A. CALL TO ORDER: Chairman Richard Morell called the meeting to order at 7:00 PM.
B. ROLL CALL and SEATING of ALTERNATES:
Present: Chairman Richard Morell, Vice Chairman Douglas Lee and Peter Chalecki. Brandon
Hyde arrived at 7:01 PM.
Absent: Robert McCoy
Also Present: Dan Daniska, Assistant City Planner and Katherine Rose, Recording Secretary.
C. APPROVAL OF MEETING MINUTES:
Douglas Lee put forth a motion to APPROVE the February 3, 2022 regular meeting minutes. Peter
Chalecki seconded. Peter Chalecki, Douglas Lee, Brandon Hyde, Michael Lahan and Richard Morrell
voted in favor. The motion passed unanimously.
D. COMMUNICATIONS:
Dan Daniska stated in February he received a notice from First Light Hydro, in regards to the Taftville
Generating Station, stating they would be submitting a NPDES permit application for incidental
discharges associated with running the plant. Dan Daniska stated he also received a notice on March
17th from DACO stating they submitted a DEEP permit for 190 South Thames Street to conduct work
water ward of the high tide line in tidal coastal or inevitable waters of the state in that area.
E. PUBLIC HEARINGS: None.
F. OLD BUSINESS:
1. IWWCC #22-02: 722 Boswell Avenue - Proposed activity in the Upland Review Area related to the
reconfiguration and upgrade of an existing gas station and convenience store. Upland area proposed
work includes demolition of existing store and construction of the new store, reconfiguration of the
existing parking and circulation drives, grading for compensatory storage within the FEMA Floodway,
and grading required to construct a rain garden for the roof drainage from the proposed store and
fueling island canopy. Application and property of M and T Land, LLC. Assessor’s Map 79, Block 1, Lot 2.
Zone GC.
David McKay from Boundaries LLC reported, on behalf of the applicant M and T Land LLC, that they are
seeking to make improvements to the existing fueling station and convenience store at 722 Boswell
Avenue. David McKay stated there are wetlands located at 682 Boswell Avenue which are separated
from the property at 722 by a driveway that runs to the car wash at 690 Boswell Avenue. David McKay
continued that the upland review area from the wetland system runs halfway down through the
middle of the property at 722 Boswell Avenue. David McKay stated that the proposal included
reconstructing the convenience store from 590 square feet to 2,100 square feet; adding a canopy over
the fueling islands; and reconfiguring the parking lot to reduce pavement around the site, while
introducing some landscape islands. David McKay reviewed the existing conditions survey, site
demolition plan and current site plan, which included comments from the city. David McKay stated the
existing convenient store would be demolished and pavement would be removed for new landscaping.
David McKay discussed the work that would be occurring within the upland review area such as
constructing the new parking spaces, the new building footprint and the re-striped parking area. David
McKay stated a rain garden would be installed in the northwest corner of the property that would be
sized to take 1” off run off from the new roof surface and canopy over the fueling stations. David
McKay discussed the site grading plan which included grading to provide compensatory storage as the
property is located within the FEMA floodway. David McKay discussed how drainage on the site would
flow. David McKay added that the demolition plan proposed a row of silk fences at limits of grading
that will extend along limits of driveway and limits of grading, as well as an intermediate barrier of silk
fence along top of the slope. David McKay reviewed the erosion and sedimentation control notes.
David McKay stated they would be repairing the catch basin to the rear of the property per the
comment by Brian Long.
Brandon Hyde asked if there would be an increase in impervious surface overall on the site. David
McKay responded there was a decrease in impervious surface from 3,000 feet overall. Brandon Hyde
asked how much of the parking lot goes towards the back of the property versus towards Boswell
Avenue. David McKay responded that all of the parking lot essentially drains north to south, then is
collected in a concrete gutter that runs to the catch basins. Robert Morrell noted the amount of
flooding that occurs in the area. David McKay responded the issue had been discussed and showcased
where his understanding of flooding extends. Discussion ensued. David McKay stated the building will
be dry flood-proofed in an effort to address the existing flooding condition. David McKay discussed
comments made by the city engineer and what was done to the plans to address them. Dan Daniska
stated all comments made by himself and the city engineer were addressed.
