The regular meeting of Council was held this date at 2:00 P.M. in the Council Chambers
of City Hall. The Invocation was given by Alderman Osborne followed by the Pledge of
Allegiance to the Flag. The Minutes of the meeting of June 30, 2011 City Council
Meeting and the June 30, 2011 Summary/Final Minutes of the City Council Workshop
and City Manager’s Briefing were approved upon motion of Alderman Thomas,
seconded by Alderman Jones and carried.
PRESENT: Mayor Otis S. Johnson, Presiding
Mayor Pro-Tem Edna B. Jackson
Alderman Tony Thomas, Chairman of Council
Aldermen Larry Stuber, Clifton Jones, Jeff Felser,
Mary Osborne and Mary Ellen Sprague
City Manager Rochelle D. Small-Toney
City Attorney James B. Blackburn
Asst. City Attorneys William W. Shearouse and Lester B. Johnson, III
ABSENT: Alderman Van Johnson II, Vice-Chairman of Council,
Upon motion of Alderman Thomas, seconded by Alderman Jones, approval was given for
the Mayor to sign an affidavit and resolution for an Executive Session held today to
discuss personnel, where no votes were taken (SEE RESOLUTIONS).
LEGISLATIVE REPORTS
As advertised, the following alcoholic license petitions were heard. No one appeared in
objection to the issuance of the licenses and upon motion of Alderman Thomas, seconded
by Alderman Felser, and carried, they were approved:
ALCOHOL BEVERAGES LICENSE HEARING
April Sanderson for Mimi San LLC d/b/a Sammy Green’s, requesting a beer and wine
(drink) license at 1710 Abercorn Street, which is a new location between E. 33rd and E.
34th Streets in District 1. (New location.) Recommend approval. The TN-2 zoning
permits a restaurant to sell alcoholic beverages provided that such sales must be approved
as a special use by the Zoning Board of Appeals (which did so on June 28, 2011),
outdoor table service is a privilege offered by the City subject to the City’s policy to
regulate uses on City-owned property and public right-of-way, and any outdoor noise
shall be subject to the City’s noise control ordinance.
James A. Shanks for Millies Little Italy, Inc. d/b/a Bella’s Italian Café, requesting a wine
(package with tasting) license at 4420 Habersham Street, which has a beer and wine
(drink) license with Sunday sales and is located between E. 61st and E. 60th Streets in
District 4. (Adding wine tasting and bottle sales.)
Chong C. Wong for Fire Horse Inc. d/b/a Harry’s Liquorama, requesting a liquor, beer
and wine (package) license from Jerry E. Hendrix at 288 Pennsylvania Avenue, which
had a 2011 liquor, beer and wine (package) license and is located between Greenwood
and Capital Streets in District 3. (New owner/applicant.)
1
Allen Gregory Scott for A&M Lounge LLC, requesting a beer and wine (drink) license at
1501 W. Bay Street, which is a new location between Hudson and Millen Streets in
District 1. (New location meets distance requirements for beer and wine but not for
liquor. (Continued from June 16, 2011.) Alderman Jackson asked if the applicants had
met with the community. Tom Vanderhorst, Revenue Director stated they did, indeed
meet with the community. Ms. Pam Oglesby wanted to be on record that she opposed
this because it was not good for the neighborhood. Randall Williams presented signed
petitions from citizens against the lounge. City Manager suggested approval because the
applicant met all requirements; contingent upon applicant getting a Certificate of
Occupancy. Alderman Felser asked the City Attorney if the Council was allowed to
consider if the establishment would be a nuisance in the proposed use. Attorney
Blackburn stated the nuisance has to be created before it becomes a nuisance. If Council
denies the request they would need to state legal reasons for denial. The applicant would
be entitled to a hearing to determine if they can meet all legal requirements. Alderman
Felser questioned the parking issue. Randolph Scott, Zoning Administrator stated he
received 2-letters authorizing remote parking. Alderman Felser pointed out that one of
the owners of the funeral home signed the letter and another one signed the petition. City
Attorney Blackburn suggested the request be continued and ask the Zoning Administrator
to give a zoning report and have the petitioner give in writing how they will meet the
zoning requirements. Allen Scott, the petitioner, presented the Council with a petition
himself. Upon motion by Alderman Felser, seconded by Alderman Thomas and carried,
the request will be heard July 28, 2011.
