Transportation Committee
Regular MeetingMount Pleasant, SC · March 4, 2019
Minutes
TOWN OF MOUNT PLEASANT, SOUTH CAROLINA
TRANSPORTATION COMMITTEE
Monday, March 4, 2019
1:45 p.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
Minutes
Members Present: Mayor Will Haynie, Chair; Bob Brimmer, Joe Bustos,
Kevin Cunnane
Staff Present: Eric DeMoura, Brad Morrison, Paul Lykins
Mayor Haynie called the meeting to order at 2:43 p.m.
1. Approval of Minutes from the February 4, 2019 meeting
Mr. Bustos moved for approval of the February 4, 2019 minutes; motion
seconded by Mr. Cunnane. Motion carried unanimously.
2. Public Comments
Jim Jones, 2nd Street, stated that his application for speed humps was denied
because the petition area included the On the Harbor subdivision and
suggested staff should base the petition only on the residents that live on 2nd
Street and 5th Street. If speed humps are not a possibility, residents would be
interested in radar feedback signs to warn drivers that they are speeding.
Becky Hollingworth, 77 5th Avenue, stated that residents continue to seek a
remedy to the speeding problem to the Remley’s Point Boat Landing due the
traffic calming application being denied. The residents in Remley’s point need
a remedy for tranquil livability.
Mayor Haynie stated that the Remley’s Point traffic calming application was
not an agenda item and that by law, the Committee is not allowed to take any
action but that the Committee will take the comments under advisement and
follow up in the appropriate manner.
Transportation Committee Minutes
March 4, 2019
Page 2 of 14
Mary Waddell, 112 2nd Street, stated speeders are out of control with the
population increase and speed humps or another solution is needed.
3. Presentation of Design Concepts for the Park West Boulevard and
Stockdale Drive Intersection
Mr. Lykins referred to a graphic stating that that the Committee directed staff
to study the intersection of Stockdale Street and Park West Boulevard with a
goal to consolidate side street movements into one intersection where the
movements could be better managed, commenting that the accident history
reflect that most of the accidents are rear end type collisions. In the study,
all development of Park Avenue Boulevard to include Faison Road was
accounted for to include two (2) traffic counts at all the schools. Three (3)
alternatives were identified and each alternative includes a roundabout and
a signalized intersection option, costs and capacity differences and new
access points. Alternative 1 is the recommended option and utilizes a
roundabout that allows traffic to enter and exit Thomas Cario Boulevard with
limited right turns out. Salterbeck Drive will become a right-in/right-out
turning movement. The estimated cost of Alternative 1 is approximately
three million dollars ($3,000,000). Staff examined a signalized intersection at
the same location that would operate similarly at an estimated cost of one
million five hundred thousand ($1,500,000). Alternative 2 is a dual
roundabout scenario where most school traffic is accessed at one location.
Access would be restricted on Thomas Cario Boulevard and it would become
two-way. The estimated cost of Alternative 2 is approximately three million
five hundred thousand ($3,500,000) and not an option that will be
recommended to the Committee. The Alternative 2 signalized intersection
option has not been discussed with Charleston County School District (CCSD),
but would be the same with a signal and a roundabout with two-way traffic
on Thomas Cario Boulevard. Staff does not believe this alternative is feasible
and the alternative is very expensive with an approximate cost of two million
five hundred thousand dollars ($2,500,000) for a signalized intersection.
Alternative 3 utilizes two (2) roundabouts on Park West Boulevard with one
located at the school entrance and another located at Salterbeck with a
realigned Thomas Cario Boulevard. Alternative 3 works very well but does
Transportation Committee Minutes
March 4, 2019
Page 3 of 14
create additional traffic onto Salterbeck Street with Stockdale Street
becoming a right in/right out movement. The option works well but will cost
approximately five million dollars ($5,000,000).
Mr. Morrison stated that a left turn from Salterbeck Street would be via an
indirect left though the roundabout.
Mr. Lykins stated the alternatives were compared based on capacity, queue
lengths, safety, potential environmental impacts, potential right-of-way
impacts, potential utility impacts and probable construction costs, and the
recommendation by staff is to proceed with Alternative 1.
Mayor Haynie stated that Alternative 1 had the best score and asked if
Stockdale Street would be a right-in/right-out maneuver.
Mr. Lykins replied in the negative stating the Stockdale Street would have full
access.
Mayor Haynie stated that a driver would be able to access the roundabout
easily from Stockdale Street.
Mr. Lykins replied in the affirmative and stated that Salterbeck Street would
become a right-in/right-out maneuver.
Mayor Haynie asked if Alternative 1 will alleviate the traffic issues on
Salterbeck Street.
Mr. Morrison replied in the affirmative stating that the option is expected to
provide good operations since most travel between Park West Boulevard and
Park Avenue Boulevard is expected to utilize the roundabout.
Mr. Brimmer asked if the probable construction cost takes into consideration
property that the Town will soon acquire.
Mr. Morrison stated that the costs shown are only for construction.
Mr. Brimmer asked if there would be any land acquisitions associated with
Alternative 1.
Mr. Lykins stated that the Town would need permission from CCSD to alter
Thomas Cario Boulevard but there would not be a need to acquire any right-
of-way except though the vacant property.
Transportation Committee Minutes
March 4, 2019
Page 4 of 14
Mr. Brimmer stated that the Town will acquire the vacant soon and that
should not be an issue. Any alternative that incorporates a signal at that
location will degrade the service and having traffic free flow at the
intersection is something that is critical to keep traffic moving.
Mr. Cunnane stated that Alternative 1 is the best option because it protects
Salterbeck Street. The Stockdale Street turn is difficult with the Wando traffic
in the afternoon and Alternative 1 will address the issue by having a constant
flow.
Mr. Morrison stated that if the Committee is comfortable with Alternative 1,
then staff could get the direction from the Committee to proceed with its
design. The other alternatives would need to be further discussed with CCSD
because the traffic flow on campus would be altered by making Thomas Cario
Boulevard two-way traffic.
