Planning Board
Regular MeetingMount Vernon, NY · July 12, 2023
Minutes
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
MEETING MINUTES
PLANNING BOARD
REGULAR MEETING
for July 12, 2023
A regular meeting of the City Planning Board was held on Wednesday, July 12, 2023 a t
6:30 PM in the Memorial Room on the second floor of City Hall. Applicants and
members of the public were permitted to attend and make public comment via in person
attendance.
The Chair read the meeting notice into the record then indicated that the roll call was the
first item on the agenda. The Chair asked the staff to start the live streaming of the meeting
on Facebook.
ROLL CALL
The Chair called the roll: in addition to Chairman Darryl Selsey, attending were the following
Commissioners: Ms. Helene Thompson-Njenga, Mr. Charles Whites, and Mr. Jamael
Thompson. Commissioner Frank Trolio attended via Zoom.
Also attending were Katherine Mella, Associate Commissioner, Maria Pace, Secretary to the
Planning Board, Will Hyland, Senior Planner, and U. Nkechi Nwachukwu, land use counsel.
The Chair indicated that there was a quorum present and opened the meeting at 6:30 pm.
APPROVAL OF MINUTES
The Chair asked if the Commissioners had an opportunity to review the minutes of May 3,
2023. There being no further changes, Commissioner Whites made a motion to approve the
1
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
minutes for May 3, 2023, seconded by Commissioner Thompson and carried by a vote of 5-0.
PUBLIC HEARINGS
Adjourned
3.1 Case No. PB-22-1: 24 Locust Lane (Section 159.81, Block 2032, Lot 2) in the R1-7 Zoning
District.
The Applicant requested an adjournment to the September Planning Board meeting to allow
the City Engineer and consultants to complete a hydraulic modeling study and make a
determination regarding how best to address drainage and stormwater retention issues.
Continued Public Hearing
3.2 Case No. PB-23-1: 602 South Third Avenue (Section 169.47, Block 3105, Lot 1) in the
Landscaped Industrial (LI) 7.5 District
Regarding public notice, the Board previously received proof of mailing, proof of
publication in the Journal News, and proof of initial sign posting for the application.
The Board also received an Affidavit of Sign Posting stating that on June 26, 2023 a sign
was posted at the site giving notice of the Planning Board’s July 12, 2023 meeting. The
Board also received photographs showing that the sign posting on the property had been
updated providing notice of today’s meeting.
The owner is Kovar Hill Associates, LLC represented by Mr. Tom Abillama, Architect.
The subject property is in the Landscaped Industrial (LI) 7.5 Zone and is 1.20 acres. The
application is for site plan review by the Planning Board for a two-story, 18,375-sf
addition for manufacturing and office use at the rear of an existing two-story office and
one-story warehouse at 602 South Third Avenue.
The application also included expanding the existing curb cut and driveway on East 7th
Street and South 4th Avenue. A stormwater management system is proposed for the site
with 42 cultec chambers where none now exists. The Project is zoning compliant and will
need ARB approval in addition to site plan review by the Planning Board. The facility is
occupied by Commodore Construction Corp. Their business hours are M-F 7am-4pm.
The company also works two Saturdays a month from 7am-2pm.
The Applicant has retained JMC Engineering to conduct a traffic study for the project.
At the May meeting, the Planning Board requested that the applicant revise their site plans to
reflect a new fence, lighting, and a landscaping plan, provide the traffic study, and provide
further information regarding new jobs tied to the expansion.
2
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
SEQRA Determination – The proposed action is an Unlisted action under SEQRA. The
Planning Board can establish itself as the Lead Agency for the environmental review of
this site plan. Planning Board will need to complete the SEQRA process before completing
their review.
This application was sent to the Fire Department, the Police Department, the Water
Bureau, the Commissioner of DPW, and the City Engineer.
