Inland / Wetlands & Water Courses Agency
Regular MeetingMiddletown, CT · October 2, 2024
Minutes
Chair Joseph Carta
Vice-Chair Ken McClellan
Members Fred Terrasi Trevor Davis
Inland Wetlands David Pritchard
Jammie Middleton
Jennifer Greenberg
Brian Gartner
And Alternates
Steven Skultety
Jack Pieper
Vacant
Paul Dyka
Watercourses Agency Christine Raczka (’27) Kristen Rzasa
Nanette Albright Fresher (’27)
Staff James Sipperly, Environmental Planner
REGULAR MEETING MINUTES
Wednesday – October 2, 2024
Meeting held in person only, Municipal Building, Common Council Chambers
7:00pm A video tape of this meeting was recorded.
Present: Paul Dyka
Jack Pieper
Ken McClellan
Joseph Carta
Nanette Albright Fresher
Fred Terrasi
David Pritchard
Trevor Davis
Absent: Steven Skultety
Brian Gartner
Jammie Middleton
Kristen Rzasa
Christine Raczka
Jennifer Greenberg
Public: Jim Cassidy, David Winkel, Mike Cannata,
Staff: James Sipperly, Environmental Planner
A. Call to Order
1. Chairman J. Carta called the meeting to order at 7:03pm and led the Pledge of Allegiance.
K. McClellan would like to add the August 14, 2024 minutes to the agenda under H. 2.
Motion: To add the August 14, 2024 under item H.2. Moved by K. McClellan; seconded by D.
Pritchard; approved unanimously.
B. Public Hearing
1. Proposed new 70,000 SF office and warehouse located at Middle Street (Map Lot, 01-0075)
Applicant/Agent: Gary Dayharsh/EriKelAri, LLC. W2024-12
J. Sipperly read a letter from Nina Fazio, R Levesque Associates, dated September 30, 2024, on
behalf of Gary Dayharsh to continue the Public Hearing until November 6, 2024 when site plan
revisions should be completed.
Motion: To table this application until November 6, 2024 to continue the Public Hearing.
Moved by K. McClellan; seconded by F. Terrasi; approved unanimously.
Page 1 of 7
C. Old Business
1. Proposed construction of a single family home within the upland review area located at
Middle Street (map-lot: 10-0156) Applicant/Agent: James Cassidy/Hallisey, Pearson &
Cassidy, Engineering Associates, Inc. W2024-11
J. Sipperly stated that the applicant has answered the commission’s concerns as well as the city
Engineer’s comments and the Public Hearing was closed. A draft motion was sent to
Commission members for consideration. Staff was asked to read the draft motion into the
record.
IWWA APPPLCATION W 2024-11
Applicant/Agent James Cassidy/Hallisey, Pearson & Cassidy Eng. Assoc. Inc.
Draft Motion:
That the Inland Wetlands and Watercourses Agency (hereinafter, “Agency”), having considered
application 2024-11 with due regard to the criteria enumerated in Section 22a-41 of the Connecticut
General Statutes and Section 8 of the Inland Wetlands & Watercourses Regulations of the City of
Middletown finds the following:
1. That the proposed activities are to construct a single family dwelling, driveway grading within
the upland review area.
2. That a similar application 2006-03 was approved by this Agency in 2006 but construction
activities were never commenced.
3. That the inlands wetlands and watercourses on the site were delineated by Matt
Davidson, Professional Soil Scientist on 6/01/24 and 6/24/2, and shown correctly on the plan
referenced below.
4. That the comments from Tom Nigosanti, City Engineer dated September 5, 2024 have been
addressed by the applicant.
5. That a wetland report dated July 9, 2024 from Matt Davidson was received on July 26, 2024.
6. That a request for review of the NDDB was sent to the CT DEEP wildlife division but a response
has not been received.
7. That the site will be served by city water and city sewer.
8. That there are two proposed driveway crossings. The first will have 672sqft of disturbance and
the second 320sqft of disturbance. The entire site is within the 100’ upland review area.
9. That the proposed work, as specified and conditioned below, is in conformance with the
purposes and provisions of said sections and furthermore, will not have a significant adverse
effect on the adjacent inland wetlands and watercourses.
