City Council
Regular MeetingSaratoga Springs, NY · May 6, 2004
Minutes
CITY OF SARATOGA SPRINGS
CITY COUNCIL WORKSHOP
CITY COUNCIL ROOM
THURSDAY, MAY 6, 2004
7:00 P.M.
PRESENT: Commissioner Thomas Curley, DPS
Michael Lenz, Mayor (arrived7:15 p.m.)
Commissioner Matthew McCabe, Finance
Commissioner Thomas McTygue, DPW
Commissioner Stephen E. Towne, Accounts
SUPERVISORS Phil Klein, Supervisor
Anthony Scirocco, Supervisor
ALSO PRESENT: William McTygue, Director, Utilities
Doug Ward, Young, Somer & Ward
Rich Straut, Barton & Loguidice
Matthew Dorsey, City Attorney
Ray Callanan, Saratoga County Board of Supervisors
Dan Lowenstein, Malcolm Pirnie
Paul Bessett, Malcolm Pirnie
Ed Vopelak, C.T. Male Associates
CALL TO ORDER
Commissioner Thomas McTygue called the workshop meeting to order at 7:00 p.m. and welcomed Ray
Callanan and members of the Saratoga County Water Committee.
WATER PRESENTATION
Ray Callanan, Chair of the Saratoga Water Committee thanked the Council for allowing them the opportunity
to present their proposal to the Council. He said they are looking for a regional solution to this water issue.
He then introduced members of the team.
Dan Lowenstein, Malcolm Pirnie, said the objective was to meet the drinking water needs of the City of
Saratoga Springs with a regional water solution. He said that components of the regional water solution
include: safe reliable water supply, state-of-the-art treatment technology; integrate multiple communities and to
provide forward-looking planning for future generations with the total lowest cost. He then reviewed the
agenda for tonight’s meeting with Council members.
Source of Supply: Dan Lowenstein that the County identified the upper Hudson River as the source of supply
for the following reasons: long-term suitability of water quality, no seasonal turnover, high quality water, no
pcbs, minimal vulnerability and more than a 4,000 square mile watershed. He then displayed an aerial
photographs of the proposed intake area. He explained that the proposed intake area is directly across from
the Town of Queensbury intake area. He said the Town of Queensbury tests their raw water, finished water
and the sludge and has been doing so since 1993. He said they have not detected any pcbs in any of those
components. He said more importantly they have not detected any pcbs in the sludge. He said that during the
treatment process, pcbs would be concentrated in the sludge and it was important to note that they have not
been detected in the sludge.
Dan Lowenstein said the proposed site of the water treatment plant would be on county owned property near
Butler & Potter Roads. He said it is a 100-acre parcel, remote and a secure location with little traffic. He said
Page 1 of 5
City of Saratoga Springs City Council Workshop Meeting Minutes
Thursday, May 6, 2004
using this location also decreases the cost of the project since it is already owned by the County. He informed
Council members that all of the filtration would be done inside the building, therefore, there would be little
impact to the surrounding properties. He also noted that because of the size of the site, there is room for
expansion.
Dan Lowenstein said they are proposing to use the water treatment membrane filtration technology. He said it
was important to note that the American Water Works Association has stated, “To meet recently enacted and
forthcoming regulatory requirements, surface water utilities are increasingly moving toward integrated
membrane systems for their superior finished water quality.” Therefore, they are proposing to use this new
technology.
Dan Lowenstein said low pressure membranes are ideally suited for drinking water. He said they provide an
absolute filtration barrier, low turbidity filtered water, excellent cyst (giardia/cryptosporidium) removal, is cost
competitive with conventional technology, less susceptible to changes in source water quality than
conventional treatment, highly automated and easy to operate and have small footprints. He noted that the
following communities are using this new technology: Scottsdale, AZ, Phoenix, AZ, Seattle, WA, Pittsburgh,
PA, Boise, ID, Minneapolis, MN, and San Jose, CA. He said it was important to note that this technology is
being used in both warm and cold climates.
Ed Vopelak then reviewed the water transmission route by displaying a map. He said the for the most part,
the route would following existing easements or rights-of ways. He said it would cross the Towns of Moreau,
Wilton, Greenfield, Milton, Ballston, Malta and City of Saratoga Springs. He said it would begin at Potter Road,
following the existing old railroad right-of-way, parallel the gas transmission route, follow that gas main
through Wilton, then follow local roads in Greenfield, pass by Loughberry lake, go around Saratoga Springs by
following railroad right-of-way, through the state park then parallel the county trunk sewer line down to Luther
Forest. He said the site elevation would be at 420 feet. He said the tower would be about 80 feet tall but
could be taller. He said the City could be served by gravity feed, however, some towns may need pressure
pumps. He said the system is designed to have a five million gallon storage tank at the end. He said that most
municipalities have a storage tank already, but this would be for the operation of the system.