Mr. Jack Addesso, the attorney for this project, began by confirming that the plans for
the site had been revised as requested. He also said that Kevin Masciovecchio from JMC
Engineering was in attendance to review the traffic study.
Mr. Masciovecchio explained that traffic counts were conducted from 6:30-8:30 AM and
from 2:00-6:00 PM at several intersections on Tuesday, April 25, 2023. Peak hour
volumes occurred between 7:30-8:30 AM during the weekday morning and 2:45-3:45 PM
during the weekday afternoon but the uptick was small.
Commissioner Thompson-Njenga asked what time operations would normally start.
Mr. Masciovecchio replied that optimally the operations would normally run from 7:00
AM-4:00 PM, but that the applicants wish to work and coordinate with the local school
schedule to ensure that incoming trucks will not affect school traffic.
Mr. Addesso said that the new addition would not significantly impact the traffic at the
site and that trucks have been rerouted in such a way to create less impact.
The Chair asked if the truck size at the facility would change.
Mr. Tom Abillama and Ms. Carla Tannous said the size would stay the same with no
more than 2-5 trucks entering the facility at any one time. There will also be a dedicated
entrance and egress exit with trucks coming in one way and cars another way.
Mr. Addesso then said that previously there were 145 parking spaces but that another 21
spaces will be added.
Ms. Tannous explained that the impervious surface would be 89.5%. Evergreen hedges
would be added, and a heavy gauge aluminum fence would be installed around the
property. There will also be wall lighting all around as well as security cameras at all
entrances. The cameras will have a 60-day retention time.
The Chair asked if this project would result in any additional jobs.
Mr. Addesso said yes, about 5-7 semi-skilled positions would be added.
Land Use Counsel suggested that language be incorporated into a potential resolution
reflecting the applicant’s intent to hire locally.
3
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
Land Use Counsel inquired about a handicapped parking area and if there is adequate
access for fire and emergency vehicles.
Ms. Tannous pointed out the handicap parking spot as displayed on the proposed 1st
Floor plan and its proximity to the elevator. Mr. Addesso and Mr. Abillama indicated
that the facility is designed to accommodate trucks and would provide adequate access
for fire and emergency vehicles.
Land Use Counsel then asked if there was a potential for installing solar panels in the
future and whether the manufacturing would produce any noise.
Mr. Abillama said there was room on the existing roof for solar panels. Applicant’s
attorney and architects also explained that the facility is mostly used to manufacture
large glass for high-rise and other buildings. They indicated that the manufacturing done
in the existing building does not produce objectionable noise and the proposal is simply
an expansion of the current use.
The Chair then asked if there were any public comments. There were none.
The Chair then made a motion to establish the Planning Board as lead agency under
SEQRA, seconded by Commissioner Whites and carried by a vote of 5-0.
Land Use Counsel then reviewed the Part II Full EAF with the board.
The Chair made a motion to issue a Negative Declaration, seconded by Commissioner
Whites and carried by a vote of 5-0.
The Chair made a motion for Planning Department staff to draft a resolution with
conditions, including the 60-day retention of the security cameras and that Applicant
demonstrate good faith efforts to hire locally, seconded by Commissioner Thompson-
Njenga and carried by a vote of 5-0.
Continued Public Hearing
3.3 Case No. PB-23-4: 250 East Sandford Blvd. (Section 169.41, Block 4085, Lot 1) in the CB
Zone
Regarding public notice, the Board previously received proof of mailing, proof of
publication in the Journal News, and proof of initial sign posting for the application.
The Board also received an Affidavit of Sign Posting stating that on June 23, 2023 a sign
was posted at the site giving notice of the Planning Board’s July 12, 2023 meeting. The
Board also received photographs showing that the sign posting on the property had been
updated providing notice of today’s meeting.
4
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
Applicant, 250 E. Sandford Realty, LLC, is the owner of the 2.579-acre (112,364 sf) property.
