MP Regional Water Authority TAC Meeting
Regular MeetingMonterey, CA · April 4, 2016
Minutes
MINUTES
MONTEREY PENINSULA WATER AUTHORITY (MPRWA)
TECHNICAL ADVISORY COMMITTEE (TAC)
Regular Meeting
10:30 AM, Monday, April 4, 2016
COUNCIL CHAMBER
580 PACIFIC STREET
MONTEREY, CALIFORNIA
Members Present: Narigi, Riedl, Riley, Stoldt, Van Der Maaten, Cullem
Members Absent: Scuito, Huss
Staff Present: Legal Counsel Freeman, Clerk Romero
CALL TO ORDER
Executive Director Cullem called the meeting to order at 10:31am.
ROLL CALL
Member Huss and Sciuto absent. Member Van Der Maaten came in at 10:34am.
PLEDGE OF ALLEGIANCE
REPORTS FROM TAC MEMBERS
None
PUBLIC COMMENTS
None
APPROVAL OF MINUTES
1. Approve Minutes from January 27, 2016 - Romero
Action: Approved
PUBLIC COMMENTS
None
On a motion by Member Narigi, seconded by Member Riley, and carried by the following vote,
the MPRWA Technical Advisory Committee approved the January 27, 2016 minutes:
AYES: 6 MEMBERS: Narigi, Riedl, Riley, Stoldt, Van Der Maaten,
Cullem
NOES: 0 MEMBERS: None
ABSENT: 2 MEMBERS: Huss, Sciuto
ABSTAIN: 0 MEMBERS: None
RECUSED: 0 MEMBERS: None
MPRWA TAC Minutes Monday, April 4, 2016
CONSENT ITEMS
PUBLIC COMMENTS
Tom Rowley, from the Monterey Peninsula Taxpayers Association (MPTA), asked for
clarification on the time of the California Public Utilities Commission (CPUC) workshop
in April.
Receiving no further requests to speak Director Cullem closed public comments.
Member Stoldt responded to Mr. Rowley that the workshop on April 14th with the CPUC during
the next Monterey Regional Peninsula Water Authority (MPRWA) meeting, and the topic will be
the extended schedule for the Environmental Impact Study (EIR), and the conversation will
include causes for the delay in the schedule and what can be done to expedite it. He added that
the CPUC staff present at the Workshop will be able to answer questions on behalf of the entire
organization.
On a motion by Committee Member Narigi, seconded by Committee Member Riley and carried
by the following vote, the MPRWA Technical Advisory Committee Approved the Consent Items:
AYES: 6 MEMBERS: Narigi, Riedl, Riley, Stoldt, Van Der Maaten, Cullem
NOES: 0 MEMBERS: None
ABSENT: 2 MEMBERS: Huss, Sciuto
ABSTAIN: 0 MEMBERS: None
RECUSED: 0 MEMBERS: None
2. Receive "Notice to Parties" Concerning the CPUC Schedule for the Monterey Peninsula Water
Supply Project (MPWSP) - Cullem
Action: Approved
AGENDA ITEMS
3. Receive Update on GWR Schedule and Financing - Sciuto/Stoldt
Action: Received update; Discussed
Member Stoldt gave an update on the Ground Water Replenishment (GWR) schedule and
briefly explained different processes that are affecting the schedule, such as: water rights
negotiations and protests, the water purchase agreement, and the biological opinion on wildlife.
The Office of Ratepayer Advocates (ORA) has found that most of their criteria on GWR has
been met but want to know what the “soft cost cap” will be. He added that an energy purchase
agreement was approved which will provide the power needed for the advanced water
treatment facility and pump station at a discounted rate compared to the desal project. He also
said the Marina Coast Water District approved a contract for the design of the pipeline from the
water treatment facility to the Seaside Basin. Member Stoldt said that GWR will be more cost
effective with a smaller desal plant.
2
MPRWA TAC Minutes Monday, April 4, 2016
PUBLIC COMMENTS
Tom Rowley, MPTA, asked for clarification on the soft cost cap. He also asked if there is
anything that will cause a delay to GWR.
Receiving no further requests to speak Director Cullem closed public comments.