PETITIONS
Marsha Rodrigues – Petition 13303, requesting that the City declare surplus the 90’
unopened portion of Panama Street, lying north of 56th Street, in order to offer it to the
adjacent property owners. The unopened right-of-way is located as it dead-ends into 56th
Street Lane, west and adjacent to Ms. Rodriguez’s property at 1502 E. 56th Street (PIN 2-
0097-19-008) in the Sackville neighborhood. The petitioner believes that closing the
unopened right-of-way will reduce crime, drug activity, and illegal dumping. The
petition has been reviewed by Water Resources and Public Works, Sanitation, and
Development Services. Water Resources and Sanitation both recommend approval.
Development Services recommends approval of the petition subject to the adjacent
property owners agreeing with this petition. Recommend that the City declare surplus the
90’ unopened portion of Panama Street, in order to offer it to the adjacent property
owners
Dr. Walter O. Evans for Walter O. Evans Trust, Property Owner – Petition 13290,
requesting to encroach onto City right-of-way at 411 W. Alice Street (PIN 2-0045-15-04)
for the construction of entry stoops. The property is legally described as Lot 11-A as
shown on a plat of a “Minor Subdivision of Lots 11, 12, and 13, Berrien Ward” and is
located on the southerly side of W. Alice Street, between Martin Luther King Jr.
Boulevard and Montgomery Street. The right-of-way is the sidewalk that fronts this
property. The petitioner plans to construct four townhomes and requests the
encroachment in order to provide entry stoops into the individual units. Historical maps
show a row of six townhomes that previously existed on the site with similar
encroachments. Comparable conditions are found in the surrounding area. The design
has been approved by the Historic Review Board. The petition has been reviewed by
Water Resources and Public Works, Sanitation, and Development Services. Water
Resources and Sanitation both recommend approval. Development Services recommends
approval subject to the property owner assuming responsibility for maintenance of the
entry stoops and all liability. All City permitting and construction guidelines must be
followed, and the entry stoops must meet all federal, state and local codes. Recommend
advising the petitioner of the above conditions. Recommend also advising the petitioner
that the encroachment grants no ownership rights to the property and that, if ever
required, the structures must be removed at petitioner’s expense.
Upon motion by Alderman Thomas, seconded by Alderman Felser and carried, the
petitions were approved.
2
ORDINANCES
Ordinance read for the first and second time in Council July 14, 2011 placed upon its
passage, adopted and approved upon motion of Alderman Thomas, seconded by
Alderman Felser and carried.
No Parking – Graham Street. An ordinance to prohibit on-street parking on the west side
of Graham Street from Bay Street to Hudson Street. Parking on both sides of the street
creates a safety hazard as motorists do not have good visibility of children crossing the
street going to and from Hudson Park. This no parking zone would complement an
existing no parking zone along the Hudson Street side of the park. (Traffic Engineering
Report approved June 30, 2011.)
Ordinance read for the first and second time in Council July 14, 2011 placed upon its
passage, adopted and approved upon motion of Alderman Thomas, seconded by
Alderman Felser and carried.
Taxi Fuel Surcharge. An ordinance to amend Code Section 6-1458, Maximum rates of
fare; posting required, to make a fuel surcharge permanent when regular unleaded gas
prices move above $3.50 per gallon. The surcharge would add $1.00 to all fares when
gas prices are above $3.50 per gallon and $2 to all fare when gas prices are above $4.00
per gallon. This is being recommended due to the volatile nature of gasoline prices over
the last two years. Although taxis receive an inflationary increase in fares annually, fuel
prices have far exceeded those inflationary increases. The surcharge would stay in effect
until March of 2015 when it would be evaluated and possibly adjusted again. Mayor
Johnson stated this is a result of work of the Mobility Department, the Taxi Cab
Community, Acting Assistant City Manager Marty Johnston, and City Manager Toney.
