Floodplain Permit Committee Meeting
Regular MeetingNorman, OK · September 7, 2021
Minutes
FLOODPLAIN PERMIT COMMITTEE MEETING
201 West Gray, Building A, Conference Room D
Tuesday, September 7, 2021
3:30 p.m.
Minutes
PRESENT: Scott Sturtz, City Engineer
Lora Hoggatt, Planning Services Manager
Ken Danner, Subdivision Development Manager
Bill Scanlon, Citizen Member
Sherri Stansel, Citizen Member
OTHERS PRESENT: Todd McLellan, Development Engineer
Amy Shepard, Staff
Preston Caldwell, SMC
Bret Cabbiness, Garver
Toni Bragg, The McKinney Partnership
The meeting was called to order by Mr. Scott Sturtz at 3:30 p.m.
Item No. 1, Approval of Minutes:
Five members of the committee were present, and Amy Shepard called roll. Mr. Shawn O’Leary
and Ms. Jane Hudson were absent. Mr. Sturtz called for a motion to approve the minutes from
the meeting of August 16, 2021. Ms. Sherri Stansel motioned to approve the minutes with two
(2) spelling corrections. The motion was seconded by Mr. Bill Scanlon. The minutes were
approved 5-0, with corrections.
Item No. 2, Floodplain Permit Application No. 641:
Mr. Sturtz said this application is for an 8 inch sanitary sewer crossing of the Upper Dave Blue
Creek floodplain for the proposed Summit Valley Addition Section 3 development. Mr. Todd
McLellan gave the staff report for Floodplain Permit Application No. 641. Mr. McLellan said
the Applicant is Summit Valley Development, LLC, the Contractor is Central Contracting
Services, and the Engineer is SMC Consulting Engineers P.C. Mr. McLellan said Mr. Preston
Floodplain Permit Committee Meeting
September 7, 2021
Page 2
Caldwell of SMC Consulting Engineers is in attendance to represent the Applicant. Mr.
McLellan said this application is located in the Upper Dave Blue Creek floodplain for the
proposed Summit Valley Addition Section 3 development. Mr. McLellan reviewed photos and
aerial maps of the site location and the location of floodplain impact. Mr. McLellan said the
proposed Summit Valley Addition Section 3 development will require new public utilities to
be constructed including water line, sanitary sewer, and storm sewer. Mr. McLellan said
approximately 2,650 feet of 8 inch sanitary sewer main will be required to serve the
development and a section of the proposed sanitary sewer main will cross the Dave Blue Creek
floodplain to connect to the existing sanitary sewer main. Mr. McLellan said the sanitary sewer
crossing will be open cut and will be encased with 40 feet of steel pipe for added protection,
the crossing will be backfilled to original grade, and any excess spoils will be removed from
the floodplain. Mr. McLellan reviewed the applicable ordinances for Floodplain Application
No. 641 and verified all ordinance requirements have been met. Mr. McLellan said staff
recommended approval of Floodplain Permit Application No. 641. Mr. Sturtz asked if the
Engineer, Mr. Caldwell would like to add anything to the presentation. Mr. Caldwell had no
additional comments to add. Mr. Sturtz asked if there were any questions from the committee.
Mr. Bill Scanlon asked if there was anything unusal about the pipe or installation requested in
Floodplain Application No. 641. Mr. Scanlon asked in reference to the pressure testing
presented in the staff report. Mr. McLellan said this is completed to ensure compliance with
Floodplain Ordinance Section 4(b)(12), that states all new and replacement sanitary sewage
systems shall be designed to minimize or eliminate infiltration of flood waters into the system
and discharge from the systems into flood waters. Mr. McLellan said and that pipe joints have
gaskets making the system watertight, and the entire system is leak tested prior to going into
Floodplain Permit Committee Meeting
September 7, 2021
Page 3
service. Mr. Scanlon asked if pressure testing was completed periodically to monitor for issues.
Mr. Sturtz said since this pipe is a gravity main it will not be under pressure and would be
inspected as part of the City of Norman Utilities Department routine maintenance operations.
Mr. Ken Danner added that additional protection would be provided by the proposed casing
installed on the pipe. Mr. Danner recommended approval of Floodplain Permit Application No.
641. Mr. Scanlon seconded the motion. The committee voted to approve the application 5-0.
Item No. 3, Floodplain Permit Application No. 643:
Mr. Sturtz said this application is for a solar farm project at the Norman Water Treatment Plant
located at 3000 East Robinson Street, which is in the Rock Creek floodplain. Mr. Sturtz said
the Applicant, City of Norman Utilities Department has requested postponement until the
October 4, 2021 Floodplain Permit Committee meeting. Mr. McLellan said the Utilities
Department is working with their design team to address some concerns about the final installed
height of the solar panels to ensure compliance to the two (2) foot freeboard requirement. Mr.