The architectural firm is Perkins Eastman. The site is located on the south side of East
Sandford Blvd at the corner of Nuber Avenue. The property is currently occupied by an
existing, 110,360 sf warehouse at 250 East Sandford Blvd. in the Commercial Business (CB)
district. The existing use has on-site parking for 137 vehicles which will not be changed. The
warehouse is an existing non-conforming building. The surrounding neighborhood consists of
mostly commercial buildings, retail businesses and fast-food restaurants.
The ARB issued a certificate of appropriateness for the renovations and alterations on
10/27/21 including life safety code compliance. Previous work included new elevator and
bathroom core, new egress stair, exterior façade upgrades with EIFS finish, aluminum
coping and new energy efficient windows. Landscaping with street trees has been installed in
front of the building along East Sandford Blvd.
The Applicant is seeking a special permit from the Planning Board for tenant fit out of
wholesale businesses including storage, warehousing and distribution in fully enclosed
buildings (alteration level 2 – change of use). The proposed use requires a special permit
under §267-20 (D)(3)(e). Applicant has provided a Narrative addressing the following
standards of the special permit:
A) The location and size of the special permit use, the nature and intensity of the operations
involved with it, the size of the site in relation to it and the location of the site with respect
to streets giving access to it are such that it will be in harmony with appropriate and orderly
development of the area in it is located.
B) The location, nature and height of the building walls, and fences and the nature and extent
of existing or proposed plantings on the site are such that the special permit use will not
hinder or discourage the appropriate development and use of adjacent land and buildings.
C) Operations in connection with any special permit use will not be more objectionable to
nearby properties by reason of noise, traffic, fumes, vibration or such other characteristics
than would be the operation of permitted uses not requiring a special permit.
At the May meeting, land use counsel requested a copy of the easement agreement between
the building and the Stop & Shop next door. This was subsequently provided the next day to
the Planning Department and forwarded to the Planning Board for review.
SEQRA Determination – The proposed action is a Type II action based on 617.5(c)(2)
“replacement, rehabilitation or reconstruction of a structure or facility, in kind, on the same
site, including upgrading buildings to meet building, energy, or fire codes.”
As requested at the May meeting, a draft resolution as a Type II Action was provided to the
Planning Board for review.
5
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
Mr. Addesso then reviewed the narrative submitted for the special use permit.
The Chair asked if there were any public comments. There were none.
The Chair then made a motion to close the public hearing, seconded by Commissioner
Whites and carried by a vote of 5-0.
The Chair then made a motion to approve the resolution, seconded by Commissioner Trolio
and carried by a vote of 5-0.
New Public Hearing
3.4 Case No. PB-23-9 159 North Fulton Avenue (Section 165.55, Block 2057, Lot 27) in the
RMF- 6.75 District.
Regarding public notice, the Board previously received proof of mailing, proof of
publication in the Journal News, and proof of initial sign posting for the application.
The Board received an Affidavit of Sign Posting stating that on June 23, 2023 a sign was
posted at the site giving notice of the Planning Board’s July 12, 2023 meeting. The Board
also received photographs showing that the sign posting on the property had been
updated providing notice of today’s meeting.
Filomena & Ilda Tavares are the owners of a 17,128-sf subject property on the east side of North
Fulton Avenue opposite Willow Place. The owner is represented by Mr. Ted D’Amore, Architect.
The application is a proposal to subdivide a 17,128.3-sf lot with a 100' frontage to two lots of
50' frontage each. The present lot is not a rectangle, so the lots will not be of equal size. The
lot with the present house and garage will be on the larger lot. Both lots meet the
requirements for two-family houses according to R2-4.5 regulations, which is allowed in
RMF-6.75 (three-family house) zones.
