Water Resources Board
Regular MeetingMurfreesboro, TN · August 27, 2019
Minutes
MINUTES
MURFREESBORO WATER RESOURCES BOARD
July 23, 2019
The Murfreesboro Water Resources Board met on Tuesday, July 23, 2019 in the conference room
at the Operations and Maintenance Building, 1725 S. Church Street. Present at the meeting were Board
members: Mr. John Sant Amour, Dr. Al Carter, Mr. Ron Crabtree, Ms. Sandra Trail, Ms. Kathy Nobles,
Mr. Kirt Wade, and Ms. Madelyn Scales-Harris. Also present were Darren Gore, Valerie Smith, Doug
Swann, Michele Pinkston, Anita Heck, Adam Tucker, Steve Tate, Donald Hughes, Alan Cranford, Joe
Russell, John Strickland, Mr. Randy McCullough, Mike Bernard, Lynda Sullivan, Ronnie Martin, and
Travis Wilson along with other members of the public.
Item G was removed from the Consent Agenda.
Items A through F of the Consent Agenda were presented for the following considerations:
A. Consider sole source purchase of Pit Raider & Nutri Pro odor control products –
In 2013, O&M noticed an increase in the number of odor complaints from the Saratoga Drive area.
After investigating the matter, it was found the odor was coming from the Kensington Drive Pump Station
which is fed by Tortuga Court Pump Station. The force main between these two pump stations is long and
often experiences low velocity. These factors create an odorous and corrosive conditions.
O&M conducted a trial of Pit Raider, a sole source proprietary odor control product, to improve
these conditions. It is a bacteria-based hydrogen sulfide treatment combined with a nutrient supplement
furnished by State Chemical Products. The trial demonstrated Pit Raider reduced hydrogen sulfide to a
minimal level, virtually eliminating the odor and greatly reducing corrosive effects to the manholes. The
chemicals were purchased and distributed through the Kensington Pump Station to control ongoing odor
issues. Odor complaints greatly diminished, and the Department works closely with a state chemical
representative to minimize costs by maintaining optimal feed rates during summer dry and winter wet
months.
Staff recommended the Board recommend to City Council to approve the sole source purchase of
Pit Raider and Nutri Pro odor control from State Industrial Products.
State Chemical pricing for the Pit Raider and Nutri Pro will remain the same through the FY
2019/2020. The Department has budgeted $50,000 in the operating account.
B. Consider abandonment of sewer easement along Florence Road –
This easement abandonment request is from Shane Hastings, partial owner of the property along
Florence Road encumbered with the easement. The family is requesting the abandonment of the existing
20-foot sanitary sewer easement. This easement was recorded in May of 2017 and was intended for a
Page 14
Water Resources Board Minutes July 23, 2019 Page 2
proposed sewer forcemain easement which was to be installed to serve the new Shelton Square Subdivision.
During the design and review stage of the project, Mr. Bob Parks purchased this easement from the
Hastings, however, when staff submitted the project to the Tennessee Department of Transportation
(TDOT) for review and approval of the sewer forcemain crossing of I-24, TDOT required the design of the
forcemain to change and to cross I-24 further to the north. Therefore, this easement is no longer necessary.
Staff recommended that the Board recommend to the Planning Commission and City Council
approval of abandoning this existing sewer easement.
C. Consider Ransom Drive P.S. Replacement Final Change Order –
In May 2015, the Board approved the Engineering necessary for the design to replace the existing
Ransom Drive Pump Station (PS#9) and forcemain as well as some gravity sewer main replacement. Bids
were received on June 13, 2017 for the pump station replacement and brought to the Board at the June 2017
meeting with the recommendation to reject the bids. The project rebid May 10, 2018 and was awarded to
SBW Constructors, LLC in the amount of $934,832.
At the January 2019 meeting the Board approved of the use of a portion of the Miscellaneous
Allowance through a Work Directive. It was approved to use $5,174 of the $10,000 Allowance amount.
