Inland / Wetlands & Water Courses Agency
Regular MeetingMiddletown, CT · September 7, 2022
Minutes
Chair Joseph Carta
Vice-Chair Ken McClellan
Members Fred Terrasi Trevor Davis
Inland Wetlands David Pritchard
Jammie Middleton
Jennifer Greenberg
Brian Gartner
And Alternates
Steven Skultety
Jack Pieper
Vacant
Paul Dyka
Watercourses Agency Vacant
Vacant
Kristen Rzasa
Staff James Sipperly, Environmental Planner
MEETING MINUTES
Wednesday – September 7, 2022
Meeting held in person only, Municipal Building, Common Council Chambers
7:00 P.M.
Present: Ken McClellan
Joseph Carta
Paul Dyka
David Pritchard
Jennifer Greenberg
Kristen Rzasa
Steve Skultety
Absent: Fred Terrasi
Jack Pieper
Brian Gartner
Trevor Davis
Jammie Middleton
Public: Seth Lenz, Assistant Chief Engineer, Water and Sewer Dept.; Pat Benjamin, Bascom and
Benjamin Engineering; Atty. Rich Carella; Guy Hesketh, P.E., Anthony Zemba, Soil Scientist; Mike
Stone, 28 members of the Public
Staff: James Sipperly, Environmental Planner
A. Call to Order
J. Carta, Chairman called the meeting to order at 7:02 pm and led the Pledge of Allegiance.
B. Public Hearing
1. Request to fill 983sgft of wetlands and mitigate 6,079sgft of wetland area for a commercial
development at 550 highland Avenue. Application # 2022-10
Atty. Rich Carella introduced the project to the Commission. The grocery store will be a Big
Y and will be located between RT 17 and Highland Avenue.
Guy Hesketh the project engineer discussed the plans in detail, including the existing site
conditions, proposed site improvements, traffic and parking layout and construction details.
Anthony Zemba, Soil Scientist discussed the two wetland areas of the site. Wetland A is a
wetland associated with a watercourse and has medium to high value and provides many
wetland functions. Wetland B is an isolated wetland area that has low value and is located in a
mowed lawn area. Old drainage via a concrete pipe bisects this wet area and that may be the
cause of the wetness, Mr. Zemba stated. Wetland B was formed in human transported
materials. There also is a report he submitted dated July 28, 2022.
Page 1 of 8
Guy Hesketh then talked about storm water drainage and treatment. There are to be three
underground structures that are all custom designed. He explained how they would treat the
storm water and then recharge it back into the ground. Mr. Hesketh then explained the erosion
and control measures to be used to stabilize the site while under construction.
Chairman J. Carta then opened up the Public Hearing for members of the public.
Howard Godwin, Durwin Street, asked about how this whole project will impact the Condo’s
down the hill and how it will affect the Apple Rehabilitation Center. He also is concerned
about all the sand and salt that will used in the parking lot.
Kate Wilson, Brown Street, asked about the pollutants going down to the southeast wetlands
and how much stormwater drainage goes into wetland B presently.
Mary Ellen Sulkens, asked about what will be done to wetland A specifically and during
construction where will the silt fence be installed.
Mr. Hesketh responded to those questions. Mr. Sipperly asked him to explain how the
hydrodynamic separators work for the public.
Chairman Carta opened up questions to commission members.
K. McClellan asked about erosion and sedimentation controls again and asked to see their
proposed locations. Mr. Hesketh said that there will be an inspector on site to do weekly
inspections. Mr. Sipperly stated that as part of his job, he conducts inspections of working site
as well.
K. Rzasa asked about possible flooding issues. Mr. Hesketh said that the existing site
conditions were reviewed and using the standard calculations for a 100 year storm event sized
the drainage structures accordingly.
D. Pritchard asked about a schedule for maintenance for these drainage systems. Mr. Hesketh
responded that they do routine street sweepings in the parking lot especially in the winter to
remove sand and silt before it enters the system. The catch basins are twice annually inspected
and cleaned.
J. Carta asked about the quality of wetland B and asked about saving some large trees along
the truck entrance drive.
J. Sipperly asked about site construction activities and phasing and about temporary storm
water storage basins. Mr. Hesketh stated that when the contractors are hired staff will be
contacted to attend meetings to address those very issues and will allow input from him
moving forward.
Motion: To close the Public Hearing on application # 2022-10.
Moved by K. McClellan; seconded by K. Rzasa; approved unanimously.