Mr. Brimmer questioned if CCSD would be contributing toward the
construction costs.
Mr. Morrison replied that assumption has not been made.
Mayor Haynie asked if a schedule had been established and how the timing
will align with the Park West Boulevard Widening project.
Mr. Lykins replied that a project schedule has not been developed stating that
it will take approximately one (1) year for the project to be designed and
approved and one (1) year to construct. The Park West Boulevard Widening
project is expected to begin in June 2019 and will take approximately fifteen
to eighteen (15-18) months to construct.
Mr. Morrison stated that construction of this project will depend its
placement in the CIP.
Mayor Haynie asked if we would build this into the CIP and that is how we
would finance it.
Mr. DeMoura replied in the affirmative.
Transportation Committee Minutes
March 4, 2019
Page 5 of 14
Mayor Haynie commented that residents that live in Park West may
experience construction fatigue and become aggravated with two (2)
consecutive construction projects.
Mr. Brimmer commented that residents will be frustrated, but it is important
to have a free-flowing Park West Boulevard before any construction begins
on SC 41. Residents will recognize that this is all part of traffic flow in this area
of town.
Mayor Haynie asked what time estimate would be for the construction
portion of the project.
Mr. Lykins replied that the construction portion of the project would take
approximately eighteen (18) months and that during the summer, traffic
could be detoured to Thomas Cario Boulevard to construct some of the
improvements.
Mr. Morrison stated that he does not anticipate any overlap of the project
unless there is a change in the funding for the project to make it occur
simultaneously. Staff is estimating that the Park West Boulevard Widening
project will be complete by the end of 2020.
Mr. Cunnane moved to direct staff to proceed with the concept design of
Alternative 1 as presented by staff; motion seconded by Mr. Brimmer. Motion
carried unanimously.
4. Presentation of Design Concepts for the Long Point Road Maritime
District
Mr. Lykins referred to a graphic and stated that the improvements are a result
of the Economic Development Study that was conducted several years ago
that examined land use in the area. Staff is now studying the traffic
component on Long Point Road from I-526 to the entrance of the State Port
Authority Wando Terminal. The purpose of the project is to improve the
mobility and safety of Long Point Road at the intersections of Wando Park
Boulevard and Shipping Lane and will include enhanced landscaping and
potential medians to achieve a boulevard concept and provide
interconnectivity between Shipping Lane and Wando Park Boulevard. It
Transportation Committee Minutes
March 4, 2019
Page 6 of 14
would be desirable to have a system of cross streets between Shipping Lane
and Wando Park Boulevard or extending Shipping Lane to meet Wando Park
Boulevard to create more access points and a grid network. One issue on Long
Point Road is the weave condition that exists between I-526 and the
intersections of Long Point Road at Lone Tree Drive, Hobcaw Bluff Drive, and
Wando Park Boulevard. This area includes a dedicated right-turn lane
originating from the I-526 off-ramp and a median opening at Lone Tree Drive.
Another issue is the Wando Park Boulevard and Hobcaw Bluff Drive
intersection split phase signal condition that prevents vehicles from turning
left at the same time. Realigning the intersection will create more capacity
and allow the side streets to turn left at the same time. There are two
thousand (2000) vehicles during morning and afternoon peak hours with a
high percentage of the traffic being container trucks. Shipping Lane is an
unsignalized intersection with over one thousand (1000) vehicles during
morning and afternoon peak hours. Container trucks account for
approximately fifty-one percent (51%) of the traffic. Improvements bear the
Wando Park Boulevard intersection could include turn lane improvements and
a connection road between Lone tree Drive and Hobcaw Bluff Drive. Other
improvements considered are a traffic signal at Shipping Lane and a
connection road from Lone Tree Drive to Hobcaw Bluff Drive. An alternative
to the Shipping Lane signal could be a roundabout that would cost
approximately six million dollars ($6,000,000) and has more severe impacts to
properties. The typical sections reflect the extension of the right-turn lane for
Long Point Road, the dual left turn lanes for Wando Park Boulevard and the
individual lanes on Hobcaw Bluff Drive. Section 1 is the extension of the right
turn lane and a longer-term project with an approximate cost of four hundred
forty thousand dollars ($440,000). Sections 2 and 3 are improvements
associated with Wando Park Boulevard for an approximate cost of seven
hundred fifty thousand dollars ($750,000). Sections 4 and 6 are the options
for a signal or roundabout at Shipping Lane, Section 5 is a connector road
between Lone Tree Drive and Hobcaw Bluff Drive and Section 7 is the
extension of Shipping Lane to Wando Park Boulevard. The estimated cost for
all the improvements range from two to seven million dollars ($2,000,000 -
$7,000,000).
Transportation Committee Minutes
March 4, 2019
Page 7 of 14
The next step would be to design the Section 2 and Section 3 intersection
improvements at Wando Park Boulevard and Hobcaw Bluff Drive.
Mayor Haynie asked if staff had received feedback from the residents.
Mr. Lykins replied in the affirmative.
Mayor Haynie asked when comments were received and if the presentation
reflects the comments.
Mr. Lykins replied that it took time to schedule a meeting where residents
from Hobcaw Creek Plantation and Hidden Cove were available to meet with
staff at the same time and that the meeting occurred on Friday, March 1,
2019. Residents are in favor of the improvements, except the do not support
Section 5 connection between Lone Tree Drive and Hobcaw Bluff Drive.
Mr. Brimmer questioned the purpose of the connector road.
Mr. Lykins replied that the purpose is to eliminate the weave coming off I-526,
explaining that vehicles coming off the interstate have a very short distance
to get to the left-turn lane at Lone Tree Drive.
Mr. Brimmer asked if you would come off the exit ramp and go straight
through.
