Committee of the Whole
Regular MeetingOconomowoc, WI · August 11, 2020
Agenda
REVISED
City of Oconomowoc
Committee-Of-The-Whole
Tuesday, August 11, 2020 - 6:00 PM
City Hall – Council Chambers
Notice: If a person with a disability requires that the meeting be accessible or that materials at the
meeting be in accessible format, call the City Clerk at least 48 hours prior to the meeting to request
adequate accommodations. Tel: 569-2186.
1. Call to order and confirmation of appropriate meeting notification
2. Committee Business
a. Workshop/act on City of Oconomowoc Long Term Financial Plan and Capital Projects for
2021-2025
3. Adjourn
________________________________
Diane Coenen, City Clerk
City of Oconomowoc
Notice is hereby given that a majority of the Common Council will be present at the above scheduled meeting to gather information
about a subject over which they have decision-making responsibility. This constitutes a meeting of the Common Council pursuant to
State ex rel. Badke v. Greendale Village Board, 173Wis. 2d 553, 494 N.W. 2d 408 (1993) and must be noticed as such, although the
Common Council will not take any formal action at this meeting.
MEMORANDUM
DEPARTMENT
Date: August 6, 2020
To: Mayor Magnus, City Council
From: Laurie Sullivan, Finance Director
Re: 2021-2025 Capital Plan
RELATES TO THE STRATEGIC PLAN
Strategic Goal- V. Enhance the Effectiveness of our City Government
BACKGROUND
The Draft 2021-2025 Capital Plan workbooks have been distributed. The workbook outlines the capital needs of
the City and the recommended funding sources. Department heads will be at the COW workshop to review the
capital requests and answer questions.
We realize that the capital needs are greater than the funding available. Council and staff will work together to
prioritize the needs and match them with funding sources.
ADDITIONAL ANALYSIS
The 2020 levy budget for Capital is $2,107,403. The goal would be to keep the Levy for Capital relatively steady
over the years. Allowing for a 3% increase in Capital would put a levy funding goal for 2021 at about $2,171,000.
FINANCIAL IMPACT
The expenditures in the current five year plan outpace the funding available. The Council has some funding
options available to explore as outlined in the August 4, 2020 Committee of the Whole packet.
RECOMMENDATION
Review the Capital requests and discuss revisions as needed. Council should come to a consensus to approve a
2021 Capital funding plan, and agree with the 2022-2025 plan in concept.
SUGGESTED MOTION
Motion to adopt the 2021 Capital Plan and insert into the 2021 Annual Budget.
1
2
2021 Proposed Capital Funding Plan
Levy Funded Non-Levy Funded Non-Levy - Reserves
Amt Amt Requested Amt
Dept Type Description Requested Funding Source Dept Type Description Funding Source Dept Type Description Requested Funding Source
Buildings & Grounds Debt Financing Reserves
DPW B&G Transfer Underground fuel pumps to above ground $ 35,000 Levy DPW Infra Expanded Street Plan $ 1,000,000 Debt Electric Equip Electric Meters - New & Replacement $ 50,000 Electric Reserves
DPW B&G Restore Faces on Clock Tower $ 36,000 Levy DPW Infra Reconstruct Thackeray Trail $ 3,960,000 Debt Electric Equip Transformers - New & Replacement $ 350,000 Electric Reserves
