Finance
1 Presentation – The Downtown Schenectady Assessment District (DSAD) Budget (PH 11-22-21) Jim Salengo
Presentation – The Upper Union Street Business Improvement District (BID) Budget (PH 11-22- Chris DiCocco
2
21)
3 City Council to Act as Lead Agency and Issue a Negative Declaration to SEQR Anthony Ferrari
4 Bond Ordinance for Construction of Water Well Anthony Ferrari
5 Discussion – Preliminary ARPA Survey Gary R. McCarthy
Public Safety
1 FY2021 State Homeland Security Grant Program (SHSP) Mike Seber
City Development & Planning
Authorize the Issuance of Revocable Permit No. 663 to Simply Beautiful for a Sign that Will Chris Wallin
1
Overhang the City’s Right-of-Way at 158 Jay Street, Schenectady, New York
A Call for a Public Hearing: Right-of-Way Acquisition for the Kings Road over Amtrak / CSX Chris Wallin
2
Bridge Replacement Project – PIN 1758.95
Supplemental Agreement #2, PIN 1760.62 (D035937) Nott Street (Rosa Road to Wendell Chris Wallin
3
Avenue) Paving, City of Schenectady, Schenectady County
4 CR – Schenectady Belmont Pop Warner Marion Porterfield
Government Operations
1 Discussion – OSM Broadcast of City Council and Committee Meetings John Polimeni
Discussion – Calling for a Public Hearing to Amend Chapter 87-11 of the Code of the City of Marion Porterfield
2
Schenectady regarding Holidays (Follow-up from 06/21/2021 re: Juneteenth)
3 Discussion – Seating 2 New Council Members to Fill Vacancies John Mootooveren
Claims
1 James Gulneck v. City of Schenectady Andrew Koldin
2 Edward Ritz v. City of Schenectady Andrew Koldin
3 Lisa Williams v. City of Schenectady Andrew Koldin
Monday, November 15, 2021
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Finance Committee Date: Monday, November 15, 2021
From: Jim Salengo
Subject Reminder - The 2022 Downtown Special Assessment District (DSAD) Budget (PH held on 11-22-
2021)
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
SCHENECTADY DOWNTOWN SPECIAL ASSESSMENT DISTRICT (0540)
2022 Budget - APPROVED 11-2-21 Page I of 2
2021 DSAD ASSESSMENT 2022 DSAD ASSESSMENT
DSIC Program Category ALLOCATED TO DSIC ALLOCATED TO DSIC
Total DSAD Assessment Levy for 2022 $305,160 $330,000
Total DSAD Assessment Levy for 2022 - Frontage Factor $152,580 $165,000
Total DSAD Assessment Levy for 2022 - Size Factor $152,580 $165,000
Total of DSIC Programs $747,531 $882,657
2021 2022
Base Participation Fee $295 $315
NOTES
4. The funding reflected in the budget of the Downtown Special Assessment District (DSAD) as approved by City Council represents
a portion of the funding utilized by the Downtown Schenectady Improvement Corporation (DSIC) for its operations, as set forth in the
separate budget of the DSIC.
2. A base participation fee is determined by calculating a percentage of total DSIC programming (not to exceed 25%) and dividing it
by all eligible parcels (506). The percentage proposed in 2022 is 18.16%.
