CITY OF SAND SPRINGS
COUNCIL/AUTHORITY STAFF REPORT
MEETING DATE: January 28, 2019
SUBJECT: WATER TREATMENT PLANT BEAUTIFICATION WALL
COSS PROJECT NO. M-1801, BID NO. 1065
AWARD OF BID & CONSTRUCTION ADMINISTRATION SERVICES
STAFF RECOMMENDATION:
1) Awarding the Water Treatment Plant Beautification Wall project, (Bid No. 1065) to
Crossland Construction Company, Inc. in the amount of $1,113,807.60 and authorize the
Mayor to sign the agreement.
2) Approving the proposed Amendment No. 2 to the professional engineering services
agreement with Keithline Engineering Group, PLLC for construction administration
and periodic construction inspection services associated with the Water Treatment Plant
Beautification Wall project at a cost not-to-exceed of $98,118.87.
BACKGROUND AND HISTORY:
Proposition 4 of the 2017 G.O. Bond included $1,905,500 for City-Wide Beautification and
Landscaping. One area mentioned in the proposition was the screening/fencing of the west and
north perimeter of the Water Treatment Plant located on the southeast corner of the intersection
of Morrow Road and HWY 97. On June 25, 2018, the City executed Amendment No. 1 to
the professional engineering services agreement with Keithline Engineering Group, PLLC
for design and bidding services for this project.
EXECUTIVE SUMMARY:
Keithline Engineering Group, PLLC prepared plans and specification and on January 8,
2019, staff received and opened sealed bids from three (3) bidders. Crossland
Construction Company, Inc. submitted the lowest total base bid of $1,113,807.60 (see
attached bid tabulation). The total base bid includes add alternate 1 which will add lights
to every wall column at a cost of $89,850.00. Estimated start of construction is March 2019
with a 210-calendar day contract time.
In addition, Amendment #2 is for Keithline Engineering Group, PLLC to perform
construction administration and periodic construction inspection services. Both items
were reviewed at the January 22, 2019 Public Works Advisory Committee meeting.
BUGETARY IMPACT:
Total construction and construction administration/inspection service cost of $1,211,926.47
COMPILED BY: Jesse Vaverka APPROVED BY:
Attachments: Engineer’s Letter of Recommendation
Tabulation of Bids
Amendment No. 2
8556 EAST 101ST STREET, SUITE C
KEITHLINE ENGINEERING GROUP, PLLC TULSA, OKLAHOMA 74133
O: (918) 369-7911
dan@KEngineering-US.com
www.KeithlineEngineering.com
January 8, 2019
City of Sand Springs
ATTN: Jesse Vaverka
13101 West 46th Street
Sand Springs, Oklahoma 74063
Subject: Recommendation of Award
COSS Project M-1801 Bid No 1065
RELOCATION OF PERIMETER SECURITY AND BEAUTIFICATION FOR WATER
TREATMENT PLANT FROM SH-97 WIDENING PROJECT
Dear Mr. Vaverka,
Three (3) bids for the above project were received on January 8, 2019, at the Sand Springs Municipal
Building. The three (3) bids were opened and publicly read aloud at 10:00 a.m. No irregularities were
found or unit prices out of line.
Crossland Construction Company Inc submitted the apparent low TOTAL BASE BID for the amount of
$1,113,807.60, which is 2.8% below the Engineers Estimate of $1,146,095.00. Attached herewith is the
certified tabulation for bids received. The bid unit prices appear to be considered reasonable.
Keithline Engineering Group recommends the City of Sand Springs award this contract to Crossland
Construction Company Inc. for COSS Project M-1801, Bid No 1065 for the RELOCATION OF PERIMETER
SECURITY AND BEAUTIFICATION FOR WATER TREATMENT PLANT FROM SH-97 WIDENING PROJECT for a
TOTAL BASE BID including Add Alternate 1 in the amount of $ 1,113,807.60.
KEITHLINE ENGINEERING GROUP
Daniel A. Keithline, P. E.
Attachment: Bid Tabulation
Cc: Jim Umdenstock, P.E.
ASSESSMENT – STUDIES – CONCEPTUAL – ENGINEERING – CONSTRUCTION SERVICES i
PROJECT: RELOCATION OF PERIMETER SECURITY AND BEAUTIFICATION
FOR WATER TREATMENT PLANT AT SH-97 WIDENING
COSS PROJECT NO M-1801, BID NO 1065
BID TABULATION
Engineer: Keithline Engineering Group, PLLC
DATE: January 8 2019
ENGINEER'S ESTIMATE
CROSSLAND CONSTRUCTION CO., INC. WYNN CONSTRUCTION CO., INC. 11901 NABHOLZ CONSTRUCTION CORP.
