Public Works
Regular MeetingRochester, NH · February 19, 2026
Minutes
Public Works and Buildings Committee
City Hall Council Chambers
Meeting Minutes
February 19, 2026
6:00PM
MEMBERS PRESENT
Chairman - Councilor Larochelle
Vice Chairman-Councilor Fitzpatrick
Councilor David Walker
Councilor Hamann
Councilor Sullivan
Mayor Grassie
MEMBERS ABSENT
OTHERS PRESENT
Peter C. Nourse PE, Director of City Service
Gretchen Young, P.E., Deputy Director – Technical Services
Jenn Marsh, Deputy Director – Operations and Administration
Dan Camera, GIS
Ian Rohrbacher, Superintendent of the Water Treatment Facility
Mark Sullivan, Finance Director
Rick Davee, Wright-Pierce
Jason Gllant, Wright-Pierce
Sam Foritier, CMA Engineers
Phil Corbent, CMA
Sam Foriter, CMA Engineers
MINUTES
Councilor Larochelle called the Public Works and Building Committee to order at 6 PM
1. Roll Call
Ms. Marsh took the call attendance. Councilor Larochelle, Councilor Fitzpatrick, Mayor
Grassie, Councilor Walker, Councilor Hamann and Councilor Sullivan were present for
the roll call.
2. Approval January 19, 2026, PWC Minutes
Councilor Walker made a motion to accept the minutes of January 15, 2026, meeting as
presented. Councilor Sullivan seconded the motion. The motion passed unanimously.
3. Public Input
There were no members of the public present for public input.
4. Drinking Water Project Updates
Round Pond Reservoir Augmentation
Public Works & Building Committee Meeting Minutes
February 19, 2026
Mr. Nourse gave an overview of the city’s drinking water projects. The Round Pond
Augmentation is the first project which will raise the level of the reservoir from 390 to 398
above sea level, tripling its volume. He explained that with both population and
commercial growth that the need for this improvement is necessary. He also noted that the
draught of 2016 almost drained Round Pond.
Mr. Nourse stated that since 2014 they have worked toward the goal of conducting
extensive environmental impact study to retain rights to the entire shoreline of the
reservoir, now designing impoundment structures and starting the permitting process. Rick
Davee of Wright-Pierce was present with a presentation of the drinking water projects.
(see attached). Mr. Davee noted that the primary source of water for the City of Rochester
is surface water and this project will enable the city to store more water in Round Pond.
Mr. Davee said that the permitting is the next step. The permitting schedule is currently as
follows: December 29, 2026 submit the geotechnical report and prepare the abutter
shoreland plans, January 5, 2026 to submit abutter shoreland plans to City for review,
January 15, 2026 to submit dam design alternatives analysis, January 1, 12-26, 2026
schedule individual correspondence/meetings with abutters to review plans, and February
2026 finalize draft site specific soil map and report and submit request for project review.
Councilor Sullivan asked for the materials of the dams. Mr. Davee confirmed there are
two dams and each is different; one is concrete and the other is a mix of earth and concrete.
Tufts Pond Dam Rehabilitation
Mr. Nourse introduced The Tufts Pond Dam Rehabilitation project to the Committee.
Mr. Nourse noted this reservoir holds approximately 84 million gallons of drinking water.
It was built in 1927 and has had some minor repairs but no major rehabilitation since it’s
been built. Jason Gallant of Wright-Pierce presented this project (see attached). Mr.
Gallant stated this project will look at specific repairs that will be made including repair
to the left and right sides, spillway and low-level outlet, left side training was and to the
safety accessway.
Berry’s River Impoundment Dam
Berry River Impoundment Dam (NHDES dam 224.11) is a non-menace dam (reclassified
from significant hazard in 2009, dam was downgraded to poor condition in 2007 due to
cracks on several occasions along the dam resulting leakage and loss of water. Mr.
