Comprehensive Plan Committee
Regular MeetingSaratoga Springs, NY · May 14, 2013
Minutes
PRESERVING
OUR PAST.
CITY OF SARATOGA SPRINGS
SHAPING
OUR FUTURE. 2013 COMPREHENSIVE PLAN UPDATE
MEETING SUMMARY
Purpose: Comprehensive Plan Committee (CPC) Meeting #1
Date and Time: May 14, 2013 7:00-9:00 pm
Location: City Recreation Center Community Room, 15 Vanderbilt Avenue
Attendees: See attached Sign-In
Agenda Item Discussion Action
Mayor Scott Johnson provided a brief welcome and
introduction to the process. Chairman Van Wagner
began the CPC introductions. Each CPC member
Welcome and
provided an introduction and shared any None.
Introductions
organizations or community activities they have
been or are currently involved in. The project team
also introduced themselves.
Comprehensive A general overview of a comprehensive plan was
Plan 101 provided by the project team. A comprehensive plan None.
(PowerPoint is a broad plan that provides a future direction for a
presentation – community. It is often referred to as a blueprint for
see attached) a community’s growth.
A comprehensive plan looks at the Current State
(existing conditions), then the Desired State (the
community vision), identifies actions to Achieve the
Vision and then outlines how to Implement the
action items.
A Comprehensive Plan looks from higher level and
will not be identifying parcel specific zoning. The
Comprehensive Plan process is also not the venue to
address projects or applications currently under
review by the City.
The comprehensive plan process is guided by NYS
General City Law §28-a.
The current City comprehensive plan was adopted in
2001. A review occurred, but no amendments were
adopted, in 2007. The City Charter (§2.8f) requires
Comprehensive Plan Committee Meeting Summary – May 14, 2013 1
the comprehensive plan be reviewed every 5 years.
It is good practice to review a comprehensive plan at
least every 10 years to reflect changing demographic
and economic trends.
Project Scope
and Process The project scope and process were identified and Project Team to prepare for
(see attached include the following tasks: Public Workshop #1 and CPC
presentation) to help spread the word.
1. Project Management and schedule
(including coordination with CPC)
2. Public Participation (multiple and varied
opportunities throughout)
3. Analysis of Existing Conditions & Trends
(answering the ‘so what does that mean’
question)
4. Review of Existing Plan Policies and
Strategies (report card)
5. Development of Draft Comprehensive Plan
Update (vision, goals, action items and
implementation matrix)
The Project Team also identified potential alternate
tasks such as an additional graphic or economic
analysis to be determined by the City if needed.
Additional CPC Comments:
• A question of the State Environmental
Quality Review compliance (SEQR) was
asked. The goal of SEQR is to avoid / limit
possible negative impacts on the
environment from proposed actions. The
comprehensive plan update will be subject
to SEQR and the Project will assist the City
Council in complying. At this point, the
preparation of a Long Environmental
Assessment Form (EAF) is contemplated. A
Generic Environment Impact Statement
(GEIS) is typically an entire program / plan
having wide application or restricting the
range of future alternative policies or
projects. If the lead agency has determined
that the proposed action will not have a
significant adverse impact on the
environment, then a negative declaration is
prepared.
Comprehensive Plan Committee Meeting Summary – May 14, 2013 2
• How do we decide if we should acknowledge
alternate task? Alternate task ideas will be
flushed out during initial process, team will
recognize and bring back to CPC for
discussion.
• Suggestion – Can visuals be created that
show old plan vs. new suggestions side by
side (so CPC does not have to flip back and
forth in reading material)
• Will there be an advisory opinion from the
land-use boards? Previous efforts where
plan not shown to land use boards has
caused political problems. This is not
contemplated as part of this process.
However, all land use board members are
encouraged to participate and a
representative from each land use board is
on the CPC. Perhaps there is also an
opportunity for the planning staff to provide
updates to the land use boards – maybe at a
quarterly land use board meeting?
