NORWICH
PUBLIC SCHOOLS
SCHOOL CONSTRUCTION
STRATEGIC PLANNING SERVICES 05 July 2022
Norwich Public Schools 14 BUILDINGS | 7 ES | 2 MS
DISTRICT
Norwich Public Schools
OFFICES
90 Town Street
Bishop School Early Learning | PK
EARLY 526 East Main Street
CHILDHOOD
Norwich Transition Academy | 18-21 yrs.
30 Case Street
Huntington School| K-5 Moriarty Environmental Sciences Magnet School | K-5
80 West Town Street
Mahan School| PK-5 Wequonnoc Arts and Technology Magnet School | K-5
94 Salem Turnpike
Case Street Early Learning | PK
Moriarty Environmental Sciences Magnet School| K-5
20 Lawler Lane
ELEMENTARY
Huntington School | K-5
John B. Stanton School| K-5
SCHOOLS
386 New London Turnpike Kelley STEAM Magnet School | 6-8
Norwich Public Schools
Uncas Elementary School| K-5
280 Elizabeth Street Extension
Adult Education
Veterans Memorial Elementary School| PK-5 Teachers’ Memorial Global Studies Magnet School | 6-8
80 Crouch Avenue Transition Academy | 18-21 yrs
Wequonnoc Arts & Technology Magnet School| K-5 Stanton School | K-5
Bishop School Early Learning | PK
155 Providence Street
Kelley STEAM Magnet School| 6-8 Uncas School | K-5
Mahan School | K-5
MIDDLE 25 Mahan Drive
SCHOOLS Teachers’ Memorial Global Studies Magnet School| 6-8 Veterans Memorial School | K-5
15 Teachers Drive
District Offices
SPECIALTY 201 Hickory Street
PROGRAMS Norwich Regional Adult Education
191 Hickory Street
Agenda – 05 July 2022
1.Backgrounds
• Existing Building Assessments
• Demographics & Enrollment
• Educational Programming
• Potential Options
2.Potential Options
• Do nothing – Repair Existing
• Four Elementary Schools
Agenda – 05 July 2022
1.Backgrounds
• Existing Building Assessments
• Demographics & Enrollment
• Educational Programming
• Potential Options
2.Potential Options
• Do nothing – Repair Existing
• Four Elementary Schools
Physical Conditions Assessment School Facilities
Kelley STEAM Magnet School| 6-8
25 Mahan Drive
MORE
Case Street Early Learning | PK
SUITABLE 30 Case Street
Teachers’ Memorial Global Studies Magnet School| 6-8
15 Teachers Drive
RANGE of PHYSICAL CONDITION
Veterans Memorial Elementary School| K-5
80 Crouch Avenue
Huntington School| K-5
80 West Town Street
Mahan School| K-5
SUITABLE
94 Salem Turnpike
Uncas Elementary School| K-5
280 Elizabeth Street Extension
Moriarty Environmental Sciences Magnet School| K-5
20 Lawler Lane
Bishop School Early Learning | PK
526 East Main Street
Wequonnoc Arts & Technology Magnet School| K-5
155 Providence Street
LESS
SUITABLE John B. Stanton School| K-5
386 New London Turnpike
Enrollment / Demographics Forecasts – By Current School Area
2031
Total City population is forecast to drop by approximately 300 people
Enrollment / Demographics Forecasts – 20 Years PK – Grade 5
Enrollment / Demographics Forecasts – 20 Years Grades 6 - 8
Attendance Zones –
Current ES Zones
LEGEND
School Type
Elementary School
Middle School
Other
ES Zones 2021-22
John B. Stanton School
Samuel Huntington School
Thomas W. Mahan School
Uncas Network School
Veterans’ Memorial School
Moriarty Magnet School
Wequonnoc Magnet School
Enrollment / Demographics – Student Density Locations
Programming
Programming
Desire to better align enrollments across facilities
• Some enrollments are too small to be effective
• Not fiscally or logistically feasible
• Does not provide parity across the District
• Buildings do not meet guidelines for room sizes
• Projected enrollment will stretch some schools
Programming
The ideal size of an elementary school
• Fostering student growth
Appropriately scaled for a large age range
• Not more than 800 elementary students
• Target is 300 to 500 students
• Serve a balanced mix of students
Programming
Planning for elementary school populations over 400
• Communities of Learners
Design smaller learning environments within larger facilities
• Freestanding small schools
• Small schools in one building sharing the same administration; and
• A school within school, each with their own administration
Programming
Three approaches considered
Existing configuration
• Seven schools of 300 students each
Alternate configurations
• Four schools of 550 – 600 students each
• Three schools with 700 students in each
Agenda – 05 July 2022
1.Conclusions from prior work
