Airport Commission
Regular MeetingRussellville, AR · August 1, 2023
Minutes
RUSSELLVILLE AIRPORT ADVISORY COMMISSION
Minutes of Meeting
DATE 8/01/2023
MEMBERS PRESENT: GUESTS:
Bill Rowlett X McClelland Engineer, Mitch Rose
Kevin Burnham X (Mitch Rose)
Nathan George X Mayor Fred Teague
Vacant position Airport Director, Patrick Karp
Dwight Talburt X Kevin Hopkins
Les Teaff absent
Bill West X
Meeting Started at _6:00 PM_
Introduction of Guests :
Accept the Minutes
Motioned by: Kevin Burnham
Seconded by: Nathan George
Accepted Unanimous - Minutes of 5/23/23 and 6/27/23
Manager’s Report
July 2023 Jet-A Sales: 5,997 gallons $ 25,937
July AVGAS Sales: 3,301 gallons $ 16,401
YTD Jet-A Sales: 34,048 gallons $152,887
YTD AVGAS Sales 23,648 gallons $111,541
Financial - Accounts Receivable Aging for March 2023 1>90
0-30 Days: $16,251
31-60 Days: $ 8,123
61-90 Days: $ 2,073
>90 Days: $ 1,502
City Hanger Occupancy in February 2023 was: 80 %_ City Enclosed Hangar _100% _
City Shade Hangars _65__% Private Hangars__100%_____
Hangar waiting list #: 8 aircraft
Aircraft Stationed at (KRUE): Movements by type:
Single engine: 51 Aircraft Single engine: 469
Twin Engine: 8 Aircraft Twin engine: 22
Jet: 1 Aircraft Jet: 17
Helicopter: 4 Aircraft TurboProp: 76
Helicopter 49
RUSSELLVILLE AIRPORT ADVISORY COMMISSION
Minutes of Meeting
DATE 8/01/2023
Transit airspace 56
Total: 5,031 YTD
MANAGER’S REPORT / FINANCIAL REPORT:
Accept the Manager’s - Unanimous
Motioned by: Nathan George
Seconded by: Bill West
OLD BUSINESS
1. Asbestos Hangar 1W.
There was anonymous tip to the Dept of Environmental Quality re: Asbestos
in office of Hanger 1W. The airport was forced to hire company to certify no
asbestos is or was present. The cost was $1,200. The report has been
submitted to the Dept of EQ
2. New commission member recommendations:
By next meeting please submit recommendations. Nathan George mentioned
the names Brandon Ball. Mr. Ball has also expressed a desire to serve. Bill
Rowlett mentioned the name of Kelly Mabry. Dwight Talburt mentioned Lance
Oakley. Mayor Teague state he would like to see some females
recommended.
3. Discussion/Completion of SOP Document
Draft copy of distributed. Mr. Talburt requested any comments and/or
recommendations be submitted within 2 weeks, at which time Teaff & Rowlett
will edit the comments/recommendations into the document to be submitted to
be reviewed at next meeting.
4. Potential Amendments to Commission Ordinance
Re: The proposal submitted by Seth Lake last month to give the Airport
Commission over-ride authority over the Airport Director. Bill West in favor
the commission remaining an “advisory” commission only. He expressed
dissatisfaction with prior advice not be heeded. Bill Rowlett stated the same –
advisory only. The Mayor has no objection to allowing the Commission more
oversight if we can find away to make it happen within the law. Dwight
brought up the situation of the commission voting unanimously to allow one-
wheelers (with restrictions), but Airport Director Jason Duval disregarded the
commission and caused several problems for the airport.
5. CIP, Taxiway Crack Seal
No changes to CIP
2
RUSSELLVILLE AIRPORT ADVISORY COMMISSION
Minutes of Meeting
DATE 8/01/2023
NEW BUSINESS:
1. Hangar 1 West Door Replacement
Door has been repaired. Director Karp is not in favor of installing a door
opener. Rail has been repaired and door works fine now. Discussion of
replacing exterior metal of the door for aesthetics.
