City Council
Regular MeetingMountain Lakes, NJ · September 28, 2022
Agenda
BOROUGH OF MOUNTAIN LAKES
SEPTEMBER28, 2022
PAGE2
d. R156-22, Authorizing the Execution of Construction and Drainage Easements from Various Property Owners to
the Borough of Mountain Lakes in Conjunction with the Sunset Lake Dam Improvement Project
e. R157-22, Authorizing the Settlement of a Tax Appeal (Zorlas James/Barbara v. Borough of Mountain Lakes -
Block 31 Lot 27
f. R158-22, Authorizing the Execution of an Application for Utility Opening Permit from the New Jersey Department
of Transportation and a Hold Harmless Agreement between the Borough of Mountain Lakes and Highview
Commercial, LLC
*APPROVAL OF MINUTES
519/22 (Executive)
9112122 (Regular)
*BOARD, COMMITTEE AND COMMISSION APPOINTMENTS
16) DEPARTMENT REPORTS SUBMITTED FOR FILING
� Construction Department
� Department of Public Works
� Fire Department
� Health Department
� Police Department
� Recreation Department
� Code Enforcement/Property Maintenance
17) COUNCIL REPORTS
18) PUBLIC COMMENT
Please state your name and address for the record. Each speaker is limited to one (1) comment of no more than
five (5) minutes and no yielding of time to another person.
19) NEXT STEPS AND PRIORITIES
20) ADJOURNMENT
Project Update
Borough Hall & Public Safety Infrastructure Advisory Committee
September 28, 2022
1
Agenda
• Construction & Procurement Update
• Schedule Update
• Budget Update
• Borough Hall Administration & Public Safety Operations During Construction
2
Completed since April
üRoof Installation
üHVAC Roof Curbs, Ductwork and Piping Penetrations
üHVAC Equipment Delivered & Installed (OAU-1 & Miscellaneous Air Handling Equipment)
üExterior Wall Framing & Sheathing
üElevator Cab & Equipment Delivered and Preparations for Elevator Installation
üFront Addition Concrete Floor and Sally Port Floor (Including new Radiant Heating System)
üInterior Partition Framing
üPermanent Power Connection Completed
üValue Engineering of Upper-Level Lighting
Construction In Progress
& Procurement • Exterior Window & Door Delivery
• HVAC Interior Ductwork (Currently 90% Complete)
Update • Plumbing Rough-In (Currently 90% Complete)
• Electrical Rough-In (Currently 90% Complete)
• Sanitary Sewer Connection
• Sheet Rock Installation
Looking Ahead
• Exterior Window & Door Installation
• Exterior Finishes Systems (Stucco, Stone & Wood) Installation
• Elevator Equipment & Infrastructure Installation
• Low Voltage Fire, Security, Police & AV Wiring
• HVAC Roof Top Units 1 (Dec ’22), 2 (Jan ’23), 3 (Mar ‘23) Delivery and Installation
3
Roof & Equipment Installation
4
Exterior Framing & Sheathing
5
Electrical Rough-In & Power Connected
6
HVAC Ductwork Interior Installation &
Plumbing Rough-In
7
New Egress at Rear-Side of Building
8
Interior Partitions & Sheetrocking
9
Schedule Update
Construct Rear Addition: December 2020 – June 2023
Foundations – Above Grade Masonry – Steel Framing/Pour 2nd Floor – Frame & Sheath Exterior Walls –Roof – Fire Stairs Installation –
Exterior Windows & Finishes – Rough-Ins & Equipment Installation – Interior Fit Out
Construct Front Addition: April 2021 – June 2023
Foundations – Above Grade Masonry/Elevator Shaft – Steel Framing/Pour 2nd Floor Deck – Frame & Sheath Exterior Walls – Roof –
Entry Stairs Installation – Elevator Installation –Exterior Windows & Finishes – Rough-Ins & Equipment Installation – Interior Fit Out
Exterior Envelope/Interior Remodel: April 2021 – June 2023
Replace Roof –Asbestos Remediation – First & Second Floor Demo – Frame First Floor Walls – Frame Second Floor Walls – Exterior
Windows & Finishes – Rough-Ins & Equipment Installation – Interior Fit Out
Work Completed
Work In Process
Work To Be Completed
10
Budget Update
Project Budget through 8.31.22
Total Budget Expenses Encumbered Balance
$4,539,000 ($2,325,000) ($433,000) $1,781,000
Project Contingency
Contingency Contingency Key Changes (cumulative)
Initial Projected
- Steel, stairs/railings, and other material cost increases
- Additional work: steel; stair exit footing; storm & roof drains; sanitary
sewer installation
- Unexpected asbestos abatement and excavation issues
- COVID-related HVAC upgrades
$89,000 ($73,000) - 420 Boulevard lease extension
+ Roofing cost savings
+ Sunshade design change
+ Federal funding for HVAC upgrades
+ Demo equipment savings
+ Metal Stud Walls
11
Budget Update (continued)
• The construction team meets twice a month to review staffing, schedule, and
material pricing – with a focus on minimizing cost and delivering quality work
• Supply chain issues, materials cost increases, and a tight skilled labor market
are challenges that the team is working to manage
• Current budget projections remain very close to the original budget; budget
projections are updated monthly
12
Borough Hall Administration & Public Safety
Operations During Construction
Borough Hall Administration Mountain Lakes Police Department
Borough Administration has relocated to 420 The Police Department has relocated
Boulevard for the duration of the project to 420 Boulevard and to a trailer facility
at 400 Boulevard
Public Meetings
ML Volunteer Fire Department
• Borough Council and Planning has returned
to in-person meetings at Mountain Lakes The Fire Department will remain at 400
High School Boulevard for the foreseeable future
• Zoning Board is continuing to meet
virtually
13