• Demographics & Enrollment
• Educational Programming
• Potential Options
• Existing Building Assessments
2.Potential Options
• Do nothing – Repair the Existing
• Three Elementary Schools
Potential Options – Repair the Existing
“Do Nothing”
Seven Elementary, Two Middle Schools
All of the buildings except Kelly require investment
• Would maintain the existing
• Would not address educational shortfalls
• Would not address all code requirements
Potential Options – “Do Nothing” – Repair the Existing
Potential Options – Repair the Existing
Potential Options – Repair the Existing
The projected costs are for repairs and maintenance
• Expansion is not included
• Total renovation is not included
• Limited opportunities for State grants
Potential Options – Repair the Existing
2023: $142,000
2025: $8,685,000
2030: $4,728,000
2035: $2,815,000
2040: $4,485,000
Total:
$20,854,000
Potential Options – Repair the Existing
2023: $614,000
2025: $5,843,000
2030: $12,785,000
2035: $3,489,000
2040: $1,045,000
Total:
$23,746,000
Potential Options – Repair the Existing
2023: $2,801,000
2025: $42,887,000
2030: $107,900,000
2035: $63,014,000
2040: $54,891,000
Total:
$271,494,000
Without Kelly MS:
~$225,806,000
Potential Options – Repair the Existing
Projected costs are spread over 20 years
• Include escalations allowances
• Project start dates can change, but there is a limited window
• Work will take place in occupied schools
• Work will take place in multiple schools at the same time
Potential Options – “Replace the Existing” – New-Build Options
Potential Options – New-Build Options
New-Build Options
Four Elementary, Two Middle Schools
Program Elementary Schools to provide:
• Appropriately sized spaces
• Inclusive and flexible learning areas
• Outdoor learning and play opportunities
• Room for SPED
• Incorporate STEAM and project-based learning
Potential Options – New-Build Options
New School Building Program
• Established through educational programming with District leadership
• Considers OSCGR guidelines as the basis for beginning
• Provides spaces for programs that OSCGR may not recognize
• Accommodates different educational pedagogies and methodologies
• Provides a starting point for the planning process
Potential Options – New-Build Options
Four School Option
Four New Elementary Schools of 525 students
Renovate Teacher’s Middle School
Potential Options – New-Build Options
Potential Options – New-Build Options
Site Evaluations Population Centers / Potential Schools
Case Street 18 – 22 New Moriarty ES
Renovate Huntington Kelly MS
Administrative Center New Golden Street
Renovated Teachers MS (Greenville)
New Stanton ES
New Uncas ES
Recommended:
Four Elementary Schools
Two Middle Schools
One Transition Services
One Administrative Building
Norwich Public Schools – Four Elementary Schools Option
DISTRICT
Huntington School
80 West Town Street
OFFICES Central Office / Nurse / Registration / Tech / Adult Ed / Virtual Learning
Moriarty Environmental Sciences Magnet School| PK-5 / 550 Students
Replace 20 Lawler Lane
PK – 5 John B. Stanton School| PK-5 / 550 Students
Replace
SCHOOLS 386 New London Turnpike Moriarty Environmental Sciences Magnet School | PK-5
Replace Uncas Elementary School| PK-5 / 550 Students
280 Elizabeth Street Extension
NEW SCHOOL New School| PK-5 550 Students
LOCATION – Golden Street (Greenville School) Case Street
Transition Program
NO WORK Kelley STEAM Magnet School| 6-8 / 650 Students Huntington School
MIDDLE 25 Mahan Drive District Offices
SCHOOLS Teachers’ Memorial Global Studies Magnet School| 6-8 / 650 Students
ADD/RENO Kelley STEAM Magnet School | 6-8
15 Teachers Drive
SPECIALTY Case Street School| Teachers’ Memorial Global Studies Magnet School | 6-8
NO WORK
8 Chase Street
PROGRAMS New School | PK-5
Transition Services Stanton School | PK-5
Uncas School | PK-5
Site Evaluations Moriarty - locus
Moriarty ES
Site Evaluations Moriarty - 2
Wetland
Slopes of more than 5%
Site Evaluations Moriarty - 5
Potential area for a new,
two-story school
Bus and parent drop off
Parking area
New ballfield
New rectangular field
Site Evaluations Stanton - locus
Stanton ES
Site Evaluations Stanton - 2
Wetland areas
100 year floodplain
Stanton School
Slopes of 2 – 5%
Slopes of more than 5%
