Neighborhood and Community Improvement Program Committee Meeting
Regular MeetingMonterey, CA · February 24, 2016
Minutes
MINUTES
NEIGHBORHOOD IMPROVEMENT PROGRAM COMMITTEE
Wednesday, February 24, 2016
7:00 PM
COUNCIL CHAMBER, FEW MEMORIAL HALL
580 PACIFIC STREET
MONTEREY, CALIFORNIA
NIP Representatives Aguajito Oaks Olivia Morgan, Rep.
& Alternates Present: Casanova-Oak Knolls Richard Ruccello, Rep., Michael
Brassfield, Alt., Kimberly Svetich-Will, Alt.
Deer Flats Dave Overton
Del Monte Beach Jayme Fields, Rep.
Del Monte Grove-Laguna Grande Merrily Alley, Rep. Kathleen Baker, Alt.
Fisherman Flats Henry Smith, Rep.
Monterey Vista Pat Venza, Rep. Jean Rasch, Alt., Jerry
Azevedo, Alt., Hans Jannasch, Alt.
New Monterey Sharon Dwight, Rep., Carole Hayter, Alt.
Oak Grove Tom DiMaggio, Rep.
Old Town April Harrison, Rep., Susan Rickertson,
Alt.
Skyline Forest Dennis Duke, Rep.
Skyline Ridge Julie Engell, Rep.
Villa Del Monte Katrina Hintz Rep., Carole Pavlo, Alt.
Staff Members Jeff Krebs, Sara Myers, Louie Marcuzzo, Jim Courtney, Inga Waite
Present:
CALL TO ORDER
NIP Staff Coordinator Jeff Krebs called the meeting to order at 7:00.
ROLL CALL
Twelve neighborhoods were represented with Alta Mesa unrepresented and Skyline
Ridge Representative Julie Engell absent until arriving at 7:03 p.m.
APPROVAL OF MINUTES
January 28, 2016
Sharon Dwight made a motion to approve the minutes as amended. Olivia Morgan
seconded the motion. The motion was carried by twelve of the representatives
present, with Henry Smith abstaining.
PUBLIC COMMENTS
Mr. Krebs opened Public Comments for items not on the agenda. Seeing no comments,
Mr. Krebs closed Public Comments.
INFORMATIONAL REPORTS & STAFF COMMENTS
NIP INFORMATIONAL REPORTS
1. NIP Spokesperson Reports
Richard Ruccello stated that he went to the Parks and Recreation Commission meeting
regarding the basketball court. The next step is for Mr. Krebs to go to the Coastal
Commission for administrative review.
Neighborhood Improvement Program Committee Minutes Wednesday, February 24, 2016
PUBLIC APPEARANCE
2. Rescope Fire Station One Exhaust Extractor Project
Mr. Krebs provided a presentation for a change in scope of the Fire Station One Exhaust
Extractor Project. The rescope involves a new filtration system to be installed at all three
fire stations. There is no additional cost and the system will go above and beyond the
previously scoped project.
Ms. Engell asked for details on the filtration system. Jim Courtney, Assistant Fire Chief,
responded that the system is called an Air-Vac System and provides four stages of
filtration.
Henry Smith made a motion to rescope the Fire Station One Exhaust Extractor
Project. Sharon Dwight seconded the motion. The motion was approved by the
thirteen representatives present.
3. Recommend City Council Approve Additional Funding for Via Del Rey/Herrmann Right
Turn and Library Kitchen Addition Projects
Mr. Krebs presented the Via Del Rey/Herrmann Right Turn project and explained that
only the base bid was awarded due to funding. The base bid can build half of the project
and bring the intersection to a 3-way stop. With additional funding, Additive Alternate No.
1 can be added so that the curb return and drainage can be completed as well.
Mr. Krebs also presented the Library projects and described the two additional requests
for supplemental funding: terrace lighting and the fence. With this funding, the sunken
patio behind the Library will be raised up to grade. There is also a large painting upstairs
that will be moved during construction.
Mr. Smith asked to confirm the total funding request for both projects and Mr. Krebs
responded that it is $74,789. The NIP Contingency Account has a balance of
$909,600.06. Ms. Alley stated that the request is for $80,000. Mr. Krebs confirmed that
he is asking for just $74,789 to be transferred from the contingency account.
