Norman Forward Citizens Financial Oversight Board Meeting
Regular MeetingNorman, OK · September 11, 2017
Minutes
NORMAN FORWARD CITIZENS FINANCIAL OVERSIGHT BOARD MINUTES
September 11, 2017
The Norman Forward Citizens Financial Oversight Board (CFOB) of the City of Norman,
Cleveland County, State of Oklahoma, met at 3:30 p.m. in the Municipal Building Conference
Room on the 11th day of September, 2017, and notice and agenda of the meeting were posted in
the Municipal Building at 201 West Gray and the Norman Public Library at 225 North Webster
24 hours prior to the beginning of the meeting.
PRESENT: Members MacKenzie Britt, Cynthia Rogers, Anil Gollahalli, Andy
Rieger, Tom Sherman, and Chair Bill Nations
ABSENT: Members Don Hiebert, Bree Montoya, and Andy Paden
OTHERS PRESENT: Robert Castleberry, City Council Member
Terry Floyd, Development Coordinator
Anthony Francisco, Finance Director
Jud Foster, Director of Parks & Recreation
David Hopper, Chair Senior Citizens Center Ad Hoc Group
Leslie Taber, ADG
Kyle Lombardo, ADG
Montgomery Johnston, Citizen
Robert Huskey, Citizen
CALL TO ORDER AND ROLL CALL
Chair Nations called the meeting to order at 3:37 p.m. A quorum was present.
******
ITEM 1, being
APPROVE MINUTES FROM JULY 10, 2017 MEETING
After review and discussion of minutes of July 10, 2017 meeting, a motion was made by
Member Gollahalli and seconded by Member Sherman to approve the minutes. Motion passed
unanimously.
Items submitted for the record:
1. Norman Forward Citizens Financial Oversight Board Minutes July 10, 2017.
Norman Forward Citizens Financial Oversight Board Minutes
September 11, 2017
Page 2
******
ITEM 2, being
DISCUSSION OF FINANCE REPORTS-FINANCE DEPARTMENT
Anthony Francisco gave the presentation. He stated we are continuing on the same track as we
have been which is negative. We continue to hope this will turn around. We currently have a
significant amount of expenditures being made due to the Westwood Pool and Central Library
projects construction progress.
Member Sherman asked if the “paid” on the report was monthly paid out. Francisco stated that
this was from conception and not monthly. The total is total encumbrances and not the total
from conception.
Member Gollahalli asked if the budget numbers are budgeted to date per project. Francisco
stated these are the total budgeted amounts for projects that have been put on the City’s books,
but they do not include any projects that are planned but have not been budgeted for.
Member Rieger asked what was paid out for James Garner on the report. Francisco stated that
the line item was for some survey work done on the project.
Items submitted for the record:
1. Norman Forward Expenditure Report
2. Norman Forward Sales Tax Revenue Report
3. Norman Forward Sales Tax Fund Annual Sales/Use Tax Growth Factor (FYE 2018)
4. Norman Forward Sales Tax Fund Annual Sales/Use Tax Growth Factor (FYE 2019-
2031)
5. City of Norman Norman Forward Sales Tax, Versus Projection
******
ITEM 3, being
IMPLEMENTATION PLAN UPDATE
Norman Forward Citizens Financial Oversight Board Minutes
September 11, 2017
Page 3
Francisco gave the presentation. He stated the project timing in the Implementation Plan is
where there have been a few changes.
Leslie Tabor stated that projects in white have had some sort of update which may have caused
the timelines to change slightly. These changes have been reflected on the “in progress” projects
in the updated Implementation Plan.
Member Rogers asked if the land acquisitions for all the projects have been completed.
Francisco stated that for Griffin Park, the land acquisition is ongoing but has not been completed
as of yet. The Griffin Park Master Plan process just states what we plan to use the land for.
Member Rogers asked how certain we are of the land acquisition. Francisco stated he believes it
is 90-95% certain. The negotiations are not about whether we will purchase the land, but what
the seller will use the proceeds for and what the payout schedule will be.
Member Sherman stated that he has reservations about investing so much capital in something
that we wouldn’t own. Francisco stated that nothing on the Master Plan will be implemented
until the land acquisition is settled.
Member Rogers asked about the land acquisition for the indoor aquatic facility. Francisco stated
that this should be completed by the end of this calendar year.