2. Runway Remarking
Mitch Rose. Scheduled for August 7, 8, 9 Airport will be closed at night for
work. 30 days later the 2nd coat will be applied. No changes to CIP. Director
will issue NOTAMS
3. Apron Reconstruction Phase I
Mitch Rose
4. New Courtesy Car
Nothing
5. Aircraft Campsite Construction
Would have to be city funded. Not in FAA documents.
6. Fall Fly-In Schedule
Directory Karp would like to see a fly-in for Mid-October. Recommended to
have a fly-in the weekend before STOL weekend at Byrd’s. Director will
report back on next meeting.
7. FBO Prop Discussion
Bill West reported on a phone app for pilots to write comments and rate
airports. Airport advertising is $40-$50.
8. Women’s Aviation Cross Country Race
Bill West suggested the airport apply to be one of the fuel stops.
MISCELLANEOUS:
1. Taxiway next to Hangar 5E that was closed at last taxi-way rebuild. Bill West
would like to see it be put back as an active taxiway
MEETING ADJOURNED: 7:03 PM
These minutes were compiled from notes taken by Bill Rowlett and a voice recording of
the meeting.
Respectfully submitted: Leslie Teaff
Committee Secretary
3
Preconstruction Meeting
RUSSELLVILLE REGIONAL AIRPORT (RUE) RUNWAY REMARKING
AIP NO. 3-05-0056-021-2023
MCE PROJECT No. 22-2181
This is intended to serve as a record for the referenced meeting conducted at the Russellville Regional
Airport at 3:00 pm on July 19, 2023.
Information contained herein is intended to be clarification of job specific requirements, all relevant sections
of the Project Manual Specifications and Conditions of Contract shall remain in full-effect.
General points discussed regarding the above project are summarized below per the format of the
Preconstruction Meeting Agenda:
1. Sign-In Sheet (Attendance)....see attached.
2. Project Contacts:
• Owner Representative: City of Russellville, Arkansas
o Patrick Karp, Airport Director Mobile: (501)-351-1749
• Engineer: McClelland Consulting Engineers
o Mitch Rose, Project Manager Office: (501) 371-0272
Mobile: (501) 658-4823
o , MCE Observer Mobile:
o Jarrett Elliott, Project Designer Office: (501) 371-0272
Mobile: (318) 623-8689
• Contractor: Metro Construction Services, LLC
o Danny Morrow Mobile: (615) 578-9192
o Sean Walsh, Superintendent Mobile: (724) 986-7434
3. Distribution of Contract Documents.... completed after Contract signatures.
4. General Discussion of Contract
• Amount: $46,388.55
• Construction Schedule: 7 calendar days effective Notice To Proceed (NTP). Work commences
on/prior to NTP Date August 7, 2023, Substantial Completion Date September 14, 2023.
• Liquidated Damages: $350.00/day
• Payment Schedule: Every 30 days. Once approved, engineer will submit to Airport Director for
payment. FAA processing can take up to 2 weeks.
5. Subcontractors: None.
Page 1
6. Procedures for Processing of :
• Field Decisions: Via MCE Observer; to Engineer if necessary.
• Submittals: All submittals required have been approved.
• Alternates: N/A
• Applications for Payments: Coordinate with Observer prior to submitting pay request. Submit
pay request electronically.
• Change Orders: To Engineer for review/approval. NO additional work unless approved in writing
by Owner. Change orders greater than 10% ($4,638.86) may need to receive City Council
approval.
• Contract Closeout: Per spec.
7. Responsibilities:
• Contractor: Complete work as shown on plans and specifications. Meet FAA Requirements as set by
the specs (i.e. DBE, CSPP, Certified Payroll, etc.)
• Owner: Pay for work completed and accepted. All acceptance criteria are detailed in the
specifications. Issue NOTAMs, local communication, and shut-off and turn on airfield lighting and
NAVAIDs.
• Engineer: Complete pay requests, change orders, review submittals, and answer questions associated
with the design and construction.
8. Staking of Work. By contractor.
9. Rights-of-Way and Easements. N/A. All work on Airport owned property.
10. Materials Testing. Retro-reflectivity testing performed by the Contractor and submitted to the Engineer for
approval.
