MP Regional Water Authority TAC Meeting
Regular MeetingMonterey, CA · June 20, 2016
Minutes
MINUTES
MONTEREY PENINSULA WATER AUTHORITY (MPRWA)
TECHNICAL ADVISORY COMMITTEE (TAC)
10:30 AM, Monday, June 20, 2016
MONTEREY COUNCIL CHAMBERS
580 PACIFIC STREET, MONTEREY
MONTEREY, CALIFORNIA
Members Present: Alternate Member Ellis, Member Reidl, Member Riley, Member Stoldt,
Member VanDerMaaten, Executive Director Cullem
Members Absent: Member Sciuto, Member Narigi, Member Huss
Staff Present: Legal Counsel Freeman, Clerk Romero
CALL TO ORDER
Executive Director Cullem called the meeting to order at 10:34am.
ROLL CALL
Members Scuito, Narigi and Huss were absent. Member Stoldt came in at 10:36am.
PLEDGE OF ALLEGIANCE
REPORTS FROM TAC MEMBERS
Riley said that “Public Water Now” has filed an objection to the return water agreement.
Member Stoldt reported that the preliminary staff recommendation on the Cease and Desist
Order (CDO) is available on California American Water’s (Cal Am) website.
PUBLIC COMMENTS
None
APPROVAL OF MINUTES
1. Approve Minutes from March 7 and April 4, 2016 - Romero
On a motion by Committee Member Riley, seconded by Committee Member Stoldt, and carried
by the following vote, the MPRWA Technical Advisory Committee Approved the Minutes from
March 7 and April 4, 2016:
AYES: 5 MEMBERS: Riedl, Riley, Stoldt, VanDerMaatten, Cullem
NOES: 0 MEMBERS: None
ABSENT: 3 MEMBERS: Huss, Narigi, Sciuto
ABSTAIN: 1 MEMBERS: Ellis
RECUSED: 0 MEMBERS: None
MPRWA TAC Minutes Monday, June 20, 2016
CONSENT ITEMS
PUBLIC COMMENTS
None
On a motion by Committee Member Riley, seconded by Committee Member Stoldt, and carried
by the following vote, the MPRWA Technical Advisory Committee approved the Consent
Agenda:
AYES: 6 MEMBERS: Ellis, Riedl, Riley, Stoldt, VanDerMaatten, Cullem
NOES: 0 MEMBERS: None
ABSENT: 3 MEMBERS: Huss, Narigi, Sciuto
ABSTAIN: 0 MEMBERS: None
RECUSED: 0 MEMBERS: None
2. Receive Report on the Submission of a Brine Disposal Agreement and a Return Water
Agreement to the CPUC - Cullem
Action: Received Report
3. Receive Report on Water Authority Motion on April 19, 2016 for Modification to the CPUC
Phase 2 Process to Include the 36 inch Monterey Transfer Pipeline in the GWR Decision -
Cullem
Action: Received Report
4. Receive Report on Joint Meeting with the Water Authority Board on August 11 for Presentations
on Deep Water Desal and People's Desal- Cullem
Action: Received Report
AGENDA ITEMS
5. Receive Update on GWR Schedule and Financing - Stoldt
Action: Received update
Member Stoldt gave an update on the current schedule and financing for the Pure Water
Monterey (PWM) Ground Water Replenishment (GWR) project:
Water rights protests from National Marine Fishery Service and California Department
of Fish and Wildlife are expected to be dismissed.
The dismissal of the protests will enable National Incident Management System (NIMS)
to consult with the Environmental Protection Agency (EPA) and issue biological
assessment on the project. They have 135 days to do, but will try to expedite it.
The California Public Utilities Commission (CPUC) will have a public workshop on
September 1st regarding consideration of the Monterey pipeline, Aquifer Storage
2
MPRWA TAC Minutes Monday, June 20, 2016
Recovery (ASR) pump station, and GWR. It is hopeful that a preliminary decision by
the CPUC will be made by August 18, 2016. If not, the decision may be delayed until
the end of September.
Negotiation is in process for the pipeline contractor so that construction can begin as
soon as the CPUC final decision is made, possibly by October, 2016.
Marina Coast Water District and the Monterey Regional Water Pollution Control
Agency (MRWPCA) announced their joint pipeline partnership.
The SWRCB has added a milestone of approval of GWR in September as part of the
Cease and Desist Order (CDO) modification. However, an extension of that milestone
date has been requested.
Member Riley questioned the significance of the biological assessment report and its delay.
Member Stoldt responded that the EPA does its biological assessment first before permits are
approved for the engineers to tunnel under the Salinas River to ensure there is no taking under
the Endangered Species Act.