To understand the level of effort and the City’s
approach to the update, the project budget was
explained. The budget is $65,000. To maximize the
budget a short / aggressive schedule has been
identified by the City through the Request for
Proposal process.
One reason team was selected was based on their
knowledge and familiarity with Saratoga Springs (MJ
and Cardinal Direction). The other benefit of the
project team is that River Street also offers fresh
outside perspective for issues that may be
overlooked
Public Workshop #1 has been scheduled for
Wednesday, May 29th. See flyer handout for more
information. The CPC was asked to help spread the
word.
Roles and
Responsibilities The various roles and responsibilities of the CPC, the
project team and the working group were described.
The CPC will guide the plan development, provide
feedback and input through the process and review
the draft plan vision, concepts and action items. The
Comprehensive Plan Committee Meeting Summary – May 14, 2013 3
CPC will also function as a community ambassador
or liaison to their respective organizations and
neighborhoods.
The Working Group includes the City Planning Staff,
the Project Team and the CPC Chair. The role of the
Working Group is to assist with project logistics
(such a meeting scheduling, location, etc) and to
review draft information so that information
provided to the CPC is as complete as possible to
maximize the CPC meeting time.
The Project Team will facilitate and coordinate the
planning process. This will involve constant
coordination with the CPC, the working group and
the public engagement process. The bulk of the
drafting the plan language will be done by the
project team and then provided to the CPC for input.
Additional Discussion about roles and
responsibilities:
• What is CPC role at May 29th public
workshop? Attendance by CPC is
encouraged. This is, however, an
opportunity for the public to share thoughts.
The project team will also share information
gathered from workshop with CPC at next
meeting or via FTP site.
A report card will be prepared for the 2001 adopted
Comprehensive comprehensive plan. The report card will evaluate
Plan Report the (A) status of each plan recommendations (has
Card the recommendation been achieved, it is in
progress/ongoing or not yet been initiated) and (B)
the relevance of the recommendation (what is no
longer relevant, relevant or very relevant). The
purpose of the report card is to understand what
still makes sense, what still needs to be addressed
and what might be missing.
Report Card – The CPC was asked to engage in a series of short
Analyzing the exercises. The first involved identifying what makes
Vision Saratoga Springs unique. The following items were
Statement listed by the CPC:
• Broadway
• high density core
• race track
• “city in the country”
• proximity to Adirondacks and farmland
Comprehensive Plan Committee Meeting Summary – May 14, 2013 4
• diversity
• value of history
• cultural amenities
• Yaddo
• Spa State Park
• downtown area
• SPAC
• “cool, hip college town”
• diversity of employment
• free parking
• school system
• restaurants
• diversity of houses
• City Center
• night life
• walk-ability
• cleanliness
• safety
• two YMCAs within five miles of each other
• healthcare (Saratoga Hospital)
• artists
• access to Saratoga Lake
• Greenbelt
• stewardship
The next exercise involved the CPC evaluating the
existing Vision. Following are CPC discussion items
about the existing Vision:
• Vision statement usually not that long,
should be 2-3 sentences, too broad –
doesn’t say much
• Agree with ideas of sustainability and city in
the country idea within vision, too much
clutter included, must identify goals vs.
vision
• Too long, says nothing
• All things stated are important
• Core elements are located in vision
(sustainability, city in the county, etc.),
missing value in history, needs to be 2-3
powerful sentences
• People see “city in the county” idea
differently – needs to be explained more
clearly so everyone understands concept
and it is not lost
Comprehensive Plan Committee Meeting Summary – May 14, 2013 5
Miscellaneous • The plan update should pay attention to Items noted.
Discussion smooth transitions between zones (city into
Items country), suggestions on how to support
(generated by agriculture and city at the same time? The
the CPC) concept of farm to table should be
evaluated.