Therefore, permit # W 2024-11 is granted, with conditions, to allow the following regulated activities
as depicted on the submitted plan entitled:
“Property/Topographic Survey, showing existing conditions prepared for The Cannata Construction
Company, Mile Lane (Map-Lot: 10-0156) Lot 4 Mile Lane, Middletown, CT,
Scale 1”=40’, dated July 25, 2024, revised September 3, 2024, prepared by Hallisey, Pearson and
Cassidy, Civil Engineers and Land Surveyors”
This Permit is issued by the Agency subject to the following conditions and/or modifications as
follows:
Page 2 of 7
1. If the authorized activity is not completed within five (5) years from the date of approval
by the Agency that is, on or before October 2, 2029 said activity shall cease and, if not
previously revoked or specifically extended, this Permit shall be null and void.
2. The permittee shall notify the Wetlands Officer immediately upon the commencement of
work and upon its completion.
3. Prior to the commencement of any site work, the Permittees and/or their agent shall
properly install any and all sedimentation and erosion (S&E) control measures as depicted
on the site plans approved by the Agency. Changes to S&E controls may be made in order
to accommodate field conditions so long as they provide equal or greater protection
against S&E into the regulated wetlands and upland review area.
4. A copy of the plans approved by the Agency shall be kept at the job site for the duration of
construction activities as approved herein.
5. During construction, as represented to the Agency, no material shall be stockpiled within
the regulated area or in areas other than those depicted on the site plans approved by the
Agency.
6. The City reserves the right to inspect the site work area at any time from commencement
to conclusion of the property to ensure permit conditions and compliance with the
regulations is being met.
7. All sedimentation and erosion control devices shall remain in place until the end of
construction and the site is deemed stabilized by the City’s Wetlands Enforcement Officer
or other authorized agent of the Land Use Department. An inspection can be scheduled by
calling 860-638-4590.
8. All work, including all regulated activities conducted pursuant to this authorization, shall
be consistent with the terms and conditions of this Permit. Any structures, excavation, fill,
obstructions, encroachments, and/or regulated activities not specifically identified and
authorized herein shall constitute a violation of this Permit and may result in its
modification, suspension, or revocation. Upon initiation of the activities authorized herein,
the Permittees accept and agree to comply fully with all terms and conditions of this
Permit.
9. No equipment or material including, without limitation, fill, construction materials and/or
debris, shall be deposited, placed, and/or stored in any regulated area, on or off site,
unless specifically authorized by this Permit.
10. The authorizations and activities set forth in this Permit are not transferable without the
written consent of the Agency or its Authorized Agent.
11. In evaluating this application, the Agency has relied on information provided by the
Permittees. If such information subsequently proves to be false, deceptive, incomplete
and/or inaccurate, this Permit may be modified, suspended, or revoked by the Agency.
12. If applicable, flagging associated with the wetland boundary shall remain until the
completion of construction activities and shall not be removed until all work is complete
and the site is stabilized.
13. The Permittee shall employ best management practices, consistent with the terms and
conditions of this Permit, to control stormwater discharge, to prevent erosion and
sediment migration beyond the work area(s), and to otherwise prevent pollution of inland
wetlands and watercourses. The Permittees shall immediately inform the City’s Inland
Wetlands Enforcement Officer of any problems related to activities in the regulated area,
which have been impacted during the course of, or caused by, the authorized work.
Page 3 of 7
14. This Permit is subject to, and does not detract from, any present or future property rights
or other rights or powers of the State of Connecticut, and conveys no property rights in
real estate or material nor any exclusive privileges, and is further subject to any and all
public and private rights and to any federal, state, or local laws or regulations pertinent to
the property or activity affected hereby.
15. Nothing in these regulations shall obviate any requirement for the Permittee to obtain any
other assent, permit, or license required by law and/or regulation by the Government of
the United States, the State of Connecticut, or any other political subdivisions thereof.
Obtaining such assents, permits, and/or licenses is solely the responsibility of the
Permittee.
16. That any storage of fuel, oils and other chemicals on the site shall be stored in a secondary
container to prevent the possibilities of spills and/or leaks.
17. That any comments received from the CT DEEP regarding the NDDB review shall be
incorporated herein by reference and adhered to.
18. That a bond calculated by the Town Engineer covering the erosion and sedimentation
control measure costs shall be submitted to the City of Middletown using a bank check or
money order prior to the commencement of construction activities.
Moved by D. Pritchard; seconded by T. Davis. Discussion ensued. T. Davis feels that there
are too much wetlands on the site and that all of the lot is within the 100’ upland review
area. N. Albright Thresher doesn’t like the fact that there has been no response from CT
DEEP regarding the NDDB request.
Vote was called: Approved with a vote of 6-2, with T. Davis and N. Albright Thresher voting
no.