The project is now complete and Civil Infrastructure Associates (CIA) has sent a recommendation letter
and final balancing change order for approval.
Even with the use of the Miscellaneous Allowance, the contract amount will be reduced by a total
of $73,219.75 for a final contract amount of $861,612.25.
Staff recommended that the Board recommend to City Council approval of this final balancing
change order.
D. Consider Equipment Operator reclassification –
As a result of a resignation last fiscal year and an accompanying voluntary demotion from an
Equipment Operator to a Worker, staff is requesting the Board to allow reinstating the Equipment Operator
position for the Operations & Maintenance division.
Darryl Williams was an Equipment Operator working the Jordan and Coleman Farm irrigation
operations. He was transferred to O&M in June of 2017, maintaining his position as Equipment Operator
working on a vacuum truck.
In July of 2018, Mr. Williams voluntarily requested a demotion to a Worker position which allowed
him to drive a dump truck at O&M. In August of 2018, Mr. Williams resigned from the Department.
His original position as Equipment Operator was never replaced and the reclassification from his
vacant Worker position to an Equipment Operator was not included as part of the Department’s FY20
budget.
Staff recommended to reclassify a Worker job classification to Equipment Operator.
Page 15
Water Resources Board Minutes July 23, 2019 Page 3
E. Consider Sodium Hypochlorite chemical contract extension –
Invitations to Bid on chemicals for use at the Water Resource Recovery Facility (WRRF) were
advertised and released on May 12, 2017. Staff reviewed the bid submissions and determined the lowest
responsible and responsive bidder.
With the approval of the Board and the Council, Dycho Company Inc. was contracted through
FY19 to supply Sodium Hypochlorite. The contract included the option for renewal for additional one-year
terms.
Staff recommended that the Board recommend to City Council approval of a one-year contract
extension for the purchase of Sodium Hypochlorite from the lowest bidder, Dycho Company Inc.
Supplier Chemical Price/Gallon Estimated Annual Expense
Dycho Company Inc. Sodium Hypochlorite $0.855 $75,000
The expense for the product is reflected in the 2019-20 Operating Budget. The contract price will
be good through June 30, 2020.
F. Consider precast manhole structures contract renewal –
On July 12, 2018 bids were opened at O&M to provide precast manhole structures to Murfreesboro
Water Resources Department. Two vendors submitted bids and the contract was awarded to the lowest
bidder, Foley Products.
The contract with Foley Products expires August 31, 2019. Staff is pleased with the services
provided by Foley Products and recommended the Board recommend to City Council to extend the
agreement. The contract may be renewed, by mutual written agreement, for two additional two-year periods
for a maximum of 5 years at the option of the City. Foley has agreed to extend the contract and the Legal
Department is drafting the amendment.
The Operations & Maintenance Department uses an estimated 10 precast manhole structures on
sewer projects yearly with an estimated cost of $13,000. All terms and conditions of the contract will
remain the same.
A motion was made by Kirt Wade to accept Items A through F of the Consent Agenda as presented
and it was seconded by Dr. Carter. The Board voted unanimously to approve.
The May 28, 2019 Board Minutes were unanimously accepted as presented.
The Board considered bids for the 2019 Sanitary Sewer Rehabilitation Contract.
At the December 6, 2018 Board meeting the Board approved the Engineering, Construction
Administration & Resident Inspection necessary for this next sanitary sewer rehabilitation project with
S&ME.
Page 16
Water Resources Board Minutes July 23, 2019 Page 4
This project includes 168 linear feet of open cut sewer main replacements, 17,240 linear feet of
cured in place pipe (CIPP), lining and/or repairing 136 manholes which is approximately 1335 vertical feet
of manhole lining and 170 sewer lateral linings. The design is complete, and bids were received on July
11th.
Two bids were received out of a total of five possible prime contractors. S&ME recommends
awarding the project to SBW Constructors, LLC (SBW) in the amount of $3,842,301. They were the lowest
responsible and responsive bidder for the project, they also were the contractor on the two previous
rehabilitation projects and were very good to work with.