The subject parcel sits in a neighborhood of predominantly two- and three-family houses on
lots of 50’ x 100.’ The subject parcel is one of the largest in the neighborhood, at over 17,000
sf. The minimum lot size under R2-4.5 requirements is 4,500 sf. This proposal is for the lot
with the existing house and garage to have 9,209.9 sf, more than double the requirement, and
to have the vacant lot at 7,925.4 sf, more than 50% larger than the minimum
requirement. The lot with the existing house and garage meets all the zoning regulations. No
variances are required.
The vacant lot is not proposed to be developed at this time by the owner.
6
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
SEQRA Determination– The proposed action is an unlisted action under SEQRA. The
Planning Board is the only interested agency and as such can assume Lead Agency status at
its meeting on July 12, 2023.
This application was sent to the Fire Department, the Police Department, the Water
Bureau, the Commissioner of DPW, and the City Engineer. Fire Safety responded with
the recommendation to install a sprinkler system. The Fire Department had no issues
with the application provided that they have access to the site in the event of an
emergency. The Police Department responded with no objections.
Mr. Ted D’Amore confirmed that there were no variances or setbacks on the lots and that the
vacant lot could accommodate a large house. As the owners are retired, the intent is to
subdivide and sell the vacant lot.
He also explained that, according to New York State code, a sprinkler system is not
necessary or required in houses that are only two stories.
Commissioner Whites suggested that a condition to ensure that only a two-family house
be built on the vacant lot be added to a future resolution.
The Chair asked if there were any public comments. There were none.
The Chair asked about the parking.
Mr. D’Amore said that there is a garage and two parking spots on the first lot; there are
no changes to the house. He said that there is adequate space on the second (vacant) lot
for a garage in back or underneath the potential house.
Land Use Counsel inquired about landscaping.
Mr. D’Amore said that there are trees on the property, including a street tree, and that
the site is all grass, so the site is already landscaped.
The Chair said that the site needed a landscape plan based on the code and requested this
for the August meeting.
The Chair made a motion to adjourn the application to the August meeting, seconded by
Commissioner Whites and carried by a vote of 5-0.
The Chair then made a motion that the Planning Department staff write a draft
resolution for the August meeting that includes a condition for a landscaping plan,
seconded by Commissioner Thompson and carried by a vote of 5-0.
The Chair made a motion that the Planning Department prepare the Part II EAF,
seconded by Commissioner Whites and carried by a vote of 5-0.
7
City of Mount Vernon Meeting Date
Planning Board Meeting Minutes July 12, 2023
There being no further business, The Chair made a motion to adjourn the meeting, seconded
by Commissioner Thompson and carried by a vote of 5-0.
The meeting was adjourned at 8:09 PM.
Note: Work Sessions will be open to the public but closed to public participation subject to
the Open Meetings Law, [Section 105 of New York State Public Officers Law, Article 7].
Note: Items listed on the agenda are subject to change and amendments and/or additions may
be placed on the agenda.
Maria Pace, Secretary to the Planning Board
Bob Galvin, AICP, Planning Administrator
8
Agenda
City of Mount Vernon Meeting Date
Planning Board Agenda July 12, 2023
PLANNING BOARD
MEETING/HEARING
JULY 12, 2023
AGENDA
A regular meeting of the City Planning Board will be held on Wednesday, July 12, 2023, at 6:30
PM in the Memorial Room on the second floor of City Hall. Applicants and members of the
public will be permitted to attend and make public comment via in person attendance and
Zoom.
ITEM #1 ROLL CALL
ITEM #2 APPROVAL OF MINUTES
• May 3, 2023
ITEM # 3 PUBLIC HEARINGS
Adjourned
3.1 Case No. PB-22-1: 24 Locust Lane (Section 159.81, Block 2032, Lot 2) in the R1-7 Zoning
District.
Applicant requested an adjournment to the September Planning Board meeting to allow the
City Engineer and consultants to complete a hydraulic modeling study and make a
determination regarding how best to address drainage and stormwater retention issues.