Gallant continued with discussion on this project and noted they will look at structural
upgrades and reconstruction of the Berry’s River Impoundment Dam, which is currently
in early design stages. The most recent repairs were conducted in 2007 under emergency
authorization. The repairs were interim and intended to be augmented with permanent
repairs or reconstruction in three-to-five year timeframe and valve maintenance
completed in 2007. Dam has been in good condition since repairs but not suitable for
further rehabilitation focus is reconstruction this is currently in study phase for structural
upgrades at intake and dam and raw water transmission redundancy. Mr. Gallant
reviewed the construction costs of the project. Tufts Pond Reservoir Dam Repairs $1.65-
Public Works & Building Committee Meeting Minutes
February 19, 2026
1.93 million, Upper Raw Water Transmission Main Construction $1.30-1.50 million,
Berry’s River Impoundment Dam Reconstruction $3 -$4.50 million the total for all three
projects is between $5.95-$7.93 million.
Mr. Gallant said that the project’s necessity is maintaining state of good repair for water
storage and transmission infrastructure and will provide needed drinking water for the
City of Rochester for the next 50-year period. He noted prior repairs have exceeded their
useful service life and these projects allow the city to proactively our drinking water
system.
Councilor Fitzpatrick commended the city for its impressive drinking water system.
Councilor Hamann asked for the timeframe of the project. Mr. Gallant said The Berry’s
River project would be one construction season project. Councilor Larochelle said as a
State representative, Rochester has set a good example at the state level for their
wastewater and water systems. Mr. Nourse stated that the prices presented were current
prices and could ultimately cost more. Councilor Walker asked about the wells on
Salmon Falls Road and if they were viable. Mr. Nourse stated there were 12 sites they
were looking at however all were expensive. Mr. Rohrbacher said they investigated
many sites, and they ranged from 100 to 300 gallons per minute but were million dollars
a well to treat. Councilor LaRochelle asked about PFAS in drinking water. Mr. Nourse
stated they follow the Environmental Protection Agency and are in compliance with all
regulations. Ms. Young stated that it makes sense to use the reservoir and Berry River
and it is critical to keep it in good shape.
5. Pavement Preservation Program Overview
Mr. Nourse gave the committee an overview of the pavement preservation program. He
stated the city revised their pavement program over a decade ago and started using CMA
as a more cost effective and efficient way to analyze the 152 miles of roads in Rochester.
Phil Corbet and Sam Foriter from CMA Engineers were present to go over the pavement
preservation program (see attached presentation). CMA presented a presentation on the
pavement preservation program to familiarize the committee with how the program works.
Mr. Corbet said that they get ratings for the condition of the roads they use in the pavement
condition index (PCI), this is based on surface distress and ride quality. Mr. Corbet said
that the Pavement Condition Index (PCI) method was used in accordance with the
American Society for Testing and Materials (ASTM) D6433 to assess the condition of the
City’s pavements. The city-wide average PCI was=61, Target range 70-80. Rochester
measures pavement conditions by an automated survey by IMS using laser-based
technology. CMA analysis the roads every five years.
The Committee discussed the amount of funding the paving program has received in recent
years. Mr. Nourse stated he typically requests $2 million with cuts usually made to $1.5
to $1 million.
Public Works & Building Committee Meeting Minutes
February 19, 2026
Mr. Nourse stated the $3,000,000 in pavement funding is needed to maintain the current
PCI of 61, and not 70-80. Mr. Nourse also stated that because the city has not funded the
program to that extend in the past that they are behind on maintaining the 61 PCI. Mr.
Nourse stated that once roads are paved, they typically start cracking within one to two
years. He noted that if we used a deeper pavement like the State of NH then the cost of
paving would increase but the roads would deteriorate at a slower rate. Rochester’s
standard is 4-inches of asphalt, and the State has an 11-inches standard with added
curbing and drainage.
6. Northridge Development Agreement: Finance Director
Director of Finance, Mark Sullivan, was present to give an update on Northridge
Development, which is located north of Tractor Supply, on Route 11. His presentation
attached shows three lots that make up what Waterstone Development calls Northridge
Development and are looking to purchase in the next year. Mr. Sullivan said Waterstone
is bringing their proposal to the Public Works Committee and is also planning on attending
the Finance and Planning Committee’s as well.
Mr. Sullivan noted the plans are at preliminary phases, but he wanted to bring the
committee’s attention to it now since it’s a large development. There would be
approximately three phases which would include medical, residential, commercial and
entertainment uses. This is also located in an aquifer protection zone, and the entire parcel
is part of the Tax Increment Financing District (TIF). Councilor Hamann asked if there
were any discussions on expanding Two Rod Road, in which Mr. Mark Sullivan answered
no, not at this time. Councilor LaRochelle asked if there was a master plan that included
Two Rod Road at one time. Some discussion was had were Councilors believed there may
have been at one time, and they will follow up to see if they can find said plans.