Library B&G Book Shelving - Children's $ 31,000 Levy Water Infra Well #8-Pumping Station $ 2,000,000 Water Debt Electric Equip Locator $ 10,000 Electric Reserves
Parks B&G Champion Fields - Lighting $ 110,000 Levy Water Infra *Water Main (Thackeray Trail) $ 900,000 Water Debt Electric Equip Probewell XT3 Transformer Rated Site Tester $ 13,000 Electric Reserves
Parks B&G Landscape Supply Storage $ 90,000 Levy Electric Equip New Meter Test Bench $ 28,000 Electric Reserves
Parks B&G Swim Pier Replacement $ 95,000 Levy Electric Fleet Reel Trailer T23 Replacement $ 25,000 Electric Reserves
Parks B&G Skate Park $ 250,000 Levy Total Debt Funded $ 6,860,000 Electric Fleet Replace Hydro Excvator $ 415,000 Electric Reserves
Electric Fleet Installation of Distribution Capacitors $ 275,000 Electric Reserves
Total Buildings & Grounds $ 647,000 Levy Impact Fees Electric Fleet Small truck for Locating $ 35,000 Electric Reserves
Electric Fleet MultiOne Machine (Replace Skid Steer) $ 57,000 Electric Reserves
Equipment & Vehicles Electric Fleet Convert Dump Bed to Flat Bed Truck 14 $ 7,500 Electric Reserves
FIRE Equip WLFD 2021-2025 CIP $ 365,157 Levy+ Total Impact Fee Funded $ - Electric Fleet 750 gallon Mix System Water tank for directional drill $ 7,800 Electric Reserves
Police Fleet Squad Car Replacement $ 105,000 Levy Electric Infr New Services $ 45,000 Electric Reserves
DPW Fleet Flail Mower $ 175,000 Levy Other Funding Electric Infr Primary Extensions $ 150,000 Electric Reserves
DPW Fleet Pickup Truck 3/4 Ton with Liftgate $ 50,000 Levy Fleet Equip Large Shop Tools $ 30,000 Fleet Reserves Electric Infr Injected Cable Replacement $ 350,000 Electric Reserves
DPW Fleet Skidsteer $ 96,000 Levy Fleet Equip Heavy Duty Diagnostic Scanner $ 13,000 Fleet Reserves Electric Infr Outage Management & System Automation $ 150,000 Electric Reserves
DPW Fleet Plow Truck # 57 $ 220,000 Levy Tech Equip Fire Wall - Sonic $ 40,000 Tech Electric Infr CB84 Forest St Bury Feeder $ 200,000 Electric Reserves
Parks Fleet Polar Trac $ 60,000 Levy Tech Equip IT Upgrades $ 75,000 Tech Electric Infr Jefferson Sub and Wis Sub Secondary Conversion $ 50,000 Electric Reserves
Parks Fleet GMC 3/4 Ton Pickup -replace $ 40,000 Levy Parks B&G Community Center Improvmts/Replcmnts $ 30,000 Reserves Electric Infr South Feeder Ext CB82 and CB74/CB83 $ 275,000 Electric Reserves
WLFD Equip WLFD Capital $ 100,000 Other-Ambo Fund Electric Infr Second Street CB75 Customer Conversion $ 100,000 Electric Reserves
Total Equip & Vehicles $ 1,111,157 Total Other Funded $ 288,000 Electric Infr Collins St & Collins St Lot, CB 76-77 $ 325,000 Electric Reserves
Electric Infr North Feeder Ext CB65 to CB80 $ 340,000 Electric Reserves
Infrastructure Electric Infr Decommission Jefferson Substation $ 30,000 Electric Reserves
DPW Infra DESIGN Street Program $ 50,000 Levy TOTAL NON LEVY FUNDED $ 7,148,000 Electric Infr Pole Inspection and Inventory $ 35,000 Electric Reserves
DPW Infra Street Maintenance Program $ 1,050,000 Levy Electric Infr Pabst Farms Distribution Looping $ 100,000 Electric Reserves