Mr. Lykins stated that staff is not proposing that initial concept option,
because the South Carolina Department of Transportation (SCDOT) will be
examining the interchange soon.
Mr. Morrison stated the Section 5 option would eliminate left-turns at Lone
Tree Drive and move them to a safer location that can be controlled under a
protected left phase and the connector road provides access back to the
medical facility.
Mr. Brimmer asked for clarification that the connector road is to traffic
Hobcaw Bluff Drive as the main access.
Mr. Morrison replied in affirmative.
Mr. Lykins restated that the neighborhood is not in favor of that option.
Transportation Committee Minutes
March 4, 2019
Page 8 of 14
Mr. Morrison expressed that residents are most likely concerned with
additional traffic on the entrance roadway.
Mr. Lykins expressed that residents’ primary issues are with the Port-related
traffic.
Mayor Haynie asked what staff needed from the Committee and if options are
ready to be chosen.
Mr. Lykins stated that staff recommends proceeding with design for Sections
2 and 3. Funds for Sections 2 and 3 are available and the design is fairly
straight forward. The other sections are future projects and are more long-
term projects.
Mayor Haynie asked if the connector road to Lone Tree Drive is included in
Section 2 or 3.
Mr. Lykins replied in the negative.
Mayor Haynie asked if the connector road would require land acquisition.
Mr. Lykins replied in the affirmative.
Mr. Brimmer asked if the Port had a preference to a roundabout or traffic
signal at Shipping Lane and if so, would the Port be willing to contribute
toward the expense, especially if the preferred option was more expensive.
Mr. Lykins stated it is more likely the Ports preference would be to install the
traffic signal. A roundabout would need to be very large to accommodate two
(2) tractor trailers side by side. Regarding funding for a roundabout, he
believes the Port would not be interested in contributing toward that project.
Mr. Brimmer expressed that contributing to the funding of the project needs
to be discussed with the Port.
Mr. Lykins stated that the neighborhoods are actively pursuing the Ports
Authority to contribute to the funding of some of the improvements.
Mr. Morrison stated that discussion has occurred between Senator Larry
Grooms and SCDOT on the Hidden Cove/Shipping Lane intersection and he is
involved with trying to get the Port to listen to the residents and requested
that SCDOT perform a traffic signal warrant study.
Transportation Committee Minutes
March 4, 2019
Page 9 of 14
Mayor Haynie stated that he and Senator Grooms have discussed the issue at
length and agreed that it would be good to discuss with the Port options for
financially contributing to the project. The Town has expressed the concern
of our residents sharing Long Point Road with the tractor trailers and staff has
done a good job trying to address the issues thus far. He expressed the need
to increase efforts to get the Port to expedite options with a funding
contribution.
Mr. Morrison stated that one million five hundred thousand dollars
(1,500,000) is available in the CIP budget and the recommended intersection
improvements are a good start and staff will continue to involve the Port in
the conversation. The I-526 east project is ongoing and encompasses
improvements for all of I-526, including the Long Point Road interchange.
Mayor Haynie asked if any residents from the area neighborhoods were
present or wanted to speak to the Committee.
Mr. Lykins replied in the negative and added that the residents had submitted
some alternate design proposals for the interstate ramp configurations to
SCDOT. Most of the proposed changes appear infeasible and are out of the
scope of the Town’s project. He emphasized the residents are in favor of the
signal and the other improvements, except for the connection to Lone Tree
Drive. Staff estimates the connection will add approximately one hundred
sixty cars in the morning and approximately forty (40) cars in the afternoon
and have very minimal impact on the neighborhood traffic.
Mayor Haynie commented stated that the Port’s new headquarters is in this
area and employees will be driving the roads more frequently.
5. Status of possible improvements at Park Avenue/Faison Road
intersection
Mr. Morrison referred to a graphic and explained some interim improvements
have been made and some of the crash data that was available. SCDOT
reviewed the intersection and agreed with our previous recommendations,
but did suggest upgrading the stop sign size to forty-eight inches (48”) due to
two (2) of the crashes being stop sign violations. Other upgrades being
considered included better lighting at the intersection, warning signs on the
Transportation Committee Minutes
March 4, 2019
Page 10 of 14
Faison approaches and enhanced pavement markings at the intersection
should be pursued. Most of the upgrades have been completed and the
pavement markings will be enlarged from four inch (4”) widths to eight inches
(8”). As for future signal placement that is required by the developer, staff is
updating the warrant study again based on more recent development
proposals at the intersection. The warrant study will provide more definition
to be able to predict traffic flows to include in the warrant. If the Town finds
the updated study meets warrants based on volume projections, then staff
may be able proceed with a signal installation.
Mr. Bustos stated that police have turned that into a right-turn only when
school is dismissed and asked if that will continue.
Mr. DeMoura replied in the affirmative, stating that the plan is to keep the
additional policing until the school year ends and consider doing the same the
following year if necessary.
Mr. Brimmer asked if the warrant studies are based primarily on volume.
Mr. Morrison replied in the affirmative.
Mr. Brimmer asked if the safety of the intersection is taken into consideration
of a warrant study need for a signal.
Mr. Morrison stated that four (4) crashes have occurred within the previous
six (6) month with one (1) of the crashes occurring due to a driver running the
stop sign, which may not be considered a qualifying crash. A qualifying crash
is a crash that would have been likely prevented by a signal. If five (5) crashes
occur within a one-year period, then the volume threshold warrant can be
reduced. If five (5) crashes are met, staff will seek to use the lower threshold,
even on the projection of future volumes.
Mr. Cunnane asked if Oceanside Academy had been in contact with
Transportation staff concerning staggering dismissal times to not line up with
Wando High School and if that is an issue that would be addressed by the
Transportation Department or the school district.
Transportation Committee Minutes
March 4, 2019
Page 11 of 14
Mr. Morrison stated that he is unaware of any Transportation staff being
contacted by Oceanside Academy and that perhaps it was the Mount Pleasant
Police Department, but that staff would assist if they requested.