7. Veterans Park Plaque
Mr. Nourse stated the City Council approved the removal of the Shaw Park plaque and
renaming the park to Veteran’s Park. Mr. Nourse asked for the sense of the committee on
how the new plaque should look. Councilor Sullivan suggested asking the Veteran’s
Council for their opinion. The census of the committee is to move forward and have DPW
request input from the Veteran’s Committee.
8. Other
Little Falls Bridge Road Maintenance
Mr. Nourse noted there will be upcoming maintenance on Little Falls Road Bridge and that
the message boards will be going out soon. The Bridge will be closed starting March 19,
2026, through April 30, 2026, the police and Fire Department are aware of this closure.
This work is scheduled to be completed before the Route 11 project begins in May of 2026.
Copy of Slides from Presentation
Mayor Grassie requested a copy of the slides from tonight’s presentation.
Sig Saur Project Update
Public Works & Building Committee Meeting Minutes
February 19, 2026
Councilor Hamann asked when the Sig Saur Project was going to begin. Mr. Nourse stated
that due to some process issues on Sig Sauer’s side, the bid was held up and will most
likely go out in April of 2026.
Meeting adjourned at 7:42 PM
Minutes respectfully submitted by Laura McDormand, Admin. Services & Utility Billing
Supervisor
Public Works & Building Committee Meeting Minutes
February 19, 2026
Surface Water Supply Expansion Project
Rochester, New Hampshire
February 2026
Richard Davee, PE
Wright-Pierce
Berry’s River Watershed
2
Major Impoundment
Round Pond
• Round Pond is located entirely in Barrington, approximately 3,000 feet
south of the Rochester Reservoir
• Largest of the reservoirs (Tuffs Pond, Rochester Reservoir, Round Pond)
• It can either receive water from Berry's River through the diversion
pipeline or discharge water to the Rochester Reservoir
• Filled primarily during the spring melt and rainy seasons
3
Supply Capacities (Firm Yield)
Rochester’s Reservoirs – Existing Elevations
Reservoir Full Pond Elevation Firm Yield (mgd)
Tufts Pond Reservoir 482 ft. 1 mgd
Berry River Dam Impoundment 401 ft. -0-
Rochester Reservoir 375 ft. 0.25 mgd
Round Pond Reservoir 390 ft. 1.0 mgd
Total 2.25 mgd
• Firm yields of Rochester’s existing reservoirs (existing elevations) subject to stream flow
agreement w/ NHDES
4
Existing & Projected 40-Year Demands with Alternative Firm Yields
5.00
Annual FW ADD (from Records)
4.50
Projected FW ADD (from population and GPCD)
Firm Yield = 4.40 MGD
4.00 Annual FW MDD (from Records)
Million Gallons per Day, MGD
Firm Yield = 3.89 MGD
Projected FW MDD (from 5-Yr Avg Ratio MDD/ADD)
3.50
Annual RW MDD (from Records)
3.00
Projected Future RW MDD (from 5-Yr Avg Ratio RW
ADD/RW MDD)
2.50 Firm Yield without increase to Round Pond elevation, and
with 2 cfs downstream req't
Firm Yield = 2.25 MGD Firm Yield with 8-Ft increase to Round Pond elevation, and
2.00 with 2 cfs downstream flow req't
Firm Yield without pond elevation increase and without 2
cfs minimum downstreatm flow requirement
1.50
5
Project Need
• Raw Water Supply – Berry’s River , One Well w/ Limited Capacity
• Prior to 2008 Berry’s River Safe Yield 4.4 MGD
o Post 2008 (Agreed Minimum Stream Flow) Safe Yield 2.25 MGD
• 2040: Average Day Demand 2.2 MGD, Peak Daily Demand 3.7 MGD,
Maximum Daily WTP Output > 6 MGD
• Multiple Studies have Shown Limited Groundwater Availability
• Rasing Round Pond 8 feet can increase Safe Yield by1.6 MGD to a
total of 3.8 MGD
6
Round Pond 2016
7
Supply Capacity (Firm Yields) of Rochester’s Reservoirs
Round Pond Reservoir Elevation Increased
Reservoir Full Pond Elevation Firm Yield (mgd)
Tufts Pond Reservoir 482 ft. 1 mgd
Berry River Dam Impoundment 401 ft. -0-
Rochester Reservoir 375 ft. 0.25 mgd
Round Pond Reservoir 398 ft. 2.64 mgd
Total 3.89 mgd
• Firm yields of Rochester’s reservoirs (Round Pond Reservoir elevation increased to 398 ft)