1
City of Mount Vernon Meeting Date
Planning Board Agenda July 12, 2023
Continued Public Hearing
3.2 Case No. PB-23-1: 602 South Third Avenue (Section 169.47, Block 3105, Lot 1) in the
Landscaped Industrial (LI) 7.5 District
Regarding public notice, the Board previously received proof of mailing, proof of publication
in the Journal News, and proof of initial sign posting for the application.
The Board has also received an Affidavit of Sign Posting stating that on June 26, 2023 a sign
was posted at the site giving notice of the Planning Board’s July 12, 2023 meeting. The
Board also received photographs showing that the sign posting on the property has been
updated providing notice of today’s meeting.
The owner is Kovar Hill Associates, LLC represented by Mr. Tom Abillama, Architect. The
subject property is in the Landscaped Industrial (LI) 7.5 Zone and is 1.20 acres. The
application is for site plan review by the Planning Board for a two-story, 18,375-sf addition
for manufacturing and office use at the rear of an existing two-story office and one-story
warehouse at 602 South Third Avenue.
The application also includes expanding the existing curb cut and driveway on East 7th
Street and South 4th Avenue. A Stormwater management system is proposed for the site
with 42 cultec chambers where none now exists. The Project is zoning compliant and will
need ARB approval in addition to site plan review by the Planning Board the facility is
occupied by Commodore Construction Corp. Their business hours are M-F 7am-4pm. The
company also works two Saturdays a month from 7am-2pm.
The Applicant has retained JMC Engineering to conduct a traffic study for the project.
At the May meeting, the Planning Board requested that the applicant revise their site plans to
reflect a new fence, lighting, and a landscaping plan, provide the traffic study, and provide
further information regarding new jobs tied to the expansion.
SEQRA Determination – The proposed action is an Unlisted action under SEQRA. The
Planning Board can establish itself as the Lead Agency for the environmental review of this
site plan. Planning Board will need to complete the SEQRA process before completing their
review.
This application has been sent to the Fire Department, the Police Department, the Water
Bureau, the Commissioner of DPW, and the City Engineer.
2
City of Mount Vernon Meeting Date
Planning Board Agenda July 12, 2023
Continued Public Hearing
3.3 Case No. PB-23-4: 250 East Sandford Blvd. (Section 169.41, Block 4085, Lot 1) in the CB
Zone
Regarding public notice, the Board previously received proof of mailing, proof of publication
in the Journal News, and proof of initial sign posting for the application.
The Board has also received an Affidavit of Sign Posting stating that on June 23, 2023 a sign
was posted at the site giving notice of the Planning Board’s July 12, 2023 meeting. The
Board also received photographs showing that the sign posting on the property has been
updated providing notice of today’s meeting.
Applicant, 250 E. Sandford Realty, LLC, is the owner of the 2.579-acre (112,364 sf) property.
The architectural firm is Perkins Eastman. The site is located on the south side of East Sandford
Blvd at the corner of Nuber Avenue. The property is currently occupied by an existing, 110,360
sf warehouse at 250 East Sandford Blvd. in the Commercial Business (CB) district. The existing
use has on-site parking for 137 vehicles which will not be changed. The warehouse is an existing
non-conforming building. The surrounding neighborhood consists of mostly commercial
buildings, retail businesses and fast-food restaurants.
The ARB issued a certificate of appropriateness for the renovations and alterations on 10/27/21
including life safety code compliance. Previous work included new elevator and bathroom
core, new egress stair, exterior façade upgrades with EIFS finish, aluminum coping and new
energy efficient windows. Landscaping with street trees has been installed in front of the
building along East Sandford Blvd.
The Applicant is seeking a special permit from the Planning Board for tenant fit out of
wholesale businesses including storage, warehousing and distribution in fully enclosed
buildings (alteration level 2 – change of use). The proposed use requires a special permit under
§267-20 (e). Applicant has provided a Narrative addressing the following standards of the
special permit:
A) The location and size of the special permit use, the nature and intensity of the operations
involved with it, the size of the site in relation to it and the location of the site with respect to
streets giving access to it are such that it will be in harmony with appropriate and orderly
development of the area in it is located.