RESOLUTIONS
A RESOLUTION OF THE MAYOR AND ALDERMEN OF THE CITY OF
SAVANNAH AUTHORIZING THE MAYOR TO SIGN AFFIDAVIT OF
EXECUTIVE SESSION
BE IT RESOLVED by the Mayor and Aldermen of the City of Savannah as follows:
At the meeting held on the 14th day of July, 2011 the Council entered into a closed
session for the purpose of discussing personnel. At the close of the discussions upon this
subject, the Council reentered into open session and herewith takes the following action
in open session:
1. The actions of Council and the discussions of the same regarding the matter set forth
for the closed session purposes are hereby ratified;
2. Each member of this body does hereby confirms that to the best of his or her
knowledge, the subject matter of the closed session was devoted to matters within the
specific relevant exception(s) as set forth above;
3. The presiding officer is hereby authorized and directed to execute an affidavit, with
full support of the Council in order to comply with O.C.G.A. §50-14-4(b); 17
4. The affidavit shall be included and filed with the official minutes of the meeting and
shall be in a form as required by the statute.
ADOPTED AND APPROVED THIS 14th DAY OF JULY UPON MOTION BY
ALDERMAN THOMAS, SECONDED BY ALDERMAN JONES AND CARRIED.
*****************************************
A RESOLUTION TO AUTHORIZE THE EXECUTION OF AN EASEMENT TO
GEORGIA POWER FOR TRANSMISSION LINES CROSSING THE CITY-OWNED
PROPERTY LOCATED AT 100 WALZ CIRCLE, PIN 2-0115-09-001.
WHEREAS, the Mayor and Aldermen of the City of Savannah are authorized by Georgia
law to grant easements across municipal property for the benefit of the public and for
such compensation as deemed reasonable; and
3
WHEREAS, this request will serve the interests of Georgia Power in allowing the
relocation and installation of transmission lines associated with improving service in the
area; and
WHEREAS, the Mayor and Aldermen of the City of Savannah find that the request for an
easement to allow a transmission line across the property at 100 Walz Circle is in the
interest of the community at large; and
WHEREAS, it has been determined that said lines will not interfere with the operation of
the adjacent City facilities;
NOW, THEREFORE, the Mayor and Aldermen in regular meeting assembled, with more
than two-thirds of the Aldermen present and voting in the affirmative, approve the
granting of said easement and authorize the City Manager to execute the easement
document in conformance with this Resolution.
ADOPTED AND APPROVED THIS 14th DAY OF JULY UPON MOTION BY
ALDERMAN FELSER, SECONDED BY ALDERMAN STUBER AND CARRIED.
****************************************************
A RESOLUTION TO AUTHORIZE THE EXECUTION OF AN ENCROACHMENT
AGREEMENT FOR EASEMENT WITH GEORGIA POWER COMPANY FOR THE
CONSTRUCTION, OPERATION AND MAINTENANCE OF A 72” STORM LINE
ACROSS AN EXISTING GEORGIA POWER TRANSMISSION LINE.
WHEREAS, the City of Savannah needs to replace a failing brick line with a new line
connecting an existing 60” storm line located within a private drive (lying east of Warner
Street and north of Bay Street) and the Springfield Canal; and
WHEREAS, the new line will cross a forty (40’) foot Georgia Power transmission line
(easement); and
WHEREAS, Georgia Power Company requires an encroachment agreement in order for
the City to install and maintain said line across their easement;
NOW, THEREFORE, the Mayor and Aldermen in regular meeting assembled, with more
than two-thirds of the Aldermen present and voting in the affirmative, authorize the City
Manager to execute the Governmental Encroachment Agreement for Easement with
Georgia Power Company in conformance with this Resolution.
ADOPTED AND APPROVED THIS 14th DAY OF JULY UPON MOTION BY
ALDERMAN FELSER, SECONDED BY ALDERMAN STUBER AND CARRIED.
***************************************************
WHEREAS the City of Savannah has been awarded two Housing Opportunities for
Persons With AIDS (HOPWA) grants, on behalf of project sponsor, Union Mission, Inc.,
from the U.S. Department of Housing and Urban Development totaling $954,974; and
WHEREAS these two grants are in the amount of $685,696 and $269,278; and
WHEREAS it is necessary for the City to enter into a grant agreement in the amount of
$666,995.00 with Union Mission, Inc. to implement the project known as Project House
Call- Renewal #4. This amount represents the total grant amount of $685,696.00 less
$18,701.00 in administrative fees to be retained by the City of Savannah.