Henry Smith made a motion to approve the funding transfer. Sharon Dwight asked
for further discussion and to separate the projects. Richard Ruccello seconded the
motion.
Ms. Dwight stated that voting two projects together sets a bad precedent. She asked to
confirm that the Via Del Rey work is within the original scope. Mr. Krebs confirmed it is
and described the work to be done in the intersection.
Mr. Ruccello addressed the Library projects and stated that it is a complex issue, but
they’ve done a great job. Raising the sunken patio and adding extra lighting will make the
area much more secure.
Sharon Dwight confirmed that the motion is to transfer $74,789 from contingency
as follows:
Via Del Rey/Hermann Right Turn $55,759
Neighborhood Improvement Program Committee Meeting Minutes
Wednesday, February 24, 2016
2
Neighborhood Improvement Program Committee Minutes Wednesday, February 24, 2016
Library Kitchen addition $19,030
Total appropriation and transfer $ 74,789
The motion was approved by twelve of the representatives present with Skyline
Forest voting no.
4. Discuss Proposed Policies and Procedures Manual Revisions from Policies and
Procedures Subcommittee
Sharon Dwight continued the item to the March 31, 2016 meeting.
5. Project Screening
Mr. Krebs explained that the proposal packet lists the projects as they were submitted.
No edits have been made. The purpose of this screening is to review whether or not
each submittal qualifies as a project.
AM-1 Don Dahvee Greenbelt maintenance. Mr. Krebs stated that AM-1 and AM-2
are almost identical. Louie Marcuzzo suggested pulling AM-1 in favor of
AM-2. Removed.
AM-2 Greenbelt maintenance. Project.
AM-3 Parking control on Iris Canyon. Mr. Krebs stated he has reviewed with
Traffic and will need to work with the applicant to change the scope due to
the large boulders. Project.
AM-4 Restoring ground cover in Lagunita Mirada Park. Project.
COK-1 Create a cul-de-sac at Stuart Avenue. Project.
COK-2 Reforestation to areas with tree loss. Project.
COK-3 Casanova Oak Knoll Park sitting area and benches. Project.
COK-4 North Fremont traffic signal adaptive system. Project.
DF-1 Elk Run & Deer Forest Drive traffic mirrors. Mr. Krebs explained that the
City cannot install traffic mirrors and will need to speak with the applicant,
Dave Overton, to rescope the project. Mr. Overton approved the rescope.
Project.
DF-2 Mule Deer Way drainage and surface repair reconstruction. Project.
DMB-1 Montecito Park Phase 2. Duplicate of VDM-5. Removed.
DMG-1 Reconfigure Hannon storm drain. Ms. Alley explained that the applicant’s
issue is whether she would be liable if a child fell into the storm drain in
front of her house and she is willing to withdraw the project if a City
department can handle the issue. Mr. Krebs responded that it will be
considered a project for now, but City staff will go out and investigate.
Project.
DMG-2 Lily Palmer memorial plaque. Project.
DMG-3 Phase two of the English Avenue 200-300 block sidewalk, curb, and gutter
project. Project.
DMG-4 Traffic study of Casanova, Virgin, English, and Montecito. Project.
DT-1 Hartnell Gulch Stream restoration. Project.
DT-2 Jack’s Park irrigation. Project.
FF-1 Fisherman Flats Greenbelt fire fuel reduction. Project.
FF-2 Install sidewalk and curbing at 2005 Marsala Circle and 1600 Via Isola.
Project.
FF-3 Install street light on Via Marettimo. Project.
Neighborhood Improvement Program Committee Meeting Minutes
Wednesday, February 24, 2016
3
Neighborhood Improvement Program Committee Minutes Wednesday, February 24, 2016
FF-4 Landscaping and play equipment upgrades at Fisherman’s Flats Park.
Project.
FF-5 Prepare security plan for protection and security of public art. Renamed as
CW-31. Project.
FF-6 Install two video surveillance systems for historic art/assets. Renamed as
CW-32. Project.
GW-1 Pedestrian safety and ADA improvements to MST bus stop adjacent to 500
Glenwood Circle. Project.
MV-1 Add pickleball striping to Via Paraiso Tennis Courts. Project.
MV-2 Pacific Street sidewalk repair. Ms. Dwight suggested adding “Phase II” to
title of project. Mr. Krebs suggested adding the limits of the project.