subject to minimum stream flow requirements
• Increasing the water elevation Round Pond Reservoir to El 398 bring the Firm Yield of the
surface Water Supply close to Firm Yield (3.89MGD) w/out minimum stream flow requirements
8
Future Water Supply Management
• Raising Round Pond’s elevation could almost double storage with
minimal impact
• Harvest a greater abundance of river flow
• Periods of >50 cfs (22500 gpm, 32MGD) in river that we could store
for the summer months
• Help to improve and manage downstream flows
• Close diversion valve and draw down Round Pound, maintaining
river flow
• Prepares us for impact of in-stream flow regulations
9
Project Status
• Substantial Field Work has been completed:
o Survey
o Wetlands Delineation
o Vernal Pool Assessment
o Endangered Species Identification
• Preliminary Dam Design
• Easements Obtained from Seven (7)
Private Property Owners
10
Preliminary Dam Design
11
Preliminary Dam Design
12
Estimated Construction Costs
North and South Dam - $10 Mil
Offsite Improvements - $2 Mil
13
Permitting Scope of Work
Impact Assessment
• Set the baseline with existing data
• Comparative analysis of existing pond elevation to 8-foot increase
• Used the mapped areas, habitat types, and species data we had to develop a baseline scenario
• Assessed the potential for impact to the mapped areas, habitat types, and species data in terms of
level of impact
• Analyzed the “after” scenario to identify “new” extents of habitat types, in terms of increases and
decreases
14
Rare Species
In Area of Inundation
• Blanding’s = State Endangered
• Records known from Round Pond and “Pond C”
• Scrub-Shrub, Aquatic Bed, Marshes, and Vernal
Pools provide important habitats
• Fish and Game requested Trapping
15
Results
Rare Species
• Turtle trapping was
completed during 2015
& 2016 according to
regional protocols
View of Turtle Trap in “Pond C”
16
Results
BL001 “Dragon”
Captured in Pond 3
17
Transmitter Attachment
18
Results
BL002 “Storm”
Captured in Pond 3 – Near BL001
19
Overall Results
• Project is expected to maintain large portions of most
habitats (except vernal pools)
• Maintaining high habitat diversity serves to maintain high
wildlife diversity
• 11 additional vernal pools were observed nearby outside
of inundation area
• Project creates 22.25 acres of wetland and open water
habitat
• Fish and Game will expect minimization of potential
habitat changes to Blanding’s turtle habitats
20
Permitting Schedule
Round Pond Reservoir
Plan development for abutting parcels Ongoing
DECEMBER 2026
Geotechnical Report 12/29/2026
Prepare abutter shoreland plans
JANUARY 2026
Submit abutter shoreland plans to City for review 1/5/2026
Submit Dam Design Alternatives Analysis to City 1/15/2026
Individual correspondence/meetings with abutters to review plans 1/12 -1/26/26
FEBRUARY 2026
Finalize draft Site Specific Soil Map and Report
Submit NH DHR Request for Project Review
21
Permitting Schedule
Round Pond Reservoir
MARCH 2026
DRAFT abutter Shoreland permit applications to City for review 3/2/2026
30% DRAFT dam design plans to City for review 3/31/2026
APRIL 2026
Submit Ecological Review Request (previously NHB Review)
Submit Protected Species Consultation Memo as required by DES
MAY 2026
NH DES Pre-Application meeting
Protected Species/NHFG Consultation meeting as directed by DES
JUNE 2026
60% DRAFT dam design plans to City for review 6/15/2026
22
Permitting Schedule
Round Pond Reservoir
JULY 2026
Submit draft DES permit applications for proposed dam work
(Dam, Wetland, AoT) to City for review 7/27/26
Submit draft Barrington CUP applications to City for review (if 7/27/26
required)
AUGUST 2026
Attend Barrington Board Meetings to present project
Submit permit applications to the DES
SEPTEMBER 2026
90% DRAFT dam design plans to City for review 9/14/2026
NOVEMBER 2026
100% dam design plans to City for review 11/16/26
January 2027
Anticipated NHDES/USACE Permit Approvals
23
Questions?