DPW Infra Dam Failure Analysis $ 20,000 Move to Operating Electric Infr Electric & Fiber Optic System Study $ 105,000 Electric Reserves
DPW Infra Peacock Dam Improvements $ 75,000 Levy 2020 Capital Plan Electric Infr Annual Street Project Relocations $ 50,000 Electric Reserves
Parks Infra 525 New Park Improvements $ 150,000 Levy Total City $ 7,426,157 Total Electric Reserves $ 3,578,300
Total Infrastructure $ 1,345,000 Total Utility $ 10,095,300
TOTAL 2020 CAPITAL PLAN: $ 17,521,457 Water Equip GPS and Locator Equipment Replacements $ 24,000 Water Reserves
Water Equip Large Meter Test Equipment $ 20,000 Water Reserves
Other Water Equip Air Conditioner Water SCADA Room $ 8,000 Water Reserves
DPW Other Adaptive Management Program $ 75,000 Levy Water Fleet Small dump truck 4500-5500 series $ 80,000 Water Reserves
Water Infr Water Main (In Conjunction w/ Streets) $ 880,000 Water Reserves
TOTAL LEVY FUNDED $ 3,178,157 ANNUAL RECURRING CAPITAL EXPENSES: Water Infr Distribution Water Mains & Valves $ 20,000 Water Reserves
Street Maintenance Program & Design $ 1,100,000 Water Other Capital Contingency $ 70,000 Water Reserves
Levy Funding Goal =$2,100,000 $ 1,078,157 Over Goal Squad Car replacement $ 101,000 Water Other Outage Management & System Automation $ 75,000 Water Reserves
WLFD Equip $ 400,000 Total Water Reserves $ 1,177,000
Unable to fund from 2021 Levy Funding Goal #NAME? Adaptive Management Program $ 75,000
Levy funding #NAME? Plow Truck replacement $ 220,000 WWTP Equip Pump station-Submersible pumps $ 35,000 WWTP Reserves
Amount Over/(Under) #NAME? WWTP Infr Metering Station Upgrades $ 30,000 WWTP Reserves
Total Annual Expenses $ 1,896,000 WWTP Infr Sewer Main (In Conjunction w/ Streets) $ 350,000 WWTP Reserves
Total Levy Funding Available $ 2,100,000 WWTP Infr Treatment Plant Upgrades $ 1,700,000 WWTP Reserves
WWTP Infr Treatment Plant Upgrades-HVAC $ 10,000 WWTP Reserves
Remaining Levy Available after Recurring Expenses $ 204,000 WWTP Infr Lift Station Pavement Work $ 100,000 WWTP Reserves
WWTP Other Wastewater GIS $ 100,000 WWTP Reserves
WWTP Other Lift Station SCADA System $ 80,000 WWTP Reserves
WWTP Other Wastewater Laboratory Software $ 35,000 WWTP Reserves
Total WasteWater Reserves $ 2,440,000
FUNDING OPPORTUNITIES:
*Public Fire Protection Charges $ 815,000 Allocate portions to both Capital and Operating Budgets
*Debt program for Street Maintenance $ 1,000,000 10-15 yr Revolving Debt Program TOTAL FUNDED BY RESERVES $ 7,195,300
*Spend Down of Fund Balance $4,300,000 One-Time Funding
*Unused Levy Funds from 2019 & 2020 $ 144,000 One-Time Funding
3
2020 Capital Funding Plan
Levy Funded Non-Levy Funded Non-Levy - Reserves
Amt Amt Amt
Dept Type Description Requested Funding Source Dept Type Description Requested Funding Source Dept Type Description Requested Funding Source
Buildings & Grounds Debt Financing Reserves
Parks B&G *Roosevelt Park- Parking lot $ 25,835 Levy DPW Infra Expanded Street Plan $ 1,000,000 Debt Electric Equip Electric Meters - New & Replacement $ 50,000 Electric Reserves
Library B&G Sliding Door Replacement $ 36,000 Levy DPW Infra *Forest Street $ 600,000 Debt Electric Equip Transformers - New & Replacement $ 175,000 Electric Reserves