2. Proposed park improvements which include a walking trail, larger parking lot and sidewalks,
and relocation of a portion of Thomas Street within 100 feet of Butternut hollow Pond located
at 297 Butternut Street. Applicant/Agent Howard Weissberg/City of Middletown. W2024-10
Mr. Sipperly stated that all the Commission’s questions were answered at the last meeting by
Acting Public Works Director, Howard Weissberg. Staff was asked to read a draft motion into
the record.
1.000000000000000000000
IWWA APPLICATION W 2024-10
Applicant/Agent Howard Weissberg/City of Middletown
Draft Motion:
That the Inland Wetlands and Watercourses Agency (hereinafter, “Agency”), having considered
application 2024-10 with due regard to the criteria enumerated in Section 22a-41 of the Connecticut
General Statutes and Section 8 of the Inland Wetlands & Watercourses Regulations of the City of
Middletown finds the following:
1. That the proposed activities are to make park improvements which include a walking trail, a
larger parking area with improved drainage and sidewalks, and relocation of a portion of Thomas
Street.
Page 4 of 7
2. That the proposed work, as specified and conditioned below, is in conformance with the
purposes and provisions of said sections and furthermore, will not have a significant adverse
effect on the adjacent inland wetlands and watercourses.
Therefore, permit # W 2024-10 is granted, with conditions, to allow the following regulated activities
as depicted on the submitted plan entitled:
“Butternut Pond Improvements, scale 1”=50’, date received July 16, 2024, prepared by Tom
Nigosanti, City Engineer”
This Permit is issued by the Agency subject to the following conditions and/or modifications as
follows:
1. If the authorized activity is not completed within five (5) years from the date of approval by
the Agency that is, on or before October 2, 2029 said activity shall cease and, if not previously
revoked or specifically extended, this Permit shall be null and void.
2. The permittee shall notify the Wetlands Officer immediately upon the commencement of
work and upon its completion.
3. Prior to the commencement of any site work, the Permittees and/or their agent shall
properly install any and all sedimentation and erosion (S&E) control measures as depicted on
the site plans approved by the Agency. Changes to S&E controls may be made in order to
accommodate field conditions so long as they provide equal or greater protection against S&E
into the regulated wetlands and upland review area.
4. A copy of the plans approved by the Agency shall be kept at the job site for the duration of
construction activities as approved herein.
5. During construction, as represented to the Agency, no material shall be stockpiled within
the regulated area or in areas other than those depicted on the site plans approved by the
Agency.
6. The City reserves the right to inspect the site work area at any time from commencement to
conclusion of the property to ensure permit conditions and compliance with the regulations is
being met.
7. All sedimentation and erosion control devices shall remain in place until the end of
construction and the site is deemed stabilized by the City’s Wetlands Enforcement Officer or
other authorized agent of the Land Use Department. An inspection can be scheduled by calling
860-638-4590.
8. All work, including all regulated activities conducted pursuant to this authorization, shall be
consistent with the terms and conditions of this Permit. Any structures, excavation, fill,
obstructions, encroachments, and/or regulated activities not specifically identified and
authorized herein shall constitute a violation of this Permit and may result in its modification,
suspension, or revocation. Upon initiation of the activities authorized herein, the Permittees
accept and agree to comply fully with all terms and conditions of this Permit.
9. No equipment or material including, without limitation, fill, construction materials and/or
debris, shall be deposited, placed, and/or stored in any regulated area, on or off site, unless
specifically authorized by this Permit.
10. The authorizations and activities set forth in this Permit are not transferable without the
written consent of the Agency or its Authorized Agent.
Page 5 of 7
11. In evaluating this application, the Agency has relied on information provided by the
Permittees. If such information subsequently proves to be false, deceptive, incomplete
and/or inaccurate, this Permit may be modified, suspended, or revoked by the Agency.
12. If applicable, flagging associated with the wetland boundary shall remain until the
completion of construction activities and shall not be removed until all work is complete and
the site is stabilized.
13. The Permittee shall employ best management practices, consistent with the terms and
conditions of this Permit, to control stormwater discharge, to prevent erosion and sediment
migration beyond the work area(s), and to otherwise prevent pollution of inland wetlands and
watercourses. The Permittees shall immediately inform the City’s Inland Wetlands
Enforcement Officer of any problems related to activities in the regulated area, which have
been impacted during the course of, or caused by, the authorized work.