Project.
MV-3 Develop upper end of Don Dahvee Park into a dog park. Renumbered as
CW-33. Project.
MV-4 Pacific Street/Monterey High sidewalk replacement and adding metal
benches for pedestrians and students. Project.
MV-5 Safety improvements to Via Paraiso and Via Gayuba. Project.
MV-6 Install Rapid Rectangular Flashing Beacon at Via Gayuba mid-block
crosswalk. Project.
MV-7 Cuesta Vista Drive/Toyon Drive greenbelt cleanup. Ms. Dwight asked if this
was all city property. Mr. Krebs confirmed it is. Project.
MV-8 Via Ventura/Via Descanso greenbelt cleanup. Project.
MV-9 Soledad drainage improvement project. Ms. Dwight asked if this project
was to improve an individual driveway. Ms. Venza confirmed that the block
floods and will not go around this individual driveway. The project covers
the whole block. Project.
MV-10 Pacific Street stabilization by installing 3’ TOP wall. Ms. Dwight asked if this
project has been submitted before. Ms. Venza confirmed it is the same
project, but this is to add a wall at the base of the property. Project.
NM-1 Devisadero Street gutter improvement. Ms. Dwight stated this is the same
project as NM-11. Removed.
NM-2 Repair 600 block of Taylor. Mr. Krebs stated this is a current project.
Removed.
NM-3 Street widening or a sidewalk on one or both sides of the 500 block of
Newton. Ms. Dwight suggested renaming the project “Newton 500 Sidewalk
Widening.” Project.
NM-4 Iriving sidewalk repair. Ms. Dwight stated this is the same project as NM-
14. Removed.
NM-5 Install bicycle racks on Lighthouse between Irving and Reeside and at
Bonifacio Plaza. Ms. Dwight recommended making sure this has not
already been funded at Bonifacio. Project.
NM-6 Aeneas Bridge restoration. Mr. Krebs confirmed that the city owns the
bridge. Project.
NM-7 Adaptive traffic signal control from Lighthouse along Del Monte corridor.
Project.
NM-8 Phase II to construct seating, wall, and stairs at Scholze Park. Project.
NM-9 Hood existing light fixtures at Hilltop Park Center. Project.
NM-10 Replace existing security lights at Archer Park. Project.
NM-11 Upgrade drainline on 700 block of Devisadero. Project.
NM-12 Upgrade drainline on 700 block of Lobos. Project.
NM-13 Install three free-standing exercise stations at Scholze Park. Project.
Neighborhood Improvement Program Committee Meeting Minutes
Wednesday, February 24, 2016
4
Neighborhood Improvement Program Committee Minutes Wednesday, February 24, 2016
NM-14 Restore concrete-stabilized decomposed granite on Irving. Project.
NM-15 Phase II to replace New Monterey street signs. Project.
NM-16 Fish Hopper repair and signage on Cannery Row. Project.
NM-17 Hilltop Park retaining and handrail on the Jessie side. Project.
NM-18 Replace 5 sets of timber stairs on the Rec Trail. Project.
NM-19 Scholze Park parking lot ADA upgrade. Project.
NM-20 Interior and exterior redesign and engineering study for Hilltop Park Center.
Project.
NM-21 Laine 300 block street widening. Project.
OG-1 Block left turns onto Camino Aguajito from 10th and 8th. Mr. Krebs stated
that Traffic has suggested this project be changed to a traffic study. He will
discuss with the applicant and rescope the project as a traffic study.
Project.
OG-2 Design and development of the Tot Lot on the corner of 5th and Ocean.
Project.
OT-1 Larkin Park swings. Project.
OT-2 Remove fencing at Monroe, Eddie Burns, and Seeno. Ms. Harrison
suggested contacting the applicant for clarity. Project.
OT-3 Install solar flashing beacons at the crosswalk of Franklin and High.
Project.
OT-4 Larkin Park irrigation and turf renovation. Project.
OT-5 Franklin Street beautification. Ms. Harrison commented that there is a
neighborhood sign at the top of the hill once you are leaving Old Town.
Project.
OT-6 Remove and replant Friendly Plaza garden bed. Ms. Harrison requested
that this project be changed to Citywide. Renamed CW-34. Project.