Dan Lowenstein then review the costs. He said they used the following scenarios:
Regional communities: 2 mgd average B 4mgd peak
1.5 percent population growth
Saratoga Springs: 2 mgd average B 4mgd peak
3 mgd average B 6 mgd peak
4 mgd average B 8 mgd peak
Chip Fabs: 0 chip fab B 0 mgd
1 chip fab B 2 mgd
2 chip fab B 4 mgd
Dan Lowenstein said that chip fab plants do not peak.
Dan Lowenstein said that to date there is an estimated $10 million available for construction costs through
grants and an additional $2 million/year for the first five years through other grants.
Dan Lowenstein said that the range of costs was estimated as follows:
first five years $1.29 -- $1.08/1,000 gallons
years 6-10 $2.60 -- $1.50/1,000 gallons
He said those costs were to build and deliver.
Schedule: Dan Lowenstein said they estimate the following schedule: design 12 months, DEIS (if required) 12
months concurrent with design and construction 24 months (aerial photography already completed).
Administration: Ray Callanan said financing would come from both the federal and state government at $10
million each and then bonding by the County. He said the water committee would be comprised of individuals
Page 2 of 5
City of Saratoga Springs City Council Workshop Meeting Minutes
Thursday, May 6, 2004
from each community using water and with both of the City supervisors on that committee.
Planning a flexible solution: Dan Lowenstein said the water treatment plant, transmission main size and water
storage is all based on flow demands. He said the plant could be easily expanded.
Offer: Dan Lowenstein said the County is offering a water system which is safe, reliable, cost effective water to
the current and future resident to the City of Saratoga Springs and that could be tailored to meet the needs of
the City. He said the are very willing to work with the City.
Commissioner Thomas McTygue opened the meeting to comments/questions from Council members.
Mayor Michael Lenz asked about the controlling board. Ray Callanan said it would be comprised of a
representative from each of the municipalities participating. He said there would be two from the City and two
from Clifton Park. He said it would be “one man one vote”.
Commissioner Thomas Curley asked if the County had control over 100 percent of the rights-of-way. Ed
Vopelak said the county owns the parcel of land where they propose to construct the plant and he was
anticipating cooperation from the towns for easements. He said they have not yet spoken to Niagara Mohawk
and they may need to purchase some rights-of way.
Commissioner Stephen Towne asked for an explanation on the comment that a DEIS “may” be required. Dan
Lowenstein said traditionally the impact of a project is what triggers a DEIS. He said the plant will be located
inside a building on a 100 acre site, therefore, the impacts of noise, odor, traffic and other disturbances were
minimal. He said they will be required to obtain permits from DEC, OGS and other agencies and those
permits might trigger a DEIS.
Commissioner Matthew McCabe asked if the projected dollar costs was for bringing the water to the City. He
said once it gets to the City, the City would then need to distribute it to homeowners. Dan Lowenstein agreed.
Commissioner Matthew McCabe asked if there had been any discussions with the County of Warrensburg on
partnering with them. Ray Callanan said no. Commissioner Matthew McCabe asked if it was feasible to get
water from the north side of the upper Hudson near the Town of Queensbury intake. Dan Lowenstein said that
yes it was technically possible, however, to use the Town of Queensbury intake would require that their
system be upgraded at the County’s expense. Commissioner Thomas McTygue pointed out that suggestion is
fully discussed in the City’s DEIS. Commissioner Matthew McCabe asked if the County had discussed this
proposal with all of the interested towns in the county and more importantly the impact of having a water line
running through the county. He said the towns need to be prepared for this through the zoning laws. He said
that everyone is concerned about rapid growth.
Ray Callanan said the Town of Ballston currently purchases water from the Town of Glenville. He said they
would commit to purchasing from the County of Saratoga rather than the Town of Glenville. He said he
recognized that once water lines were installed there would be an increase in development but he has not
talked to the towns about that growth.
Commissioner Thomas McTygue said that would likely be part of the DEIS. He said it would be suicide for the
County to not do a DEIS. Dan Lowenstein said that the proposed flow at this point is only about 2 mgpd which
was not a huge amount.
Commissioner Stephen Towne asked if the seven communities where the water will flow through have
expressed an interest in the water. He also asked about the new technology, how recent is the technology,
most the communities using the technology are on the west coast, is it more effective, how does it compare to
sand and are they on the “front end” of this technology. Dan Lowenstein they proposed this technology for two
reasons: the superior finished project and it is more cost effective. He said this is a modular technology that is
easily expanded. Paul Bessett said this technology started to be used in the mid 1990s. He said it is used a
lot near the great lakes area. He said the only place in New York is Westchester County. Commissioner
Stephen Towne asked for an update on projected costs. He asked if more communities had expressed an
Page 3 of 5
City of Saratoga Springs City Council Workshop Meeting Minutes
Thursday, May 6, 2004
interest and what was their anticipated volume. Ray Callanan said that the communities that initially
expressed an interest are still interested. He said that the Town of Ballston has increased their anticipated
volume from 350,000 to 400,000 mgpd. He said though that the anticipated volume was still about the same
as before.