• Will the comprehensive plan address the
proposed zoning changes for south
Broadway (former Weathervane property)?
The Comprehensive Plan process is also not
the venue to address projects or
applications currently under review by the
City.
• Clearer definition of city in the country
• “creative place making”
• climate change
• LEED Certification, climate change - great
opportunity to bring ideas up. Don’t
necessarily use LEED checklist. Save money
by paying for LEED certification and use
savings to put into more structures /
infrastructure that will be efficient for the
community.
• How will CPC reach consensus? That will
likely varies by issue and topic – some
majority vote, give and take, etc.
Next CPC Monday, June 17th at 6:00pm – 8:00 pm at the City Project Team to send email
Meeting Recreation Center at 25 Vanderbilt Avenue. (CPC will notice and materials to the
meet every third Monday of the month) CPC approximately one week
in advance of next meeting.
Sharing of information and materials for the CPC
was discussed. The CPC generally prefers email
notices with all project materials.
Identification of The CPC identified the following initial list of Project Team will schedule
Stakeholders stakeholder groups: Sustainable Saratoga, stakeholder group roundtable
Preservation Foundation, Skidmore, Saratoga meetings.
Hospital, Saratoga School District, Saratoga PLAN,
NYRA, Saratoga Chamber, neighborhood
associations, CDTA, Beekman Street Arts, Navy
Housing, Complete Streets, Downtown Business
Association, Special Assessment District
Public Comment Members of the public present, but no comments None.
provided.
This meeting summary conveys our understanding of the items discussed and agreements reached at
this meeting. Please forward any additions, corrections and/or questions to my attention.
Comprehensive Plan Committee Meeting Summary – May 14, 2013 6
Submitted by:
Carly DeThomasis/Jaclyn Hakes
MJ Engineering and Land Surveying, P.C.
cc: City Planning Office, CPC, Project File
Comprehensive Plan Committee Meeting Summary – May 14, 2013 7
6/10/2013
1. Welcome and Introductions
2. Comprehensive Planning 101
3. Project Scope and Process
4. Project Schedule
5. Roles & Responsibilities
6. Discussion: Report Card
7. Next Steps
8. Public Comment
Current State
Families plan to buy a house, to take a vacation,
Opportunities
for a child’s education.
Challenges
Implementation / Monitor
Desired State
es Businesses plan for profit and growth.
Implementation Partners
Ongoing review Vision for future
Communities plan for…
population growth
Action Plan economic growth
roads, community character, property values,
Policies and Tools
tax base, schools, environmental protection,
Achieve the Vision
transit, recreation, pedestrian safety, sewage
disposal, water supply…
1
6/10/2013
Identify Long-term Community Vision
1. Analysis of existing conditions
Community and Stakeholder Input
2. Identification of vision
3. Goals
Outline / Describe pp
Approach to Achieve 4. Action items
Vision 5. Implementation schedule
6. Public/stakeholder input
“If you don't know where you are going,
you'll end up someplace else.”
― Yogi Berra
NYS General City Law §28-a
Adopted 2001 City Charter
Reviewed 2007 (revisions not adopted)
§2.8(F) – Initiation of Reviews
Review Comprehensive Plan every 5 years
Good Practice to evaluate every 10 years
Changing demographic/economic trends
Goals accomplished
1. Project Management
2. Public Participation
3. Analysis of Existing Conditions & Trends
4. Review of Existing Plan Policies and
Strategies (report card)
5. Development of Draft Comprehensive
Plan
2
6/10/2013
1. Concentrated / active engagement
1. Coordination with Project Team, Staff
and CPC 2. Monthly CPC meetings open to public
2. Keep process on track 3. Project Website (interactive)
4. Public Workshops/Meetings (2)
5. Multi-day Public Charrette
6. Stakeholder Group Interviews
7. Formal Public Hearings
8. Periodic City Council Updates
Anticipated Deliverable: Project Schedule
Anticipated Deliverables: Public Participation
Plan/Guide, website, meetings/workshops, formal
hearing
1. Understand changes since 2001
2. Use existing data
Demographics
Socio-economics
Development
Land use
Etc.