Member Stoldt mentioned that the group, which includes the Authority, submitted the
application to extend the CDO. The group will come together and make and file an alternate
proposal for the pipeline. He added that public comments on the application are due July 13th,
and the hearing for the CDO is on July 19th.
Executive Director Cullem suggested that the GWR schedule and progress be revisited at the
next meeting so that the board can give a recommendation to the Monterey Peninsula
Regional Water Authority (“Authority”).
PUBLIC COMMENT
Tom Rowley, Monterey Peninsula Tax Association, questioned if GWR will be ready by
early 2017, since it is tied to the Cease and Desist Order (CDO). He also questioned
what the true cost of GWR will be.
Member Stoldt responded to Mr. Rowley saying that the pipeline cost is determined at the state
revolving fund rate, and 71% of the cost is covered by the cost of water.
Member Stoldt said regarding the CDO, the 300 acre ft. difference in the diversion limit on the
Carmel River poses a danger of rationing for the community, but doesn’t have as much of an
effect on the fish. Executive Director Cullem said the forbearance will be a short-term cost, but
will benefit the river is long-term.
Member Riley commented that ratepayers will suffer paying the penalty and California
American Water (Cal Am) will unfairly benefit from this.
PUBLIC COMMENT
3
MPRWA TAC Minutes Monday, June 20, 2016
Chuck Chech commented that there is no safeguard that Cal Am won't increase the cost
of water to the public if the milestones are not reached. He opined that ratepayers
should not be penalized, and Cal Am should not be allowed to raise the water rates
because of this.
Executive Director Cullem said that the CDO has nothing to do with the cost of water. The issue
of water cost is addressed by the CPUC, and the Authority’s mission is to focus on getting a
water supply to the community. He added the Authority Joint Powers Agreement (JPA) prohibits
the Authority to be involved in water rate issues.
Member Riley said that the Authority has been involved in a value engineering studies before,
which is related to cost issues.
No action was taken on this item; update received and discussed.
6. Receive Report and Discuss the Detailed MPWSP Schedule Including Status of Upcoming
Permit Requirements and the Status of the Test Slant Well - Crooks
Action: Received Report; Discussed
Ian Crooks, Cal Am, gave an update on the latest Monterey Peninsula Water Supply Project
(MPWSP) schedule, including upcoming permit requirements and test well results. Mr. Crooks
reported that the test well started back up on May 2, 2016 and is currently running at 2,000
gallons per minute (GPM) with no problems, and salinity is about 92%. He summarized that the
current focus is getting the pipeline and the pump station permitted and prepared to be built
after the August 18 decision. The overall project has a list of permits that are currently being
worked on. The approval of the permits is pending the Environmental Impact Report (EIR) and
the Coastal Development permit. GWR is estimated to be available for use in early 2018. Mr.
Crooks clarified for the Board that the remaining cost of the pipeline construction is around $59
million.
The Board voiced concerned about the short time frame for the permit process. Mr. Crooks said
that the timeline could shift based on a number of factors.
Member Stoldt commented that proposed amendment to the CDO presupposes that the
pipeline and ASR will be built and GWR will be approved. He suggested showing the schedule
to the CPUC. He also informed the Board that when GWR is ready water will be available for
use the same day.
PUBLIC COMMENT
Tom Rowley, MPTA, asked about the distance between where the GWR water will be
injected and the out-take wells. He questioned if Seaside will be getting free water.
Chuck Chech, resident, voiced concerns about the Monterey pipeline such as the bends
in the pipe, digging up the streets, the route, and the timeline. He said the pipeline route
should be reanalyzed.
4
MPRWA TAC Minutes Monday, June 20, 2016
Member Stoldt responded to Mr. Rowley saying that the distance between the injection and the
wells is about a half mile, and Seaside may get some benefit over several years but not
significantly.
No action taken on this item; report received and discussed.
7. Receive Report and Discuss the Technical, Financial and Environmental Reasons for Cal Am
Use of a Transfer Pipeline Through Monterey Rather Than Through Los Laureles Grade -
Crooks
Action: Received Report; Discussed
Ian Crooks, Cal Am, gave a presentation on the Hydraulic Trough Overview Schematics. He
gave a detailed explanation of the existing pipeline limitations due to hydraulic constraints. He
then clarified how the new 36” pipeline works to fix these current constraints. He described the
type of material that will be used for the new pipeline, and gave a list of other cities that are
currently using pipelines with the same material.