WHEREAS it is necessary for the City to enter into a grant agreement in the amount of
$261,934.00 with Union Mission, Inc. to implement the project known as Daniel-Flagg
Villas-Renewal #3. This amount represents the total grant amount of $269,278.00 less
$7,344.00 in administrative fees to be retained by the City of Savannah.
4
NOW, THEREFORE, BE IT RESOLVED that the Mayor and Aldermen of the City of
Savannah, Georgia, hereby resolve and authorize Rochelle D. Small-Toney, City
Manager, to enter into two grant agreements with Union Mission, Inc. for the purposes
cited above.
ADOPTED AND APPROVED THIS 14th DAY OF JULY UPON MOTION BY
ALDERMAN JONES, SECONDED BY ALDERMAN JACKSON AND CARRIED.
********************************************
Upon motion of Alderman, seconded by Alderman and carried, the following bids,
contracts and agreements were approved:
BIDS, CONTRACTS AND AGREEMENTS
E911 Back-Up System for Emergency Command and Control Center – Sole Source –
Requisition No. 11203454. Approval to procure a back-up E911 System from
AT&T/Positron in the amount of $312,289.00 and for a year of maintenance services for
the system in the amount of $28,260.00 for a grand total of $340,549.00. The
maintenance will begin 30 days following installation of the system. This system will be
installed at the E911 Backup Center currently being constructed at the Civic Center. It
will provide failover backup services to the E911 system in operation at the main
Dispatch Center. The recommended system incorporates newer technology such as voice
over internet protocol (VOIP) and addresses the increasing use of wireless devices
instead of landlines. Funds are available in the 2011 Budget, E911 Wireless
Reserve/Wireless Reserve/Office/Building Furniture/Equipment (Account No. 242-4140-
51520).
Savannah Gardens Design Services – Contract Modification No. 3 – Bid No. 09.066.
Approval of Contract Modification No. 3 in the amount of $117,550.00 with Thomas &
Hutton for additional design services. The original contract with Thomas & Hutton was
for the construction observation of Phase 2A & 2B concurrent with the observation of
Phase 1 of this project. Due to funding sources at the time, only Phase 1 of the project
was initially awarded. As a result of separating the construction schedules, separate
construction and project acceptance services are required and will thus extend the
contract with Thomas & Hutton. The City’s general contractor for infrastructure,
ASTRA Group, is nearing completion of Phase 1 infrastructure and is preparing to begin
Phase 2A and 2B infrastructure. The City Council approved funding Phase 2A and 2B
infrastructure on March 10, 2011. We are now seeking approval to amend Thomas &
Hutton’s contract with the City so funds will be available for them to monitor Phase 2A
and 2B infrastructure. Approval of Contract Modification No. 3 in the amount of
$117,550.00. Funds are available in 2011 Budget, Capital Improvement Fund/Capital
Improvement Projects/Other Costs/Savannah Gardens Phase I (Account No. 311-9207-
52842-PD400).
Savannah Gardens Phase I Civil Site Construction – Contract Modification No. 1 – Bid
No. 10.156. Approval to procure Contract Modification No. 1 from Astra Group, Inc. in
the amount of $147,551.81. Due to field conditions for underground work in Savannah,
changes to the plans were necessary to avoid conflicts in the field and to build the project
to City’s specifications. The force main along Elgin Street was not able to be located
during the design nor was it in the location where the original as-built had it located.
Once located it was found to be in conflict with the sanitary sewer line. For work along
the east side of Elgin Street, a sewer line had to be relocated to avoid the 72” storm sewer
line. The water line in the same area required a gate valve. Additional sewer was needed
along Elgin Street to accommodate the CHSA Phase III housing units. Along Greenville
and Vincent Streets, a protector sanitary sewer line was needed because of grade changes.