Chairman Carta reported that this will now go under Old Business item #3.
C. Old Business
Page 2 of 8
1. Request to upgrade Red Road sewer pump station which was originally constructed in 1969
at 90 Red Road. Applicant/Agent: City of Middletown Water and Sewer Department. 2022-7
Mr. Sipperly reported that there was a public hearing on this and there was a question about
the arborvitaes to be planted. This was referred to the Urban Forestry commission and they
recommended planting eastern red cedars instead, because the deer eat the arborvitaes.
K. McClellan asked about want will be demolished and S. Lentz. PE responded that the above
structure and wet well will be removed.
Motion:
IWWA APPPLCATION W 2022-7
Applicant/Agent Middletown Water & Sewer Department
That the Inland Wetlands and Watercourses Agency (hereinafter, “Agency”), having considered
application 2022-7 with due regard to the criteria enumerated in Section 22a-41 of the Connecticut
General Statutes and Section 8 of the Inland Wetlands & Watercourses Regulations of the City of
Middletown finds the following:
1. That the proposed construction activities include, abandonment of the existing pump station
(built in 1969), installation of a new precast wet well and valve vault and minimal site work.
2. That there is no direct impacts to the inland wetlands and watercourses on the site. There will
be a total of 3,359 sqft of impact to the regulated area.
3. That the proposed work, as specified and conditioned below, is in conformance with the
purposes and provisions of said sections and furthermore, will not have a significant
adverse effect on the adjacent inland wetlands and watercourses.
Therefore, permit # W 2022-7 is granted, with conditions, to allow the following regulated activities
as depicted on the submitted plan entitled:
“Red Road Pump Station Improvements, Site Plan (page C-301) & Demolition (page C-201)
Dated June 8, 2022, scale 1”=10’, prepared by Weston and Sampson Engineers, Inc.”
This Permit is issued by the Agency subject to the following conditions and/or modifications as
follows:
1. If the authorized activity is not completed within five (5) years from the date of approval
by the Agency that is, on or before September 7, 2027 said activity shall cease and, if not
previously revoked or specifically extended, this Permit shall be null and void.
2. The permittee shall notify the Wetlands Officer immediately upon the commencement of
work and upon its completion.
3. Prior to the commencement of any site work, the Permittees and/or their agent shall
properly install any and all sedimentation and erosion (S&E) control measures as depicted
on the site plans approved by the Agency. Changes to S&E controls may be made in order
to accommodate field conditions so long as they provide equal or greater protection
against S&E into the regulated wetlands and upland review area.
Page 3 of 8
4. A copy of the plans approved by the Agency shall be kept at the job site for the duration of
construction activities as approved herein.
5. During construction, as represented to the Agency, no material shall be stockpiled within
the regulated area or in areas other than those depicted on the site plans approved by the
Agency.
6. The City reserves the right to inspect the site work area at any time from commencement
to conclusion of the property to ensure permit conditions and compliance with the
regulations is being met.
7. All sedimentation and erosion control devices shall remain in place until the end of
construction and the site is deemed stabilized by the City’s Wetlands Enforcement Officer
or other authorized agent of the Land Use Department. An inspection can be scheduled by
calling 860-638-4590.
8. All work, including all regulated activities conducted pursuant to this authorization, shall
be consistent with the terms and conditions of this Permit. Any structures, excavation, fill,
obstructions, encroachments, and/or regulated activities not specifically identified and
authorized herein shall constitute a violation of this Permit and may result in its
modification, suspension, or revocation. Upon initiation of the activities authorized herein,
the Permittees accept and agree to comply fully with all terms and conditions of this
Permit.
9. No equipment or material including, without limitation, fill, construction materials and/or
debris, shall be deposited, placed, and/or stored in any regulated area, on or off site,
unless specifically authorized by this Permit.
10. The authorizations and activities set forth in this Permit are not transferable without the
written consent of the Agency or its Authorized Agent.
11. In evaluating this application, the Agency has relied on information provided by the
Permittees. If such information subsequently proves to be false, deceptive, incomplete
and/or inaccurate, this Permit may be modified, suspended, or revoked by the Agency.
12. If applicable, flagging associated with the wetland boundary shall remain until the
completion of construction activities and shall not be removed until all work is complete
and the site is stabilized.