Staff recommended that the Board recommend to the City Council awarding the contract to SBW.
Funding for the Engineering, Construction Administration, Inspection and Construction was approved
from a combination of 2018/2019 and 2019/2020 Budget & Working Capital Reserves. The Department
has not dipped into these fiscal years for the rehab funding to date. We have been working
from the 2017/2018 Budget & Reserves allotments.
Kathy Nobles made a motion to approve. Ron Crabtree seconded. The motion unanimously
passed.
The Board considered Walter Hill Dam Change Order No. 1.
Change Order No. 1 for the Walter Hill Dam Maintenance project is necessary to adjust the contract
time from 60-day completion to a 347-day completion project, as well as add an additional $75,505.55 to
the original contract price of $492,000. The time is necessary due to high flow conditions experienced in
the East Fork Stones River (EFSR) last fall, and the additional cost is required due to underwater repair and
maintenance work that is outside the original scope of the contract.
Staff offered the following justification and recommendation to approve Change Order No 1:
• Time – September through December of 2018 was unseasonably wet and as such created much
higher flows in the EFSR that disallowed Haren Construction from completing the dam
maintenance project. Haren was issued a stop work order on December 21, 2018. The TN Wildlife
Resource Agency and Corps of Engineers permit disallowed any work to occur instream within the
river from January 15, 2019 through July 1, 2019 due to the spawning season of certain endangered
species in the river. Haren has just remobilized and is starting work on the dam remediation
activities and the extension of time is due primarily to the time frame that they were prohibited
from working.
• Cost – The original scope of work involved lowering the water level behind the dam six feet.
Lowering the water level this low renders the raw water pump station upstream of the dam
nonoperational due to inability for the pumps to maintain suction. The auxiliary raw water pump
station on the lake was intended to solely supply water to the plant when the water level was
Page 17
Water Resources Board Minutes July 23, 2019 Page 5
lowered; however, due to two Variable Frequency Drive (VFD) failures at the auxiliary raw water
pumping station, this station is effectively shut-down until the VFD’s are replaced. The time frame
for these replacements is 8 weeks. Staff considers this too long and puts us back into the same
season as last year that created the higher flows prohibiting the dam remediation from occurring.
As a least cost, least risk solution, Haren Construction has proposed to perform the work underwater
with divers and not lower the water level behind the dam. This increased cost is $75,505.55. Haren
is leveraging an existing relationship to get the divers on the project as soon as possible. There is
2.5% markup on this by Haren for the proposed increase in lieu of the standard 5% markup.
Staff recommended the Board recommend to City Council approval of Change Order No. 1 which
adds 287 days to the contract time and adds $75,505.55 to the contract price to the Walter Hill Dam
Maintenance Project.
The original bid for the Walter Hill Dam Maintenance contract was $492,000. The additional cost
of $75,505.55 is a 15% increase. There is a $15,000 contingency fund in the contract that could absorb
some of the added cost, but staff would recommend keeping the contingency fund whole until the project
is completed for other potential unforeseen costs. The additional funding is requested to come from the
Department’s working capital reserves.
Sandra Trail made a motion to approve. Kathy Nobles seconded. The motion unanimously passed.
The Board considered condemnation of sanitary sewer easement on Armstrong Valley Road.
Cornerstone Development, LLC, the developer of Westwind Reserve, requires off-site sanitary
sewer easements from three property owners. Two of them have been obtained by agreement. The third
owner is willing to grant the easement but has a mortgage with a California lender with MERS as the
lender’s agent. The developer is concerned about the time that may be required to deal with MERS, and
that ultimately the lender may not agree. This third owner does not object to condemnation. The developer
will agree to bear all costs of the condemnation and will indemnify the City from any damage claim.