B) The location, nature and height of the building walls, and fences and the nature and extent of
existing or proposed plantings on the site are such that the special permit use will not hinder
or discourage the appropriate development and use of adjacent land and buildings.
3
City of Mount Vernon Meeting Date
Planning Board Agenda July 12, 2023
C) Operations in connection with any special permit use will not be more objectionable to nearby
properties by reason of noise, traffic, fumes, vibration or such other characteristics than
would be the operation of permitted uses not requiring a special permit.
At the May meeting, land use counsel requested a copy of the easement agreement between the
building and the Stop & Shop next door.
SEQRA Determination – The proposed action is a Type II action based on 617.5(c)(2)
“replacement, rehabilitation or reconstruction of a structure or facility, in kind, on the same site,
including upgrading buildings to meet building, energy, or fire codes.”
New Public Hearing
3.4 Case No. PB-23-9 159 North Fulton Avenue (Section 165.55, Block 2057, Lot 27) in the
RMF- 6.75 District.
Regarding public notice, the Board previously received proof of mailing, proof of publication
in the Journal News, and proof of initial sign posting for the application.
The Board has also received an Affidavit of Sign Posting stating that on June 23, 2023 a sign
was posted at the site giving notice of the Planning Board’s July 12, 2023 meeting. The
Board also received photographs showing that the sign posting on the property has been
updated providing notice of today’s meeting.
Filomena & Ilda Tavares are the owners of a 17,128-sf subject property on the east side of North
Fulton Avenue opposite Willow Place. The owner is represented by Mr. Ted D’Amore, Architect.
The application is a proposal to subdivide a 17,128.3-sf lot with a 100' frontage to two lots of 50'
frontage each. The present lot is not a rectangle, so the lots will not be of equal size. The lot with
the present house and garage will be on the larger lot. Both lots meet the requirements for two-
family houses according to R2-4.5 regulations, which is allowed in RMF-6.75 (three-family
house) zones.
The subject parcel sits in a neighborhood of predominantly two- and three-family houses on
lots of 50’ x 100.’ The subject parcel is one of the largest in the neighborhood, at over 17,000 sf.
The minimum lot size under R2-4.5 requirements is 4,500 sf. This proposal is for the lot with
the existing house and garage to have 9,209.9 sf, more than double the requirement, and to have
the vacant lot at 7,925.4 sf, more than 50% larger than the minimum requirement. The lot with
the existing house and garage meets all the zoning regulations. No variances are required.
The vacant lot is not proposed to be developed at this time by the owner.
SEQRA Determination– The proposed action is an unlisted action under SEQRA. The Planning
4
City of Mount Vernon Meeting Date
Planning Board Agenda July 12, 2023
Board is the only interested agency and as such can assume Lead Agency status at its meeting on
July 12, 2023.
This application has been sent to the Fire Department, the Police Department, the Water
Bureau, the Commissioner of DPW, and the City Engineer. Fire Safety responded with the
recommendation to install a sprinkler system. The Fire Department had no issues with the
application provided that they have access to the site in the event of an emergency. The
Police Department responded with no objections.
Note: Work Sessions will be open to the public but closed to public participation subject to the Open
Meetings Law, [Section 105 of New York State Public Officers Law, Article 7].
Note: Items listed on the agenda are subject to change and amendments and/or additions may
be placed on the agenda.
Upcoming Dates
• Tuesday, August 1 at 6:30pm - Planning Board Work Session.
• Wednesday, August 2, 2023, at 6:30pm - regular meeting of the Planning Board.
James Rausse, Planning Commissioner
Marlon Molina 2nd Deputy Planning Commissioner
cc: Shawyn Patterson-Howard, Mayor
Building Department
Corporation Counsel
City Clerk
5