Council Roads Committee 1/9/2026
1. Keep Noblesville Beautiful Update - 15 Minutes
2. Federal Aid & State Aid Projects
a. Grant Applications
a. MPO Grant Applications submitted by 11/28/25
i. Nickel Plate Trail over 146th
ii. Greenfield Avenue (10th Street to 16th Street)
iii. Stony Creek Trail
iv. 191st & Moontown Roundabout
b. INDOT Rural Call Grant Applications submitted by 11/22/25
i. Boden Road Pedestrian tunnel by Finch Creek
ii. Prairie Baptist at 146th Roundabout
iii. Olio Road expanded to 4-lanes from 156th to SR38
b. Pleasant Street - Phase 1
a. MPO Award: $8.5M (State Funds)
b. Final landscaping items in spring
c. Project close-out soon
c. Pleasant Street - Phase 2
a. MPO Award: $494,400 (State Funds)
b. Pavement over Wilson Drain structure placed.
c. Curb and additional lifts of asphalt to come in spring
d. Widening for additional turn lanes at SR 37 ongoing for next few weeks
e. Full Closure of Pleasant Street (10,400 vpd)
i. 13th Street to 16th Street
ii. Open to traffic (one lane each direction) on December 23, 2025
iii. Temporary signal and no left turn at 16th Street remain in place as additional
work is ongoing
iv. Surface will be placed in 2026
d. Pleasant Street - Phase 3
a. MPO Award: $5,475,700 (State Funds)
b. Punch list work ongoing and continuing through spring
c. Railing installation along trail (temp fencing currently to open Midland Trace Trail)
e. Olio Road between 146th and 156th
a. Rural Award (SFY 2027): $8.9M (State Funds)
Council Roads Committee – 1/9/2026
b. INDOT Safety Call: $2.8M award for Olio Rd & 156th Roundabout
c. Construction in 2027 (Closed to through traffic in 2027 construction season)
d. 90% plans submitted to INDOT in November 2025.
i. Duke is reimbursable due to 1930s easements. Relocation agreement to be
presented in February 2026. Work completed by April 2027 per their work
plan.
e. 1 condemnation filed, settled. Rest of parcels are settled or finalizing documents
f. Lochmueller is highest score on RFP for Construction Inspection. Contract to be
presented in January or February 2026.
f. Boden Road & 166th Roundabout
a. SFY: MOVED to 2027/28
b. Rural Award: $3.01M (State HSIP Funds - 90% Federal/10% City)
c. Design: Stage 2 submittal - occurred December 1, 2022
d. Utilities: Timeline for Duke relocation has necessitated move of CN
e. Construction: Moved to 2028 to allow utility relocation to occur
f. R/W: Complete
g. In final environmental review at INDOT
g. Boden Road (Beauty Berry Drive (Ruoff Music Center) and 156th Street)
a. SFY 2028 (was pushed back a year to 2029 after initial award, but returned to
SFY2028)
b. Rural Award: $6,041,525 (plus $422,650 for R/W) (State Funds)
c. Design: Stage 1 complete
i. In environmental review - Determination of project impacts still not fully
determined.
h. Highway Safety Improvement Program
a. Sign Modernization Project
i. Awarded $441,000.00
ii. For replacement of regulatory and warning signs in "pre-1995 Noblesville"
a. Includes Old Town, Wellingtons, Harbours, among others
iii. Likely 2027 CN
iv. Design agreement signed 2/28
v. 90% submittal to INDOT in early February.