Mr. Cunnane stated Oceanside Academy claimed they had made contact.
Residents that were regularly complaining have reported back positively
about the police presence and is important that we need to stay on through
the school year.
Mr. Morrison stated that it is being considered and that right-turn lane
improvements being proposed in the CIP should help with queuing and
reduce anxiousness and impatience. The design is very simple and can be
done very quickly over the summer.
6. Review of Resident Parking Permit Study
Mr. Morrison stated this agenda item is a continuation of a discussion and the
Committee had directed staff in December to examine parking issues within
the Old Village area. A public meeting was recently conducted and Jonathon
Guy, the Principle Investigator with Kimley Horn, was present to provide an
overview of their study.
Jonathan Guy, Kimley Horn, stated two (2) community discussions were
conducted on the January 17, 2019 and a total of six (6) individuals attended,
and those were primarily residents near the Whilden Street and Hibben Street
intersection. Issues expressed were concern over parking control, availability,
roadway drainage and utilization of right-of-way. Some guidelines for a
Residential Parking Permit Program (RPPP) include qualifying criteria that will
enable the process and the process should be petition-based. Impacted
streets need to be identified and how they are going to be examined. The
program can be based on a block-by-block or a street-by-street district basis
which would be decided by the Committee. The main component of the
program incorporates citizen participation that is essential to move the
process forward. There is also a need to create an entity for implementation,
enforcement and adjudication. The process for creating a RPPP is to first
determine if there is a need, then develop a draft proposal, conduct a public
hearing and adopt an ordinance. Council will need to establish what the cause
Transportation Committee Minutes
March 4, 2019
Page 12 of 14
is and understand that the program is not a one size fits all solution.
Establishing an RPPP may create more issues and can be problematic if you
are dealing with issues such as short-term rentals. Signage can clutter the
rights-of-way and can become a visual nuisance. The program will also need
to identify the new Town resources to maintain, enforce, and coordinate the
program, as this is not something that could be handled by existing staff. The
public will need to be engaged early and often as the process moves forward.
Finding from the study indicate a program is not a good fit for the community.
Other recommendations are to consider additional off-street parking near
activity zones, delineate on-street parking where applicable, and partner with
local restaurants to minimize parking in residential areas. There is value in
these restaurants working with the private parking deck owner to make the
pricing more attractive. A shuttle between activity zones and available
parking facilities during peak events/times is also recommended.
Mr. Cunnane asked for clarification that six (6) residents attended the open
house.
Mr. Guy replied in the affirmative.
7. Discussion of Lucy Beckham High School bicycle and pedestrian access
Mayor Haynie asked if the Town had coordinated with CCSD for Lucy Beckham
High School.
Mr. Morrison replied in the affirmative stating that the issue dates back to
2016 when the school site was approved and the site design process began.
There has been a lot of coordination with the site design engineer and the
Office of School Facilities (OSF), and the SCDOT representative the reviews
site plans for OSF. The Mount Pleasant Fire Department (MPFD) was heavily
involved because the student drop-off area must provide continuous open
laneage and that has a significant effect on the site design. All driveways
except one utilize a right-in/right-out maneuver and have left turn lanes into
the driveways. The bus access is the only access that does not have a right
turn lane due to the low volume. There will be two thousand feet (2000’) of
queuing space in the student drop-off area and student driver access will be
located through Driveway 1 off Whipple Road. All roadways in the area have
Transportation Committee Minutes
March 4, 2019
Page 13 of 14
either sidewalks or multi-use paths. Through a resurfacing project, bike lanes
were added on Long Point Road between I-526 and Whipple Road. Staff is
also coordinating with the SCDOT to incorporate bike paths when Whipple
Road is resurfaced. The site plan provides an indication of what is planned
for access and how traffic will flow on the site. The last graphic displays a one-
mile radius of the school and highlights that almost all the roads (Mathis Ferry
Road, Whipple Road, Long Point Road, Hungryneck Boulevard and Venning
Road) have sidewalks to the site and some have multi-use paths.
Mayor Haynie stated that at the District 2 Constituent Board Meeting Sarah
Johnson, Constituent District 2 Board of Trustees Chair asked if staff would
attend the March 20, 2019 board meeting and asked if the Board had
coordinated that meeting with staff.
Mr. Morrison stated he contacted Mr. Borowy and asked if there were any
issues that need to be addressed by transportation department staff. Mr.
Borowy stated that the Board did not need any additional information on
these issues, but indicate they were coordinating with Mr. Jeff Ulma, Town of
Mount Pleasant Planning Director, to understand the housing stock and
growth projections to consider in their zone/districting.
Mayor Haynie stated that Ms. Johnson asked specifically if staff would attend,
stating that he would coordinate with Ms. Johnson.
Mr. Morrison stated a member of staff would be happy to attend the meeting.
Mr. Cunnane stated that he placed then item on the Town Council Agenda in
February and that it was moved to Transportation Committee agenda. He felt
it was a missed opportunity to reiterate the Town’s support for our citizens
who are under attack from the island citizens on the zoning issue. Residents
are expressing that they are not able to cross US 17 on a bicycle. I wanted to
ask staff to go beyond the actual boundary of the school to look at the
neighborhoods to ensure that there are safe options in the area. There are
some trails on the other side of Whipple that have been used in the past and
perhaps the trails should be walked to see if there is a need any
improvements between now and next September. There is a section of
sidewalk on Venning Road that is a mud-like sidewalk and it should be
Transportation Committee Minutes
March 4, 2019
Page 14 of 14
determined if there is a sidewalk in place or if one needs to be installed. These
issues are why this item was placed on the agenda so that we can come back
with concrete answers for the people that are actually within biking distance
of the school. In addition, there is an area on Nantahala Boulevard that has a
Mount Pleasant Waterworks pump station and one of the neighbors has
informed me that the area was used to access the old school. The question
is, is that feasible now. Speaking with the principle of Lucy Beckham High
School, as an individual, the question is can we coordinate a connection from
the school to Nantahala Boulevard, which also connects to Indigo Square and
US 17 and Towne Centre. A person on bicycle would be able to bicycle from
Belle Hall to Towne Centre or from Mathis Ferry Road through the school
property to Towne Center avoiding the scary intersections. It was a simple
item to put it on the agenda to help our citizens and it was kicked to the
Committee and is a missed opportunity to officially come back again and back
up our citizens.