Downtown Schenectady Improvement Corporation
2022 Budget - APPROVED 11-2-21 - Page 2 of 2
Difference
Business Comm. & Marketing Environmental Enhancement &
Administration 2022 TOTALS 2021 TOT ALS Between 2022 &
INCOME & Development Maintenance
2021
1 Donations/Soonsorshios 41 ,500 17,000 58,500 40,300 18,20 €
2 DSAD Assessment 9,900 99,000 221,100 330,000 305,160 24,840
3 EEM Greenmarket Assistance 1 ,000 1 ,000 1 ,000 0
4 EEM Landscaping Services - Metroplex 100,000 100,000 55,000 45,000
5 Grant Revenue - Other 750 22,500 16,750 40,000 o 40,000
6 Marketing Participation Fees o 3,000 -3,000
7 Metroplex Operating Grant 240,000 240,000 240,000 o
8 Parking Note Receivable (Interest)" 2,870 2,870 4,243 -1 ,373
9 Product Sales/Silent Auction o o o
10 Ticket Sales/Vendor Fees 47,000 47,000 40,000 7,000
INCOME TOT ALS 10,650 212,870 595,850 819,370 688,703 130,667
Difference
Business Comm. & Marketing Environmental Enhancement &
EXPENSES Administration 2(122 TOT ALS 2021 TOT ALS Between 2022 &
& Development Maintenance
2021
1 Advertising 10,050 1 ,300 11,350 5,460 5,890
2 Business Development 500 o 500 500 o
3 Communications/Phone/Internet 243 2,434 5,436 8,113 8,447 -334
4 EEM Contracted Services 3,000 3,000 2,600 400
5 EEM Landscape Services - Materials/Supplies 5,000 5,000 5,000 o
6 Equipment 30 305 680 1,015 o 1,015
7 Fees/License/Permits 18 179 400 597 374 223
8 Gas - EEM Equipment 6,300 6,300 6,000 300
9 Insurance (Liability, D&O, NYSIF, etc.) 973 9,727 21 ,724 32,424 26,127 6,297
10 Flowers 15,200 15,200 15,200 o
11 Lease/Utilities - EEM Garage 28,080 28,080 12,300 15,780
12 Mileage Reimbursement 6 60 134 200 300 -1 00
13 Maintenance/Repairs 435 4,350 9,715 14,500 13,000 1 ,500
14 Memberships 61 606 1 ,353 2,020 1 ,066 955
15 Networking/Sponsorships/Meals 300 3,000 6,700 10,000 5,500 4,500
16 Office Lease 825 8,250 18,425 27,500 26,000 1 ,500
17 Postage/Mailing 33 330 737 1,100 500 600
18 Professional Services 1,940 19,403 43,333 64,676 54,010 10,666
19 Printing 465 4,650 10,385 15,500 2,400 13,100
20 Salaries/Benefits 17,333 173,335 387,114 577,782 513,432 64,350
21 Special Events/Promotions 34,000 34,000 30,700 3,300
22 Subscriptions 36 360 804 1,200 1,216 -16
23 Supplies 318 3,180 7,102 10,600 8,000 2,600
24 Outdoor D6cor 7,500 7,500 4,900 2,600
25 Utilities - Office 90 900 2,010 3,000 3,000 o
26 Work Clothes - EEM o 1 ,500 1 ,500 1 ,500 o
EXPENSETOTALS 23,107 275,618 583,932 882,657 747,531 135,126
DIFFERENCE -12,457 -62,748 11,918 -63,287 -58,828
Appropriation of 2022 Parking Payment' 47,130 45,757
DIFFERENCE -16,157 -13,071
Appropriation of General Fund Balance 16,157 13,323
DIFFERENCE o o
Remaining Parking Funds Deposited to Reserve Account
"Note: Parkjng Note Receivable (Interesd) of'J2,870* Appropriation of 2022 Parking Payment 547,130 = !550,000 Annual Parking Payment
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Finance Committee Date: Monday, November 15, 2021
From: Chris DiCocco
Subject Reminder - The 2022 Upper Union Street Business Improvement District (BID) (PH held on 11-22-
2021)
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
Upper Union Street Business Improvement District
2022 Projected Budget
28-Oct-21
Budget
Income
Assessment $ 46,100
Donation Received -
Total Income $ 46,100
Expenses
Advertising 8,000
Bank Service Charges 64
Dues & Subscriptions 400
Executive Director 12,000
Fees (NY) 50
Holiday Festival 2,000
Insurance 1,100
Landscaping 4,000
Marketing Consultant 3,000
Meeting Expense 600
Member Support -
Office Expense 250
Professional Fees 900
Scholarship Expense 2,000
Snow Removal 6,000
Storage 2,400
Urban Beautification (Banners/Lights) 3,000
Miscellaneous 250
$ 46,014
Profit (Loss) $ 86
City of Schenectady
Legislative Request Form
COMMITTEE ASSIGMENT: F7 DATE:11/12/2021
TO: City Council
FROM: Anthony Ferrari
SUBJECT: Act as Lead Agency and Negative Declaration to SEQR
TO BE PLACED ON COUNCIL AGENDA OF: November 15, 2021
Background Information:
The City of Schenectady wishes to make improvements to the existing water treatment
plant to prevent possible issues with the reliability and quality of the source supply;
The City of Schenectady proposes to address this issue by:
Installation of three new production wells, complete with well house buildings,
well pumps, variable frequency drives, valves, vaults, and piping;
Replacement of the three existing 24-inch venturi flow meters and vaults;
Removal, replacement, and consolidation of the existing piping within the
northern area of the site;
Removal and replacement of all tanks, equipment, piping, conduits, lighting,
electrical, and ventilation equipment within the fluoride bulk and day storage
buildings;
Installation of a redundant chlorine injection system within an existing
building (liquid sodium hypochloride);
Emergency interconnection along Rice Road with the Town of Rotterdam;
Replacement and upsizing of one of the existing diesel generators;
Roof and HVAC Replacements for the existing active well houses;
Roof replacement for the main treatment building;
Installation of additional security cameras around the site property;
Supervisory Control and Data Acquisition (SCADA) improvements to
allow continuous monitoring between the City’s main treatment facilities; and
Other miscellaneous improvements to support the work outlined above to
increase the redundancy and resilience in the City’s water supply system.
