1. Call to Order
Chairman Hale called the Airport Commission meeting to order at 5:00 PM at the Owatonna
Degner Regional Airport.
2. Roll Call
Attendance
Todd Hale Chairman
James Keltgen Vice Chairman
Greg Krueger Commissioner
Justin Lindee Commissioner
Paula Snitker Commissioner
Sharon West Commissioner
Dave Beaver Airport Manager
Visitors
Ron Roetzel Bolton & Menk, Inc.
3. Approval of Agenda
Chairman Hale presented the agenda and Commissioner Keltgen made a motion to approve
and Commissioner West seconded the motion. The motion was approved.
4. Minutes
Commissioner West made a motion to approve the minutes from the October 11, 2018
Airport Commission meeting and Commissioner Krueger seconded the motion. The motion
was approved.
5. Action Items
Chairman Reports
There were no chairman reports.
Staff Reports
Airport Manager Beaver reported on airport activities and presented the fuel volumes
dispensed to date. Mr. Beaver reported that business traffic has been brisk for the month of
October and fuel volumes comparable to same time frame last year.
-MnDOT Inspection
Mr. Beaver reported that an on-site inspection of the airport was conducted by
representatives of MnDOT Office of Aeronautics. This is done is coordination with the
FAA 5010 Inspection Program conducted approximately every three years. Items inspected
include current physical condition and status of the facility, visual landing aids, and
obstructions and are intended to enhance safety. Data is built into directories, charts, and
procedure publications. Mr. Beaver explained that the inspector identified three areas that
either crop or brush was in an obstruction free area or slightly beyond the allowable crop
distances to runways. Mr. Beaver reported that the brush was already scheduled for removal
once the crop is out of the field and now that the crop is out the issue will be resolved.
Appropriate distances from runway to crop line will be remarked for the farmer next spring.
The inspector also wanted an additional fuel shut off sign near the jet pumps. Mr. Beaver
reported that all items have been or are in the process of being addressed. Mr. Beaver added
that overall, the inspector appeared to be pleased with the facility finding only minor issues
to address.
-Digital Advertising
Regarding marketing efforts, Mr. Beaver presented the current digital advertising package
analytics. Mr. Beaver reported that the report indicates that over the three month period, ads
performed well with a higher than average click through rate. After discussion, there was
general agreement that the digital ad campaign should continue and be coupled with a
review of website analytics to help gage ongoing effectiveness. Mr. Beaver will work with
the city technology department to obtain more detailed analytics data.
-FAA Supplemental Appropriation Funding Request
Airport Manager Beaver explained that the FAA has been authorized to spend an additional
$1 billion in supplemental appropriation for airports in the National Plan of Integrated
Airport System (NPIAS) based on eligibility. The new legislation provides that certain
airports classified as regional, local, or basic airports not located within certain metropolitan
statistical areas will receive priority consideration for one hundred percent federal Airport
Improvement Program (AIP) funding. The Owatonna airport does not qualify for priority
consideration but is still eligible for obtaining funds under the appropriation.
Mr. Beaver explained that three projects that are identified on the airport Capital
Improvement Program (CIP) have been submitted for the supplemental appropriation
funding. These projects include the main aircraft parking apron reconstruction, runway 30
selected concrete panel repair and grooving, and development of the south quadrant building
area and taxiway. There was a brief discussion regarding these projects. Ron Roetzel with
the airport engineering firm, Bolton and Menk, anticipates a large nationwide demand for
this special funding and projects should be prioritized based on FAA discretionary funding
guidelines including safety and runway development needs. Mr. Beaver will update the
commission on award timeline as information becomes available.
-Bi-Fold Hangar Door Project
Ron Roetzel with the airport engineering firm, Bolton and Menk, Inc. provided an update on
the airport bi-fold door replacement project. Bolton and Menk has completed much of the
evaluation of the existing hangar building and the required structural engineering for the
installation of new large hangar doors. Mr. Roetzel explained that a number of qualified
companies have submitted full or partial quotes for the work. There was a general
discussion regarding the project and types of hangar doors available. Mr. Beaver reported
that MnDOT grant participation is anticipated for this project.
6. Adjournment
The Airport Commission meeting was adjourned at 6:05 PM with a motion made by
Commissioner Keltgen and seconded by Commissioner Krueger.
Agenda
OWATONNA AIRPORT COMMISSION AGENDA
5:00 p.m. Nov 18, 2018 - Owatonna Degner Regional Airport
AIRPORT COMMISSION:
Todd Hale Chairman
Tom Harrison Commissioner
James Keltgen Vice Chairman
Greg Krueger Commissioner
Justin Lindee Commissioner
Paula Snitker Commissioner
Sharon West Commissioner
Dave Beaver Airport Manager
AGENDA
1. Call to Order
2. Roll Call
3. Approval of Agenda
4. Minutes: Approval of the October 9, 2018 Airport Commission meeting minutes.
5. Action Items
a. Chairman Reports
b. Staff Reports
1. MnDOT Inspection
2. Digital Advertising
3. FAA Supplemental Appropriation Funding Request
4. Bi-Fold Hangar Door Project
6. Adjournment