EZ Valves were requested by the Water Department. These valves were different than
what were on the plans; however, these are the same type of valves the Water Department
currently uses. Phase I of Savannah Gardens Infrastructure is nearing completion and all
facilities installed are working. Twenty-nine calendar days are being added to the
contract. Approval of Contract Modification No.1 to Astra Group, Inc. in the amount of
$147,551.81. Funds are available in the 2011 Budget Capital Improvements
5
Fund/Capital Improvements Projects/Other Costs/Savannah Gardens Phase I (Account
No. 311-9207-52842-PD400).
Laundry Facilities for Grayson Stadium – One Time Purchase – Bid No. 11.120.
Approval to procure construction services from Harbor Construction and Contracting,
LLC in the amount of $64,800.00. The services will be used by Design and Construction
to renovate an area under the west bleachers at Grayson Stadium to provide an in-house
laundry facility for the players. Minor League Baseball is requiring that all stadiums
provide in-house laundry facilities for both the local and visiting players. Per the City’s
contract with the Sand Gnats, the City must provide this service to maintain the stadium’s
rating as a minor league facility. Delivery: As Required. Terms: Net-30 Days. Funds
are available in the 2011 Budget, Capital Improvement Fund/Capital Improvement
Projects/Other Costs/Grayson Stadium Renovations (Account No. 311-9207-52842-
PB227).
Mohawk Street Fire Station No. 11 – Contract Modification No. 8 – Bid No. 10.138.
Approval of Contract Modification No. 8 in the amount of $27,961.00 with Dabbs-
Williams for construction of the fire station located on Mohawk Street. The
modifications include a ($1,589.00) reduction in cost for the elimination of the exterior
sign and the removal of restroom accessories from the original contract. Both will be
purchased outside of the construction contract. The modifications also include the
addition of electrical heaters in the apparatus bay and an upgrade of the electrical system
that will cost an additional $29,550.00. The heating apparatus was not included in the
original contract but has since been determined to be needed for department operations
and to maintain the department’s ISO rating. Approval of Contract Modification No. 8 to
Dabbs-Williams in the net amount of $27,961.00. Funds are available in the 2011
Budget, Capital Improvements Fund/ Capital Improvements Projects/Other
Costs/Southside Fire Station (Account No. 311-9207-52842-PB520).
Savannah-Chatham Metropolitan Police Department Police Support and Training Center
Administration Building Design Services – Contract Modification No. 3 – Bid No.
08.293. Approval of Contract Modification No. 3 in the amount of $54,302.00 with
Watkins & Associates. The original contract was for architectural design for the SCMPD
police support and training center administration building design services. The
modification requires additional site modifications to reduce the construction cost of the
site and building. The services include changes to the existing design drawings and
production of new site design drawings. Approval of Contract Modification No. 3 to
Watkins & Associates in the amount of $54,302.00. Funds are available in the 2011
Budget, Capital Improvements Fund/Capital Improvements Projects/Other Costs/Public
Safety Training Facility (Account No. 311-9207-52842-PB836).
Engineering Service for Project DeRenne – Contract Modification No. 8. Authorization
to amend the contract with Kimley-Horn and Associates in the amount of $85,147.00 to
reflect changes suggested by Federal Highway Administration (FHWA ) staff to the
development of the Project Concept Report. The project we now know as Project
DeRenne has evolved as three separate projects in the MPO/GDOT Transportation
Improvement Plan (TIP). The three projects are East DeRenne, area east of Abercorn;
West DeRenne, Abercorn to 516; and the New Boulevard Option, the new connector
between 516 and White Bluff Road. The DeRenne Project team had intended to
consolidate these three into the single project we know as Project DeRenne, however,
FHWA staff suggest that regulatory approval would likely be better handled as the
existing three separate projects. This proposed contract amendment will enable efforts to
create the three newly required Project Concept Reports to continue while staff finalizes
the terms of an Intergovernmental Agreement with the County to release SPLOST funds
for the third phase of Project DeRenne.
SPA Park Water and Sewer Improvements Engineering Services – RFP No. 11.103.
Approval for engineering consulting services for the SPA Park Water & Sewer
Improvements to Thomas & Hutton Engineering in the amount of $268,800.00. SPA
Park was annexed by the City of Savannah 10 years ago but the water and sewer
infrastructure has been operated and maintained by Chatham County. The purchase of
the water and sewer system was approved in May of 2010 but has not yet been completed
due to acquisition of easements. The water improvement will ensure the business
6
establishments within the park will have adequate fire flow to meet the existing needs as
well as to provide water and sewer service for future expansions. This project includes
design and construction services to provide water and to improve existing force mains.