Evaluation/Analysis: The project which will modernize the system to reliably meet
the needs of future generations, is consistent with the goals and objectives of the City
of Schenectady; and
This project is an Unlisted Action pursuant to the State Environmental Quality Review
Act (SEQR) and therefore subject to the regulations of that law (6 NYCRR 617); and
The City of Schenectady has conducted coordinated review with the involved agencies
pursuant to 6 NYCRR 617.6 and no agencies objected to the City of Schenectady’s
request to act as Lead Agency;
and the City of Schenectady has reviewed the potential impacts identified in the Parts 1,
2 and 3 of the Full Environmental Assessment Form (EAF) and as a result has found no
significant impacts that would potentially occur as a result of the project;
Recommendation: We respectfully recommend that the City Council approve the
Negative Declaration Pursuant to the State Environmental Quality Review Act.
LEGISLATION WILL BE PREPARED BY_
Law Department
CITY OF SCHENECTADY
LEGISLATIVE REQUEST FORM
COMMITTEE ASSIGNMENT: FINANCE DATE: November 11, 2021
TO: CITY COUNCIL
FROM: ANTHONY FERRARI
SUBJECT: Bond Ordinance for Construction of Water Wells
TO BE PLACED ON COUNCIL AGENDA OF November 15,2021
Background Information: The City wishes to make improvements to the
existing water treatment plant to prevent issues with reliability and quality of
the source supply. The City proposes to address this issue Installation of three
new production wells, complete with well house buildings, well pumps,
variable frequency drives, valves, vaults, and piping;
Replacement of the three existing 24-inch venturi flow meters and vaults;
Removal, replacement, and consolidation of the existing piping within the
northern area of the site;
Removal and replacement of all tanks, equipment, piping, conduits, lighting,
electrical, and ventilation equipment within the fluoride bulk and day storage
buildings;
Installation of a redundant chlorine injection system within an existing
building (liquid sodium hypochloride);
Emergency interconnection along Rice Road with the Town of Rotterdam;
Replacement and upsizing of one of the existing diesel generators;
Roof and HVAC Replacements for the existing active well houses;
Roof replacement for the main treatment building;
Installation of additional security cameras around the site property;
Supervisory Control and Data Acquisition (SCADA) improvements to
allow continuous monitoring between the City’s main treatment facilities; and
Other miscellaneous improvements to support the work outlined above to increase the
redundancy and resilience in the City’s water supply
Evaluation/Analysis: , To offset the cost of this project, the City of Schenectady is
applying for financing through the New York State Clean Water State Revolving Fund.
The City Of Schenectady projects to be eligible for $6 million in WIIA grant funding.
Recommendation: It is respectfully recommended that the City Council approve
and authorize the financing of the Purpose as defined in Section 2 hereof by the issuance
of bonds and notes in an aggregate amount not to exceed [$7,775,470], including costs of
issuance for the City Water Supply.
LEGISLATION WILL BE PREPARED BY: LAW DEPARTMENT
EXTRACT OF MINUTES OF MEETING OF THE CITY
COUNCIL OF THE CITY OF SCHENECTADY ADOPTING
A BOND ORDINANCE
At a meeting of the City Council of the City of Schenectady, New York, duly held in
nd
Schenectady, New York on the day of November, 2021.
Present:
Absent:
___________________ presented the following Ordinance and moved that it be adopted:
ORDINANCE NO. 2021-__
BOND ORDINANCE, DATED NOVEMBER 22, 2021
AUTHORIZING NOT TO EXCEED [$7,775,470] AGGREGATE
PRINCIPAL AMOUNT SERIAL BONDS GENERAL
OBLIGATIONS BONDS TO FINANCE THE COST OF
CONSTRUCTION, RECONSTRUCTION AND INSTALLATION OF
IMPROVEMENT AT AND IN CONNECTION WITH THE RICE
ROAD WATER TREATMENT PLANT IN THE CITY OF
SCHENECTADY, AT AN ESTIMATED MAXIMUM COST NOT TO
EXCEED [$7,775,470], LEVY OF TAX IN ANNUAL
INSTALLMENTS IN PAYMENT THEREOF, THE EXPENDITURE
OF SUCH SUM FOR SUCH PURPOSE AND DETERMINING
OTHER MATTERS IN CONNECTION THEREWITH.