8. Project Updates
Due to time constraints the agenda item was not discussed. Project updates
will be provided to the Committee and included in the minutes.
9. Adjourn
There being no further business, the meeting was adjourned at 3:35 p.m.
Respectfully submitted by,
Cathy Godsey
March 7, 2019
Mount Pleasant
Transportation
Committee
March 4, 2019
1. Approval of Minutes
from the February 4, 2019
meeting
2. Public Comments
3.Presentation of Design
Concepts for the Park West
Boulevard and Stockdale
Drive Intersection
PARK WEST BOULEVARD &
STOCKDALE STREET INTERSECTION
IMPROVEMENT STUDY
PROJECT STUDY AREA MAP
Rear-end/stop collisions accounted for majority of crashes
Proposed Developments along Park Avenue Boulevard & Faison
Road were taken into account in the study
24-Hour Tube Counts & Peak Hour Turning Counts were collected
within the project corridor
Signalization is currently not warranted at the Park West
Boulevard/Stockdale Street Intersection, but will likely meet
warrants in near future
DATA & ANALYSIS
Total of 3 alternatives were investigated
Each alternative contained both a roundabout and signalized
option
Each alternative involves new access point(s) to school complex
ALTERNATIVE ANALYSIS
ALTERNATIVE 1 - ROUNDABOUT
Traffic Enters from Thomas
Cario Boulevard
Thomas Cario Boulevard
exit becomes right turn
only
Probable construction
cost - $3,000,000
RIGHT
TURN
ONLY
RIGHT
TURN
ONLY
ALTERNATIVE 1 - SIGNALIZED
Traffic Enters from Thomas
Cario Boulevard
Thomas Cario Boulevard
exit becomes right turn
only
New Signal at Park West
Boulevard / Stockdale
Street and new
connector roadway. RIGHT
TURN
Probable construction ONLY
cost - $1,500,000
RIGHT
TURN
ONLY
ALTERNATIVE 2 - ROUNDABOUT
Thomas Cario Boulevard
will now operate as two
way traffic
Thomas Cario Boulevard
egress/ingress to Park
West Boulevard is utilized
as restricted access
New access road from
roundabout is now the
primary access to the
RIGHT
TURN
ONLY
school complex
Probable construction
cost - $3,500,000
RIGHT
TURN
ONLY
ALTERNATIVE 2 - SIGNALIZED
Thomas Cario Boulevard
will now operate as two
way traffic
Thomas Cario Boulevard
egress/ingress to Park West
Boulevard is utilized as
restricted access
New access road from
roundabout is now the
primary access to the
school complex
RIGHT
TURN
ONLY
New Signal at Park West
Boulevard / Stockdale
Street and new connector
roadway
Probable construction cost
- $2,500,000
RIGHT
TURN
ONLY
ALTERNATIVE 3 - ROUNDABOUT
New roundabout
constructed at Thomas
Cario Boulevard entrance
Thomas Cario Boulevard
exit is relocated to new
intersection with
Salterbeck Street
No left turns permitted at
Stockdale Street / Park
West Boulevard
Intersection (right in/right
out)
Probable construction
cost - $5,000,000
COMPARISON PARAMETERS
Capacity
Queue Lengths
Safety
Potential Environmental Impacts
Potential Right of Way Impacts
Potential Utility Impacts
Probable Construction Costs
Objective Score
Best – 1 to Worst – 5
RECOMMENDATION
Alternative 1 – Roundabout
Most typical design
Probable construction cost -
$3,000,000
RIGHT
TURN
ONLY
RIGHT
TURN
ONLY
4. Presentation of Design
Concepts for the Long
Point Road Maritime
District
CDM SMITH
LONG POINT ROAD
Area Land Use
• Western end of Long Point Rd.
• State Port Authority Wando Welch
Terminal
• North of Long Point Rd.
• Office Buildings
• Breweries
• Long Point Grill
• Other Commercial, Mixed Use
• Residential
• South of Long Point Rd.
• Primarily Residential
• Some Mixed Use
Purpose of the Project?
Long Point Rd.
Objective:
1. To improve the mobility and safety of Long Point Road at
its intersections with Wando Park Boulevard and
Shipping Lane.
2. Enhanced landscaping and potential medians to achieve
a boulevard concept
3. Provide interconnectivity between Shipping Lane and
Wando Park Boulevard
What are the Issues?
Wando Park Blvd. Intersection
• Weaving Movements within 700 LF from I-526 and Long Point Rd. to Lone Tree, Hobcaw Bluff, Wando Park
and Long Point.
• Dedicated Right Turn Lane originating from I-526 Off-Ramp
• Median Opening at Lone Tree Dr.
• Left Turns from Wando Park conflict with Left Turns from Hobcaw Bluff Dr. – Cannot turn simultaneously
• Over 2000 vehicles during AM and PM Peak Hours
• Daily Trucks: 36% of EB traffic and 24% of WB traffic
I-526
Wando Park Blvd.