The method used for this procurement was the Request for Proposal which evaluates
other criteria in addition to price. The criteria evaluated as part of this RFP were
experience designing of similar projects, project approach, project team, schedule and
MWBE participation as well as cost. Proposals were received from ten firms and
evaluated on the stated criteria. The reason for not awarding to the lowest proposer was
that following evaluation of the proposals, it was determined through interviews with the
low proposer that the firm did not submit fees based on the requirements of the RFP but
rather on what the firm thought should be done for the work. While the firm was willing
to do the work for the submitted fees, City staff felt that the extreme low price was not
adequate enough to complete a quality project with the necessary hours for construction
inspection and proper document preparation, and recommends award to the next low
proposer. Delivery: 226 Days. Terms: Net-30 Days. Funds are available in the 2011
Budget, Capital Improvements Fund/Capital Improvements Projects/Other Costs/SPA
Park (Account No. 311-9207-52842-WT527).
Guardrail Repair and Installation – Annual Contract Renewal – Bid No. 11.153.
Renewed an annual contract to procure guardrail repair and installation services from
Leon's Fence and Guardrail in the amount of $81,250.00. The contract is used by Streets
Maintenance primarily to repair guardrail along Truman Parkway and on City streets as
needed. This is the last of two renewal options available. The reason for not originally
awarding to the low bidder is that SS Property Pros is no longer in business. Leon's was
the secondary contractor and has performed most of the contract work in the past year.
Delivery: As Required. Terms: Net-30 Days. Funds are available in the 2011 Budget,
General Fund/Street Maintenance/ Other Contractual Services (Account No. 101-2105-
51295).
Brake Parts for Medium to Heavy Trucks – Annual Contract Renewal – Bid No. 11.154.
Renewed annual contract to procure brake parts from TNT Parts, Inc. in the amount of
$27,430.62. The brake parts will be used by Vehicle Maintenance to repair and maintain
heavy duty trucks in the City’s fleet. This is the first of two renewal options available.
Delivery: As Required. Terms: Net-30 Days. Funds are available in the 2011 Budget,
Internal Service Fund/Inventory-Vehicle Parts (Account No. 611-0000-11325).
Mikell Avenue/SR 307 Intersection Upgrade – Bid No. 11.111-6-21 – Savannah/Hilton
Head International Airport. The Savannah Airport Commission received authorization to
enter into a contract with E & D Contracting Services, Inc. in the amount of $155,867.00
for modifications to the Mikell Avenue/SR 307 intersection which will include a new
four-way traffic signal and appurtenances. This project is being funded in its entirety by
the Georgia Air National Guard.
Military Construction Cooperative Agreement with Georgia Air National Guard –
Modification No. 1 – Savannah/Hilton Head International Airport. The Savannah Airport
Commission received approval of Modification No. 1 to the Military Construction
Cooperative Agreement (MCCA) with the Georgia Air National Guard (GaANG) for
Mikell Avenue/SR 307 Intersection Upgrades. The original GaANG estimate of
$120,000.00 for the project was lower than the low bid from E&D Contracting Services,
Inc. The GaANG submitted Modification No. 1 of the MCCA in the amount of
$39,659.22 to the National Guard Bureau which will cover the deficit of $35,867.00 on
the low bid. This cost also covers the architectural and engineering services in the
amount of $3,792.22 for a revised overall total of $159,659.22.
Coffee Bluff Marina Design Services – Bid No. 11.104. Approval to award a contract for
architectural consulting services for the Coffee Bluff Marina from EMC Engineering in
the amount of $190,667.00. The project includes design services to upgrade the marina
facility and bulkhead, improve roadways and parking areas, grassing and landscaping, an
ADA compliant restroom, playground and picnic areas, floating dock and a new fishing
pier/observation deck. The consultant will provide: a site survey, geotechnical reports,
soil testing, evaluations and reports for all existing facilities, design development, a
master plan for redevelopment, a cost estimate for construction and signed and sealed
architectural and engineering drawings. The method used for this procurement was the
7
Request for Proposal which evaluates other criteria in addition to price. The criteria
evaluated as part of this RFP were qualifications and experience, proposed methodology,
schedule, references and MWBE participation as well as cost. Proposals were received
from ten proposers and evaluated on the stated criteria. Delivery: 120 Days. Terms:
Net-30 Days. Funds are available in the 2011 Budget, Account No. 311-9207-52842-
RE309. Alderman Thomas thanked the Council for their support and thanked City
Manager Toney and her staff who worked on this project. This will be the only marina in
the City limits.