OT-7 Construction of a handicapped accessible trail to Sloat Monument from the
Museum. Ms. Harrison requested that this project be changed to Citywide.
Renamed CW-35. Project.
SF-1 Convert Skyline Crest lighting to LED. Mr. Krebs explained that these are
not City lights and therefore this cannot be a project. Removed.
SF-2 Adjust center median at Veteran’s Park entrance to Skyline Forest. Mr.
Krebs stated he will need to speak with the applicant because we cannot
remove the curb and median. Mr. Duke stated he will speak with the
applicant. Project.
SF-3 Skyline Forest greenbelt fire fuel reduction. Project.
SF-4 Skyline Forest greenbelt tree removal and trimming. Project.
SF-5 Recreation Trail Active Transportation Grant development. Ms. Venza
suggested changing the project to Citywide. Renamed CW-36. Project.
SR-1 Install radar speed sign on Dry Creek Road. Mr. Krebs suggested changing
the project name to “Install Radar Sign.” Project.
VDM-1 Construct a sound wall along northbound lane of Highway One at Casa
Verde and Del Monte. Ms. Fields stated her understanding is that we
cannot do this. Mr. Krebs confirmed. Removed.
VDM-2 Ferrante Park usage, review, recommendation and design. Ms. Hintze
stated that VDM-2 and VDM-3 are similar projects and she will meet with
the applicant to see if they can be combined and potentially broken into
phases. Project.
VDM-3 Ferrante Park revitalization. Ms. Hintze to meet with applicant to combine
VDM-2 and VDM-3. Project.
VDM-4 Casa Verde bicycle lane improvements. Ms. Dwight suggested confirming
Neighborhood Improvement Program Committee Meeting Minutes
Wednesday, February 24, 2016
5
Neighborhood Improvement Program Committee Minutes Wednesday, February 24, 2016
that this plan is within the Citywide bicycle plan. Project.
VDM-5 Phase II of Montecito Park. Ms. Dwight suggested adding “per approved
Parks Master Plan” into the scope of the project. Project.
CW-1 Install a roundabout at Glenwood Circle and Aguajito Road. Mr. Krebs
stated he would need to talk to the applicant to change this to a traffic
study. Mr. Ruccello stated this would need to be a City project, it should not
come from NIP. Ms. Dwight suggested referring the project to the City
Traffic Engineer as it does not qualify as an NIP project. Removed.
CW-2 Provide limited access to Dennis the Menace Train. Mr. Krebs stated this is
a duplicate project to CW-29. Removed.
CW-3 Design and implement Colton Hall ADA upgrades. Ms. Dwight asked for
the applicant to narrow the scope of the project. Mr. Krebs stated he would
speak with the applicant regarding the scope of the project. Project.
CW-4 Old Salinas Highway signing, striping, and lighting. Project.
CW-5 Purchase and install 5 themed bike racks. Project.
CW-6 Design and build a backstop for Jacks Park ballfield. Project.
CW-7 Replace tennis court lights at Jacks Park. Project.
CW-8 Purchase and install whale climbing structure at Monterey Bay Park.
Project.
CW-9 Replace worn and rotten timber steps along Recreation Trail B. Ms. Alley
asked if this was a duplicate of NM-18. Ms. Dwight confirmed they are
different sections of the Recreation Trail. Project.
CW-10 Sports Center landscape improvements. Project.
CW-11 Restore failing 1930s redwood sardine hopper at Shoreline Park. Project.
CW-12 Complete ADA walkways in Dennis the Menace Park. Project.
CW-13 Foam and Lighthouse landscape improvements. Project.
CW-14 Supplemental funding for the Library ADA compliance upgrades. Project.
CW-15 Supplemental funding for the Sports Center ADA compliance upgrades.
Project.
CW-16 Planting of replacement trees around the city. Project.
CW-17 Public safety improvements at the Library. Mr. Ruccello confirmed this is
the project that just received additional funding. Removed.
CW-18 Sports Center water fountain upgrades. Project.
CW-19 Study to identify a suitable location for homeless shelter and complete any
required modifications. Project.
CW-20 Improvements to Fire Station 3. Project.
CW-21 Jack Ballpark modernization and safety improvements. Project.