Commissioner Thomas McTygue asked if the chip fab volumes had been included. Ray Callanan said no.
Ed Vopelak said the Town of Clifton Park has committed to 1 mgpd and has expressed an interest for another
1 mgpd. He said a good portion of the Town of Malta is serviced by the Clifton Park Water Authority.
Commissioner Thomas Curley asked about the reliability and the length of use of this proposed system. Dan
Lowenstein said the system could last for quite some time with replacement of the membranes in about ten
years. He said the volume of water in the upper Hudson was large enough to last for quite some time.
Commissioner Thomas McTygue asked why the size of the pipes had been reduced. He said it was likely that
in another ten years, those pipes would need to be replaced with larger ones. Dan Lowenstein said if the
demand was there that would be true. Commissioner Thomas McTygue said that would be a cost to
municipalities to add or replace pipes. Dan Lowenstein that the revenues needed for that expansion would be
generated by the new users. Ed Vopelak said to install the larger pipe today could increase the user fee to as
much as $4.00 per thousand gallons. He said the proposed pipeline can accommodate 25 mgpd. He said if
there is a need, the plant can be expanded.
Mayor Michael Lenz asked who would pay for the second line of pipes. Paul Bessett said it would be paid for
through the revenues generated by the new users. He also noted that using a 48 inch line takes the water
twice as long to get to the City as it does with a 36 inch line.
Commissioner Thomas McTygue said that the county report said the plant could accommodate 16 mgpd. Ed
Vopelak said the pipe line can accommodate 25 mgpd.
Commissioner Matthew McCabe asked if this plant and lines could potentially serve whatever the desired
number is in the county. Dan Lowenstein said the plant is not designed to serve the entire county.
Commissioner Matthew McCabe asked if it was potentially possible that the population could double. Dan
Lowenstein said that flows drive costs. He said that commitments are an important part of the cost also. He
said the lines can handle 20 mgpd and it can be expanded if there is a demand. He said the plant can be
designed to handle whatever the County wanted, and the proposed pipe line can handle approximately 20
mgpd.
Commissioner Thomas Curley asked about the watershed management plan. Paul Bessett said it would be
somewhat similar to the Town of Queensbury’s plan. He said they have agreements with companies such as
International Paper that if there is a spill from their facility, they notify the Town of Queensbury and then the
town notifies DEC. He said there are similar agreements with DEC that DEC would notify the Town in the
event of a hazard.
Commissioner Thomas McTygue said in the original county proposal there were three scenarios one of which
called for the 48 inch water main. He asked what has changed since that original plan in 1990 to reduce the
size of the pipe. Ed Vopelak said that neither Clifton Park nor the Town of Halfmoon had water treatment
plants at that time, therefore, there were more potential users. Commissioner Thomas McTygue said he did
not believe that was the case.
Doug Ward said he believed there was some confusion on the DEIS. He asked if the County would comply
with SEQR. Dan Lowenstein said yes. Doug Ward said as he understood the conversations this evening the
County would be looking for a negative SEQR determination. He said, though, he believed the DEC would
want a DEIS. He said that with the DEIS process, there is public involvement through public hearings and
comment periods. He said if the County chooses to have a negative SEQR determination, then there is no
public involvement. Dan Lowenstein said there could be an expanded EAF. He said if it is determined that the
Page 4 of 5
City of Saratoga Springs City Council Workshop Meeting Minutes
Thursday, May 6, 2004
impacts are more than minimal through an expanded EAF, it could be determined to a DEIS. Doug Ward said
the Council has strived to be as transparent as possible with their process.
Commissioner Stephen Towne asked if the June 2003 draft plan from the County was the current proposal.
Dan Lowenstein said yes. He said the dollar amounts had not been provided in the original plan but have
been this evening.
Commissioner Matthew McCabe said he was glad to have this opportunity this evening to meet with the
County and said it should be done more often. He asked if the county plan would move forward without the
participation of the City. Ray Callanan said the County Board of Supervisors wants the water source to be a
self-sustaining program paid for by the users. He noted that there would be some towns such as Hadley and
Day that would likely never participate in this program. Ray Callanan said it would be difficult to proceed
without the City’s participation.
Commissioner Thomas Curley asked if the chip fab volumes were included in the calculations. Ray Callanan
said no. He said the numbers that were provided were informational only and not included.
Commissioner Stephen Towne asked about representation on the controlling board. Ray Callanan said the
controlling water board would have representation from all of the participating municipalities. He said there
would be two from the City. He also noted again that it was “one man, one vote”.
Ray Callanan said the County was offering a ten year program and he hoped the City would participate.
Commissioner Thomas McTygue thanked the County for coming here this evening and making this
presentation.
ADJOURNMENT
There being no further business, Mayor Michael Lenz adjourned the meeting at 8:05 p.m.
Respectfully submitted,
Kathy Moran
Clerk
Approved:
Page 5 of 5
Get email alerts for Saratoga Springs
A daily email when new agendas and minutes are posted.