Member Rieger asked about the land acquisition for the adult football/softball facility. Francisco
stated that this acquisition is expected to be completed by the end of this calendar year as well.
Member Gollahalli asked if there was anything in the updated Implementation Plan that was
giving ADG any pause. Kyle Lombard stated that ADG feels good about the updates and the
progress with the projects.
Items submitted for the record:
1. Memo from ADG on Norman Forward project timeline update No. 1
******
ITEM 4, being
UPDATED PRO FORMA FINANCIAL PROJECTION
Francisco gave the presentation. He stated that column D now has the actual expenditure from
2016. The expenditures are a little bit behind what we thought they would be for fiscal year
2017, but overall they are about where we thought they would be. The third financing was
originally projected to be completed in fiscal year 2018, but that has now been moved to fiscal
year 2019 projections. The overall conclusions are pretty much the same as the last financial
projection. Some of the years will run kind of thin, but overall we still believe we will have
money to complete all of the promised projects. Francisco stated he used a 3.5% rate for the
projections for the third financing package.
Norman Forward Citizens Financial Oversight Board Minutes
September 11, 2017
Page 4
Member Rogers asked if this budget is using the same percentage as the City budget. Francisco
stated we used 4.5% for Norman Forward, where they City used 4%, but at the time that we
adopt the annual budgets it will revert to the adopted sales tax rate.
Member Sherman stated that the Ad Hoc Committee has done a good job of staying within the
budgets and completing the projects promised.
Member Rieger asked why we were pushing the third round of debt issuance. Francisco stated
that it was because the expenditure rate for project costs did not require it at this time.
Member Sherman asked what rate was being used for this updated projection.
******
ITEM 5, being
DISCUSSION OF ANNUAL REPORT TO COUNCIL
Francisco gave the presentation. He asked if someone on the Committee would like to draft an
annual report and have the rest of the Committee go over that report, or would they like to have
staff draft a report and present it to the Committee for change/approval. Chair Nations asked
what the due date would be. Francisco stated that would be up to the Committee as well. Chair
Nations stated that he thinks a 3 person Committee could be chosen to work with staff to draft
the annual report.
Member Sherman stated that the report should be done by fiscal year and the staff should help.
Member Britt stated that he thinks staff could put together the report for the Committee to
approve.
Member Gollahalli stated that he agrees there should be a 3 person Committee to work with staff
on the report. He would recommend Members Rogers, Sherman, and Paden to work on this
Committee. Chair Nations stated that he will double check with Member Paden about joining
the 3 person Committee.
*****
ITEM 6, being
Norman Forward Citizens Financial Oversight Board Minutes
September 11, 2017
Page 5
DISCUSSION OF PREVIOUSLY APPROVED COUNCIL ACTIONS AND POSSIBLE
ACTION
Francisco gave the report. He stated that all of the actions taken at the last City Council meeting
are included in the packet. There was an increase in a contract for the Central Library as well as
the Final Plat for the Central Library. The most significant action was the resolution adopting
the Master Plan for the Griffin Park Sports Complex.
Member Rogers stated that she is a little upset that the Committee didn’t get to see the final
Master Plan or the budget for the Griffin Park Sports Complex before it was approved by City
Council. She then asked about the wording in the Master Plan that states there will be 22 full
sized fields in addition to the northeast corner field. Then on page 9 and 10 it says there will be
21. She believes that the wording stating 22 should include the northeast corner field. Member
Gollahalli stated that the differential is about a soccer field that is where the indoor facility will
go, so when the indoor facility goes from Phase I to Phase II it drops from 22 fields to 21. Jud
Foster stated that the soccer field will eventually go away when the funding becomes available to
build the proposed park.
Member Rogers asked why things will be done in Phases. Member Gollahalli stated that Phase
II is not funded through Norman Forward. It will be funded via a private development if there is
a desire to do additional projects. Member Sherman stated that he agrees that the wording for
this Phase II future facility should state “will have”.
Member Gollahalli stated that he believed the expectation of Norman Forward was to use extra
money to fund originally planned items on projects or to use the extra money to put toward other
projects within Norman Forward. Member Sherman stated that he believes there is a
commitment within Norman Forward that projects will be completed as was originally proposed
as soon as enough funds were available over time.
Member Gollahalli stated that we should put the “will”/”shall” issue in the annual report in order
to get more clarification.
Member Sherman stated that the Master Plan dictates what is spent on a project; maybe not all at
once, but as funds become available. Chair Nations stated that we need clarification on how
future available funds should be used on these programs.
