Woodrow Wilson Building Committee
Regular MeetingMiddletown, CT · February 24, 2020
Minutes
02/24/2020
Page 1
Committee Members Committee Staff
Councilman Gene Nocera, Co-Chair Dr. Michael Conner; Superintendent
Councilwoman Jeanette Blackwell Co-Chair Marco Gaylord; Director Operations
Councilman Philip Pessina Vice-Chair Elise McDermott; Finance and Budget
Kristy Byrd Peter Staye; Director Facilities
Sheila Daniels Erin Thazhampallath; Secretary
John Giuliano
Richard Pelletier
John Phillips
Theodore Raczka
Stephen Zarger
Anita Dempsey-White
Meeting Minutes
***Special Meeting ***
Woodrow Wilson Middle School Building Committee
Monday, February 24, 2020
5:30 P.M
BOE Building, 311 Hunting Hill Avenue, Conference Room A
BUILDING IS WHEELCHAIR ACCESSIBLE
Special Note: If you require a special accommodation for our meeting, please contact Laura Riunte, ADA
Coordinator at (*60)638-4540, (*60) 638-4541 Voice and (*60)638-4812 (TDD/TTY).
Members Present: Councilman Philip J. Pessina
Councilman Gene Nocera
Councilwoman Jeanette Blackwell
Kristy Byrd
Sheila Daniels
Richard Pelletier
Theodore Raczka
Anita Dempsey-White
John Giuliano
Members Absent: John Phillips
Stephen Zarger
Staff Present: Marco Gaylord; Director Operations
Elise McDermott; Finance and Budget
Peter Staye; Director Facilities
Erin Thazhampallath; Secretary
Others Present: Mark Jeffko, Project Exec, O&G Industries
02/24/2020
Page 2
Hristo Miljovski, Project Engineer, O&G Industries
Joe Vetro; Project Manager, O&G Industries
Randall Luther; TSKP
Mary-Lynn Radych; TSKP
Daniel Penny, Middletown Resident
1. Councilman Gene Nocera, Co-Chair calls the meeting to order at 5:31pm.
2. No public comments
3. Councilman Gene Nocera calls for a Motion to Approve the Meeting Minutes of
January 27, 2020. Motion by Philip Pessina and seconded by Jeanette Blackwell to
approve the minutes of the meeting of January 27, 2020. Motion passed unanimously.
4. Construction Updates
4.1 Workflow Status: In Progress
A. O&G Status Update: Joe Vetro; Project Manager, O&G Industries presents to the
Committee a Project Report and directs the committee to the third page with the Summary
Date Sheet. This data sheet shows the original completion dates and projected current
completion dates, the physical progress percentage completed based on the school site
work & landscaping, and the construction budget. The contingency funds available are
$2,037,837.00 and the total funds available are $2,189,355.00. The total is the contingency
and allowances added together. Councilman Gene Nocera asks Joe Vetro if he is concerned
about the contingency amount based on his experience with big projects such as this. Vetro
states that we should be fine. The amount goes fast but this is not a renovation and being
that it is a new building he does not believe we will experience anything dramatic. Nocera
states that hopefully we progress on this path. Mark Jeffko; Project Exec, O&G Industries
states that we are looking at the construction contingency carried in the O&G GMP and we
are not looking at the Owners Contingency (Total Contingency) which will be a different
amount. Elise McDermott; Finance and Budget will be presenting the Total Contingency in
the Financial Report Update. Moving forward both line items will be presented on the
Summary Date Sheet.
Vetro presents project costs and schedule issues which tend to be ASI and RFI and the
Project Commentary and Items for Approval. Sheila Daniels asks Vetro if they are where
they want to be in the construction process. Vetro states that they are running 30 days
behind but they will make that time up. Right now in the construction process there are
only a few trades out on site. In a few weeks when there are more trades on site there will
be the opportunity to make up time.
02/24/2020
Page 3
Vetro presents the items for approval that have already been presented and approved by
the Change Order Subcommittee.
PCO #20: Electrical Allowances Adjustment Total -$13,271.00
Returning an unused portion of the electrical allowances from Phase One.
PCO #21: HVAC Allowances Adjustment Total = -$2,443.00
Returning unused allowances.
PCO #22: Additional Electrical Bond Cost Total= $2,163.00
The Electrician has a contract which includes the bond. Any Change Order work that was
added to his contract does not included the bond so it is normal to pay at the end when his
contract closes. This is only additional bond for his CO work.
PCO #23 CE-036, RFI-15 Waterproofing @ Orchestra Pit Total = $18,782.00
TSKP has looked at the pit and decided that it needs to be waterproofed.