Ken Danner recommended postponement of Floodplain Permit Application No. 643. Mr.
Scanlon seconded the motion. The committee voted to postpone the application 5-0.
Item No. 4, Floodplain Permit Application No. 644:
Mr. Sturtz said application is for a solar farm project at the Norman Water Reclamation Facility
located at 3500 Jenkins Avenue. The project will be located at the confluence of the Bishop
Creek/Canadian River floodplains. Mr. Sturtz said the Applicant, City of Norman Utilities
Department has requested postponement until the October 4, 2021 Floodplain Permit
Committee meeting. Mr. Sturtz said although this is in a different location the Applicant is
requesting postponement for the same reason related to achieving the elevation requirements.
Floodplain Permit Committee Meeting
September 7, 2021
Page 4
Mr. Ken Danner recommended postponement of Floodplain Permit Application No. 643. Mr.
Scanlon seconded the motion. The committee voted to postpone the application 5-0.
Item No. 4, Floodplain Permit Application No. 642:
Mr. O’Leary said this application is for the construction of a soccer complex with multiple
playing fields on the property located on the south side of Indian Hills Road approximately ¼
mile east of 72nd Ave NW, which is in the 10 Mile Flat Creek floodplain. Mr. Todd McLellan
gave the staff report for Floodplain Permit Application No. 642. Mr. McLellan said the
Applicant is Sporting Oklahoma, Inc. and the Engineer is Bret Cabbiness with Garver, LLC.
Mr. McLellan said Mr. Toni Bragg with The McKinney Partnership is the project architect. Mr.
McLellan said Mr. Cabbiness and Mr. Bragg are in attendance to represent the Applicant. Mr.
McLellan reviewed photos and aerial map of the location and proximity to the city limits. Mr.
McLellan said the property consists of approximately 74 acres and is currently going through
the Norman Rural Certificate of Survey process to be subdivided into north and south tracts that
will be 22 and 52 acres, respectively. Mr. McLellan said this Floodplain Permit application is
for the entire 52 acre (south) tract, which will be developed into a soccer complex located
entirely in the 10 Mile Flat Creek floodplain.
Mr. McLellan said the complex will be constructed in multiple phases over several years and
will include multiple playing fields, an indoor soccer complex building, a small office building
with restrooms, offices, and concessions as well as one other restroom building. Mr. McLellan
said in addition, a parking lot will also be constructed along with 2 drives with 24 inch
corrugated metal pipes installed at the intersection with Indian Hills Road. Mr. McLellan said
retention ponds and an internal underground system will be constructed for drainage and
Floodplain Permit Committee Meeting
September 7, 2021
Page 5
irrigation. Mr. McLellan said a private septic system and water well will also be constructed as
part of this project.
Mr. McLellan said it is anticipated that the first phase will consist of the construction of three
(3) outdoor fields, the retention ponds, a portion of the parking lot, and the drives. Mr. McLellan
said the initial grading of the site, excluding the retention ponds, will result in 225 cubic yards
of material being removed from the site. Mr. McLellan said the underground detention will be
installed in the parking lot areas to accommodate the proposed permeable pavement. Mr.
McLellan said the two (2) ponds shown on the site plan are retention ponds that will double as
compensatory storage, underground detention outfall, and internal irrigation ponds. Mr.
McLellan said the exact size of each pond is generally 550 feet x 130 feet with an average depth
of 5 feet. Mr. McLellan said since the anticipated depth of ground water is at 4 feet below the
surface, the volume of these ponds for compensatory storage purposes is calculated at a depth
of 4 feet with an overall average footprint of 65,000 square feet or 1.5 acres per pond. Mr.
McLellan said the volume is approximately 9,630 cubic yards for each pond (a total of 19,260
for both ponds). Mr. McLellan reviewed the total fill amounts (in cubic yards) needed to elevate
the buildings a minimum of 2 feet above the Base Flood Elevation (BFE) in future phases. Mr.
McLellan said the total fill required is 14,292 cubic yards: 12,500 for the Indoor Soccer Facility,
1,375 for Concession and Offices, and 417 for the South Restroom.
Mr. McLellan reviewed the applicable ordinances for Floodplain Application No. 642 and
verified all ordinance requirements have been met. Mr. McLellan said staff recommended
approval of Floodplain Permit Application No. 642 with the condition that an as built survey
be provided of the of the retention ponds for compensatory storage capacity and an Elevation
Certificate be submitted for all three (3) buildings at completion of construction prior to
Floodplain Permit Committee Meeting
September 7, 2021
Page 6
issuance of a Certificate of Occupancy for each structure. Mr. Bret Cabbiness added that this
project will be completed in phases and care was taken to ensure the first phase addressed
compensatory storage and drainage improvements. Mr. Cabbiness said the parking lot will
provide underground storage for detention and plans will be provided when the remaining
construction plans are submitted for approval. Mr. Sturtz asked how the underground detention
areas will discharge. Mr. Cabbiness said the water will be used as irrigation for the fields. Mr.