Brandon Hyde made a motion that the application was not a significant activity and did not require a
public hearing. Michael Lahan seconded. All members voted in favor. The motion passed unanimously.
Brandon Hyde made a motion to APPROVE IWWCC APPLICATION #22-02 with the following conditions:
1. That the approval is valid for FIVE YEARS and will expire on 04/07/2027.
2. That a bond, in an amount satisfactory to the City Engineer, be submitted for Erosion and Sediment
Control and Site Restoration.
3. That the Review Comments from the City Engineer in an email dated 03/28/2022 be addressed
before the final revised plans be submitted and reviewed by City Staff.
4. That final revised plans be submitted and reviewed by City Staff.
5. That all site activities shall be conducted in accordance with the plans, specifications and
documents of record. Any deviation from the approved plans or construction sequence shall be
cause for enforcement action by the Inland Wetlands, Watercourses and Conservation
Commission.
6. That the permittee shall notify the Inland Wetlands Agent prior to the commencement of work and
upon its completion.
7. That all work and all regulated activities conducted pursuant to this authorization shall be
consistent with the terms and conditions of this approval. Any structures, excavation, fill,
obstructions, encroachments or regulated activities not specifically identified and authorized
herein shall constitute a violation of this approval and may result in its modification, suspension, or
revocation. Upon initiation of the activities authorized herein, the permittee thereby accepts and
agrees to comply with the terms and conditions of this approval.
8. That no equipment or materials including without limitation fill, construction materials, or debris,
shall be deposited, placed, or stored in any wetland or watercourse on or off site unless specifically
authorized by this approval.
9. That the General Provisions stated in Section 11.9 of the Inland Wetlands and Watercourse
Regulations are applicable to this permit.
10. That the permit shall not be assigned or transferred to another entity without the written
permission of the Commission.
11. That all erosion and sediment control measures shall be in accordance with the Connecticut
Guidelines for Erosion and Sediment Control. Erosion and sediment control measures shall be
installed and inspected prior to site disturbance. It is the permittee's responsibility to schedule the
inspection with the Norwich Planning Department. Additional erosion and sediment control
measures shall be installed if determined to be necessary by the Designated Agent. The permittee
shall take such necessary steps consistent with the terms and conditions of the approval, to control
stormwater discharges and to prevent erosion and sedimentation and to otherwise prevent
pollution of wetlands and watercourses.
12. That this permit will be strictly enforced. The Commission may suspend or revoke this permit, may
direct the Commission's Agent to issue a cease and desist order or may require the applicant to
modify, extend, or revise the site work or restore the area to its original condition if it finds that
the applicant has not complied with the conditions set forth in this approval or if the applicant
exceeds the scope of this approval as set forth herein or if the intended use or actual use of the
general site is not as represented by the application or the plan of record.
REASON: The proposed Erosion & Sediment Controls are deemed sufficient to protect the nearby
wetlands.
Douglas Lee seconded. All members voted in favor. The motion passed unanimously.
2. IWWCC #22-03: 210 Salem Turnpike - Proposed activity in the Upland Review Area related to the
construction of a new, three-level self-storage building with associated parking. Work in the Upland
Review Area will include excavation, grading, new drainage and pavement. Approximately 0.42 acres
of disturbance is anticipated in the Upland Area. Application of Ron Lyman. Property of
OWUNNEGUNSETT, INC., Ron Lyman, Principal. Assessor’s Map 121, Block 2, Lots 22, 23, 24. Zone PC.
Darren Hayward of CLA Engineer stated the applicant is looking to put a three-level storage building at
210 Salem Turnpike and howcased the existing conditions plan. Darren explained that the parcel is
currently 1.8 acres of undeveloped vegetated lands which drains south on a moderate 6% slope into
an intermittent watercourse. Darren Hayward continued the runoff enters the wetlands and then is
conveyed by a culvert underneath Montville Road and eventually flows into Trading Cove. Darren
Hayward stated there is approximately .1 acres of regulated wetlands at the southern end of the site.
Darren Hayward stated the project proposed a new 3 level sub story building with associated parking
and that access to development will be through Salem Turnpike for both exit and entrance. Darren
Hayward stated there was also an entryway at the south portion of the parcel from Montville Road.
