Massena Electric Department
Regular MeetingMassena, NY · October 24, 2023
Minutes
Approved by the MEUB 11/16/2023
MASSENA ELECTRIC UTILITY BOARD
MINUTES of Tuesday, October 24, 2023
Town of Massena Electric Department – 71 East Hatfield Street
Present:
James Shaw Andrew McMahon, Superintendent
Richard Maginn Jeffrey Dobbins, Treasurer
John Bogosian Matt Gray, Deputy Superintendent
Rene Hart Debra Willer, Town Liaison
Charles Raiti Patrick Facteau, Town Liaison
Eric Gustafson, Attorney
Chairman Shaw opened the meeting at 1:03 p.m.
1) APPROVAL OF MINUTES:
RESOLUTION:
The Massena Electric Utility Board hereby approves the minutes of the regular meeting
of September 21, 2023 as presented.
Moved by John Bogosian - Seconded by Rene Hart - All in Favor
RESOLUTION:
The Massena Electric Utility Board hereby approves the minutes of the special meeting
of October 5, 2023 as presented.
Moved by Charles Raiti - Seconded by Richard Maginn - All in Favor
2) OPERATIONS UPDATE: by Matt Gray, Deputy Superintendent
A. Safety: MED has not had a lost time injury since June 8th, 2022. The number of consecutive
days without a lost time accident now stands at 479 days. There were no reportable injuries in
September. This brings the number of days without a reportable injury to 842 days.
Safety Note – Lou Gabrielle with NEPPA was on site to present a lock-out/tag-out and confined
space training to all line personnel. Also, our Technician department attended a two-day
Schweitzer seminar in Philadelphia, PA. This provided our Technicians the opportunity to train
on our relaying and metering devices with Schweitzer Application Engineers.
B. Customer Impact Chart: MED experienced a second consecutive month of elevated Customer
Impact Minutes with 50,656 Customer Impact Minutes recorded. The largest Customer impact
in September was a failed station service transformer at Grasse River that caused 50,656
Customer Impact Minutes. With the large amount of CIM our 12-month average has increased
to 31,490. An increase of almost 5,000 compared to last month.
C. Reliability: MED Crews responded to a comparatively low number of calls with only six calls
received in the month of September. Three of the six calls received involved a Customer impact
with the largest CIM contributor being the previously mentioned issue at Grasse River Substation.
The faulted station service transformer caused a Bus 2 fault and isolation that affected two
Approved by the MEUB 11/16/2023
thousand one hundred ninety-eight Customers for twenty-three minutes. The second CIM
contributor was due to a broken cutout that affected one Customer for one hour forty-two
minutes. The third CIM contributor occurred when a delivery truck contacted a service drop on
Gladding Road. This issue caused a 30-minute outage for one Customer. MED crews also
contended with a hit pole on Dennison Road, however no Customers were affected. The
remainder of the calls in September were minor in nature and involved no Customer impact.
D. Work Schedule: Crews have completed make-ready work associated with the fifteen pole
attachment applications that were submitted by SLIC in the Village of Massena, and the Towns of
Massena, Louisville and Norfolk. Also, Crews have addressed an issue with street lighting that has
arisen over the previous months. Some of the LED street lights that we have installed in the past
few years have begun to change to a purple shade of light. This issue has been discussed with the
light supplier and they are replacing the malfunctioning units. This issue affects approximately
40 units that were purchased since we began our conversion to LED street lighting.
3) FINANCIAL REPORTS: by Jeff Dobbins, Treasurer
A. Write-Offs:
RESOLUTION:
The Massena Electric Utility Board hereby authorizes the write-off of bad debt
totaling $4,037.02 as audited by Mr. Rene Hart.