24
Contact Information
RICK DAVEE
rick.davee@wright-pierce.com
(603).570.7100
25
THANK YOU
26
Sample Layout
27
Isinglass River Watershed
28
Radiotelemetry
29
Keys Issues
1
Water Audit – understanding current usage, natural
inefficiencies, and where room for improvement
2
Supply Capacity – existing and how it can be
improved
3
Demand/Consumption – now and in the future
30
Pavement Management
Program Overview
City of Rochester
Presented by:
Sam Fortier, P.E. & Phil Corbett, P.E.
CMA Engineers, Inc.
February 19, 2026
Why Pavement Management Matters
Rochester maintains ~152 miles of paved roads
Pavement is one of the City’s largest capital assets
Roads deteriorate every year, regardless of funding
Goal: maximize value of limited taxpayer dollars
Pavement management is about making smart
Key takeaway: tradeoffs
Pavement Management Program
What is PCI?
• Pavement Condition Index (PCI)
• Industry Standard Score 0 to 100 (higher is better)
• Based on:
• Surface distress (cracking, rutting)
• Ride quality (roughness)
Pavement Management Program
What is PCI?
• The Pavement Condition Index (PCI)
method was used in accordance with the
American Society for Testing and
Materials (ASTM) D6433 to assess the
condition of the City’s pavements.
• City-wide average PCI = 61
• Target Range: 70-80
• Neighboring Community PCI
• Portsmouth = 82 (2024)
• Somersworth = 75 (2023)
• Dover = 69 (2022)
Pavement Management Program
How Rochester Measures Pavement Condition
• Automated survey by IMS using laser-based
technology
• IMS collects data for 5 state DOTs and over 1,000
agencies
• Uses Pavermetrics Laser Crack Measuring System
(LCMS)
• Measures cracking, rutting, and roughness
• Utilizes American Society for Testing and Materials
(ASTM) and American Association of State Highway
and Transportation Officials (AASHTO) Standards
• Objective, repeatable, defensible
• Updated every 5 years
• Key point:
• This removes subjectivity from decision-making.
Pavement Management Program
In addition to IMS’s quality control,
CMA Engineers spot checks roads as
the pavement management plan is
developed and finalized
Pavement Management Program
Pavement Continually Degrades
► Slowly at first, then conditions deteriorate rapidly
New Pavement
Failed Pavement
Pavement Management Program
Pavement Rehabilitation Costs Increase with Time
► Non-linear: costs increase dramatically once roads fail
$1 of Preventive
Maintenance here…
PCI
Eliminates or delays
spending $8 - $10
on rehabilitation here.
(Pavement Condition Index)
Pavement Management Program
Types of Pavement Work
Right treatment at the right time matters
Preservation (Good roads)
Crack sealing, surface treatments – low cost, high
return
Resurfacing (Fair roads)
Mill & overlay – moderate cost
Reconstruction (Poor roads)
Full rebuild – very expensive
Reality:
• 1 mile of reconstruction ≈ cost of preserving ~13 miles of
good road
Pavement Management Program
Pavement “Treatments” as function of Pavement Condition
Pavement Management Program
Pavement Repair Unit Costs
Preservation Methods (1-4yrs) Cost Range: up to $ 0.50/sf
Crack Seal
Spot Repair
Resurfacing Methods (4-12 yrs) Cost Range: $ 1.25/sf to $ 2.50/sf
Mill, Shim, and Overlay
Reconstruction Methods (12-20 yrs) Cost Range: $ 4.00/sf to $ 7.00/sf
Reclaim and Overlay
Reclaim with Strength Additive & Overlay
Full Box Reconstruction
Pavement Management Program
Preserving Good Pavement Costs Less over Long Term
than waiting for Major Repair/Reconstruction
Pavement Management Program
Current Condition of Rochester’s Roads
45
• After 2021 scan, overall PCI was found to 40
Current Network Average Condition = 61, Backlog = 19.5%
be 61 (national average = 65) 35
30
Percentage of Network By Area
• The “backlog” is defined as roads that 25
22.0
have deteriorated beyond the point of 20
preservation and maintenance (PCI below 16.6
14.3
16.9
15.2
15
40, requiring reclaim/reconstruction) 12.0
10
5
• Rochester’s backlog was found to be 20% 2.9
of the network (typical goal is 10%) 0
V Poor (0 to 25) Poor (25 to 40) Marginal (40 to Fair (50 to 60) Good (60 to 70) V Good (70 to Excellent (85 to
50) 85) 100)
Current Pavement Condition
Pavement Management Program
Addressing a Common Concern
“The program doesn’t prioritize bad roads”
This is not true — but funding limits what can be done.