Darren Hayward stated the approximate area of disturbance on the site was 1.7 acres. Darren
Hayward showcased the erosion and sediment control plan which would include a swail running along
western side of the property to capture runoff from the site and deposit into a temporary sediment
trap during construction. Darren Hayward stated the upland area of the wetlands would be protected
by a silt fence and a hay barrel backed silt fence. Darren Hayward stated that no construction would
occur in the wetlands or watercourses. Darren Hayward stated that construction was expected to take
approximately a year and planned to commence during 2022, pending permits and reviews. Darren
Hayward stated the plan was designed to ensure no increase in run off rates or volumes and the soil
scientist concluded there would be temporary or post impact to the wetlands. Darren Hayward
discussed the details of drainage on the site. Brandon Hyde asked if there was a curbed dilleniating
grass area in the south end of the parking lot. Darren Hayward responded there was not; runoff would
sheet flow off and there would be a three foot stone level spreader to protect the grass area from
collecting sediment at the edge of the lot, which then would overflow and collect into the catch basin.
Brandon Hyde asked if the predominant grade would extend out to Montville Road and how much
water he thought would reach the road. Darren Hayward responded a small amount, based on the
proposed plan. Brandon Hyde asked if it would be a retention or detention basin. Darren Hayward it
had to be a detention basin due to the proximity to the water level.
Michael Lahan Made a motion to To APPROVE IWWCC APPLICATION #22-03 with the following
conditions:
1. That the approval is valid for FIVE YEARS and will expire on 04/07/2027.
2. That the required bond, in an amount deemed satisfactory to the City Engineer, be submitted for
Erosion and Sediment Control and Site Restoration. Bonds must be submitted in a form acceptable
to the City (check or letter of credit) prior to any land disturbance activities occurring.
3. That the Review Comments from the City Engineer in an email dated 03/11/2022 be addressed
before the final revised plans be submitted and reviewed by City Staff.
4. The property owner should install some sort of barrier to prevent vehicles from using the site as a
cut-through from the Wal-Mart parking lot in the short term before the lot is developed, as the cut
through is relatively close to the wetlands area.
5. That final revised plans be submitted and reviewed by City Staff.
6. That the City’s letter of approval be placed on the final revised plan set (cover page preferred).
7. That all site activities shall be conducted in accordance with the plans, specifications and documents
of record. Any deviation from the approved plans or construction sequence shall be cause for
enforcement action by the Inland Wetlands, Watercourses and Conservation Commission.
8. That the permittee shall notify the Inland Wetlands Agent prior to the commencement of work and
upon its completion.
9. That all work and all regulated activities conducted pursuant to this authorization shall be
consistent with the terms and conditions of this approval. Any structures, excavation, fill,
obstructions, encroachments or regulated activities not specifically identified and authorized
herein shall constitute a violation of this approval and may result in its modification, suspension, or
revocation. Upon initiation of the activities authorized herein, the permittee thereby accepts and
agrees to comply with the terms and conditions of this approval.
10. That no equipment or materials including without limitation fill, construction materials, or debris,
shall be deposited, placed, or stored in any wetland or watercourse on or off site unless specifically
authorized by this approval.
11. That the General Provisions stated in Section 11.9 of the Inland Wetlands and Watercourse
Regulations are applicable to this permit.
12. That the permit shall not be assigned or transferred to another entity without the written
permission of the Commission.
13. That all erosion and sediment control measures shall be in accordance with the Connecticut
Guidelines for Erosion and Sediment Control. Erosion and sediment control measures shall be
installed and inspected prior to site disturbance. It is the permittee's responsibility to schedule the
inspection with the Norwich Planning Department. Additional erosion and sediment control
measures shall be installed if determined to be necessary by the Designated Agent. The permittee
shall take such necessary steps consistent with the terms and conditions of the approval, to control
stormwater discharges and to prevent erosion and sedimentation and to otherwise prevent
pollution of wetlands and watercourses.
14. That this permit will be strictly enforced. The Commission may suspend or revoke this permit, may
direct the Commission's Agent to issue a cease and desist order or may require the applicant to
modify, extend, or revise the site work or restore the area to its original condition if it finds that the
applicant has not complied with the conditions set forth in this approval or if the applicant exceeds
the scope of this approval as set forth herein or if the intended use or actual use of the general site
is not as represented by the application or the plan of record.