CW-22 Acquire and install 3-D, kid-friendly art piece at the Library. Ms. Dwight
asked if this is to be interior or exterior. Inga Waite stated the original idea
was for this to be interior, but either is acceptable. Project.
CW-23 Create a secured, climate-controlled archival storage room at the Library.
Project.
CW-24 Convert former staff office adjacent to the community room into a public
classroom at the Library. Ms. Dwight asked for the project to be renamed.
Ms. Waite renamed the project “Library Learning Lab.” Project.
CW-25 Retrofit existing parks with safety lighting to improve security. Mr. Krebs
stated this should be security lighting, not safety lighting. Ms. Dwight asked
for clarification of which parks and then each neighborhood has the option
of adopting that park. Project.
CW-26 Improvements to Jacks Ballpark. Mr. Rucello asked if this was a duplicate
to CW-21. Mr. Krebs confirmed they are slightly different. Project.
Neighborhood Improvement Program Committee Meeting Minutes
Wednesday, February 24, 2016
6
Neighborhood Improvement Program Committee Minutes Wednesday, February 24, 2016
CW-27 Emergency shelter improvements to the Hilltop Center, Youth Center,
CONA Center, and Library. Mr. Ruccello stated that this project needs to be
more focused. Project.
CW-28 Youth Center redesign. Ms. Dwight stated that this project is the first step to
determine how to use the Youth Center. Project.
CW-29 Dennis the Menace Train improvements. Project.
CW-30 Emergency preparedness and implementation at City Centers. Mr. Rucello
asked for clarification and whether we want to store combustible products
at City Centers. Mr. Krebs stated he will speak with the applicant to see
exactly what they need. Mr. Overton suggested separating the project
between combustible storage sheds and a roof for the Hilltop CERT
container. Project.
COMMITTEE MEMBER COMMENTS
Julie Engell – No comment.
Katrina Hintze – No comment.
April Harrison – We’re off and running!
Pat Venza – On 3/22 at the Library, the Monte Vista Neighborhood Association is hosting
an event regarding what’s happening in the city with Libby Downey and Tim Barrett.
Everyone is invited.
Dennis Duke – Good night.
Olivia Morgan – Impressive accomplishment and thank you to all involved. Found a new
project for next year: the chambers need a new bathroom.
Sharon Dwight – The Parks and Recreation Commission said they want to come back
and talk to NIP. She asked Mr. Krebs when this meeting will take place. Mr. Krebs
responded that he will speak with Kim Bui-Burton and have it set up. Ms. Dwight also
thanked staff for the book of project nominations.
Richard Ruccello – He appreciated the binding of the project nominations. He stated
we’ve hit an important milestone: we passed $60,000,000 last year.
Dave Overton – He apologized that he had to miss last meeting, but he’ll be here from
now on.
Jayme Fields – No comment.
Merrily Alley – No comment.
Henry Smith – No comment.
Tom DiMaggio – He commented that a third of the projects are citywide and he thought
we were trying to have a few high priority citywide projects and more neighborhood
projects.
Neighborhood Improvement Program Committee Meeting Minutes
Wednesday, February 24, 2016
7
Neighborhood Improvement Program Committee Minutes Wednesday, February 24, 2016
Mike Brassfield stated that the City is looking at the funding mechanisms that can make
multiple projects unify.
NEXT MEETING
March 31, 2016 – 7:00 p.m. – Council Chamber
ADJOURNMENT
Mr. Krebs adjourned the meeting at 9:29 p.m.
Respectfully Submitted, Approved,
Sara Myers Jeff Krebs, P. E.
Recording Secretary NIP Staff Coordinator
Neighborhood Improvement Program Committee Meeting Minutes
Wednesday, February 24, 2016
8
Agenda
NIP Committee
Member listing at
Neighborhood Improvement http://www.monterey.org/en-
Program Committee Agenda us/cityhall/boardscommissions/
nipcommittee.aspx
NIP Spokesperson
Rick Heuer
Sharon Dwight (Alternate)
Wednesday, February 24, 2016
Richard Ruccello (Alternate)
7:00 PM NIP Staff Coordinator
Monterey, California
Jeff Krebs
CALL TO ORDER
ROLL CALL
APPROVAL OF MINUTES
PUBLIC COMMENTS
INFORMATIONAL REPORTS & STAFF COMMENTS
NIP INFORMATIONAL REPORTS
1. NIP Spokesperson Reports
PUBLIC APPEARANCE
2. Rescope Fire Station One Exhaust Extractor Project
3. Recommend City Council Approve Additional Funding for Via Del Rey/Hermann Right
Turn and Library Kitchen Addition Projects
4. Discuss Proposed Policies and Procedures Manual Revisions from Policies and
Procedures Subcommittee
5. Project Screening
COMMITTEE MEMBER COMMENTS
NEXT MEETING
ADJOURNMENT
Agenda packets may be reviewed by the public in the Engineering Office or on the web at
http://www.monterey.org beginning 72 hours prior to the date of the meeting.