Items submitted for the record:
1. Contract K-1516-83 AMD #2 increasing contract amount between City of Norman and
Meyer, Scherer & Rockcastle, LTD.
2. Final Plat FP-1617-16 Norman Public Library Central Addition
3. Resolution R-1718-22 Adopting the Griffin Park Sports Complex Master Plan and
Directing City Staff to Implement the Recommendations of the Plan
******
Norman Forward Citizens Financial Oversight Board Minutes
September 11, 2017
Page 6
ITEM 7, being
AD HOC LIAISON REPORTS
Jud Foster gave the report on the Griffin Park and Westwood Pool projects. He stated that the
consultant team for Griffin is working on grading plans and a lighting project. We hope this is
ready to bid around the end of November. Member Gollahalli stated that portions of Griffin Park
will be under construction during the project, but they cannot take the whole park out of
commission. Foster then stated that he believes there is about 60 days left on construction for the
Westwood Pool. The art piece is fabricated and will be powder coated soon. Installation should
be somewhere around the end of October. He then stated that the consultants for the Westwood
Tennis project are working the numbers to try to get the project back within the budget.
Member Britt asked how far out of budget the Westwood Tennis project is. Foster stated that it
was about $200,000 over the original budget.
Member Rieger gave the report on the Reaves Park project. He stated that the plan was
presented to the Parks Board recently. Foster stated that the Park Board voted to approve the
plan and send it on to City Council for consideration. Member Rieger stated that this project will
also be done in stages since the entire park cannot be under construction at the same time.
Member Gollahalli asked which plan was put forward to the Parks Board. Foster stated it was
the plan with the new entry drive. Member Gollahalli asked if this plan was available on the
website. Foster stated it wasn’t up as of yet, but it would be soon.
Member Sherman gave the report for the Senior Citizens Center. He stated that there has been
no meeting of this Committee in several months and the next step is up to the City Council.
Terry Floyd gave the report on the Library Projects. He stated that the East Branch Library
would soon be boxed in since all of the steel support beams were now in place. There is a
contract with the artist for the art project that will go at the East Branch Library, which will be
presented to Council to approve. This will be completed by the end of May 2018. The Central
Library has a lot of site work going on, including utilities and fiber optic lines. The RFP for the
Central Library art projects is being developed now.
******
ITEM 8, being
DISCUSSION OF PROJECT STATUS-PROJECT MANAGERS
Norman Forward Citizens Financial Oversight Board Minutes
September 11, 2017
Page 7
Anthony Francisco stated that some of the “pay-as-you-go” projects, such as Oakhurst Park, will
be on the upcoming City Council agenda. Jud Foster stated that there will be two on the agenda,
Oakhurst and Sonoma playgrounds.
Member Gollahalli asked if there was a single vendor for these types of projects, or do we piece
it out. Foster stated that we do not have a single vendor and we bid out every project. Member
Gollahalli stated that it might be financially beneficial to have a preferred contractor bid.
******
ITEM 9, being
MISCELLANIOUS DISCUSSION
Member Rieger asked if the use tax was continuing to trend upwards. Anthony Francisco stated
that it was continuing to climb, but it would not balance out the down trend of sales tax.
******
ITEM 10 being
ESTABLISHMENT OF FUTURE MEETING TIME(S)
The next meeting of the Norman Forward Citizen’s Financial Oversight Board will be on
November 6 at 3:30 pm.
******
ITEM 11 being
ADJOURNMENT
Motion was made to adjourn. Motion passed unanimously and the meeting adjourned at 4:45 pm.
Agenda
MEETING AGENDA
NORMAN FORWARD
CITIZEN’S FINANCIAL OVERSIGHT BOARD
Executive Conference Room
201 West Gray
Monday, September 11, 2017
3:30 P.M.
I. Approve minutes from July 10, 2017 Meeting
II. Discussion of Finance Reports – Finance Department
III. Implementation Plan Update
IV. Updated Pro Forma Financial Projection
V. Discussion of Annual Report to Council
VI. Discussion of Previously-Approved Council Actions and Possible
Action
VII. Ad Hoc Committee Liaison Reports
VIII. Discussion of Project Status – Project Managers
IX. Miscellaneous Discussion
X. Establishment of Future Meeting Time(s)
XI. Adjournment
Get email alerts for Norman