11. Record Documents. Contractor to produce a set of red-line drawings at end of the project to enable
production of As-Built Drawings for the Airport.
12. Runway Safety & Phasing Plan. Refer to project drawings and specifications. Contractor to Submit a
Safety Plan Compliance Document (SPCD) prior to start of construction. **Runway Safety Area (RSA) is
150’ wide and extends 300’ past each end of the runway. Men and equipment are not allowed inside the
RSA while the runway is open.**
13. Traffic Control / Staging Area. Refer to Construction Safety Plan found in the project documents.
14. Other Requirements by Funding Agencies.
• Contractor must submit Safety Plan Compliance Document (SPCD) prior to beginning construction.
• FAA Project – Certified Payroll
• Federal Labor Requirements, minimum wage rates are included in contract documents.
15. Other Considerations;
• Housekeeping procedures - Please keep jobsite and staging area clean of trash/debris as items as
simple as ice bags can ruin an aircraft engine. Keep all pavement areas swept free of debris.
• Haul route is indicated on Construction safety plan.
• Gate code: 1947 (East Gate)
• Warranty - Contractor will provide a 12-month warranty period on all work completed.
• Install meter on hydrant prior to construction.
16. Pictures and Reports;
• Does Client want photos and reports of the report for social media? Yes.
Page 2
While this record is intended to be a thorough and comprehensive record of the preconstruction
conference, it is likely that some items discussed at the meeting were inadvertently overlooked and
therefore, not recorded herein. You are encouraged to review this record carefully and to respond
with additional items that need to be made a part of the permanent record.
END OF DOCUMENT
Page 3
No Airport Commission meetings during the month of July 2023
Agenda
RUSSELLVILLE AIRPORT ADVISORY COMMISSION
Annotated Agenda
DATE 08/01/2023 (For July Meeting)
MEMBERS PRESENT: GUESTS:
McClelland Engineers Mitch Rose
Bill Rowlett _____
Kevin Burnham _____
Nathan George _____
Dwight Talburt _____
Les Teaff _____
Bill West _____
Airport Director:
Patrick Karp_____
Meeting Started at 6:00PM
Introduction of Guests :
Accept Last Months Minutes
Motioned by: ________
Seconded by: ________
Manager ’s Report
July 2023 Jet-A Sales: 5,997 Gallons $25937.47
July 2023 AVGAS Sales: 3,301 Gallons $16,401.38
YTD Jet-A Sales: 34,048 Gallons $152,887.09
YTD AVGAS Sales: 23,647.74 Gallons $111,540.88
Financial - Accounts Receivable Aging for May 2023 1>90
0-30 Days: $16,251.39
31-60 Days: $8,122.59
61-90 Days: $2,072.81
>90 Days: $1,502.41
City Hangar Occupancy in February 2023 was: 80%_ City Enclosed Hangar _100%
City Shade Hangars _65 % Private Hangars 100%
RUSSELLVILLE AIRPORT COMMISSION AGENDA DATE: 07/01/2023
Aircraft Stationed at (KRUE): July 2023 Movements by type:
Single Engine: 51 Single Engine: 469
Twin Engine: 8 Twin Engine: 22
Jet: 1 Jet: 17
Helicopter: 4 Turbo-Prop: 76
Total: 64 Helicopter: 49
Transit Airspace: 56
Total YTD: 5031 YTD
Hangar waiting list #: 17 aircraft
MANAGER ’S REPORT / FINANCIAL REPORT:
Accept the Manager’s ___________
Motioned by: __________
Seconded by: __________
OLD BUSINESS
1. New Commission Member to be recommend
2. Discussion/Completion of SOP Document
3. Potential Amendments to Commission Ordinance
4. KRUE Project Update
5. CIP, Taxiway Crack Seal
NEW BUSINESS:
1. Hangar 1 West Door Replacement
2. Runway Remarking
3. Apron Reconstruction Phase I
4. New Courtesy Car
5. Aircraft Campsite Construction
6. Fall Fly-In Schedule
7. FBO Prop Discussion
8. Womens Aviation Cross Country Race
MEETING ADJOURNED: PM