Member Stoldt responded to public comment saying that he doesn't see anything that would be
a show stopper to GWR. He explained that the soft cost cap is the process in which a public
authority looks at all the bids for a project and if the cost comes in below a certain amount that
has been pre-established as a “cap”, then the project will be approved by the public authority.
Member Riley asked about debt equivalency for GWR. Member Stoldt responded that ORA
considers debt equivalence a non-issue and all effects have been mitigated.
Director Cullem said GWR is the most promising project that will get through the milestones
before desal starts.
No action was taken by the Committee.
4. Receive Report, Discuss, and Make Recommendations as to Whether Cal Am Can Receive
and Utilize Ground Water Replenishment (GWR) Water Should the PWM/GWR Project Come
on Line Before Cal Am's Desal Facility - Crooks
Action: Received report; Discussed; No action taken at this time
Ian Crooks from California American Water (Cal Am) gave a presentation on whether they can
receive and utilize Ground Water Replenishment (GWR) should GWR come online before the
desal facility. He showed slides of the existing pipelines and hydraulic trough area in Monterey,
wells in Seaside, and the Aquifer Storage and Recovery (ASR). He explained that in order to
get water through the existing grid, pressures have to be increased and there is a limitation to
take GWR and get around Seaside. He specified that a 36” pipeline is needed in order allow
transfer and delivery of water anywhere in the system.
During the discussion the Committee questioned whether the 36” pipeline would be necessary
without a desal plant, and the consensus was that the pipeline would be good for the long term
and it is already approved environmentally. It was discussed that the pipeline would be bi-
directional to allow a larger capacity of water to be stored in ASR.
The Committee discussed the total cost of the pipeline project, which is estimated at $41
million. It was reiterated by Mr. Crooks that the 36” pipeline is necessary for multiple water
projects in the portfolio, and allow maximizing the use of GWR, ASR, and the permits for
extracting from the Carmel Valley River when the levels are high. In summary, the 36” pipeline
would allow the utilization of all excess water and store it for when water demands are higher
and the flexibility to get water around the hydraulic trough.
The Committee established that the 36” pipeline is a high priority, and although the cost is
significant the pipeline has many long term benefits to the entire water supply project. The
Committee discussed the surcharges for taxpayers to fund the pipeline project and the
possibility that they may be increased slowly over time. The Committee deliberated that the
3
MPRWA TAC Minutes Monday, April 4, 2016
pipeline project is necessary to maximize GWR and ASR, and will accommodate the small or
large size desal plant.
Member Van Der Maaten questioned if the pipeline project funding could be included with the
approval of funding for the GWR. Member Stoldt said that this is worth looking into. Mr. Crooks
said that the 36” pipeline is a standalone Cal-Am project and can be funded and approved
separately before the desal plant. Executive Director Cullem said that it may be an advantage
to the public to have phase II of the surcharge collected earlier and at a lower level to help fund
the pipeline project.
Member Stoldt said that the Committee should give a technical recommendation to the
Monterey Peninsula Regional Water Authority (the “Authority”) in May or June of this year after
more information is obtained. Member Riley suggested requested expedited the surcharge to
get the funding started for the pipeline project to avoid have a steep increase for the rate payer.
PUBLIC COMMENTS
Tom Rowely, MPTA, said that another $41 million for extra for the pipeline project will be
an added burden to the ratepayer. He also said that the Authority should know that the
excess flow in the Carmel River will be counted against the pumping from the river and
affects the cease and desist (CDO) extension.
Member Stoldt reported in response to Mr. Rowley that in 2010 and 2011, 1,100 acre feet of
excess water was able to be stored for later use. He said ideally any excess water would be
stored for later when it is needed, but the Fish and Wildlife group would like the water removed
from the Carmel River put back in the same year. Ian Crooks responded to Mr. Rowley and
said that the $41 million for the pipeline project is just an estimate, and some money is already
applicable toward this amount.
At the end of their discussion, the Committee decided to bring back this item at a future meeting
when there is more information available before giving a recommendation to the Authority.
No action was taken on this item.