PCO #24 CE-042, Temporary Classroom Allowance Total = $0.00
This was included in the General Trade Contract and this is the allowance for the Temp
Classroom Trailer. They are trying to close this contract and O&G will now take the cost and
continue the monthly payments.
PCO #25 Temporary Road Closure Signage Total = $0.00
This goes against the O&G contingency. When the road was closed the safety
department recognized it as a safety issue that needed a design for where the signage
legally needed to be. This cost is to pay Milone and Macbroom to do the design and provide
us with where the signage needs to go.
PCO #26 CE-037, RFI-39 Additional Waterproofing Total = $10,370.00
This is waterproofing over the stadium stairs. TSKP decided this needed waterproofing.
Sheila Daniels asks why this scope of work was not known in the planning process. Mary-
Lynn Radych; TSKP explains that the ground water level at the orchestra pit necessitates
this. After reevaluating the footing drainage TSKP identified an additional section that
needed waterproofing but the intention was always for it to be waterproofed. Vetro
explains that there is a lot of ground water here and there are already three pumps to
maintain that water.
02/24/2020
Page 4
Jeanette Blackwell calls for a motion to accept these Change Orders for a Total of
$15,601.00. Motion by Gene Nocera and seconded by Richard Pelletier. Motion approved
unanimously.
Vetro explains that the foundations are up in areas C and B and they are finishing up area B
which will be done by this Wednesday. The foundation walls are being dug now for Area A
(the auditorium). They work C, B, A. They start in area C because that is where the
mechanical rooms are and it’s a smaller area. The hardest part is the Auditorium so they
start in the easier part first to get up and moving along. Steel is starting in two weeks in
section C. Right now they are doing the under slab work in area C and laying down poly and
setting floor drains. It’s all in progress and being done in steps. Area C is slab prep work and
Area B is under slab and Area A is foundation. They will continue to flow that way. The idea
is to keep as many trades on site as possible.
5. Financial Report:
5.1: Elise McDermott; Finance and Budget, presents the Financial Update Report.
McDermott shows that the remaining balance in the fund is just a little over $7Million. The
contingency that O&G has is purely for the construction of the school but that does not
reflect how much money is left in the fund for other things that may come up. If you take
into consideration the proposed expenditures that we have currently, that would bring the
remaining balance down to $6.6Million. There are proposed expenditures such as: bonding
costs, Eversource utility bills, utility pole relocation, tank removal. When you take into
consideration all the proposed expenditures it reflects a slightly different number than
would be shown in the system. It’s good to be aware that there are things coming up that
will impact the balance. McDermott states that after reviewing O&G Application #7 with
Peter Staye, everything is good and in line with each other. The budget is balanced to the
penny and the O&G invoice looks great and ready for approval. McDermott ask O&G about
a previous conversation about a temporary new service meter and Joe Vetro states that it is
not installed yet. McDermott asks for an estimate so she can add that to the report for next
month. McDermott asks Co-Chair Gene Nocera if there is an update to the cost savings
letter from the Mayor to Eversource. Peter Staye gives an update on Eversource. Eversource
originally proposed that if the City agreed to change the existing boilers in the current
structure to natural gas within 5 years than the $81,000/84,000 pole line relocation fee
would be waived. When we got confirmation of the Mayor signing that contract Eversource
changed the deal to 2 years to connect with $54,000 saved. Staye mentioned to them that
that may be a problem and didn’t feel good about the sudden change in the agreement.
Now Eversource has provided a draft agreement with the 5 Year period of time connection
agreement or a $54,800 Fee with the provision that they reserve the right to look at the
consumption over those 5 years at the middle school and if consumption is not adequate
02/24/2020
Page 5
then they can change the amount that needs to be payed back. Eversource is to provide the
City Attorney a formal agreement letter rather than a draft which they stated would be
provided by next week. Gene Nocera thanks Peter Staye for the time he has spent on the
negotiations with Eversource and it looks like this is moving to a satisfactory conclusion.
TSKP Financial Update: Mary-Lynn Radych; TSKP presents to the committee two fee
proposals from CES. The first one is for the additional work for the increase in the smoke
detection scope requested by the Fire Marshall and the other one has to do with Eversource
underground routing work. The smoke detection design work fee is $5,500 (including the
TSKP markup fee). The Eversource underground routing design work fee is $7,700 (including
the TSKP markup fee). Jeanette Blackwell makes a motion for the approval of the two
updates provides by TSKP regarding the Smoke Detection and Eversource routing in the
amount of $13,200. Sheila Daniels questions where this is included on the Agenda and that
in the future this should be more clearly noted. Radych also notes that TSKP will not be
charging additional services for these two items. Motion by Gene Nocera and seconded by
Richard Pelletier. Motion is approved unanimously.