b. ADA Sidewalk Project
i. Awarded $244,800.00
ii. For installation of curb bump-outs, ramps, striping, and signage on 10th Street
a. Proximity of North Elementary: Wayne, Harrison, Monument, Grant
iii. Likely 2027 CN
iv. Design agreement signed 2/28
v. Survey completed, Initial design started
vi. Environmental process underway
i. Nickel Plate Trail Bridge over 146th Street
a. Next Level Trails Award: $3,130,000
b. Coordination with Duke Energy ongoing due to easement along entire rail corridor
Page 2/6
Council Roads Committee – 1/9/2026
c. Applied for MPO Grant for construction - Fishers has agreed to be a funding partner,
Hamilton County considering
j. Little Chicago Road and Carrigan Road Roundabout
a. MPO FFE (State) Funds: $1,633,915 (FY2028)
b. Design contract with United Consulting executed on 5/27/2025
c. Survey complete & preliminary engineering underway
k. 141st Street and Howe Road Roundabout
a. MPO FFE (State) Funds: $2,002,400 (FY2028)
i. Tentative Bid: July 2027, either fall 2027 OR spring 2028 construction,
dependent on utility relocation
b. 30% plans to be submitted to City in March 2026
3. Local Projects
a. 2025 Street Rehabilitation
a. Contract III
i. Will use local funds
ii. Includes portion of Pine Knoll, Monterey Village, Sagamore, Wellington
Heights, 146th Street (Olio to Prairie Baptist)
iii. Awarded contract 5/27 to E&B Paving
iv. Sagamore - Complete
v. Wellington Heights - Concrete Complete
vi. Pine Knoll - Concrete complete
vii. Monterey Village - Concrete sidewalk repairs completed
viii. Paving on Wellington Hts, Pine Knoll, Monterey Village to occur Spring 2026
b. Street Rehab budget for 2026 is $1M less than 2025 (Senate Bill 1 - property taxes
impact)
b. 2025 Old Town Sidewalk Program
a. Harrison Street and area near Stony Creek Elementary
b. Pre-construction activities have begun.
c. Contractor anticipating re-mobilizing on Harrison Street late January, weather
permitting
c. 2026 Trail Gap Program
a. Project bid and awarded November 2025
b. Construction spring 2026
d. Boden Road Corridor
a. Segment 2 (156th Street - 166th Street)
i. Preliminary design complete (40% design, includes drainage masterplan and
right-of-way limits)
ii. Submitted INDOT Rural grant application for pedestrian tunnel under Boden
connection Finch Creek Park and Pulte's Finch Creek subdivision
b. Segment 3 (166th Street -SR 38)
i. Preliminary design complete (40% design, includes drainage masterplan and
right-of-way limits)
ii. Design: Final design started, coordinating with 166th Roundabout
iii. Utilities: Also coordinating with 166th Roundabout
Page 3/6
Council Roads Committee – 1/9/2026
iv. R/W: Offers have been accepted.
v. INDOT constructed single lane RAB at SR 38, so we will have to reduce to
single lane to match roundabout. Does not affect Boden Road level of service
vi. Construction: 2028, during Boden/166th construction
e. Embrace Downtown
a. Economic Impact Study being finalized
b. Appropriation ordinance first reading to council on 1/13, second reading on 1/27
c. Schedule
i. Bid: December 16, 2025
ii. Awarded: December 23, 2025
iii. Contractor: William Charles Construction
iv. Preconstruction meeting: January 9
v. Ceremonial Ground breaking: February 2 @ 2:00 PM
vi. Construction: February 2026-November 2026
d. Website: www.embracedowntownnoblesville.com
f. Logan Street/Clinton Street Brick Rehabilitation
a. Initial scoping of project to begin spring 2025 to determine limits/phases
b. Design agreement to Board of Works - April 15
c. Draft report received. Review of alternatives forthcoming.
g. Little Chicago Road Corridor Improvements
a. Limits: SR 38 - Carrigan Road
b. Project under same contract as the LCR & Carrigan Road RAB
c. Report complete in early 2026
h. Carrigan Road and North Harbour Drive/Oakbay Drive
a. Begin preliminary engineering/alternatives analysis late 2025
b. Scoping meeting held with consultant
c. Includes trail gap along Carrigan Road and intersection improvements
d. Preliminary survey has started. Alternative layout underway.