5. Receive Suggestions from Authority President Jason Burnett on Modifications to the Policy
Position Statement and Discuss Progress of the TAC Ad Hoc Committee Considering Changes
to the Statement - Cullem
Action: Received Suggestions to Policy; Discussed Progress of the Ad Hoc Committee
Executive Director Cullem explained that at the last meeting the Committee formed an Ad Hoc
Committee consisting of George Riley and Paul Sciuto, and has met to discuss modifications to
the Policy Position Statement for the Authority. It was agreed that the policy should be more
succinct and clear, and possibly separate the objectives and tasks. Authority President Burnett
has given some suggestions on modifications to the existing Policy Position Statement, and the
Ad Hoc Committee will discuss these suggestions at their next meeting.
4
MPRWA TAC Minutes Monday, April 4, 2016
PUBLIC COMMENTS
None
The Committee reviewed the input from Authority President Burnett, and agreed that the Ad
Hoc Committee will have another meeting to modify and shorten the Position Policy Statement,
and bring back the modified Statement to the Committee when it is finalized.
ADJOURNMENT
Meeting adjourned at 11:44am.
Respectfully Submitted, Approved,
Nova Romero, Committee Clerk President MPRWA
5
Agenda
Agenda
Monterey Peninsula Regional Water Authority (MPRWA)
Technical Advisory Committee (TAC)
Regular Meeting
10:30 AM, Monday, April 4, 2016
Council Chamber
580 Pacific Street
Monterey, California
CALL TO ORDER
ROLL CALL
PLEDGE OF ALLEGIANCE
REPORTS FROM TAC MEMBERS
PUBLIC COMMENTS
PUBLIC COMMENTS allows you, the public, to speak for a maximum of three minutes on any
subject which is within the jurisdiction of the MPRWA TAC and which is not on the agenda. Any
person or group desiring to bring an item to the attention of the Committee may do so by
addressing the Committee during Public Comments or by addressing a letter of explanation to:
MPRWA TAC, Attn: Monterey City Clerk, 580 Pacific St, Monterey, CA 93940. The appropriate
staff person will contact the sender concerning the details.
APPROVAL OF MINUTES
1. Approve Minutes from January 27, 2016 – Romero
CONSENT ITEMS
CONSENT AGENDA consists of those items which are routine and for which a staff
recommendation has been prepared. A member of the public or a Councilmember may request
that an item be placed on the regular agenda for further discussion.
2. Receive "Notice to Parties" Concerning the CPUC Schedule for the Monterey Peninsula
Water Supply Project (MPWSP) – Cullem
AGENDA ITEMS
3. Receive Update on GWR Schedule and Financing - Sciuto/Stoldt
4. Receive Report, Discuss, and Make Recommendations as to Whether Cal Am Can
Receive and Utilize Ground Water Replenishment (GWR) Water Should the PWM/GWR
Project Come on Line Before Cal Am's Desal Facility - Crooks
5. Receive Suggestions from Authority President Jason Burnett on Modifications to the Policy
Position Statement and Discuss Progress of the TAC Ad Hoc Committee Considering
Changes to the Statement - Cullem
ADJOURNMENT
Created date 03/31/2016 2:18 PM Monday, April 4, 2016
The Monterey Peninsula Regional Water Authority is committed to including the disabled in all
of its services, programs and activities. In compliance with the Americans with Disabilities Act,
if you need special assistance to participate in this meeting, please contact the Monterey City
Clerk’s Office at (831) 646-3935. Notification 30 hours prior to the meeting will enable the City
to make reasonable arrangements to ensure accessibility to this meeting [28 CFR 35.102-
35.104 ADA Title II]. Later requests will be accommodated to the extent feasible. For
communication-related assistance, dial 711 to use the California Relay Service (CRS) to speak to
City offices. CRS offers free text-to-speech, speech-to-speech, and Spanish-language services 24
hours a day, 7 days a week. If you require a hearing amplification device to attend a meeting, dial
711 to use CRS to talk to the Monterey City Clerk's Office at (831) 646-3935 to coordinate use of a
device.
Agenda related writings or documents provided to the MPRWA are available for public
inspection during the meeting or may be requested from the Monterey City Clerk’s Office at 580
Pacific St, Room 6, Monterey, CA 93940. This agenda is posted in compliance with California
Government Code Section 54954.2(a) or Section 54956.