Hobcaw Bluff Dr Lone Tree Dr
Shipping Ln. Intersection
• Unsignalized
• Over 1000 vehicles during AM and PM Peak Hours
• Daily Trucks: 51% of EB traffic and 41% of WB traffic
Shipping Ln
Initial Concepts
COST ESTIMATE BY
SECTION
SECTION 1 $ 440,449
SECTION 2 $ 187,145
SECTION 3 $ 504,178
SECTION 4 $ 439,532
SECTION 5 $ 399,103
SECTION 6 $ 4,853,256
SECTION 7 $ 958,205
TOTAL ESTIMATED COST:
$ 2,928,612 - $ 7,342,336
Next Steps
• Design intersection improvements at Wando Park Boulevard and
Hobcaw Bluff Drive
• Realign Left Turn on Hobcaw Bluff Drive (Section 2)
• Develop Additional Dedicated Left Turn on Wando Park Boulevard (Section 3)
• Complete final design
• Construction
• Evaluate budget for additional improvements
5. Status of possible
improvements at Park
Avenue/Faison Road
intersection
5. Status of possible improvements at Park Avenue/Faison
Road intersection
• Signal Warrant update in progress to
account for proposed development
adjacent to intersection
• Developer required to place mast arm
signal
TOWN OF MOUNT PLEASANT, S.C.
5. Status of possible improvements at Park Avenue/Faison
Road intersection
TOWN OF MOUNT PLEASANT, S.C.
5. Status of possible improvements at Park Avenue/Faison
Road intersection
TOWN OF MOUNT PLEASANT, S.C.
6. Review of Residential
Parking Permit Study
6. Review of Residential Parking Permit Program (RPPP) Study
• January 17th Community Discussion
• Two Meeting Times: 10am-Noon and 4pm-6pm
• Six (6) Residents attended
TOWN OF MOUNT PLEASANT, S.C.
6. Review of Residential Parking Permit Program (RPPP) Study
What we heard from the Residents
• Parking Control
• Parking Availability
• Roadway Drainage
• Utilization of right-of-way
TOWN OF MOUNT PLEASANT, S.C.
6. Review of Residential Parking Permit Program (RPPP) Study
Primary RPPP Components
• Guidelines and qualifying criteria must be established first
• Petition-based implementation is necessary for success
• Identification of impacted streets and data collection
• Can be based on a block-by-block, street, subdivision,
district basis
• Citizen participation is essential
• Establishment of an entity for implementation,
enforcement and adjudication
TOWN OF MOUNT PLEASANT, S.C.
6. Review of Residential Parking Permit Program (RPPP) Study
Process for creating a RPPP
1. Determine if there is a need for an RPPP
2. Establish a draft proposal for the RPPP – zones, restrictions, permitting
process, etc.
3. Conduct a public hearing
4. Council Endorsement/Adoption
TOWN OF MOUNT PLEASANT, S.C.
6. Review of Residential Parking Permit Program (RPPP) Study
RPPP Takeaways
1. Establish what the cause for parking concerns is first…supply, proximity, cost, etc.
2. Not a one-size fits all solution
3. Can be seen as a nuisance to residents – overreach by government
4. Signage can be visual nuisance
5. Significant government investment to maintain, enforce, and coordinate the
program – additional departmental resources required
6. Engage the public early and often for implementation
TOWN OF MOUNT PLEASANT, S.C.
6. Review of Residential Parking Permit Program (RPPP) Study
Conclusions
• Residential Parking Permit Program is not a good fit for the Community
• Consider additional off-street parking near activity zones
• Delineate on street parking where applicable
• Partner with local restaurants to minimize parking in residential areas
• Restaurant consortium should work with the private parking deck
owner to make parking in the deck more attractive
• Shuttle between activity zones and available parking facilities during
peak events/times
TOWN OF MOUNT PLEASANT, S.C.
7. Discussion of Lucy
Beckham High School
bicycle and pedestrian
access
7. Discussion of Lucy Beckham High School bicycle and
pedestrian access
1. The access and circulation plan was coordinated extensively with CCSD engineers, the Office of School
Facilities, SCDOT’s district office and their School Operations division in Columbia.
2. Significant input and design guidance was also provided by our fire department.
3. Note the following on the site plan:
• Except the right-in/right-out only Driveway #2, all access points have left-turn lanes into the site.
• Except for Bus Only access #4, all access points have right-turn lanes into the site.
• There is 2,000’ of on-site stacking provided for student drop-off/pick-up, which occurs on the Mathis
Ferry side of the campus.
• Student drivers access the site via Driveway #1 on the Whipple side of the campus.
4. Sidewalks and/or multi-use paths currently exist on all primary and secondary roads leading to the school
5. Bike lanes exist on Long Point Road and staff is working with SCDOT staff to implement bike lanes on Whipple
Road through upcoming resurfacing contract
TOWN OF MOUNT PLEASANT, S.C.
TOWN OF MOUNT PLEASANT, S.C.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
8. Project Updates
Coleman Boulevard Revitalization
Contractor: Blythe Development
Start Date: September 11, 2017
Completion Date: December 27, 2019
Status:
• Stage 1 Westbound – Complete.
• Stage 2 Eastbound – Sidewalk and curb going in.
• Stage 3 Median Construction – February to August.
• Stage 4 Final Paving - August to October.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Coleman Boulevard Revitalization
Project Progress as of February 28, 2019
•All Phase 1 Storm Drain Complete • 2,000 Feet of Lighting and Irrigation Conduits
•7500 Feet of Storm Drain • Simmons Street Force Main Relocation
•80 Drainage Structures • Simmons Street Gravity Sewer Relocation
•3 Water Quality Treatment Devices • Simmons Street Gravity Sewer Repair
•5000 Feet of Curb and Gutter • Simmons Street Paving
•4,500 Feet of Sidewalk • Fairmont Avenue Force Main Relocation
• 2,400 Feet of New Waterline on Coleman
• 3 Waterline Relocations Completed
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Coleman Boulevard Revitalization
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
US 17 to Rifle Range Road Connector
Project Cost Estimate:
• $10.641M ($5.74M Funded)
Designer: JMT
Completion Date:
• Design: September 2019
• Construction: September 2022
Status:
• Design of road between Billy Swails Blvd. and Rifle Range Road is
ongoing.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Long Point Road Extension
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Patriots Point Gateway Intersection Improvements
Project Cost Estimate:
• $6,765,800 Fully funded via adoption of 2019-2023 CIP
Designer: STV Incorporated
Completion Date:
• Design and Permitting: July 2020
• Construction: July 2020 - December 2021
Status:
• Utility coordination is ongoing. Consultant working DE for 11 ft.
lanes.