A portion of the sewer improvements that will be installed within these easements for this
development are shown on the Departments 201 Wastewater Facilities Plan (Plan) and will serve a larger
basin (Basin 97). The design of this sewer and associated costs are not finalized, but staff anticipates the
developer to ask for participation in the near future, since staff in following the Plan has asked for a
larger/deeper sewer main than necessary for the proposed development.
Staff recommended the Board recommend City Council to approve condemnation, subject to a
contract and indemnity agreement with the developer in form approved by the City Attorney.
Sandra Trail made a motion to approve. Ron Crabtree seconded. The motion unanimously passed.
The Board considered testing of Hobas Pipe involving the Southwest Interceptor failure.
Page 18
Water Resources Board Minutes July 23, 2019 Page 6
In February 2019, a structural failure occurred on the Southwest Interceptor pipeline on the
Hutchinson property. The Department expended $314,055 in an emergency contract through Garney
Construction to repair the failure and reinstate service through the interceptor. At that time, observers from
MWRD, SSR and Garney all indicated that the installation of the pipeline and the backfill surrounding the
pipeline were correct per the material specifications and the Contract Documents. There still remains some
question as to whether the installed material met the original specifications provided by the material
manufacturer, Hobas. In order to verify the mechanical properties of both removed sections of piping as
well as those of the materials that were installed under the emergency repair, staff and SSR recommends
specimens from both sets of materials be tested.
Staff recommended approval for testing services by Applied Technical Services, Inc. to determine
if structural failure of 36” Hobas pipe was due to deficiency in the original piping material.
The cost of testing is quoted at $11,720. An additional $1,000 is budgeted for shipping the pipe to
their offices in Marietta, GA. Several materials testing vendors were solicited, and this is the best quote
that staff was able to obtain. Funding is requested to come from working capital reserves.
Dr Carter made a motion to approve. Kathy Nobles seconded. The motion unanimously passed.
The Board considered Customer Information System (CIS) software upgrade.
In June 2014 MWRD went live with Advanced Utility Systems (AUS) Customer Information
System (CIS) Infinity software, version 3 (V3). The implementation was a culmination of an almost two-
year process, beginning with development of an Information Technology (IT) Strategic Plan in the fall of
2012.
Concurrent with the implementation of the CIS software, we launched online access for customers
via Infinity.Link and moved from paper to digital with our Service Order system via Infinity.Mobile.
Replacing our legacy CIS software with state-of-the-art off-the-shelf software was the first step in
our IT Strategic Plan. Staff followed up the CIS install with Interactive Voice Response (IVR) phone
module in early 2015, new financial software (Tyler Munis) in July 2015, and Advance Metering
Infrastructure (AMI) in June 2017.
CIS, Link and Mobile have all performed well. They have improved our staff and customer
experience.
MWRD has now been using the software for five years. Staff recommends upgrading to the latest
version of the CIS and online access software. We will continue to use the Mobile module with the new
versions. Version 4 (V4) of CIS and Link offer several enhancements and improvements.
Staff recommended that the Board recommend to City Council approval to upgrade MWRD’s CIS
software and related online access module.
Page 19
Water Resources Board Minutes July 23, 2019 Page 7
The total estimated cost for the software update is $343,000. This upgrade was originally budgeted
in the FY19 Capital Expenditures at an estimated cost of $300,000. As the purchase was not approved and
secured in FY19, funding for this upgrade will come from MWRD Reserves in FY20.
Kirt Wade made a motion to approve. Dr. Carter seconded. The motion unanimously passed.
The Board considered SSR Engineering Work Order 09-47-001.3, Waste Load Allocation Model
additional cost.
The original Waste Load Allocation Model that was recommended by the Tennessee Department
of Environment and Conservation (TDEC) and was intended to predict impacts of additional Murfreesboro
Water Resource Recovery Facility (MWRRF) effluent into the West Fork Stones River (WFSR) has failed.
As such, AquAeTer has had to abandon the original WLA Model known as Water Quality Analysis
Simulation Program (WASP) and effectively start over using another model known as CE-QUAL-W2.