Danner asked if the project would include a perimeter fence. Mr. Bragg said there have been
discussions regarding a fence and they are familiar with the requirements. Mr. Cabbiness said
the Applicant is interested in installation of a five foot, vinyl chain link fence. Mr. Danner asked
if they would like to add the fence to the application. Mr. McLellan recommended that the fence
be added to the application. Mr. Sturtz asked if there would be gates at the entrance. Mr.
Cabbiness said he anticipated at some point there may be interest in installing an entrance gate.
Mr. Danner clarified the timeframe for a Floodplain Permit is two (2) years. Mr. Cabbiness said
since this is a phased plan, if the Applicant needs more time they will return to the Floodplain
Permit Committee before expiration to ensure compliance. Mr. Scanlon asked about the
usability of the complex due to flooding. Mr. Cabbiness said this project would be a great use
of the floodplain, grading this site to assist drainage and a great opportunity to use green
infrastructure. Mr. Sturtz said the model of using floodplain area for soccer fields has been used
in other places. Mr. Scanlon asked if this project will be impacted by the Norman Forward
project to expand the current Norman soccer complex. Mr. Cabbiness said the location will
facilitate Norman and all of the South Oklahoma City area. Mr. Ken Danner recommended
approval of Floodplain Permit Application No. 642 including cyclone fencing and gate with the
conditions that an as built survey be provided of the retention ponds for compensatory storage
Floodplain Permit Committee Meeting
September 7, 2021
Page 7
capacity and an Elevation Certificate be submitted for all three (3) buildings at completion of
construction prior to issuance of a Certificate of Occupancy for each structure. Ms. Stansel
seconded the motion. The committee voted to approve the application 5-0.
Item No. 6, Miscellaneous Discussion:
a) Mr. Sturtz said the meeting on September 20, 2021 has been cancelled due to lack of
quorum.
b) Mr. Sturtz said the deadline for the October 4, 2021 meeting is September 15, 2021.
Item No. 7, Adjournment:
Mr. Sturtz called for a motion to adjourn. Mr. Danner motioned to adjourn and was seconded
by Mr. Scanlon. The motion was approved 5-0. Meeting adjourned at 4:01 p.m.
Agenda
FLOODPLAIN PERMIT COMMITTEE
AGENDA
Tuesday, September 7, 2021
MEETING TIME: 3:30 p.m.
MEETING PLACE: 201 West Gray, Building A, Conference Room D
1. Approval of Minutes from the August 16, 2021, meeting.
2. Floodplain Permit No. 641: Floodplain Permit application is for an 8 inch sanitary sewer crossing of
the Upper Dave Blue Creek floodplain for the proposed Summit Valley Addition Section 3
development.
3. Floodplain Permit No. 643: Floodplain Permit application is for a solar farm project at the Norman
Water Treatment Plant located at 3000 East Robinson Street, which is in the Rock Creek floodplain.
4. Floodplain Permit No. 644: Floodplain Permit Application is for a solar farm project at the Norman
Water Reclamation Facility located at 3500 Jenkins Avenue, which is in the Bishop Creek floodplain.
5. Floodplain Permit No. 642: Floodplain Permit Application is for the construction of a soccer complex
with multiple playing fields on the property located on the south side of Indian Hills Road
approximately ¼ mile east of 72nd Ave NW, which is in the 10 Mile Flat Creek floodplain.
3. Miscellaneous Discussion:
a. The Floodplain Permit Committee meeting scheduled for September 20, 2021 has been canceled
due to lack of a quorum.
b. The filing deadline for application submittals for the October 4, 2021 meeting is Wednesday,
September 15, 2021. Currently, there is one pending application.
4. Adjournment.
It is the policy of the City of Norman that no person or groups of persons shall on the grounds of
race, color, religion, ancestry, national origin, age, place of birth, sex, sexual orientation, gender
identity or expression, familial status, marital status, including marriage to a person of the same
sex, disability, retaliation, or genetic information, be excluded from participation in, be denied the
benefits of, or otherwise subjected to discrimination in employment activities or in all programs,
services, or activities administered by the City, its recipients, sub-recipients, and contractors. In
the event of any comments, complaints, modifications, accommodations, alternative formats,
and auxiliary aids and services regarding accessibility or inclusion, please contact the ADA
Technician at 405-366-5424, Relay Service: 711. To better serve you, five (5) business days’
advance notice is preferred.