14. This Permit is subject to, and does not detract from, any present or future property rights
or other rights or powers of the State of Connecticut, and conveys no property rights in real
estate or material nor any exclusive privileges, and is further subject to any and all public and
private rights and to any federal, state, or local laws or regulations pertinent to the property
or activity affected hereby.
15. Nothing in these regulations shall obviate any requirement for the Permittee to obtain any
other assent, permit, or license required by law and/or regulation by the Government of the
United States, the State of Connecticut, or any other political subdivisions thereof. Obtaining
such assents, permits, and/or licenses is solely the responsibility of the Permittee.
16. That any storage of fuel, oils and other chemicals on the site shall be stored in a secondary
container to prevent the possibilities of spills and/or leaks.
Moved by T. Davis; seconded by K. McClellan; approved unaimously
D. New Business
None
E. Agency Review
None
F. Reports of Officers and Committees
None
H. Minutes
1. Regular meeting of September 4, 2024
Motion: To approve the minutes of September 4, 2024 as received; moved by K. McClellan;
seconded by D. Pritchard; approved unanimously
2. Special meeting of August 14, 2024
Motion: To approve the minutes of August 14, 2024; moved by K. McClellan; seconded by F.
Terrasi; approved unanimously
I. Communication and Bills
None
J. MIWWA regulation amendments
Page 6 of 7
J. Sipperly reported that the committee, J. Sipperly, J. Greenberg, K. McClellan met and reviewed
more sections. One more meeting will be needed to finish the review and then it will go to the
commission and the Ordinance Study Committee for review.
K. Adjournment
Motion to adjourn at 8:15pm
Moved by T. Davis; seconded by K. McClellan; approved unanimously
Respectively Submitted,
James Sipperly, Secretary
Department of Land Use
Page 7 of 7
Agenda
Chair Joseph Carta
Vice-Chair Ken McClellan
Members Fred Terrasi Trevor Davis
Inland Wetlands David Pritchard
Jammie Middleton
Jennifer Greenberg
Brian Gartner
And Alternates
Steven Skultety
Jack Pieper
Vacant
Paul Dyka
Watercourses Agency Kristen Rzasa
Christine Raczka (’27)
Nanette Albright Fresher (’27)
Staff James Sipperly, Environmental Planner
REGULAR MEETING
AGENDA
Wednesday, October 2, 2024
MUNICIPAL BUILDING – COUNCIL CHAMBERS
7:00 P.M.
A. Call to Order
1. Pledge of Allegiance
B. Public Hearing
1. Proposed new 70,000 SF office and warehouse within the upland review area located
at Middle Street (Map-Lot: 01-0075). Applicant/Agent: Gary Dayharsh/EriKelAri,
LLC. W2024-12
C. Old Business
1. Proposed construction of a single family home within the upland review area located
at Mile Lane (Map-Lot: 10-0156). Applicant/Agent: James Cassidy/Hallisey, Pearson
& Cassidy, Engineering Associates, Inc. W2024-11
2. Proposed park improvements which include a walking trail, larger parking lot
sidewalks, and relocation of a portion of Thomas Street within 100 feet of Butternut
Hollow Pond located at 297 Butternut Street. Applicant/Agent: Howard
Weissberg/City of Middletown. W2024-10
3. Proposed new 70,000 SF office and warehouse located at Middle Street (Map-Lot:
01-0075). Applicant/Agent: Gary Dayharsh/EriKelAri, LLC. W2024-12
D. New Business
E. Agency Review
F. Reports of Officers and Committees
1. Meriden application 836 & 840 Westfield Road – horse riding rink – 225, 000 cubic
yards of rock excavation
G. Public Open Forum
H. Minutes
1. Regular meeting September 4, 2024
If you require special accommodations for any meeting, please call the ADA Coordinator at (860) 638-4540, (voice) or (860)
638-4812 (TDD/TTY), or the Town Clerk’s Office at (860) 638-4910 at least ten (10) days prior to the scheduled meeting.
I. Communication and Bills
J. MIWWA regulation amendments
K. Adjournment
Alternate Member Seating: 1) Jack Pieper; 2) Paul Dyka; 3) Kristen Rzasa;
4) Nanette Albright Fresher; 5) Christine Raczka
If you require special accommodations for any meeting, please call the ADA Coordinator at (860) 638-4540, (voice) or (860)
638-4812 (TDD/TTY), or the Town Clerk’s Office at (860) 638-4910 at least ten (10) days prior to the scheduled meeting.
Get email alerts for Middletown