13. The Permittee shall employ best management practices, consistent with the terms and
conditions of this Permit, to control stormwater discharge, to prevent erosion and
sediment migration beyond the work area(s), and to otherwise prevent pollution of inland
wetlands and watercourses. The Permittees shall immediately inform the City’s Inland
Wetlands Enforcement Officer of any problems related to activities in the regulated area,
which have been impacted during the course of, or caused by, the authorized work.
14. This Permit is subject to, and does not detract from, any present or future property rights
or other rights or powers of the State of Connecticut, and conveys no property rights in
real estate or material nor any exclusive privileges, and is further subject to any and all
public and private rights and to any federal, state, or local laws or regulations pertinent to
the property or activity affected hereby.
15. Nothing in these regulations shall obviate any requirement for the Permittee to obtain any
other assent, permit, or license required by law and/or regulation by the Government of
the United States, the State of Connecticut, or any other political subdivisions thereof.
Obtaining such assents, permits, and/or licenses is solely the responsibility of the
Permittee.
16. That any storage of fuel, oils and other chemicals on the site shall be stored in a secondary
container to prevent the possibilities of spills and/or leaks.
Page 4 of 8
17. That no floor drains shall be allowed due to the fact that this area is in a watershed
protection overlay zone.
18. That from a recommendation from the Urban Forestry Commission is not to plant 20
Green Giant Arborvitaes but to plant 20 Eastern Red Cedars as the arborvitaes are
susceptible to damage by deer.
Moved by D. Pritchard; seconded by K. McClellan. Clarification on the demolition of the
wet well and abandonment of the pump station. Only the demolition of the wet well will
be below the surface and the rest of the station will be rebuilt. The mover and seconder
agreed with this clarification. Vote: approved unanimously.
2. Subdivision to create five residential building lots at 665 Ridgewood Road (map/lot:
10/0008). Applicant/Agent: Hubbard Properties, LLC 2022-9
Steve Skultety recused himself from this application.
Pat Benjamin, PE represented the applicant and described the project in detail. There is one
17.9 acre lot which they would like to subdivide into 5 lots off of Ridgewood Road. The
wetland activity is limited to installing two sewer pipes, 42” deep across the intermittent
watercourse, backfill and then seed with a Conservation Wet-mix seed. The construction
should take no more than half a day. The work will be done in a dry time between June 1 and
September 3.
Motion: To table this for action at the next meeting on October 5, 2022. Moved by D.
Pritchard; seconded by P. Dyka; approved unanimously.
Motion: D. Pritchard moved for a 5 minute recess. Seconded by P. Dyka approved
unanimously
J. Carta called the meeting back to order at 8:57 pm
3. Request to fill 983sgft of wetlands and mitigate 6,079sgft of wetland area for a commercial
development at 550 highland Avenue. Application # 2022-10
This was subject of a Public Hearing tonight and J. Carta stated that all the questions were
answered and ask staff to read a draft motion into the record.
Motion:
IWWA APPLICATION W 2022-10
Applicant/Agent South Main Street Investors, LLC
Draft Motion:
That the Inland Wetlands and Watercourses Agency (hereinafter, “Agency”), having considered
application 2022-10 with due regard to the criteria enumerated in Section 22a-41 of the Connecticut
General Statutes and Section 8 of the Inland Wetlands & Watercourses Regulations of the City of
Middletown finds the following:
Page 5 of 8
1. That the proposed activities are to redevelop two parcels into a 51,892sqft grocery store and
associated site improvements including paved parking areas and drives, stormwater
management systems and utility services. The existing building structures will be demolished.
2. That 983sqft of inland wetland soils located in an existing mowed field are proposed to be
filled. This small isolated wetland area was found to have very little function and is of low
value.
3. That the inlands wetlands and watercourses on the site were delineated by Anthony Zemba,
Certified Soil Scientist and Certified Ecologist on July 8 2022 and are shown correctly on the
plan referenced below. A report from Mr. Zemba dated July 28, 2022 is included in the
application materials submitted.
4. To offset the filling of the small isolated wetland area, there is no suitable location on the site
to create another wetland area. As a mitigation alternative, there will be an enhancement of
the other existing wetlands and watercourses area on the site known as wetland A.
Accumulated sediment, downed trees and brush, as well as garbage and “floatables” from the
stormwater drainage off RT 17 will be removed. The current watercourse flowing through the
existing headwall is partially blocked causing erosion of the existing banks.
5. A comprehensive stormwater management report dated August 22, 2022 prepared by F.A.
Hesketh Associates is included in the application materials.