REASON: The proposed Erosion & Sediment Controls are deemed sufficient to protect the nearby
wetlands.
Douglas Lee seconded. All members voted in favor. The motion passed unanimously.
G. NEW BUSINESS:
1. Receipt of Applications
Dan Daniska reported that there were two applications to receive, and the second application would
require a bit of discussion. Mr. Daniska asked the commission to receive them one at a time. The first
application was IWWCC #22-04, it is an application from Norwich Public Utilities regarding Water
Main installation in the vicinity of Wawecus Street. Brandon Hyde made a motion to receive and table
IWWCC #22-04 until the next meeting. Michael Lahan seconded. All voted in favor. The motion passed
unanimously.
Mr. Daniska reported that the second application, IWWCC #22-05, was for the Business Park North.
Staff would like to open the public hearing at the May 5th meeting, schedule a site walk for some time
in May, and then cancel the June 2nd meeting and schedule a Special Meeting for June 16th. Mr.
Daniska then engaged in conversation with the Commission regarding a date for the site walk, which
was anticipated to take 3-4 hours.
Douglas Lee made a motion to open the application for a public hearing at the May regular meeting.
Peter Chalecki seconded. Richard Morell, Douglas Lee, Peter Chalecki and Michael Lahan voted in
favor. Brandon Hyde abstained. The motion passed.
Michael Lahan made a motion to cancel the regular June meeting and hold a special meeting on June
16, 2022. Douglas Lee seconded. All voted in favor. The motion passed unanimously.
The Commission agreed to schedule the site walk for Thursday May 26, 2022 at 3:30 PM. Meeting
location TBD.
H. OTHER BUSINESS: None.
I. VIOLATIONS: None.
J. ADJOURNMENT: Douglas Lee made a motion to adjourn the meeting at 7:44 PM. Michael Lahan
seconded. Brandon Hyde, Peter Chalecki, Douglas Lee, and Richard Morrell voted in favor. The motion
passed unanimously.
Respectfully submitted, Katherine Rose, Recording Secretary
Agenda
INLAND WETLANDS, WATERCOURSES & CONSERVATION COMMISSION
THURSDAY, April 7, 2022 – 7:00 PM
**** VIRTUAL MEETING****
NORWICH, CT
MEETING AGENDA
Join Zoom Meeting
https://us02web.zoom.us/j/82400046468?pwd=aUEzMTVMRVRFZTk5d3d1bytpcktsZz09
Meeting ID: 824 0004 6468
Passcode: 196768
Dial by your location
+1 301 715 8592
+1 312 626 6799
Meeting ID: 824 0004 6468
*Please Test your audio & video before joining the meeting*
A. CALL TO ORDER
B. ROLL CALL and SEATING of ALTERNATES
C. APPROVAL OF MINUTES: February 3, 2022 Meeting
D. COMMUNICATIONS:
E. PUBLIC HEARING(S): None
F. OLD BUSINESS:
1. IWWCC #22-02: 722 Boswell Avenue Proposed activity in the Upland Review Area related to the
reconfiguration and upgrade of an existing gas station and convenience store. Upland area proposed
work includes demolition of existing store and construction of the new store, reconfiguration of the
existing parking and circulation drives, grading for compensatory storage within the FEMA Floodway,
and grading required to construct a rain garden for the roof drainage from the proposed store and
fueling island canopy. Application and property of M and T Land, LLC. Assessor’s Map 79, Block 1, Lot
2. Zone GC.
2. IWWCC #22-03: 210 Salem Turnpike Proposed activity in the Upland Review Area related to the
construction of a new, three-level self-storage building with associated parking. Work in the Upland
Review Area will include excavation, grading, new drainage and pavement. Approximately 0.42 acres
of disturbance is anticipated in the Upland Area. Application of Ron Lyman. Property of
OWUNNEGUNSETT, INC., Ron Lyman, Principal. Assessor’s Map 121, Block 2, Lots 22, 23, 24. Zone PC.
G. NEW BUSINESS: Receipt of Applications
H. OTHER BUSINESS
I. VIOLATIONS
J. ADJOURNMENT
Copy: City Clerk, Bulletin Board, File
Get email alerts for Norwich
A daily email when new agendas and minutes are posted.