Massena Electric Department
Regular MeetingMassena, NY · April 20, 2023
Minutes
Pending Approval by the MEUB
MASSENA ELECTRIC UTILITY BOARD
MINUTES of Thursday, April 20, 2023
Town of Massena Electric Department – 71 East Hatfield Street
Present:
James Shaw Andrew McMahon, Superintendent
Charles Raiti Jeffrey Dobbins, Treasurer
Richard Maginn Matt Gray, Deputy Superintendent
John Bogosian Margo Rochefort, Deputy Treasurer
Rene Hart Patrick Facteau, Town Liaison
Eric Gustafson, Attorney Debra Willer, Town Liaison
David Grant, Public
Chairman Shaw opened the meeting at 1:03 p.m.
1) APPROVAL OF MINUTES:
RESOLUTION:
The Massena Electric Utility Board hereby approves the minutes of the regular meeting
of March 23, 2023 as presented.
Moved by John Bogosian - Seconded by Charles Raiti - All in Favor
RESOLUTION:
The Massena Electric Utility Board hereby approves the minutes of the special meeting
of April 6, 2023 as presented.
Moved by Charles Raiti - Seconded by John Bogosian - All in Favor
2) OPERATIONS UPDATE: by Matt Gray, Deputy Superintendent
A. Safety: MED has not had a lost time injury since June 8th. The number of consecutive days
without a lost time accident now stands at 296 days.
There were no reportable injuries in March. This brings the number of days without a reportable
injury to 659 days.
Members of the Line Crew attended a training seminar presented By Lou Gabrielle with NEPPA
on such topics as wire pulling and conductor sag best methods.
B. Customer Impact Chart: MED experienced a comparatively low amount of Customer Impact
Minutes in the month of March with only 512 minutes recorded. The largest Customer Impact
was the result of an animal contact at transformer. With the low amount of Customer Impact
minutes recorded in March, the 12-month average has decreased slightly and is now 33,941.
C. Reliability: MED Crews responded to only six calls during the month of March. One call
affected no Customers and was the result of a hit pole, four calls affected one Customer and one
call affected more than one Customer. Of the calls received two calls contributed to our monthly
CIM total.
Pending Approval by the MEUB
The largest Customer impact was the previously mentioned animal contact at a transformer on
State Highway 56 that affected 10 Customers for fifty minutes. The second CIM event was the
result of a squirrel contact at a transformer feeding a single home. Fortunately, there were crews
working in the area and the Customer was affected for only twelve minutes.
D. Work Schedule: Crews are addressing issues found as a result of the winter storms that we
have experienced over the last few months. They have been installing anchors, straightening
poles, and completing follow-up service work.
Crews continue to address areas where conductor sag needs to be adjusted. This issue was
brought to light during the wind and snowstorms that occurred over the previous winter season.
This scope of work will require some time to complete and will serve as fill-in work over the
coming months.
3) FINANCIAL REPORTS: by Jeffrey Dobbins, Treasurer
A. Write-Offs:
RESOLUTION:
The Massena Electric Utility Board hereby authorizes the write-off of bad debt
totaling $5,519.43 as audited by Mr. Rene Hart.
Moved by Rene Hart - Seconded by John Bogosian - All in Favor
B. Power Comparison Graph: Power cost were over $531,000, down considerably compared to
March 2022 and last month. Supplemental power costs were just $111,500, down from
$338,500 in March. 2022. Lower than normal peak resulted in less incremental energy
purchased during the month. 6,900 MWh of incremental energy purchased during Mar 2023
compared to 10,675 March 2022. Zone D Average Energy rate was also lower at $16.20/MWh.
Impact to customers – Base PPAC for April of 0.63¢/kWh, Supplemental PPAC of 0.68¢/kWh.
MWh purchased, over 21,000. Overall temperatures were moderate, resulting in usage to be
consistent with previous years. Peak demand 35,150 kW set on March 7th at 7:00 pm. After
above average peak demands in Jan and Feb., the March demand was well below the average.
Typically, closer to or above 40,000 kW in March.
C. Cash Flow: The Operating Fund increased by $223,200. The Operating Fund at month end
was $6.2 MM. March receipts were $1.49 MM. Customer payments have picked up. Still
receiving LI-HEAP payments. Program extended to April 28th. Interest revenue remains up do to
increases to the Federal Fund Rate. March Expenditures totaled over $1.26 MM, this is $348,260
less than budgeted.
D. Approval of Bills:
RESOLUTION:
The Massena Electric Utility Board hereby approves the bills as audited by
Mr. Rene Hart totaling $918,529.57
Moved by Rene Hart – Seconded by John Bogosian - All in Favor
Pending Approval by the MEUB
4) COMMITTEE REPORTS: by Andrew McMahon, Superintendent
A. Personnel
1. Staff Update: Mr. McMahon noted to the board that one employee would be out for a few
weeks due to surgery. Mr. Raiti asked what the implications were for replacing the employee.
Mr. McMahon explained that there would be additional overtime to cover the temporary
vacancy but that filling the opening on a temporary basis was manageable.
Mr. McMahon noted that we would be going forward with hiring summer help at $17/hour.
2. Security Update: Mr. McMahon and Mr. Dobbins gave an update on front office security.
They noted that now that the front office doors have been replaced a table top exercise will take
place with the village police in early June.
B. Finance & Economic Development
1. Energy Efficiency Programs: Treasurer Dobbins reported that the Finance & Economic
Development committee met earlier in the week. Energy Answers, the third party performing the
energy audits as part of the Energy Makeover program, attended part of the meeting to discuss
the agreement between Energy Answers and the Department. Based on the discussion the
agreement will be updated to reflect a new rate structure and include additional marketing
efforts by Energy Efficiency to promote the programs offered by the Department.