Parks B&G Chaffee Road Park $ 30,000 Levy DPW Infra *Forest Street Storm Water $ 310,000 Debt Electric Fleet Reel Trailer T22 Replacement $ 17,000 Electric Reserves
Total Buildings & Grounds $ 91,835 Water Infra *Water Main (In Conjunction w/ Streets) $ 1,135,000 Water Debt Electric Fleet #56 Bobcat Skid Steer $ 83,000 Electric Reserves
Parks B&G Tennis Courts - Blain Street Park $ 120,000 Debt Electric Fleet Cable installation Boring Rig & Equp $ 400,000 Electric Reserves
Equipment & Vehicles Total Debt Funded $ 3,165,000 Electric Infr New Services $ 45,000 Electric Reserves
Police Equip Taser Replacement $ 20,000 Levy Electric Infr Jefferson Sub and Wis Sub Secondary Conversion $ 50,000 Electric Reserves
FIRE Equip WLFD 2019-2023 CIP $ 326,568 Levy Impact Fees Electric Infr Primary Extensions $ 100,000 Electric Reserves
Parks Fleet Parks Utility Vehicle $ 25,000 Levy DPW Infr Thackeray Trail-Extension $ 1,231,500 Impact Fee Electric Infr Wisconsin Substaton circuit conversion $ 150,000 Electric Reserves
Parks Fleet Truck #90 Replacement $ 35,000 Levy Water Infr **Well #8 Pumping Station-Design $ 83,000 Impact Fee Electric Infr CB86 Feeder Replacement-N Lapham St $ 200,000 Electric Reserves
Police Fleet Squad Car Replacement $ 119,000 Levy Total Impact Fee Funded $ 1,314,500 Electric Infr Outage Management & System Automation $ 282,000 Electric Reserves
DPW Fleet Truck w/ Plow, Wing, Sander #57 $ 230,000 Levy Electric Infr CB84 Forest St Bury Feeder $ 300,000 Electric Reserves
Total Equipment & Vehicles $ 755,568 TID Funded Electric Infr Southwood drive annexation $ 350,000 Electric Reserves
Parks Initiative Boat Launch Development - City Beach $ 125,000 TID Electric Infr Injected Cable Replacement $ 435,000 Electric Reserves
Infrastructure Total TID Funded $ 125,000 Electric Other Capital Contingency $ 150,000 Electric Reserves
DPW Infra Bridges-2020 Rehab program $ 110,000 Levy Total Electric Reserves $ 2,787,000
DPW Infra Design Street Program $ 50,000 Levy Other Funding
DPW Infra Street Maintenance Program $ 1,025,000 Levy
Total Infrastructure $ 1,185,000 DPW Infra *Forest Street Storm Water $ 150,000 Other - DNR Grant Water Equip Water Meters $ 40,000 Water Reserves
DPW Infra *Forest Street Storm Water $ 200,000 Other- Watershed Water Fleet Valve Operations Trailer $ 80,000 Water Reserves
Other WLFD Equip WLFD Capital $ 150,000 Other-Ambo Fund Water Infr Distribution Water Mains & Valves $ 20,000 Water Reserves
DPW Other Adaptive Management Program $ 75,000 Levy Total Other Funded $ 500,000 Water Infr **Well #8 - Drill & Cap $ 210,000 Water Reserves
Water Infr Well #7 Repair Cap $ 25,000 Water Reserves
TOTAL LEVY FUNDED $ 2,107,403 TOTAL NON LEVY FUNDED $ 5,104,500 Water Infr Booster Station Pump Replacement $ 45,000 Water Reserves
Water Other Capital Contingency $ 50,000 Water Reserves
Water Other Outage Management & System Automation $ 70,000 Water Reserves
Removed from 2020 to meet Levy Funding Goal Coming up in 2021 Total Water Reserves $ 540,000
Library B&G Book Shelving - Children's $ 45,000 Levy
DPW B&G Window Replacement $ 110,000 Levy DPW Infra Reconstruct Existing Thackeray Trail $ 3,960,000 Debt-2021