• MPW has initiated utility relocation design.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Patriots Point Gateway Intersection Improvements
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Billy Swails Boulevard 4B
Project Cost Estimate:
• $12,568,497 ($2,568,497 TOMP and $10,000,000 Federal)
Designer: Stantec Consulting Services, Inc.
Completion Date:
• Design: August 2020
• Construction: August 2022
Status:
• Currently, several alignment alternatives are being reviewed through the
NEPA process. Alignment options include studying impacts of widening US-
17 and Rifle Range Road vs. BSB. Based on this and input from SCDOT we
should be ready for the next public meeting in April.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Billy Swails Boulevard 4B
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Shem Creek Bridge Bike Lanes
Project Cost Estimate:
• $791,000 ($158,000 TOMP and $633,000 Federal)
Consultant: CDM Smith
Completion Date:
• Design: June 2019
• Construction: March 2020
Status:
• Preliminary plans have been submitted to SCDOT and are
currently under review.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Shem Creek Bridge Bike Lanes
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Park West Boulevard Widening
•Design Consultant: Mead and Hunt
•Design: Complete
•Permitting: Complete June 2019
•Project Cost Estimate: $7M with 15% contingency
•Construction Schedule: June 2019 –December 2020
•Status:
• Consultant is developing final construction quantities and estimates.
• MPW utility relocations will be included in roadway contract.
• MPW consultant is currently designing water and sewer relocations.
• Staff is currently producing bid documents for advertisement in
March 2019.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Park West Boulevard Widening
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
All American Boulevard Extension
Project Cost Estimate:$5.365M ($2.05M Funded)
Consultant: Mead and Hunt
Completion Date:
• Design: March 2018 - December 2019
• Construction: March 2020 – December 2021
Status:
•Designer is currently working on alignment alternatives.
•Wetlands have been delineated.
•Phase 1 designer under contract for plan revisions and right of way acquisition
for that phase.
•PIM held December 18.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates All American Boulevard Extension
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates All American Boulevard Extension
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Maritime Port District Improvements Study
Project Cost Estimate:
• $163,458 for concept study – $1,500,000 funded via adoption of
2019-2023 CIP
Consultant: CDM Smith
Completion Date:
• Concept Study: August 2018 - January 2019
Status:
• Concept Study is complete.
• Will provide concept plans to Committee in March.
• Met with SCSPA in November. Meet with neighborhoods in
February.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Maritime Port District Improvements Study
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Park West Boulevard and Stockdale Street
Improvements
Project Cost Estimate:
• Concept Design: $200,000
Consultant: Mead and Hunt
Completion Date:
• Concept Study: October 2018 - September 2019
• Construction: NA
Status:
• Intersection concept study is underway to be completed in
February.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Park West Boulevard and Stockdale Street
Improvements
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Transportation Sales Tax (TST) Projects
•Park West Boulevard sidewalk from Stockdale Street to the
recreation complex is complete.
•Anna Knapp Boulevard sidewalk from Johnnie Dodds Boulevard to
Hibben Ferry is complete.
•Belle Hall Parkway and Paul Foster Mini Roundabout under design.
TOWN OF MOUNT PLEASANT, S.C.
8. Project Updates
Charleston Transportation Committee (CTC) Projects
•Pelzer Drive sidewalk is complete
•Lansing Drive sidewalk project is currently under design.
•Seacoast Parkway sidewalk project is currently in design and
additional right of way needs are being evaluated.
•Cottingham Drive sidewalk design to be funded next year.
TOWN OF MOUNT PLEASANT, S.C.
9. Adjourn
Agenda
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
COMMITTEES OF COUNCIL
MEETING NOTICE
Monday, March 4, 2019
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
Bids and Purchases Committee 8:30 a.m.
Public Services Committee 8:45 a.m.
Finance Committee 9:45 a.m.
Police, Judicial, and Legal Committee 10:30 a.m.
Economic Development Committee 11:15 a.m.
Planning and Development Committee 12:15 p.m.
Transportation Committee 1:45 p.m.
Fire Committee 2:45 p.m.
Special Town Council Meeting 3:30 p.m.