5.2 Invoice Approval
A. Motion by Gene Nocera and seconded by Jeanette Blackwell to approve O&G
Invoice #7. Motion approved unanimously.
B. Motion by Gene Nocera and seconded by Jeanette Blackwell to approve TSKP
Invoice #21 in the amount of $36,238.50. Motion approved unanimously.
C. Motion by Gene Nocera and seconded by Jeanette Blackwell to approve the
Eversource Trailer Utility Bill in the amount of $1,161.11. Motion approved
unanimously.
D. Motion by Jeanette Blackwell and seconded by Richard Pelletier to approve the
WWBC Secretary Timecard in the amount of $450. Motion approved
unanimously.
6. Discussion
6.1 Discussion on the current WWMS Cafeteria: Philip Pessina states that there was a
meeting with TSKP and Landmark concerning the building design and we will stay with the
original design proposed by TSKP. If there is any expansion, it would be researched in the
rear of the building. Any work on that portion of the city project will not start until the
school project is complete. There was another meeting with Milone and Macbroom to look
at possible changes in the small field that is on the architect drawing and Pessina states that
originally Macbroom had done a study and it was always a recommendation to put a field
behind the new existing Jr High School (using the parks bond). Part of that was because the
02/24/2020
Page 6
committee wanted the Jr. High field to be up to the standards with irrigation, sod, score
board, lighting, fence, drainage. The field is being looked at in reference to the standards
and if it doesn’t meet those standards then it can be an additional field for the rec league
and will be an additional field that the youth of the city can utilize. The JR. High will also
have this field for their use. The committee will be updated if any movement is made. This is
not part of the school project. Sheila Daniels asks if that has changed because she thought
that initially it would be a practice field because the new school is being built on the current
practice field. Pessina states that because of the size of the field it does not meet the
standard of the Jr High School field but it still can be used. Daniels wants to know if the plan
has changed since the initial conversation and Pessina states that they want the field to
meet the standards that are across the street at Pat Kidney Field. Gene Nocera states that
once Pat Kidney was designed they were short a Lacrosse and Soccer Field. It was always
the intention to design a field to make up for that lose. Nocera states that fields have to be
developed properly from the beginning. Sheila asks for confirmation that the field will be
used as a practice field since the new school is being built on what was a practice field, she
notes that it is important to make sure that the field’s designated top priority use is as a
practice field. Pessina states that this field will be for the Jr. High but if possible it can be a
multiuse field.
7. Motion by Gene Nocera and seconded by Philip Pessina to Adjourn the meeting at
6:17pm. Motion passed unanimously.
Respectfully Submitted,
Erin Thazhampallath
Recording Secretary
Agenda
Committee Members Committee Staff
Councilman Gene Nocera Co-Chair Dr. Michael Conner; Superintendent
Councilwoman Jeanette Blackwell Co-Chair Marco Gaylord; Director Operations
Councilman Phillip J. Pessina Vice-Chair Elise McDermott; Finance and Budget
Kristy Byrd Peter Staye; Director Facilities
Sheila Daniels Erin Thazhampallath; Secretary
John Giuliano
Richard Pelletier
John Phillips
Theodore Raczka
Stephen Zarger
Anita Dempsey-White
AGENDA
*** Special Meeting ***
Woodrow Wilson Middle School Building Committee
Monday, February 24, 2020
5:30-6:30pm
BOE Building, 311 Hunting Hill Avenue, Conference Room A
BUILDING IS WHEELCHAIR ACCESSIBLE
Special Note: If you require a special accommodation for our meeting, please contact Laura Riunte, ADA
Coordinator at (*60)638-4540, (*60) 638-4541 Voice and (*60)638-4812 (TDD/TTY).
1. Chairman call the Meeting to order.
2. Public Comments
3. Approval of the Minutes
3.1 - Meeting Minutes of January 27, 2020
4. Construction Updates
4.1 – Workflow Status: In Progress
A. O&G Status Update
B. TSKP Status Update
4.2 - O&G Monthly project report:
A. Monthly project report review
B. Items for Approval Phase 1
C. Items for Approval Phase 2
5. Financial Report
5.1 – Financial Update
5.2 - Invoice Approval
A. O&G Invoice #7
B. TSKP Invoice #21, $36,238.50
C. Eversource Trailer Utility Bill (01/30/20) $1,161.11
D. WWBC Secretary Timecard $450
6. Discussion
6.1 - Discussion on the current WWMS cafeteria
• Future use of existing school/Community Center
6 Adjournment