Mr. Crooks then addressed the alternate route for the pipeline over Los Laureles Grade, which
was proposed by a member of the public at the last Authority meeting. He explained that the
alternate route has many significant impacts which make it not feasible, such as:
o Biological impacts, wetlands area—Tarpy Flats
o Visual impacts for pump station—Tarpy Flats
o Traffic and transportation impacts from construction of pipeline on narrow canyon and
road area
o Does not aid long-standing hydraulic trough constraint of existing water system
PUBLIC COMMENT
Tom Rowley, MPTA, said that the proposed alternate pipeline route goes through
Canada de la Segundo, not the Los Laureles Grade. He said this route was looked as
previously, but it was dropped because it wasn’t a good solution.
Chuck Chech thanked Mr. Crooks for his presentation. He voiced his concern about the
cost of the 36” pipeline to the ratepayer, especially if Cal Am charges interest on the
cost of the $41 million project over 30 years.
Member Riley responded that the Authority should seek out alternate ways to cut costs on the
Water Supply Project.
No action taken, report was received and discussed.
5
MPRWA TAC Minutes Monday, June 20, 2016
8. Receive Report and Discuss the Water Supply Needs of the Marina Coast Water District -
VanderMaaten
Action: Continued to Future Meeting
This item was recommended for continuation due to time constraints.
ADJOURNMENT
Have no further discussion Executive Director Cullem adjourned the meeting at 12:05pm.
Respectfully Submitted, Approved,
Nova Romero, Committee Clerk President MPRWA
6
Agenda
Agenda
Monterey Peninsula Regional Water Authority (MPRWA)
Technical Advisory Committee (TAC)
Regular Meeting
10:30 AM, Monday, June 20, 2016
Monterey Council Chambers
580 Pacific Street, Monterey
Monterey, California
CALL TO ORDER
ROLL CALL
PLEDGE OF ALLEGIANCE
REPORTS FROM TAC MEMBERS
PUBLIC COMMENTS
PUBLIC COMMENTS allows you, the public, to speak for a maximum of three minutes on any
subject which is within the jurisdiction of the MPRWA TAC and which is not on the agenda. Any
person or group desiring to bring an item to the attention of the Committee may do so by
addressing the Committee during Public Comments or by addressing a letter of explanation to:
MPRWA TAC, Attn: Monterey City Clerk, 580 Pacific St, Monterey, CA 93940. The appropriate
staff person will contact the sender concerning the details.
APPROVAL OF MINUTES
1. Approve Minutes from March 7 and April 4, 2016 - Romero
CONSENT ITEMS
CONSENT AGENDA consists of those items which are routine and for which a staff
recommendation has been prepared. A member of the public or a Councilmember may request
that an item be placed on the regular agenda for further discussion.
2. Receive Report on the Submission of a Brine Disposal Agreement and a Return Water
Agreement to the CPUC - Cullem
3. Receive Report on Water Authority Motion on April 19, 2016 for Modification to the CPUC
Phase 2 Process to Include the 36 inch Monterey Transfer Pipeline in the GWR Decision -
Cullem
4. Receive Report on Joint Meeting with the Water Authority Board on August 11 for
Presentations on Deep Water Desal and People's Desal- Cullem
AGENDA ITEMS
5. Receive Update on GWR Schedule and Financing - Stoldt
6. Receive Report and Discuss the Detailed MPWSP Schedule Including Status of Upcoming
Permit Requirements and the Status of the Test Slant Well - Crooks
Created date 06/16/2016 3:40 PM Monday, June 20, 2016
7. Receive Report and Discuss the Technical, Financial and Environmental Reasons for Cal
Am Use of a Transfer Pipeline Through Monterey Rather Than Through Los Laureles
Grade - Crooks
8. Receive Report and Discuss the Water Supply Needs of the Marina Coast Water District -
VanderMaaten
ADJOURNMENT
The Monterey Peninsula Regional Water Authority is committed to including the disabled in all
of its services, programs and activities. In compliance with the Americans with Disabilities Act,
if you need special assistance to participate in this meeting, please contact the Monterey City
Clerk’s Office at (831) 646-3935. Notification 30 hours prior to the meeting will enable the City
to make reasonable arrangements to ensure accessibility to this meeting [28 CFR 35.102-
35.104 ADA Title II]. Later requests will be accommodated to the extent feasible. For
communication-related assistance, dial 711 to use the California Relay Service (CRS) to speak to
City offices. CRS offers free text-to-speech, speech-to-speech, and Spanish-language services 24
hours a day, 7 days a week. If you require a hearing amplification device to attend a meeting, dial
711 to use CRS to talk to the Monterey City Clerk's Office at (831) 646-3935 to coordinate use of a
device.
Agenda related writings or documents provided to the MPRWA are available for public
inspection during the meeting or may be requested from the Monterey City Clerk’s Office at 580
Pacific St, Room 6, Monterey, CA 93940. This agenda is posted in compliance with California
Government Code Section 54954.2(a) or Section 54956.