i. Mill Creek Road over Sly Run
a. Includes trail between Promenade (Justus) and Promenade Woods
b. Hydraulic modeling showing downstream culvert limiting hydraulic improvement.
c. Project scaled back to just widening for trail, not expanding culvert size. Downstream
adjacent property owner doesn't plan to develop. Essentially how big we make the
culvert under Mill Creek Road, the downstream restrictions prevent improvements.
d. Moved to 2026 due to other closures in the area
j. 156th Street over William Lehr Ditch
a. Preliminary design underway, have received alternates for alignment
k. Prairie Baptist Roundabouts at 146th and 156th Streets
a. Approximately 4,000 new homes approved with Finch Creek and Gatewood Lakes
developments.
b. East/west intersections do not like up and provide safety benefit
c. Contract approved with American Structurepoint
d. Applied for INDOT Rural Call construction grant in November 2025
Page 4/6
Council Roads Committee – 1/9/2026
l. 191st Street and Moontown Road Roundabout
a. Design kick off meeting held 12/2/2025
b. City sent letter to nearby property owners with notice of survey. 10% plans submitted
in Spring.
c. Applied for Indy MPO construction grant in November 2025
4. Hamilton County Projects
a. 146th over Allisonville Interchange
a. 13,000 vehicles per day (vpd) (north leg of Allisonville - 2022 traffic data)
b. Project Website: www.streamline146.com
c. Interchange to operating as designed, but work ongoing
b. 146th and Hazel Dell Interchange
a. Bid May 2026 (FFE MPO Funding)
b. Utility Work in 2025
c. 2026-2027 Construction
d. Project Website: https://www.hamiltoncounty.in.gov/1798/146th-St-Hazel-Dell-Pkwy-
Interchange
c. 146th and Gray Road Improvements
a. Preliminary design underway
b. County is still working on schedule
5. INDOT Projects
a. SR37 & 141st Street Interchange
a. Completion October 2026
b. Project Website: https://37thrives.com/
c. Westside of SR37 & 141st St. is open and transition work to the eastside of SR37.
b. SR 37 through Noblesville (Greenfield Ave. to SR 32)
a. INDOT/Noblesville partnership
b. MOA Commitment
i. 30% design of corridor
ii. 80/20 partnership design & construction of SR32 & SR37 interchange
iii. No commitment on final design/construction of other interchanges
c. Working with INDOT on an Interlocal Agreement
d. Preliminary design ongoing
e. Public Information being planned for the early spring, but date not known yet
f. Applying for 2026 BUILD Grant - Submittal due in February
g. Website: www.sr37improvement.com
c. SR38 & Logan Street Roundabout
a. Letting: January 2026 (update meeting today w/ INDOT)
b. Construction: 2026
c. City responsible for R/W acquisition for project.
i. R/W offers are out, two parcels in condemnation proceedings. Three accepted
parcels, one other has agreed to terms.
d. SR32 Added Travel Lanes
a. Four lanes with median with RAB intersections (East Street in Westfield to just west
of River Road)
Page 5/6
Council Roads Committee – 1/9/2026
b. Noblesville participation: $2M for sidewalk construction - RW costs at
SR32/Hague/Pleasant and proposed developments will count as contribution
c. 90% plans by the end of the year
d. Public hearing and Community Advisory Committee meetings to be scheduled in 2026
e. December 2026 Bid
f. Construction in 2027 (mostly UT) - 2028/2029 construction for roadway (unsure if
starting in Westfield or Noblesville yet)
g. INDOT Website: https://improvetomove32.com/
e. SR 32 Road Reconstruction and Signal Project (Noblesville)
a. Contractor: Rieth-Riley Construction
i. Punch list work remaining
ii. INDOT/Contractor agreed to additional work, to be done once weather permits
b. INDOT Website: https://www.reconstructingsr32.com/
f. SR38 & Hinkle Road/Moontown
a. Scope: Signal Installation, Pavement Widening & Turn Lanes
b. Intersection open and signal operational. Requires additional paving in spring.
6. Discussion