The following Committees will not meet:
Education Committee
Human Resources Committee
Recreation Committee
Water Supply Committee
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
in accessible formats, and provided in languages other than English. If you
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
BIDS AND PURCHASES COMMITTEE
Monday, March 4, 2019
8:30 a.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the January 3, 2019 meeting
2. Public Comments
3. Review of the Construction Manager at Risk Process
4. Award of contract for adaptive signal control system upgrades on
Coleman Boulevard
5. Local Vendor Quarterly Report
6. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
in accessible formats, and provided in languages other than English. If you
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
PUBLIC SERVICES COMMITTEE
Monday, March 4, 2019
8:45 a.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the January 3, 2019 meeting
2. Public Comments
3. Review of Public Services Department Facilities Master Plan
4. Update on Old Village Drainage Improvement Project design
5. Consideration of amendments to the Environmentally Acceptable
Packaging and Products ordinance
6. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
in accessible formats, and provided in languages other than English. If you
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
FINANCE COMMITTEE
Monday, March 4, 2019
9:45 a.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the February 4, 2019 meeting
2. Public Comments
3. Employee years of service recognition
4. Discussion regarding the purchase of a fire ladder truck and pumper
from Fund Balance
5. Discussion regarding the pursuit of a SAFER grant for the hiring of
firefighters
6. Presentation by East Cooper Land Trust
7. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
in accessible formats, and provided in languages other than English. If you
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
POLICE, JUDICIAL & LEGAL COMMITTEE
Monday, March 4, 2019
10:30 a.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the February 4, 2019 meeting
2. Public Comments
3. Police matters
a. Employee years of service recognition
4. Judicial matters
No agenda items
5. Legal matters
a. Consideration of a firefighter staffing ordinance
b. Consideration of a resolution supporting H3355 also known as the
hands free while driving bill
c. Review of recommendations to improve the structure of the Town
Council agenda
d. Discussion of liquor store densities in Mount Pleasant
6. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
in accessible formats, and provided in languages other than English. If you
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
ECONOMIC DEVELOPMENT COMMITTEE
Monday, March 4, 2019
11:15 a.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the February 4, 2019 meeting
2. Public Comments
3. Consideration of an economic development incentive grant
a. Executive Session - discussion of a contractual matter related to an
Economic Development Grant
b. Post executive session
Committee may take action on any item, including any subsection of
any section, listed on an executive session agenda or discussed in an
executive session during a properly noticed meeting
4. Update on proactive efforts to reach out to landholders and/or
developers to collaborate on building Economic Development projects
5. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
in accessible formats, and provided in languages other than English. If you
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
PLANNING & DEVELOPMENT COMMITTEE
Monday, March 4, 2019
12:15 p.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the February 4, 2019 meeting
2. Public Comments
3. Old Business
a. R-01-19, Request to rezone from PI-2, Public Institutional-2 District,
to LI, Light Industrial District, one parcel in its entirety located at 520
King Street between Greenwich and Simmons Street, Parcel ID TMS
No.: 532-01-00-227
4. Annexations
a. A-4-19: 1593 Boston Grill Road. Request to annex an approximately
0.86 acre tract of land located at 1593 Boston Grill Road, identified
by TMS No. 577-00-00-078 and depicted on a plat recorded by
Charleston County ROD Office in Plat Book BQ, Page 32
5. Review of Planning Commission recommendations from the February
20, 2019 meeting and any associated annexations
a. A-3-19: Labor Camp Road. Request to annex an approximately 0.977
acre tract of land located on Labor Camp Road, identified by TMS No.
558-00-00-944 and depicted as Lot 4 on a plat recorded by
Charleston County ROD Office in Plat Book L18, Page 0563.
b. R-04-19, Request to zone PI-2, Public Institutional-2 District, an
approximately 0.98 acre tract of land located on Labor Camp Road,
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
identified by TMS No. 558-00-00-944, and depicted on a plat
recorded by the Charleston County ROD Office in Plat Book L18, Page
0563.
c. Proposal to amend Chapter 156 of the Mount Pleasant Code of
Ordinances, Section 156.325 (C), Principal Use Table, to allow Duplex
Dwellings, Multi-Family Dwellings and Single Family Dwellings as a
Conditional Use in any nonresidential zoning district, subject to the
conditions of Section 156.326 (C)(2)(e), as proposed to be amended,
and to amend Section 156.326 (C)(2)(e), Principal Use Conditions, to
include Duplex Dwellings and Single-Family Dwellings as a
Conditional Use, subject to the conditions enumerated therein.
d. Proposal to repeal sub-paragraphs (1) and (2) of Paragraph (A) of
Section 156.224 of Chapter 156 of the Mount Pleasant Code of
Ordinances pertaining to tree conditions as the basis of providing
exceptions to tree removal and replacement, and replace the same
with new language addressing the same topic.
e. Update on Comprehensive Plan
6. Consideration of extending 2017 Moratorium on Multi-Family Structures
7. Discussion of hotels, storage unit buildings, and zoning regulations
8. Discussion of building heights in the Johnnie Dodds and Chuck Dawley
portions of the Boulevard Overlay District
9. Discussion of draft of Short Term Rental regulations
10. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
in accessible formats, and provided in languages other than English. If you
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
TRANSPORTATION COMMITTEE
Monday, March 4, 2019
1:45 p.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the February 4, 2019 meeting
2. Public Comments
3. Presentation of Design Concepts for the Park West Boulevard and
Stockdale Drive Intersection
4. Presentation of Design Concepts for the Long Point Road Maritime
District
5. Status of possible improvements at Park Avenue/Faison Road
intersection
6. Review of Residential Parking Permit Study
7. Discussion of Lucy Beckham High School bicycle and pedestrian access
8. Project Updates
9. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI
of the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be
provided in accessible formats, and provided in languages other than
English. If you would like accessibility or language accommodation,
please contact the Title VI Coordinator one week in advance of the
meeting, at the Town of Mount Pleasant at 843-884-8517.
Telephone (843) 884-8517 - Fax (843) 856-2180
www.tompsc.com
MOUNT PLEASANT COMMITTEE ASSIGNMENTS
FIRE COMMITTEE
Monday, March 4, 2019
2:45 p.m.
Municipal Complex, Committee Meeting Room, 3rd Floor
100 Ann Edwards Lane, Mount Pleasant, SC 29464
AGENDA
1. Approval of Minutes from the December 3, 2018 meeting
2. Public Comments
3. Consideration of a firefighter staffing ordinance
4. Discussion with regard to placing fire department strategic plan in a
priority funding position
5. Discussion regarding the purchase of a fire ladder truck and pumper
from Fund Balance
6. Discussion regarding the pursuit of a SAFER grant for the hiring of
firefighters
7. Adjourn
Title VI Notice: The Town of Mount Pleasant fully complies with Title VI of
the Civil Rights Act of 1964, the Americans with Disabilities Act, and
related statutes and regulations in all programs and activities. Town
meetings are conducted in accessible locations, materials can be provided
in accessible formats, and provided in languages other than English. If you
would like accessibility or language accommodation, please contact the
Title VI Coordinator one week in advance of the meeting, at the Town of
Mount Pleasant at 843-884-8517.