KEITHLINE ENGINEERING
833 S EAST AVE. NORTH EASTERN AVE 10319 EAST 54th STREET
8556 E. 101ST STREET, SUITE C
COLUMBUS, KANSAS 66725 OKLAHOMA CITY, OK. 73131 TULSA, OK. 74146
TULSA OK. 74133
(620) 429-1414 (405) 753-1120 (918) 508-5456
(918) 369-7911
Item
No. ITEM DESCRIPTION UNIT QTY UNIT PRICE UNIT TOTAL UNIT PRICE UNIT TOTAL UNIT PRICE UNIT TOTAL UNIT PRICE UNIT TOTAL
BASE BID
1 CLEARING AND GRUBBING LSUM 1 $ 17,000.00 $ 17,000.00 $ 18,000.00 $ 18,000.00 $ 21,275.00 $ 21,275.00 $ 23,066.00 $ 23,066.00
2 UNCLASSIFIED EXCAVATION LSUM 1 $ 16,000.00 $ 16,000.00 $ 24,353.00 $ 24,353.00 $ 53,600.00 $ 53,600.00 $ 20,000.00 $ 20,000.00
3 SELECT BORROW CY 200 $ 80.00 $ 16,000.00 $ 105.70 $ 21,140.00 $ 33.00 $ 6,600.00 $ 40.00 $ 8,000.00
4 MACHINE GRADING WITH FILL AREA (DRAIN TOWARDS GUTTER) LSUM 1 $ 30,000.00 $ 30,000.00 $ 12,500.00 $ 12,500.00 $ 4,900.00 $ 4,900.00 $ 4,200.00 $ 4,200.00
5 SWPPP DOCUMENTATION AND MANAGEMENT LSUM 1 $ 2,000.00 $ 2,000.00 $ 1,100.00 $ 1,100.00 $ 885.00 $ 885.00 $ 6,000.00 $ 6,000.00
6 TEMPORARY SILT FENCE LF 700 $ 3.00 $ 2,100.00 $ 3.30 $ 2,310.00 $ 2.50 $ 1,750.00 $ 4.00 $ 2,800.00
7 TEMPORARY FIBER LOGS LF 100 $ 5.00 $ 500.00 $ 4.40 $ 440.00 $ 10.00 $ 1,000.00 $ 12.00 $ 1,200.00
8 SOLID SLAB SOD (800' x 30') SY 2666 $ 4.50 $ 11,997.00 $ 2.50 $ 6,665.00 $ 3.00 $ 7,998.00 $ 3.00 $ 7,998.00
9 CLASS A CONCRETE (4" THICK MOW STRIP) CY 19 $ 800.00 $ 15,200.00 $ 849.00 $ 16,131.00 $ 665.00 $ 12,635.00 $ 1,200.00 $ 22,800.00
10 6" CONCRETE DRIVEWAY (CLASS A) (SAW AND SEAL) SY 160 $ 65.00 $ 10,400.00 $ 45.90 $ 7,344.00 $ 98.00 $ 15,680.00 $ 75.00 $ 12,000.00
11 REMOVAL OF FENCE (INCLUDES GATES) LF 860 $ 5.00 $ 4,300.00 $ 3.20 $ 2,752.00 $ 3.00 $ 2,580.00 $ 12.00 $ 10,320.00
12 REMOVAL OF ASPHALT DRIVEWAY SY 160 $ 12.00 $ 1,920.00 $ 13.90 $ 2,224.00 $ 18.00 $ 2,880.00 $ 15.00 $ 2,400.00
13 MOBILIZATION EA 1 $ 60,000.00 $ 60,000.00 $ 100,000.00 $ 100,000.00 $ 40,000.00 $ 40,000.00 $ 95,000.00 $ 95,000.00
14 CONSTRUCTION STAKING LEVEL 1 LSUM 1 $ 5,000.00 $ 5,000.00 $ 10,000.00 $ 10,000.00 $ 7,900.00 $ 7,900.00 $ 20,000.00 $ 20,000.00
15 REMOVE AND RESET EXISTING SIGNS EA 10 $ 200.00 $ 2,000.00 $ 278.10 $ 2,781.00 $ 350.00 $ 3,500.00 $ 200.00 $ 2,000.00
16 CONSTRUCTION TRAFFIC CONTROL LSUM 1 $ 20,000.00 $ 20,000.00 $ 5,100.00 $ 5,100.00 $ 10,000.00 $ 10,000.00 $ 9,500.00 $ 9,500.00
17 PRECAST CONCRETE WALL SYSTEM, COMPLETE (PANELS, COLUMNS, DRILLED SHAFTS) LF 794 $ 525.00 $ 416,850.00 $ 560.00 $ 444,640.00 $ 770.00 $ 611,380.00 $ 1,065.00 $ 845,610.00
SUBMITTED BY:
18 MULTI - STAIN SURFACES, PREMIUM FINISH SF 22,706 $ 3.00 $ 68,118.00 $ 1.10 $ 24,976.60 $ 0.25 $ 5,676.50 $ 1.50 $ 34,059.00
19 CANTILIVER SLIDE GATE AUTOMATIC WITH OPERATOR, COMPLETE SYSTEM, 20' OPENING EA 1 $ 48,150.00 $ 48,150.00 $ 32,000.00 $ 32,000.00 $ 34,650.00 $ 34,650.00 $ 66,000.00 $ 66,000.00
20
KEYPAD WITH HD CAMERA (2N IP FORCE OR EQUAL) STAND AND CABLING, FOR SLIDE GATE ONLY,
LSUM 1 $ 4,500.00 $ 4,500.00 $ 5,562.00 $ 5,562.00 $ 5,725.00 $ 5,725.00 $ 5,800.00 $ 5,800.00 I, Daniel A. Keithline, P.E., do hereby certify the above "Tabulation
COMPLETE of Bids" correctly reflects each bid received for the above reference
21 CANTILEVER DOUBLE SWING GATE, MANUALLY OPERATED, 26' OPENING, COMPLETE EA 1 $ 40,000.00 $ 40,000.00 $ 17,688.00 $ 17,688.00 $ 16,225.00 $ 16,225.00 $ 13,000.00 $ 13,000.00 project.
