
OTHER BUSINESS ITEMS
ADJOURN
Disclaimer: These agendas have been prepared to provide information regarding an upcoming meeting of the
Common Council of the City of Marshall. This document does not claim to be complete and is subject to change.