Moved by Rene Hart - Seconded by Richard Maginn - All in Favor
B. Power Comparison Graph: Power Costs $489,000, higher than previous years. NYPA Energy
purchased was lower due to lower load share %. High Peak at the start of the monthly negatively
impacted Hydro allocation. Supplemental Power costs were $117,000. 4,075 MWh of incremental energy
purchased during September. Zone D Average Energy rate was $28.70/MWh. Transmission/ISO Exp totaled
$172,160 for September. Unforced Capacity was $56,600. Other ISO related charges were over $50,000.
Charges for Transmission (NYPA and Long Sault) totaled over $65,560. Impact to Customers – PPAC for
September of 1.1¢ / kWh. MWh purchased, over 14,900, highest total for September. Remainder of the
month was cooler so total MWh purchased was not as high as other summer months. Peak Demand for
September was 32,500 kW, highest Peak for Sept., 1st time over 30,000 for September. One of the highest
Summer Peaks for the Dept. Set during the warm stretch at the start of the month.
C. Cash Flow: The Operating Fund decreased by $210,300. The Operating Fund at month end
was $7.1 MM. September receipts were $938,700. Customers payments were less than projected for
the month. Interest revenue remains higher. September expenditures totaled just under $1.15 MM,
which was $199,200 less than budgeted.
RESOLUTION:
The Massena Electric Utility Board hereby approves the bills as audited by
Mr. Rene Hart totaling $779,960.09
Moved by Rene Hart – Seconded by John Bogosian - All in Favor
Approved by the MEUB 11/16/2023
4) COMMITTEE REPORTS: by Andrew McMahon, Superintendent
A. Personnel
1. Staff Update: Mr. McMahon reported there were no significant updates on staff.
B. Finance & Economic Development
1. Energy Efficiency Programs:
i. Commercial update: Treasurer Dobbins updated the board on the Massena Housing
Authority’s lighting project. MHA has completed 87 rooms/apartments. Including office space,
common areas, apartments and maintenance buildings, over 250 locations will be upgraded
once the project is complete. They have requested over $12,000 for reimbursement to date,
which is nearly half of the assistance approved by the board. Treasurer Dobbins noted he
intends to show some pictures of the work completed at the November meeting.
Treasurer Dobbins also reported additional commercial audits are scheduled. They include a
business looking to make lighting upgrades and a second that is looking to upgrade a motor used
at their facility.
ii. Residential update: Mr. McMahon discussed some heat pump ideas that MED staff has
been working on with Liberty Utilities (aka St. Lawrence Gas). We met with Mark Saltsman and
Heather Tebbets of Liberty to discuss potentially mutually beneficial ideas for home heating that
would leverage Federal grant money. Liberty has done some projects in New Hampshire where
they are based and we reviewed other alternatives. We discussed Community Geothermal
networks. But we focused on hybrid heat pumps that would utilize electric most of the year but
in the coldest periods they would utilize gas to supplement the heating needs. This allows Liberty
to stay in the home heating market. It is advantageous for MED and our ratepayers because if
electrical load is growing in the coming years this type of hybrid unit would allow the growth
without requiring MED to expand our system capacity. Liberty believes they will have support
from the PSC to do a pilot project of 30-100 homes.
Treasurer Dobbins indicated that there have been a few residential audits this fall. He is awaiting
the reports from these audits. He also noted that there has been renewed interest by residential
customers to install Heat Pumps. This was previously discussed by the Finance Committee and no
decision was made on a specific program. Based on the new interest and the recent discussion
with Liberty Utilities, Treasurer Dobbins plans to discuss this again with the Finance Committee.
2. 2024 Draft Budget: The proposed budget presented was the same as the budget discussed at
the September meeting. Treasurer Dobbins indicated that there were no significant changes to
the underlying factors that impact the budget, expected power costs and proposed capital
projects. Superintendent McMahon noted that projects listed in the capital budget are those that
Staff has identified as areas of need. Additional work is being done to more accurately determine
the cost for these projects and that as more information is received he and Staff would discuss the
projects in more detail with the board.
