Complete Streets Advisory Board
Regular MeetingSaratoga Springs, NY · March 10, 2022
Minutes
SARATOGA SPRINGS COMPLETE STREETS ADVISORY BOARD
MEETING MINUTES
MARCH 10, 2022
5:00 P.M.
ZOOM - https://us02web.zoom.us/j/83327583317
ATTENDEES: JEN NATYZAK, KEN GREY, SUZANNE JAGODA, TED OROSZ, ERIN MACIEL
STAFF: DEPUTY COMMISSIONER HEATHER CROCKER AND TINA CARTON
ABSENT: MICHELE RODDY,
PUBLIC: Olivia O’Malley & Mary Hallquist
MEETING MINUTES ARE NOT A WORD-FOR-WORD TRANSCRIPT.
CALL TO ORDER:
The meeting was called to order at 5:02 p.m.
PUBLIC COMMENT-15 MINUTES
Mary Hallquist: Parents are concerned about the safety of walking students from school. She stated that
the most recent decision from the City Council is insufficient to keep families and children safe. Students
and their families are now allowed to leave early to avoid the unsafe and concerning vehicle traffic.
Parents have asked to have it prohibited to not allow people to turn onto Schuyler, and it is currently a
mandatory one-way. The principal has not been able to get in touch with Public Safety. Reducing the
speed limit would help, but the offer is only to get the speed limit lowered only to Benton. There were no
parking signs installed which were helpful but not sufficient. For the foreseeable future the parents asked
to have traffic allowed only one way on Schuyler. A crossing guard position has been posted online.
Ken Grey responded that this issue should be brought to the safety committee and must be brought up to
Commissioner Montenegro.
Olivia O’Malley: Numerous emails have been sent to city council and it was clearly noted that parents are
disappointed they could not provide feedback to what they saw to be an insufficient solution.
Commissioner Montenegro visited the school in person. Olivia and parents will attend a public hearing
next Tuesday on this issue. “Perfect world” would include a sidewalk and a crossing guard to help
children cross the street and increased striping for the crosswalks. For the interim- she recommends doing
what Lake Ave has done, which is to wheel out a Slow Traffic sign on wheels and restricting traffic to go
one-way.
1
Erin Maciel suggests angled striping on the road for walkers for a quick, low-cost solution since there is
no on-street parking.
It was noted that a new house on 5th has no sidewalks. She expresses concerns that a sidewalk may not be
required there.
APPROVAL OF MINUTES- MINUTES WERE APPROVED.
DISCUSSION REGARDING 269 BROADWAY
The committee was provided an update on 269 Broadway. There is 18ft of public space on south side of
the building, so it may not be likely to get a full 12ft path, but the committee is hopeful that the Planning
Board recommend a 10ft path. The committee recommends that the City study on how to best get from
Congress Park to Hamilton. The original Downtown Extender engineering study evaluated Congress to
South Franklin. This section was evaluated with on street bike lanes and sharrows. This lead to loss of on
street parking. Congress in front of the Embassy Suites and CVS is also extremely busy with vehicular
traffic. City staff suggested looking at Hamilton to West Circular as an alternative to get to Railroad Run.
It connects to low income housing, a church, school, and the Saratoga Community Health Center.
Erin suggests incorporating the Visitors Center to get to Hamilton Street.
DISCUSSION ON SARATOGA SPRINGS BIKE PARK
CSAB approved with motion from Suzanne to endorse a new bike park in the City of Saratoga Springs.
UPDATE ON THE DOWNTOWN CONNECTOR TRAIL AND WILTON/SARATOGA COUNTY/CITY CDTC
PROJECT
The City is currently planning for construction to start this summer for Downtown Connector. A
construction contract is on the March 15th City Council agenda for approval. If the contract is approved,
the trail will be constructed starting in May of this year and is expected to be completed before the winter.
Preliminary study with the town of Wilton, CDTC, and Capital District Regional Planning is nearing
completion. The study is looking at pedestrian and bicycle connections from Exit 15 slip ramp and
Louden Road through the Wilton Mall area, over to Wilton YMCA, down Weibel Avenue and making
connections to Bog Meadow. It is exploring routing over to Wilton YMCA, over Lowes Drive, down
Louden Rd and considering connections to Bog Meadow Trail.
Skidmore’s license agreement for use of the Weibel Avenue Skating Rink includes the payment for a
installation of a future traffic light in front of the Weibel Ave ice rink. This will help facilitate pedestrians
and bicycles to cross the road.
UPDATE ON UNION RFP
NYSDOT is planning to add bike lanes on Union Avenue from East Ave to Henning, with sidewalk on
north side from East to the last track entrance. The project will include granite curbing to sides and
median. The NYSDOT would like to shift the landscaping/mowing responsibilities in this area since they
2
follow the regular mowing schedule and get complaints that it is not mowed frequently enough. The
Mayor is arranging meeting with NYRA and Carrie Woerner to see if NYRA can take over the
responsibility of managing the space. This would really dress up the boulevard.
The Mayor’s office will be sending out an RFP later in March for the bike/pedestrian accommodations
from East Avenue to Mary Lou Whitney Park- connecting East to Congress Park. This study would also
look at pedestrian areas and crosswalks.
OTHER BUSINESS
Saratoga County is working to create a new section of the Zim Smith Trail to connect the end of the trail
in Ballston Spa to the Saratoga Spa State Park. This could be the missing link to get into downtown
Saratoga Springs by bike. The City worked with the County to explore the potential for a RAISE grant to
complete this. Unfortunately the grant’s technical requirements are extensive and require outside
technical experts to be contracted. This would be a county-led project, approaching $9M, not including a
connection to Ballston Spa and to the Saratoga State Park.
Suzanne notes that to make a strong grant application we must include how low income communities are
affected/connected by the projects.
Infrastructure Committee Update: The majority of the federal grants will be funneling through existing
NYS DOT programs. The infrastructure committee sent emails to stakeholders asking for the top 3
projects. The infrastructure plan has specific grants for pilots, traffic studies. Complete Streets members
are submitting their top priorities to Erin Maciel who will compile for the Infrastructure Committee which
she is a part of.
ADJORN
The meeting was officially adjourned at 6:35pm.
3
Agenda
SARATOGA SPRINGS
COMPLETE STREETS ADVISORY BOARD
AGENDA
THURSDAY MARCH 10, 2021
5:00 P.M. – 6:30 PM
ZOOM
Join Zoom Meeting
https://us02web.zoom.us/j/83327583317
Meeting ID: 833 2758 3317
One tap mobile
+16465588656,,83327583317# US (New York)
1. PUBLIC COMMENT
2. APPROVAL OF FEBRUARY 10, 2022 MINUTES
3. UPDATE ON 269 BROADWAY
4. SUPPORT FOR SARATOGA SPRINGS BIKE PARK
5. UPDATE ON DOWNTOWN CONNECTOR TRAIL
6. UPDATE ON CAROLINE STREET ELEMENTARY SCHOOL SAFETY
7. UPDATE ON ADA TRANSITION PLAN
8. UPDATE ON COMPLETE STREETS PLAN
9. UPDATE ON UNION AVENUE RFP
10. OTHER BUSINESS
A. ZIM SMITH CONNECTION
B. SKIDMORE MASTER PLAN UPDATE
C. BROADWAY- TRUCKS
D. DISCUSSION ON POTENTIAL GRANTS
11. ADJOURN
NEXT MEETING: COMMITTEE MEETING THE SECOND THURSDAY WEEK OF APRIL 14 TH AT 5:00 P.M. CITY HALL /ZOOM