6. That the proposed work, as specified and conditioned below, is in conformance with the
purposes and provisions of said sections and furthermore, will not have a significant adverse
effect on the adjacent inland wetlands and watercourses.
Therefore, permit # W 2022-10 is granted, with conditions, to allow the following regulated activities
as depicted on the submitted plan entitled:
“Big Y World Class Market, 502 & 550 Highland Avenue, Middletown, CT – Inland Wetlands and
Watercourses Agency Application Plan Set, dated July 29, 2022, revised through August 22, 2022,
scale as shown, 21 sheets in total as specifically identified thereon”
This Permit is issued by the Agency subject to the following conditions and/or modifications as
follows:
1. If the authorized activity is not completed within five (5) years from the date of
approval by the Agency that is, on or before September 7, 2027 said activity shall cease
and, if not previously revoked or specifically extended, this Permit shall be null and
void.
2. The permittee shall notify the Wetlands Officer immediately upon the commencement of
work and upon its completion.
3. Prior to the commencement of any site work, the Permittees and/or their agent shall
properly install any and all sedimentation and erosion (S&E) control measures as depicted
on the site plans approved by the Agency. Changes to S&E controls may be made in order
to accommodate field conditions so long as they provide equal or greater protection
against S&E into the regulated wetlands and upland review area.
4. A copy of the plans approved by the Agency shall be kept at the job site for the duration of
construction activities as approved herein.
Page 6 of 8
5. During construction, as represented to the Agency, no material shall be stockpiled within
the regulated area or in areas other than those depicted on the site plans approved by the
Agency.
6. The City reserves the right to inspect the site work area at any time from commencement
to conclusion of the property to ensure permit conditions and compliance with the
regulations is being met.
7. All sedimentation and erosion control devices shall remain in place until the end of
construction and the site is deemed stabilized by the City’s Wetlands Enforcement Officer
or other authorized agent of the Land Use Department. An inspection can be scheduled by
calling 860-638-4590.
8. All work, including all regulated activities conducted pursuant to this authorization, shall
be consistent with the terms and conditions of this Permit. Any structures, excavation, fill,
obstructions, encroachments, and/or regulated activities not specifically identified and
authorized herein shall constitute a violation of this Permit and may result in its
modification, suspension, or revocation. Upon initiation of the activities authorized herein,
the Permittees accept and agree to comply fully with all terms and conditions of this
Permit.
9. No equipment or material including, without limitation, fill, construction materials and/or
debris, shall be deposited, placed, and/or stored in any regulated area, on or off site,
unless specifically authorized by this Permit.
10. The authorizations and activities set forth in this Permit are not transferable without the
written consent of the Agency or its Authorized Agent.
11. In evaluating this application, the Agency has relied on information provided by the
Permittees. If such information subsequently proves to be false, deceptive, incomplete
and/or inaccurate, this Permit may be modified, suspended, or revoked by the Agency.
12. If applicable, flagging associated with the wetland boundary shall remain until the
completion of construction activities and shall not be removed until all work is complete
and the site is stabilized.
13. The Permittee shall employ best management practices, consistent with the terms and
conditions of this Permit, to control stormwater discharge, to prevent erosion and
sediment migration beyond the work area(s), and to otherwise prevent pollution of inland
wetlands and watercourses. The Permittees shall immediately inform the City’s Inland
Wetlands Enforcement Officer of any problems related to activities in the regulated area,
which have been impacted during the course of, or caused by, the authorized work.
14. This Permit is subject to, and does not detract from, any present or future property rights
or other rights or powers of the State of Connecticut, and conveys no property rights in
real estate or material nor any exclusive privileges, and is further subject to any and all
public and private rights and to any federal, state, or local laws or regulations pertinent to
the property or activity affected hereby.
15. Nothing in these regulations shall obviate any requirement for the Permittee to obtain any
other assent, permit, or license required by law and/or regulation by the Government of
the United States, the State of Connecticut, or any other political subdivisions thereof.
Obtaining such assents, permits, and/or licenses is solely the responsibility of the
Permittee.
16. That any storage of fuel, oils and other chemicals on the site shall be stored in a secondary
co to prevent the possibilities of spills and/or leaks.
17. That a bond calculated by the Town Engineer covering the erosion and sedimentation
control measure costs, including the filling of the isolated wetland area and the proposed
Page 7 of 8
wetland mitigation work costs shall be submitted to the City of Middletown using a bank
check or money order prior to the commencement of construction activities.
18. That deep sumps will be installed on the last stormwater structures to remove oils and
chemicals.
