Public Services
Regular MeetingOconomowoc, WI · February 21, 2023
Minutes
City of Oconomowoc
Public Services Committee Meeting Minutes
February 21, 2023 - 7:15 PM
Aldermen Present: Lou Kowieski, Kevin Ellis, Matt Mulder
Also Present: Robert Magnus, Karen Spiegelberg, Charles Schellpeper, Chris Douglas, Jennifer Aultman Kloth,
Lucas Caine, Diane Coenen, Robert Duffy, Mark Frye, Jason Herzog, James Pfister, Laurie Sullivan-Murray
Chairman Kowieski called the Public Services Committee Meeting to order at 7:13 PM.
Call to order and confirmation of appropriate meeting notification
Committee Business
a. Consider/recommend Resolution 23-R3102 Approving 2022 Street Construction Contract
Overages
Herzog passed out a revised memo and resolution to the Committee going over the additional
analysis section of the memo. The Committee requested that moving forward they would like
updates on street projects throughout the construction and asked staff to take into consideration
when budgeting for older streets that unforeseen problems may occur and should be factored in.
Motion to recommend Resolution 23-R3102 approving 2022 Street Construction Contract overages
made by Mulder and seconded by Ellis.
Motion carried 3-0-0.
Adjourn
Motion to adjourn made by Mulder and seconded by Ellis.
Motion carried 3-0-0.
The meeting adjourned at 7:26 PM.
__________________________________
Minutes taken by Diane Coenen, City Clerk
Alderman Ellis, Secretary
1
Public Services Committee - February 21, 2023
Agenda
City of Oconomowoc
Public Services Committee
Aldermen: Kowieski, Chairman / Ellis, Secy / Mulder
Tuesday, February 21, 2023 - 7:15 PM
City Hall - Conference Room 3
174 E. Wisconsin Ave. Oconomowoc, WI 53066
(or immediately following Finance Committee)
Notice: If a person with a disability requires that the meeting be accessible or that materials at the
meeting be in accessible format, call the City Clerk at least 48 hours prior to the meeting to request
adequate accommodations. Tel: (262) 569-2186.
1. Call to order and confirmation of appropriate meeting notification
2. Committee Business
a. Consider/recommend Resolution 23-R3102 Approving 2022 Street Construction Contract
Overages
3. Adjourn
________________________________
Diane Coenen, City Clerk
City of Oconomowoc
Notice is hereby given that a majority of the Common Council will be present at the above scheduled meeting to gather information
about a subject over which they have decision-making responsibility. This constitutes a meeting of the Common Council pursuant to
State ex rel. Badke v. Greendale Village Board, 173Wis. 2d 553, 494 N.W. 2d 408 (1993) and must be noticed as such, although the
Common Council will not take any formal action at this meeting.
1
MEMORANDUM
PUBLIC WORKS
Date: February 21, 2023
To: Mayor, Common Council and City Administrator
From: Jason Herzog, Director of Public Works
Re: 2022 Street Construction exceeding 10% contingency
RELATES TO THE STRATEGIC PLAN
Strategic Goal II Improve and Maintain Our Infrastructure/Facilities; B Maintain our Existing Infrastructure
BACKGROUND
On April 5, 2022 the Common Council approved the construction contract with Wolf Paving for reconstructing the
intersection of Silver Lake St & Summit Ave, repaving Hidden Ridge subdivision, Harvard St, and miscellaneous
sanitary sewer improvements.
There were major water and sanitary improvements necessary to complete before each of the pavements could
be finished and a full signal replacement at the Silver Lake & Summit Ave intersection. The utility sub-contractor,
and many other contractors, dealt with supply issues getting utility parts, but ultimately completed the work as
proposed.
ADDITIONAL ANALYSIS
The completion of the construction resulted in a variety of unforeseen conditions increasing the scope of work and
costs. Listed below are a few of the issues that were encountered.
All of the street projects include estimated quantities of subsurface work that are based on past projects of similar
conditions. This year, each of the project locations resulted in higher-than-average subbase work. Major
stabilization to the subbase in the Hidden Ridge Subdivision was necessary.
Harvard St was proposed to only have minimal work completed outside of the pavement replacement scope. Due
to the severe condition of the curb, driveways and pavement base the street rehab required it to be fully dug out
and replaced.
Additional storm water work on High St was necessary to fix drainage issues that were identified outside of the
project scope.
Additional utility work was added throughout the project found during field inspections.
1
2
FINANCIAL IMPACT
The contract was awarded for $2,737,244.92 with a 10% approved contingency totaling an amount of
$3,010,969.41. The final construction cost $3,230,000.00. The increased cost allocations are all within the 2022
budget amounts
ORIGINAL ALLOWABLE (10% ) OVER THE 10%
BUDGET BUDGET FINAL DIFF
STREETS $ 1,462,731.26 $ 1,609,004.39 $ 1,750,000.00 $ (140,995.61)
WWU $ 618,865.31 $ 680,751.84 $ 680,000.00
WAT $ 655,648.35 $ 721,213.19 $ 800,000.00 $ (78,786.81)
$ 2,737,244.92 $ 3,010,969.41 $ 3,230,000.00 $ (219,782.42)
Funds required from each account exceeding the allowable approved contingency are shown below.
Streets 408.505.5300.820 422501.03 $140,995.61
Wastewater 601.573.7000.820.122002 Still within contingency
Water 602.573.7000.820.222009 $78,786.81
All these extra funds suggested to cover the overage cost difference are within the amounts budgeted in 2022.
We are within the budget amount but exceed the approved construction cost.
RECOMMENDATION
Motion to recommend to the Common Council to approve the allowable funding to $3,230,000.00 to fund the
construction cost overages.
SUGGESTED MOTION
Suggested Common Council Motion: Motion to adopt Resolution 23-R3102.
V:\City Projects\Streets\2022 Streets\Construction Payments and Change Orders\Change Orders\Background Memo for 2022 Street Construction
exceeding 10% contingency.docx
2
3
RESOLUTION NO. 23-R3102
RESOLUTION APPROVING 2022 STREET CONSTRUCTION CONTRACT OVERAGES
WHEREAS, the City of Oconomowoc 2022 budget provides for street and utility
improvements to public infrastructure: and
WHEREAS, Wolf Paving was the construction contractor; and
WHEREAS, Final Construction costs exceed the approved contingency for contracted
work; and
WHEREAS, Department of Public Works staff and the Public Services Committee
recommend that the overages be included to the construction contract with approved
respected budget.
NOW THEREFORE, BE IT HEREBY RESOLVED that $219,782.42 be added to the 2022
Street Construction Contract with Wolf Paving is hereby accepted for total amount of
$3,230,000.00.
BE IT FURTHER RESOLVED that these additional funds be transferred into these
accounts:
Streets 408.505.5300.820 422501.03 $140,995.61
Water 602.573.7000.820.222009 $ 78,786.81
DATED: ____________________ CITY OF OCONOMOWOC
By: ______________________________
Robert P. Magnus, Mayor
ATTEST:
___________________________
Diane Coenen, Clerk
V:\City Projects\Streets\2022 Streets\Construction Payments and Change Orders\Change Orders\Resolution 23-R3102.docx
4