RESOLUTION:
The Massena Electric Utility Board approves the Proposed 2024 Budget as presented.
Moved by John Bogosian – Seconded by Charles Raiti - All in Favor
Approved by the MEUB 11/16/2023
3. Website update: Treasurer Dobbins reported to the board that additional work had been done
to update the website. This was started earlier this year and includes a change in the layout and
content. Prior to going live with the new site, Treasurer Dobbins planned to send the board a
link to the new site for their review. He asked that they provide any feedback to him by the
following week so they could be incorporated into the new site.
C. Engineering & Energy
1. Cybersecurity: Mr. McMahon discussed cyber security training that had occurred earlier in
the day. A number of board members had participated in this training and it wasn’t as good as
Mr. McMahon had hoped but it did give some insight into what a post cyber-attack environment
would look like and how our insurer would help. Mr. McMahon had hoped for further
elaboration on what services would be covered.
2. EAB extra work: MED Contractors continue to address infected ash trees. Throughout the
summer growing season their main focus has been tree trimming, however if there was a
problem ash tree in the areas they were trimming, the ash tree was addressed. Now that the
growing season has ended, we will be able to shift our focus more towards ash tree removal.
3. NYSERDA Submittals: Mr. McMahon discussed the NYSERDA grants that are still in process.
He explained the potential benefit of the water heater control project that we are working on
with SUNY Canton. He explained that we presently control 900 water heaters that count for a
peak of approximately 600 KW of load that can be shifted to non-peak hours. We believe there
are over 4000 electric water heaters on the system already that we are not controlling. We had
tried to utilize an EPRI water heater unit that worked reasonably well and could act based on
numerous factors, but the price of the EPRI units was approximately $1700 versus a standard
electric water heater that is $600. Our goal is to find a way to control the water heaters based on
some critical factors used by the EPRI unit but at a more manageable price for our consumers.
4. Grant funding CAC/IIJA/IRA: Mr. McMahon advised the board that the NYSERDA projects
are still taking shape. Further, the Federal grant money from IIJA and IRA is just starting to flow
to the states including NY. Some money has gone out in a more direct manner but not for
projects that MED could realistically manage or fit our needs.
5.Transformer purchase update: Transformers are still coming around April next year.
6.Vehicle purchase update: Vehicles are scheduled to arrive later this year.
7. Tree Power: Trees were purchased under NYPA’s tree power program with grant money from
Alcoa.
5) LEGAL ISSUES: by Eric Gustafson, Attorney: Mr. Gustafson had no remarks for open session.
6) UNFINISHED BUSINESS: Mr. McMahon provided a written summary of the Cooperstown
meeting. Mr. Shaw elaborated on the Cap and Invest portion of the
meeting saying it creates a very dire vision for the future.
7) NEW BUSINESS:
8) ARTICLES OF INTEREST:
Approved by the MEUB 11/16/2023
9) SCHEDULE OF EVENTS: Next regular meeting scheduled for November 16, 2023
10) PUBLIC COMMENT:
11) EXECUTIVE SESSION:
Motion to move into executive session at 2:05 p.m.
Moved by Charles Raiti – Seconded by Rene Hart- All in Favor
Motion to move out of executive session at 2:45 p.m.
Moved by Richard Maginn – Seconded by John Bogosian -All in Favor
Motion to adjourn at 2:45 p.m.