19. That staff will be included in discussions with the contractor to develop a phasing plan for
the site construction and grading, including having the ability to comment on any on-site
temporary stormwater detention basins.
20. That a double rough of silt fence and/or hay bales will be installed along the northeast
corner of the site at the toe of the proposed steep slope.
Moved by K. McClellan; seconded by S. Skultety, approved unanimously.
D. New Business
None
E. Agency Review
None
F. Reports of Officers and Committees
1. Ted Bysiewicz, removal of silt from pond at 97 Poplar Road, Demerchment property.
J. Sipperly reported that a Cease and Desist was issued on December 21, 2020. Recently
Mr. Sipperly was made aware of this and contacted Ted. All parties involved met on the
site on April 5, 2022 to discuss the work to be done and when. Mr. Bysiewicz performed
the work as required and the Demerchants are satisfied as well.
Staff’s recommendation is to remove the Cease and Desist Order.
Motion: To close the Cease and Desist Order against Ted Bysiewicz. Moved by K.
McClellan; seconded by K. Rzasa, approved unanimously.
G. Public Open forum
11 members of the public stayed in attendance to talk about Pameacha Pond dam removal
project. J. Carta stated that there is no application that was submitted. Mr. Sipperly further
stated that this may not even be under this Agency’s authority as it may solely be a state
permit. This meeting was taped and recorded to hear the testimony.
H. Minutes of August 3, 2022
The minutes were reviewed as received. Motion: to approve the minutes of August 3, 2022
as received. Moved by K. McClellan; seconded by P. Dyka; approved unanimously
I. Communication and Bills
None
J. Adjournment
Motion: To adjourn at 9:58 pm. Moved by K. McClellan; seconded by D. Pritchard;
Approved unanimously.
Respectively Submitted,
James Sipperly, Secretary/Environmental Planner
Department of Land Use
Page 8 of 8
Agenda
Chair Joseph Carta
Vice-Chair Ken McClellan
Members Fred Terrasi Trevor Davis
Inland Wetlands David Pritchard
Jammie Middleton
Jennifer Greenberg
Brian Gartner
And Alternates
Steven Skultety
Jack Pieper
Vacant
Paul Dyka
Watercourses Agency Vacant
Vacant
Vacant
Staff James Sipperly, Environmental Planner
REGULAR MEETING
AGENDA
Wednesday, September 7, 2022
MEETING IN PERSON
MUNICIPAL BUILDING – COUNCIL CHAMBERS
7:00 P.M.
Meeting to be held in person. WEARING A MASK IS OPTIONAL
A. Call to Order
1. Pledge of Allegiance
1. Public Hearing
1. Request to fill 983 SF of wetlands and mitigate a 6,079 SF wetland area for a
commercial development at 550 Highland Ave. 2022-10
2. Old Business
1. Request to upgrade Red Road sewer pumping station which was originally constructed
in 1969 at 90 Red Road. Applicant/Agent: Middletown Water & Sewer Department.
2022-7
2. Subdivision to create five residential building lots at 665 Ridgewood Road (Map/Lot:
10-0008). Applicant/Agent: Hubbard Properties, LLC. 2022-9
D. New Business
E. Agency Review
None
F. Reports of Officers and Committees
1. Ted Bysiewicz, removal of silt from pond at 97 Poplar Road, Dermerchant property.
G. Public Open Forum
H. Minutes – August 3, 2022
I. Communication and Bills
1. Notification of a proposal for the redevelopment of a previously developed site.
Construction of the new residential, community and amenity buildings, townhomes,
If you require special accommodations for any meeting, please call the ADA Coordinator at (860) 638-4540, (voice) or (860)
638-4812 (TDD/TTY), or the Town Clerk’s Office at (860) 638-4910 at least ten (10) days prior to the scheduled meeting.
site drive and utilities will all be constructed almost entirely within the limits of the
original development at 100 Berlin Road and 15R Christian Hill Road, Cromwell.
Applicant/Agent: Berlin Land Holdings, LLC
J. Adjournment
Alternate Member Seating: Jack Pieper; Paul Dyka
If you require special accommodations for any meeting, please call the ADA Coordinator at (860) 638-4540, (voice) or (860)
638-4812 (TDD/TTY), or the Town Clerk’s Office at (860) 638-4910 at least ten (10) days prior to the scheduled meeting.
Get email alerts for Middletown
A daily email when new agendas and minutes are posted.