Members of the public have the right to address the Committee on any Agenda items. The Staff
Coordinator will formally open the floor for public comment. However, if you wish to speak to items
during "Consent Agenda" or "Staff Informational Report," please advise the staff or the Coordinator
prior to the action on that item and you will be recognized. Notification, as much in advance as
possible, is appreciated.
Information distributed to the Committee at the meeting becomes part of the public record. A copy of
written material, pictures, etc. should be provided to the Secretary for this purpose. For more agenda
information, call the Engineering Office at 831-646-3921.
CITY OF MONTEREY'S 24-HOUR SUGGESTION HOTLINES:
Voicemail: 831-646-3799
FAX: 831-646-3793
Email: suggest@monterey.org
WebPage: http://www.monterey.org
The City of Monterey is committed to including the disabled in all of its services, programs
and activities. In compliance with the Americans with Disabilities Act, if you need special
assistance to participate in this meeting, please contact the City Clerk’s Office at (831) 646-
3935. Notification 30 hours prior to the meeting will enable the City to make reasonable
arrangements to ensure accessibility to this meeting [28 CFR 35.102-35.104 ADA Title
II]. Later requests will be accommodated to the extent feasible. For communication-related
assistance, dial 711 to use the California Relay Service (CRS) to speak to City offices. CRS
offers free text-to-speech, speech-to-speech, and Spanish-language services 24 hours a day, 7
days a week. If you require a hearing amplification device to attend a meeting, dial 711 to use
CRS to talk to the City Clerk's Office at (831) 646-3935 to coordinate use of a device.
UPCOMING MEETINGS AT CITY HALL
Feb 26 Council Subcommittee BCC, Monterey, CA - 2:00 PM
Feb 29 Council Subcommittee BCC, Monterey, CA - 3:00 PM
Mar 1 Council Regular Meeting, Council Chamber - 4:00 PM
Mar 2 Architectural Review Committee Meeting, Council Chamber - 4:00 pm
Mar 3 Zoning Administrator Meeting, Council Chamber - 4:00 pm
Mar 7 MP Regional Water Authority TAC Meeting, Council Chamber - 10:30 AM
Mar 8 Planning Commission Meeting, Council Chamber - 4:00 pm
Mar 10 Historic Preservation Commission Meeting, Council Chamber - 4:00 pm
Mar 10 MP Regional Water Authority Meeting, TBD - 7:00 PM
Mar 15 Council Regular Meeting, Council Chamber - 4:00 PM
Mar 16 Architectural Review Committee Meeting, Council Chamber - 4:00 pm
Mar 17 Parks and Recreation Commission Meeting, Council Chamber - 7:00 PM
Mar 17 Zoning Administrator Meeting, Council Chamber - 4:00 pm
Mar 22 Planning Commission Meeting, Council Chamber - 4:00 pm
Mar 23 Oversight Board Meeting, Council Chamber - 7:00 PM
Mar 23 Council Study Session, Council Chamber - 4:00 PM
Mar 23 Library Board Meeting, Library Community Room - 5:00 PM
NIP Committee Agenda
Wednesday, February 24, 2016
2
Mar 28 Colton Hall Museum Cultural Art Commission Meeting, Council Chamber - 4:00 pm
Mar 30 Council Study Session, Council Chamber - 4:00 PM
Mar 31 Neighborhood Improvement Program Committee Meeting, Council Chamber - 7:00 PM
MORE INFORMATION IS AVAILABLE BY CALLING 646-3921
NIP Committee Agenda
Wednesday, February 24, 2016
3
Get email alerts for Monterey
A daily email when new agendas and minutes are posted.