Moved by John Bogosian – Seconded by Rene Hart- All in Favor
Approved by the MEUB 11/16/2023
MASSENA ELECTRIC DEPARTMENT
2024 Budget APPROVED
10/24/2023
2022 Actual 2023 Budget Projected 2023 2024 Budget
% Change % Change
1 REVENUES from Budget Projected
2 RECEIPTS FROM CUSTOMERS $ 13,564,127 $ 14,959,200 $ 13,023,000 $ 15,853,200
3 REIMBURSED PROJECTS 114,293 45,000 260,000 45,000
4 RVRDA CONSULTING FEE 30,000 30,000 30,000 30,000
5 INTEREST INCOME 42,813 46,800 191,500 237,600
6 TOTAL REVENUES $ 13,751,233 $ 15,081,000 $ 13,504,500 -10.5% $ 16,165,800 19.7%
7
8 EXPENDITURES
9 SALARIES & WAGES $ 1,858,448 $ 1,939,600 $ 1,924,000 $ 2,002,000
10 HEALTH INSURANCE 478,036 520,800 484,900 515,000
11 FICA & NYS RETIREMENT 439,549 358,600 348,300 393,100
12 Salaries & Employee Benefits $ 2,776,034 $ 2,819,000 $ 2,757,200 -2.2% $ 2,910,100 5.5%
13
14 NYPA POWER $ 1,905,845 $ 1,949,800 $ 1,898,600 $ 1,940,000
15 INCREMENTAL POWER 3,749,201 4,165,700 2,325,500 4,428,300
16 ISO/TRANSMISSION 676,365 1,674,000 1,904,500 2,119,400
17 CES - Clean Energy Standard 933,884 940,600 726,400 777,700
18 Power & ISO $ 7,265,296 $ 8,730,100 $ 6,855,000 -21.5% $ 9,265,400 35.2%
19
20 CONTRACT SERVICES $ 117,656 $ 196,000 $ 199,000 $ 205,800
21 CONSULTING SERVICES 56,782 148,200 120,400 85,200
22 LEGAL SERVICES 167,320 215,000 210,600 220,100
23 FINANCIAL SERVICES 28,943 31,000 30,000 32,900
24 NYS SALES TAX 556,377 588,000 515,000 627,000
25 REAL ESTATE TAXES 605,274 617,200 614,600 627,900
26 POSTAGE 55,445 66,100 64,800 68,400
27 TELEPHONE 8,124 14,400 25,400 25,400
28 CONSUMER REFUNDS 71,363 52,800 60,000 52,800
29 INSURANCE 197,309 217,800 209,700 234,300
30 OTHER OPERATING EXP. 605,901 569,900 565,100 611,500
31 Paid to Suppliers & Vendors $ 2,470,495 $ 2,716,400 $ 2,614,600 -3.7% $ 2,791,300 6.8%
32
33 MATERIALS & SUPPLIES $ 529,237 $ 512,400 $ 640,500 $ 704,400
34 DEBT SERVICE:
35 PRINCIPAL
36 INTEREST
37 Contrib. Depr Fund/Capital Exp 78,128 425,000 310,000 965,000
38 CONTRIB. TO INS FUND - - - -
39 CONTRIB. to Post Retire. Hlth Ins Fund - - - -
40 ENERGY EFFICIENCY 1,747 216,500 215,900 206,900
41 Utility Investment & Other Activities $ 609,112 $ 1,153,900 $ 1,166,400 1.1% $ 1,876,300 60.9%
42
43 TOTAL EXPENDITURES $ 13,120,937 $ 15,419,400 $ 13,393,200 -13.1% $ 16,843,100 25.8%
44
45 CASH SURPLUS (DEF.) $ 630,296 $ (338,400) $ 111,300 $ (677,300)
46
47 Operating Fund Balance (12/31) $ 6,538,226 $ 6,199,826 $ 6,649,526 $ 5,860,926
Agenda
MASSENA ELECTRIC DEPARTMENT
71 E. Hatfield Street • PO Box 209 • Massena New York 13662
Office: (315) 764-0253 • Fax: (315) 764-1498
www.massenaelectric.com
NOTICE OF REGULAR MEETING
MASSENA ELECTRIC UTILITY BOARD
DATE: Tuesday October 24, 2023
TIME: 1:00 p.m.
Location: Massena Electric Department
71 E. Hatfield St.
Massena, NY 13662
Get email alerts for Massena