Site Evaluations Stanton - 2
Playfields
Parking
Two-story school
Outdoor learning area
Parent drop-off
Bus drop-off
Parking
Site Evaluations Uncas - locus
Uncas ES
Site Evaluations Uncas - 1
Slopes of 2 – 5%
Slopes of more than 5%
Slopes of 2 – 5%
Slopes of more than 5%
Site Evaluations Uncas - 2
Realigned road
Parking
Parent drop-off
Bus drop-off
Playfield
Two-story school
Playfield
Site Evaluations Greenville School - locus
Golden Street
(former Greenville School)
Site Evaluations Greenville School - 1
Slopes of more than 5%
Slopes of 2 – 5%
Slopes of more than 5%
Site Evaluations Greenville School - 2
Playfield
Two-story school
Parking
Bus drop-off
Connecting driveway
Playfield
Norwich Public Schools – New-Build Options
Projected costs and schedule
• Projected costs include construction and soft costs
• Projected costs include escalation
• Scheduling for construction anticipates two phases
• New construction for elementary schools eliminates swing space needs
• Staffing costs need to be investigated further
two-phase approach – cost projections
two-phase approach – cost projections
Total Projected Cost
$381,526,351
Project cost to Norwich
$149,060,599
four school, two-phase approach – seven-year timespan
phase one
phase two
budget base +8% +16.16% +26.67% +35.18% +42.6% +51.19%
2022 2023 2024 2025 2026 2027 2028 2029
Early Childhood moves to Elementary Schools – Fall, 2025
Bishop Early Childhood Administrative moves to Samuel Huntington
Case Street Early Childhood Early Childhood moves to Elementary Schools
18 – 22 Transition Services – Fall 2022
New Elementary School behind existing, opens Jan 2026 Existing Elementary School demolished,
John B. Stanton Elementary fields completed, Fall, 2026
Existing Elementary School remains in service to December 2025
7 resulting buildings
Existing Elementary School New Elementary School constructed Existing Elementary School demolished,
13 existing buildings
John M. Moriarty Elementary
remains in service to Spring 2028 west of existing, opens Fall, 2028 fields completed, Fall, 2029
Existing Elementary School
Thomas W. Mahan Elementary
Decommissioned in December 2026
Existing Elementary School Administrative, transportation, facilities relocate – January 2028
Samuel Huntington Elementary remains in service to December 2026 Renovation and upgrades to select areas – completed December 2027
Existing Elementary School
Veterans Memorial Elementary
Decommissioned in December 2026
Existing Elementary School New Elementary School constructed Existing Elementary School demolished,
Uncas Elementary remains in service to Spring 2028 west of existing, opens Fall, 2028 fields completed, Fall, 2029
Existing Elementary School existing buildings
Wequonnoc Elementary Decommissioned in December 2026
Complete renovation to As-New condition
Teacher’s Memorial Middle Completed – Fall 2028
Kelly Middle No major work projected
18 – 22 Transition Services Moved to existing Case Street Facility – Fall 2022
Hickory Street Administrative Existing remains in service to Fall 2025
New Elementary School constructed opens January, 2026 new buildings
New Elementary @ Greenville
Norwich Public Schools – New-Build Options
Do Nothing Option New-Build Options
Seven Elementary Schools, Two Middle Schools Four Elementary Schools, Two Middle Schools
Total Projected Costs = ~ $225,806,000 Total Projected Costs = ~ $381,526,351
Net cost to Norwich = ~$225,806,000 Net cost to Norwich = ~ $149,060,599
(No Projects qualify for renovation grants) (All projects qualify for construction grants)
Work at Kelly MS is not included in calculations Work at Kelly MS is not included in calculations
NORWICH
PUBLIC SCHOOLS
SCHOOL CONSTRUCTION
STRATEGIC PLANNING SERVICES 05 July 2022
Agenda
NOTICE UNDER THE PROVISIONS OF CONNECTICUT GENERAL STATUTES CHAPTER 14, SECTION 1‐225
**New Time is 6:00 P.M. ****
It is hereby posted with the City and City Clerk of Norwich, Connecticut a notice that an Informational
Meeting/Workshop of the Norwich City Council will be held on Tuesday, July 5, 2022 at 6:00 P.M. in Council
Chambers of the Norwich City Hall for the following:
1. A presentation by DRA Architect Firm about the School Building Committees findings.
Mayor Peter Albert Nystrom