DPW Fleet Flail Mower $ 165,000 Levy Water Infra Reconstruct Existing Thackeray Trail $ 535,340 Debt-2021 WWTP Equip Pump station-Submersible pumps $ 35,000 WWTP Reserves
Parks B&G Champion Fields-Concession/Restroom $ 250,000 Levy WWTP Infra Reconstruct Existing Thackeray Trail $ 350,000 WWTP -2021 WWTP Fleet Truck 17 - Jet Vac $ 450,000 WWTP Reserves
Parks B&G Fencing - Champion Fields #2 $ 65,000 Levy WWTP Infr Treatment Plant Upgrades-HVAC $ 10,000 WWTP Reserves
Water Infra Well #8 - Pumping Station $ 2,000,000 Debt-2021 WWTP Infr Metering Station Upgrades $ 30,000 WWTP Reserves
Total removed from 2020 $ 635,000 WWTP Infr WWTP Pavement Overlay and replacement $ 100,000 WWTP Reserves
WWTP Infr Sewer Main (In Conjunction w/ Streets) $ 250,000 WWTP Reserves
WWTP Infr Air Flotation Drive unit replacement $17,000 WWTP Reserves
WWTP Infr Treatment Plant Upgrades $ 1,500,000 WWTP Reserves
WWTP Other SCADA Sytem upgrades $ 50,000 WWTP Reserves
KEY WWTP Other Wastewater GIS $ 75,000 WWTP Reserves
All related to Well #8 $ 2,293,000 Total WasteWater Reserves $ 2,517,000
All releated to Forest Street Storm Water $ 3,695,835
All related to Reconstruction of Existing Thackeray Trail $ 4,845,340 Tech Equip SAN Expansion $ 40,000 Tech Reserves
All Related to WLFD 2020 Capital Request $ 476,568 Tech Other Software- Open Gov $ 35,000 Tech Reserves
Changes to plan Total Tech Reserves $ 75,000
TOTAL FUNDED BY RESERVES $ 5,919,000
TOTAL 2020 CAPITAL PLAN: $ 13,130,903
4
DPW19 GF 2 DPW Infra Debt
DPW21 GF 2 DPW Infra Debt
Police2 GF 1 Police Fleet Levy
DPW1 GF 1 DPW Other Levy
DPW2 GF 2 DPW Fleet Levy
DPW3 GF 2 DPW Fleet Levy
DPW4 GF 2 DPW Fleet Levy
DPW5 GF 2 DPW Fleet Levy
DPW17 GF 2 DPW Infra Levy
DPW18 GF 2 DPW Infra Levy
DPW23 GF 2 DPW Infra Levy
DPW24 GF 2 DPW Infra Levy
DPW29 GF 2 DPW B&G Levy
DPW32 GF 5 DPW B&G Levy
Library1 GF 4 Library B&G Levy
Parks3 GF 4 Parks B&G Levy
Parks4 GF 4 Parks B&G Levy
Parks15 GF 4 Parks B&G Levy
Parks18 GF 4 Parks B&G Levy
Parks22 GF 4 Parks B&G Levy
Parks23 GF 4 Parks Fleet Levy
Parks24 GF 4 Parks Fleet Levy
??? GF 1 FIRE Equip Levy+
Fleet1 GF/Utilities 5 Fleet Equip Other
Fleet2 GF/Utilities 5 Fleet Equip Other
Tech Tech 5 Tech Equip Other
Tech Tech 5 Tech Equip Other
Finance GF 5 Finance Other
Totals
5
Expanded Street Plan $ 1,000,000
Reconstruct Existing Thackeray Trail $ 3,960,000
Squad Car Replacement $ 105,000
Adaptive Management Program $ 75,000
Flail Mower $ 175,000
Pickup Truck 3/4 Ton with Liftgate $ 50,000
Skidsteer $ 96,000
Plow Truck # 57 $ 220,000
DESIGN Street Program $ 50,000
Street Maintenance Program $ 1,050,000
Dam Failure Analysis $ 20,000
Peacock Dam Improvements $ 75,000
Transfer Underground fuel pumps to above ground $ 35,000
Restore Faces on Clock Tower $ 36,000
Book Shelving - Children's $ 31,000
Community Center Improvmts/Replcmnts $ 30,000
Champion Fields - Lighting $ 110,000
Landscape Supply Storage $ 90,000
Swim Pier Replacement $ 95,000
Skate Park $ 250,000
Polar Trac $ 60,000
GMC 3/4 Ton Pickup -replace $ 50,000
WLFD 2021-2025 CIP $ 465,157
Large Shop Tools $ 30,000
Heavy Duty Diagnostic Scanner $ 13,000
Fire Wall - Sonic $ 40,000
IT Upgrades $ 50,000
Assessment Revaluation $ 150,000
$ 8,411,157