Starting over has added to the time and expense associated with the original $303,500 task order
approved in June of 2017. AquAeTer is requesting an additional $75,000 to complete the WLA model and
prepare the final report for TDEC’s review.
Staff met with TDEC on June 5, 2017 and they approved the original work plan associated with the
Waste Load Allocation. Staff recently met again with TDEC on June 20, 2019 to review the failed results
of the WASP model and gain their approval and buy-in to change the WLA model to CE-QUAL-W2.
In June 2013, the Board approved Smith Seckman Reid, Inc. (SSR) and AquAeTer to commence
sampling of the East Fork and West Fork Stones River in support of renewing our existing NPDES permit
application, introduce the option to TDEC for an additional outfall on the East Fork Stones River, and to
demonstrate a favorable trend in biological health of the streams. The Board has approved annual
bioassessment sampling since that time and the results have been outstanding.
The WLA model approved in June of 2017 is intended to be the technical foundation that
demonstrates the more effluent discharged into WFSR, the more the WFSR is enhanced. The data
demonstrates that the biology in the stream is healthy and that the stream is in fact meeting its designated
uses.
The failure of the WASP model is an unfortunate setback, but the CE-QUAL-W2 is demonstrating
very good prediction for the flow and temperature in the WFSR.
Staff recommended the Board recommend to City Council approval of an additional $75,000 to
complete SSR Engineering Work Order 09-47-001.3.
Staff recommended funding coming from the Department’s working capital reserves. MWRD’s 5-
yr CIP earmarked $500,000 for Stones River Water Quality studies and NPDES permitting for FY19. Staff
has budgeted an additional $150,000 for FY20 through FY23.
Sandra Trail made a motion to approve. Ron Crabtree seconded. The motion unanimously passed.
Page 20
Water Resources Board Minutes July 23, 2019 Page 8
Staff gave a presentation on Sanitary Sewer Allocation for Future Land Use.
The last 20-yrs of growth in Murfreesboro has dramatically increased the demands on the
wastewater collection system. Regulation of the future allocation of wastewater collection may be
necessary for the welfare of the City and its inhabitants.
Federal and state regulations outside the City’s purview may restrain the City’s ability to obtain
additional capacity to support future land use in the City’s urban growth boundary. Allocating wastewater
treatment and/or sanitary sewer collection capacity may:
• Promote and protect public health and safety
• Enhance the economy by establishing reasonable, orderly, equitable and effective means to
allocate wastewater collection capacity
• Assist in uniform and balanced future development to serve the needs of the community and
the City’s tax digest.
Staff has prepared an analysis to review the Salem Hwy corridor and sanitary sewer service area
that was master planned in 1999 and compare it to the current build-out in 2019 to see how much sewer has
been allocated, and consequently determine how much sewer capacity is remaining for the areas yet to be
developed in this corridor.
Additionally, staff will review the annexed areas by zoning the City has experienced between 2009
and 2019 to determine future land uses that may be applied to sanitary sewer and wastewater allocation.
Under Other Business, the Board considered Murfreesboro Municipal Airport Terminal Change
Order No. 2.
Staff previously brought a proposal to the Board to participate in the watermain replacement for
the new terminal being constructed at the airport. The Department’s participation amount was $56,000
(80% of $70,000), with the City funding the remaining 20%, or $14,000. The scope of the watermain
replacement has been expanded increasing the amount to $144,692. The Department’s participation amount
would therefore increase to $115,753.
Staff recommended the Board recommend to City Council approving Change Order No. 2 as
presented.
Ron Crabtree made a motion to approve. Dr. Carter seconded. The motion unanimously passed.
Staff presented and discussed the Water Resources Dashboard Performance for June 2019.
There being no further business, the meeting was adjourned.
John Sant Amour, Chairman
Page 21
Get email alerts for Murfreesboro
A daily email when new agendas and minutes are posted.