22 LANDSCAPE, COMPLETE LSUM 1 $ 5,000.00 $ 5,000.00 $ 3,100.00 $ 3,100.00 $ 5,900.00 $ 5,900.00 $ 2,000.00 $ 2,000.00
23 PLANTSIDE TREE - LOBLOLLY PINE 14' TO 15' IN HEIGHT, COMPLETE EA 70 $ 1,500.00 $ 105,000.00 $ 441.00 $ 30,870.00 $ 650.00 $ 45,500.00 $ 575.00 $ 40,250.00
24 24”x2” STAINLESS TAPPING SADDLE WITH 2" CORP STOP AND WRAP, COMPLETE EA 1 $ 5,000.00 $ 5,000.00 $ 2,781.00 $ 2,781.00 $ 2,350.00 $ 2,350.00 $ 3,200.00 $ 3,200.00 Daniel A. Keithline January 8, 2019
25 3-INCH DEPTH RIVER ROCK MULCH WITH GEOTEXTILE FABRIC, COMPLETE SY 830 $ 50.00 $ 41,500.00 $ 22.00 $ 18,260.00 $ 28.00 $ 23,240.00 $ 21.50 $ 17,845.00 Print name Date
26 STEEL BED EDGING FOR RIVER ROCK, COMPLETE LF 700 $ 10.00 $ 7,000.00 $ 6.20 $ 4,340.00 $ 9.50 $ 6,650.00 $ 6.06 $ 4,242.00
27 IRRIGATION SYSTEM, COMPLETE LSUM 1 $ 15,000.00 $ 15,000.00 $ 17,000.00 $ 17,000.00 $ 16,500.00 $ 16,500.00 $ 26,700.00 $ 26,700.00 Keithline Engineering Group, PLLC
28 ELECTRICAL (LIGHTS, SIGN POWER, SLIDE GATE POWER, IRRIGATION POWER), COMPLETE LSUM 1 $ 65,000.00 $ 65,000.00 $ 129,000.00 $ 129,000.00 $ 106,500.00 $ 106,500.00 $ 73,000.00 $ 73,000.00 Company
29 15-INCH BACKLIT LOW VOLTAGE LED SIGN LETTERING, COMPLETE EA 1 $ 25,000.00 $ 25,000.00 $ 5,400.00 $ 5,400.00 $ 4,900.00 $ 4,900.00 $ 6,200.00 $ 6,200.00
30 HYDROVAC, COMPLETE HOURS 100 $ 150.00 $ 15,000.00 $ 220.00 $ 22,000.00 $ 350.00 $ 35,000.00 $ 232.85 $ 23,285.00
31 CONSTRUCTION RECORD DRAWINGS, COMPLETE EA 1 $ 750.00 $ 750.00 $ 3,500.00 $ 3,500.00 $ 590.00 $ 590.00 $ 1,775.00 $ 1,775.00
32 OWNER ALLOWANCE ALLOW 1 $ 30,000.00 $ 30,000.00 $ 30,000.00 $ 30,000.00 $ 30,000.00 $ 30,000.00 $ 30,000.00 $ 30,000.00 Signature
BASE BID (ITEMS 1 THRU 32 above): $1,106,285.00 $ 1,023,957.60 $ 1,143,969.50 $ 1,440,250.00
ADD ALTERNATE 1
33 LIGHTS ON ADDDITIONAL 30 COLUMNS WITH CONDUIT AND WIRING EA 30 $ 1,327.00 $ 39,810.00 $ 2,995.00 $ 89,850.00 $ 6,125.00 $ 183,750.00 $ 1,195.00 $ 35,850.00
TOTAL BASE BID (ITEMS 1 THRU 33 above): $1,146,095.00 $ 1,113,807.60 $ 1,327,719.50 $ 1,476,100.00