***************************************
APPOINTMENTS TO BOARDS, COMMISSIONS, & AUTHORITIES
COASTAL REGIONAL METROPOLITAN PLANNING ORGANIZATION
Susan Dyer
Motion by Alderman Jackson, seconded by Alderman Thomas and carried.
COSTAL WORKFORCE INVESTMENT BOARD
Marti Barrow - Kathy S. Love - Angela Watkins - Harland A. Proveaux
Reginald L. Hendricks (re-appointed) - Peter R. Doliber (re-appointed)
Motion by Alderman Thomas, seconded by Alderman Sprague and carried.
CODE ENFORCEMENT APPEALS BOARD
William Coonce
Motion by Alderman Jackson, seconded by Alderman Thomas and carried.
CULTURAL AFFAIRS COMMISSION
Elaine Shavers Campbell - Gretta Brannigan - Deborah Porter Glenn
Motion by Alderman Osborne, seconded by Alderman Felser and carried.
ELECTRICAL APPEALS AND ADVISORY BOARD
Paul Mamalakis (Re-appointed)
Motion by Alderman Felser, seconded by Alderman Osborne and carried.
GREATER SAVANNAH INTERNATIONAL ALLIANCE
Araceli Harper - Justin A. Godchaux (Alternate)
Motion by Alderman Thomas, seconded by Alderman Felser and carried.
HISTORIC DISTRICT BOARD OF REVIEWS
Keith Howington to fill a full-term; Stephen Glenn Merriman to fill an un-expired term.
Motion by Alderman Felser, seconded by Alderman Stuber and carried.
HOUSING AUTHORITY OF SAVANNAH
Celia H. Irvine
Motion by Alderman Thomas, seconded by Alderman Jackson and carried.
KEEP SAVANNAH BEAUTIFUL
Lisa Hudson - Carl A. Miller
Motion by Alderman Osborne, seconded by Alderman Thomas and carried.
PARK AND TREE COMMISSION
Russ Lee - Paul Hammond
Motion by Alderman Thomas, seconded by Alderman Sprague and carried.
PROPERTY MAINTENANCE AND ENFORCEMENT BOARD
Victor J. Tetreault
Motion by Alderman Jones, seconded by Alderman Thomas and carried.
SAVANNAH / CHATHAM COUNCIL OF DISABILITY NEEDS
Elena Thompson - Melinda Y. Miller - Marjorie Weibe-Reed - Frank Lala
Kathleen R. Holmes - Shane Berryhill
Motion by Alderman Thomas, seconded by Alderman Sprague and carried.
8
SAVANNAH FILM COMMISSION
Murray Silver - Bailey Davidson
Motion by Alderman Jones, seconded by Alderman Felsers and carried.
SAVANNAH RECREATION COMMISSION
George B. Shaw
Motion by Alderman Jackson, seconded by Alderman Sprague and carried.
SAVANNAH ZONING BOARD OF APPEALS
Quentin L. Marlin
Motion by Alderman Felser, seconded by Alderman Thomas and carried.
The City will advertise, for 30 days, openings for the Metropolitan Planning
Commission. Applicants must be City residents.
**************************************************
Alderman Sprague had tickets for a fund raiser for the United Way Women’s Legacy
Council for people needing transportation for medical appointments and job interviews.
Alderman Felser stated the appointments to the Boards and Commissions were discussed
in an open session and he felt it was for the good of the order.
Alderman Thomas spoke with Georgia Power and he was assured all 27,000 street lights
would be getting new bulbs over the next month.
There being no further business, Mayor Johnson declared this meeting of Council
adjourned.
Dyanne C. Reese
Clerk of Council