The committee also discussed a large lighting project being proposed during the meeting, and
adding rebates to the program for heat pumps. Treasurer Dobbins noted the large lighting
project will impact a number of locations owned by the Massena Housing Authority. They are
looking to change all of the old lighting in each of their buildings. A report was done by Energy
Answers and Treasurer Dobbins indicated that the committee will review the report and get back
to the board with a proposed energy credit for the project.
Customers looking to install heat pumps is increasing. The committee did not have a formal
request/proposal for the board on a rebate/credit program for heat pumps and wanted to advise
them that it is being considered. The committee will continue to review options with regards to
heat pump installations, and have a proposal to the board in the coming months.
Treasurer Dobbins also informed the board that Invoice Cloud, the third party handling on-line
payments, would be increasing the convenience fee they charge on credit and debit card
transactions from $3.95 / transaction to $4.50 / transaction. The convenience fee is set by
Invoice Cloud to cover their cost to handle these transactions and deal with the credit card
companies. The Department does not receive any proceeds from this fee. A note was added to
Invoice Clouds’ webpage informing customers that this change will go into effect on June 1,
2023. Information regarding the updated fee is also being sent to those customers receiving e-
bills through Invoice Cloud.
C. Engineering & Energy
Mr. McMahon explained that all of the items in the engineering Committee portion of the
agenda were also covered at the NYAPP meeting.
1. Cybersecurity: Mr. McMahon and Mr. Dobbins discussed the implementation of the Dragos
system to supplement existing cyber protection measures. The Dragos product is being used in
conjunction with NYPA and a few other NYAPP members.
Pending Approval by the MEUB
2. Forward Energy Procurement: Mr. McMahon has had preliminary conversations with NYPA
to get indicative pricing for the Winter of 2024. None of the options presented thus far seem
appealing, but he will stay in touch with NYPA and keep the committee and board up-to-date.
3. EAB extra work: Work has resumed on some of the more difficult and dangerous Ash Trees in
the community that would impact our lines. We are hopeful that this project will qualify for
state reliability money when it finally comes available.
4. NYSERDA Submittals: This process is continuing.
5. Grant Funding CAC/IIJA/IRA: This was the subject of extensive conversation in Saratoga at
the NYAPP conference. New York has been slow to make their submittals to the Federal
Government on how the state programs will work.
5) LEGAL ISSUES: by Eric Gustafson, Attorney: Mr. Gustafson had no remarks for open session.
6) UNFINISHED BUSINESS:
• NYAPP quarterly meeting in Saratoga
Mr. McMahon stated he will submit a written report for the board to review. One item he
did want to mention now was that the CEO of the NYISO spoke at our dinner. He stated that the
ISO seems to believe that achieving the 70% renewable goals by 2040 is achievable but the 2050
goal of 100% is more difficult in their opinion since the required technology does not exist.
Mr. Shaw relayed to the board that Mark Saltsman from Liberty Utilities in Massena was invited
to attend the meeting.
.
7) NEW BUSINESS:
Mr. McMahon reminded the board that two auto dealerships are putting in high speed
(Level 3) charging stations. This takes significant infrastructure investment from both the
Dealership and from MED. As we have discussed previously, supply chains remain a concern.
We have looked at the transformers required for these projects. We have made multiple calls to
our normal new transformer suppliers and at this moment none of them will even bid on new
transformers. Calls have also been made to some firms that we have not dealt with previously
and there are no proposals that are acceptable. There are two companies that we have dealt with
that have rewound transformers.
RESOLUTION:
In order to fulfill the proposed EV projects on an acceptable timeline the Massena
Electric Utility Board approves purchasing 1 pad mount transformer at a price not to exceed
$60,000 and 3 pole mount transforms at a price not to exceed $30,000.
Moved by Charles Raiti – Seconded by Richard Maginn - All in Favor
8) ARTICLES OF INTEREST:
Mr. McMahon directed the boards attention to the growing variability of both load and
generation and the challenges it creates. He also noted that the second article relating to crypto
and cannabis is an issue we are seeing with many of our developers.
Pending Approval by the MEUB
9) SCHEDULE OF EVENTS: Next regular meeting scheduled for May 18, 2023
10) PUBLIC COMMENT:
11) EXECUTIVE SESSION:
Motion to move into executive session at 2:06 p.m.
Moved by Charles Raiti– Seconded by John Bogosian- All in Favor
Motion to reopen meeting for public comments at 2:07 p.m.
Moved by Charles Raiti– Seconded by John Bogosian- All in Favor
Motion to adjourn and move into executive at 2:10 p.m.
Moved by Richard Maginn– Seconded by Charles Raiti- All in Favor
Motion to move out of executive session at 2:21 p.m.
Moved by Richard Maginn– Seconded by Charles Raiti -All in Favor
Motion to adjourn at 2:21 p.m.
Moved by Richard Maginn – Seconded by Charles Raiti- All in Favor
Agenda
MASSENA ELECTRIC DEPARTMENT
71 E. Hatfield Street • PO Box 209 • Massena New York 13662
Office: (315) 764-0253 • Fax: (315) 764-1498
www.massenaelectric.com
NOTICE OF REGULAR MEETING
MASSENA ELECTRIC UTILITY BOARD
DATE: Thursday April 20, 2023
TIME: 1:00 p.m.
Location: Massena Electric Department
71 E. Hatfield St.
Massena, NY 13662
Get email alerts for Massena
A daily email when new agendas and minutes are posted.