Poor roads are identified and prioritized
Reconstruction is very expensive
Limited budgets force tradeoffs
Key reality:
• Fixing only the worst roads causes the overall system to decline.
• Proactive preservation and maintenance is good financial stewardship
of tax dollars.
Pavement Management Program
Pavement Optimization- General Goals
Distribute annual budget to:
1. Keep Good Roads Good
2. Maintain or Raise Average PCI
These must be done in a practical
manner
Pavement Management Program
Pavement Optimization – Constraints
Pavement Optimization: Key Challenges
Reconstruction is extremely expensive
• One mile of reconstruction ≈ 13 miles of preservation
Heavy reconstruction spending reduces funds available for
maintenance
Preservation-first strategies can be misunderstood by the public
Some physical constraints affect treatment selection:
• Curb reveal impacts
• Thin pavement sections (<4") limit overlay options
• Other City projects
Bottom line:
• With limited funding, tradeoffs are unavoidable.
Pavement Management Program
Pavement Optimization
How the Strategy Works
Pavement Optimization: Strategy in Practice
Use the annual pavement budget as efficiently as possible
Prioritize roads nearing a more expensive treatment threshold
Coordinate with Capital Improvement Projects (CIP)
Group projects geographically to reduce inefficiencies
Rescan roadways every 5 years
• Objective, repeatable, ASTM-based
• Calibrated to Rochester’s road conditions
Identify roads with underlying issues
• Drainage problems accelerate deterioration
Result: Preservation and resurfacing maximize network-wide condition.
Pavement Management Program
Current Pavement Funding
Current Annual Pavement Investment: ~$2.0M
Includes:
• ~$1.5M in annual pavement maintenance & rehabilitation
funding
• ~$0.5M in new pavement constructed as part of Capital
Improvement Projects (CIP)
Key takeaway:
• At this funding level, overall pavement condition declines
over time.
Pavement Management Program
Current Pavement Funding Cont.
• ~1.5M in annual paving funding has been fixed for
years (steady funding since pre-2008)
Source: New Hampshire Department of Transportation (NHDOT), Bureau of Asset
Management, Performance, and Strategy, January 1, 2026
Pavement Management Program
If the Program is Underfunded
• More roads fall into the “reconstruction” category
• Backlog grows faster
• Future costs increase
• Fewer options for Council in future budgets
This is a compounding problem
Pavement Management Program
Funding vs. Pavement Condition 80
Five Year Post Rehab PCI Versus Annual Budget
Analysis Start Date = 3/1/2023 Analysis Period 2023 to 2027
75 2023 to 2027 Rehab Analysis Results
Post Rehab Network Average Condition
Rochester Budget: PCI = 59, Backlog = 26%, Annual Budget = $2000k/Yr
Steady State PCI: Final PCI = 62, Backlog = 22%, Annual Budget = $2630k/Yr
70
Maintain Current Backlog: Final PCI = 64, Backlog = 20%, Annual Budget = $3220k/Yr
65
Current PCI = 61 (2023)
60
55
50
0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 5,000
Annual Budget Each Year for Five Years ($1,000/Yr)
Pavement Management Program
Neighboring Community Comparison
Portsmouth Rochester
• 104 miles of paved roads • 152 miles of paved roads
• PCI = 82 (2024) • PCI = 61 (2021)
• $2m annual budget • $1.5m annual budget
• $19,230/mi • $9,868/mi
Dover
Key takeaway:
• 126 miles of paved roads
• PCI = 69 (2022) • Larger sustained funding = improved
• $2m annual budget roads and more cost-efficient
• $15,873/mi maintenance
Somersworth
• 50 miles of paved roads
• PCI = 75 (2023)
• $1.3m annual budget
• $26,000/mi
Pavement Management Program
Questions?