3. Mapping
4. Analyze and extract Key Findings
Answer “So What?”
Anticipated Deliverable: Trend Analysis Report & Presentation
1. Review Existing Plan policies, strategies, 1. Build on all previous tasks
goals and recommendations 2. Identify challenges and opportunities
What has been achieved? 3. Develop policies and tools to shape vision
What is in p g
rogress? 4. Illustrate vision with comp plan map
What has not been started? 5. Create action plan and implementation
What does not apply? schedule
What still makes sense?
6. Work with CPC and working group
What is missing?
Anticipated Deliverable: Report Card Anticipated Deliverable: draft plan, updated map,
implementation matrix
3
6/10/2013
Month (2013) Task / Activity
April Project Scoping
May CPC Kick-off / Public Meeting #1 /Website Launch
June Public Charrette / Public Meeting #2
July Develop Draft l
Plan
August Develop Draft Plan
September CPC Public Hearing
October Revise Draft Plan
November Revise Draft Plan
December Advance Draft Plan to City Council
Organizational
Chart
City of Saratoga Springs
Comprehensive Plan
Committee
Working Group
Project Manager
Jaclyn S. Hakes, AICP
Guide the Plan Development
Residents
Provide Feedback & Input
Business Owners
Review Draft Plan Vision, Concepts & Action
Property Owners
Items
Visitors Input!
Stakeholders
Function as an Ambassador / Liaison
Community Partners
Community
Organizations
4
6/10/2013
Facilitate & Coordinate the Planning Process
Project Team CPC
City Planning Staff
Working Group
CPC Chair
Public Engagement
Role:
Synthesize Information
Assist with project logistics
Review Draft Information
Develop Draft Plan
Review Draft Plan Language
What makes Saratoga Springs unique?
1. Review Existing Plan policies, strategies,
goals and recommendations
What has been achieved?
What is in progress?
What has not been started?
What does not apply?
What still makes sense?
What is missing?
5
6/10/2013
What does not apply? This Plan is based on the “City-in-the-Country” concept,
meaning a city with an intensively developed urban core
What still makes sense? and an economically vibrant central business district, with
well-defined urban edges and an outlying area comprised
What is missing? of open lands, a landscape of rural character and low
density residential development. The overriding philosophy
that will guide future development of our "City in the
Country" will be sustainability. Sustainable development is
development that enhances economic opportunity and
- +
community well-being while protecting the amenities upon
which our economy and our community depend. A
sustainable-growth policy recognizes that unlimited growth
Not Relevant Good or Priority is not right for our City; nor is no growth at all. Through
or Important Important Importance sustainable development, we aim to meet the needs of the
present without compromising the ability of future
generations to meet their own needs.
1. Enhance success of downtown core
2. Promote broader mix of uses 1. Downtown is key to economic health
3. Implement land use and design policies 2. Open space resources vital to economy,
4. Promote pedestrian, bicycle, transit access
aesthetics and recreation
5. Invest in amenities contributing to success
6. Support and preserve links of cultural and 3. Provide revenue sources to maintain and
open space resources enhance City services
7. Encourage housing diversity and 4. Diversity of housing types and price levels
affordability 5. Mix of social, cultural, and recreational
8. Work with other communities in region
resources essential
9. Invest in infrastructure improvements
What makes Saratoga Springs unique?
6
6/10/2013
1. Schedule future CPC Meetings
2. Sharing of Information
Public Comments Received
CPC Items for Review
3. CPC Report Card Review
4. Identify Stakeholder Groups
5. Project Kick-Off and Public Workshop #1
May 29, 2013 6:00-8:00 pm
@ City Center
Photo: Jaclyn Hakes 2012