WHEREAS, the City Council of the City of Schenectady (the “City Council” and the
“City”, respectively), hereby determines that it is in the public interest of the City to authorize the
financing of the Purpose as defined in Section 2 hereof by the issuance of bonds and notes in an
aggregate amount not to exceed [$7,775,470], including costs of issuance, and
[WHEREAS, pursuant to Article 8 of the Environmental Conservation Law, Chapter 43-B of
the Consolidated Laws of New York, as amended (the “SEQRA Act”) and the regulations adopted
pursuant thereto by the Department of Environmental Conservation of the State, being 6 NYCRR
Part 617, as amended (the “Regulations”), the City Council of the City as lead agency has determined
that the Project is an “Unlisted Action” (as defined in the Regulations) and as such will not have a
“significant effect on the environment” (as said quoted term is defined in the SEQRA Act and the
Regulations).]
23589041.1
WHEREAS, the City Council has not taken any action or adopted any local law which
would require the effectiveness of this bond ordinance be subjected to a permissive or mandatory
referendum;
NOW THEREFORE BE IT RESOLVED BY THIS COUNCIL AS FOLLOWS:
Section 1. The City is hereby authorized to construct, reconstruct and install improvements
at and in connection with the Rice Road water treatment plant, acquire land or rights in land,
furnishings, equipment, machinery or apparatus and pay incidental costs related thereto at an
estimated cost of [$7,775,470], as more particularly described in Section 3 hereof.
Section 2. The City is hereby authorized to issue its serial general obligation bonds (the
“Bonds”) in the aggregate principal amount of not to exceed [$7,775,470] pursuant to the Local
Finance Law, in order to finance the classes of objects or purposes, or specific objects or purposes,
including costs of issuance, as more particularly described in Section 3 hereof.
Section 3. The class of objects or purposes to be financed pursuant to this Ordinance is the
construction, reconstruction and installation of improvements at and in connection with the Rice
Road water treatment plant, acquisition of land or rights in land, furnishings, equipment,
machinery or apparatus and payment of incidental costs related thereto (collectively, the
“Purpose”).
Section 4. It is hereby determined that the Purpose is one of the class of objects or purposes
described in subdivision 1 of paragraph a of Section 11.00 of the Local Finance Law, and that the
period of probable usefulness of the Purpose forty (40) years.
Section 5. It is hereby determined and declared that (a) the maximum cost of the Purpose,
as estimated by the City Council, is not to exceed [$7,775,470], (b) the City has not previously
authorized the expenditure of the funds necessary to finance the cost of the Purpose, and (c) the
City plans to finance the cost of the Purpose entirely from funds raised by the issuance of the
Bonds and bond anticipation notes hereinafter referred to and referred to and a grants from the
New York State Environmental Facilities Corporation.
Section 6. Subject to the terms and conditions of this bond ordinance and the Local Finance
Law, and pursuant to the provisions of Sections 21.00, 30.00, 50.00 and 56.00 to 60.00, inclusive,
of the Local Finance Law, the power to authorize bond anticipation notes in anticipation of the
issuance of the serial bonds authorized by this bond ordinance and the renewal of such bond
anticipation notes and the power to prescribe the terms, form and contents of such serial bonds and
such bond anticipation notes, including renewals thereof, and the power to issue, sell and deliver
such serial bonds and such bond anticipation notes, including renewals thereof, is hereby delegated
to the Commissioner of Finance and Administration of the City, as chief fiscal officer of the City.
Such power shall include the power to consolidate the obligations authorized herein with other
obligations of the City and to authorize the use of substantially level or declining debt service in
accordance with the provisions of Section 21 of the Local Finance Law. The Commissioner of
Finance and Administration is hereby authorized to execute on behalf of the City all serial bonds,
issued pursuant to this bond ordinance and all bond anticipation notes, including renewals thereof,
issued in anticipation of the issuance of such serial bonds, and the City Clerk is hereby authorized
23589041.1
to affix the seal of the City to all such serial bonds and all such bond anticipation notes, including
renewals thereof, and to attest such seal. In the absence of the Commissioner of Finance and
Administration, the Deputy Commissioner of Finance and Administration is hereby authorized to
exercise the powers delegated to the Commissioner of Finance and Administration by this
Ordinance.
Section 8. This Bond Ordinance shall constitute the declaration of the City’s “official
intent” to reimburse expenditures with proceeds of the Bonds and notes, as required by United
States Treasury Regulation Section 1.150-2. Except as otherwise permitted by United States
Treasury Regulation Section 1.150-2, the City will not use proceeds of the Bonds or notes to
reimburse itself for prior expenditures for the Purpose unless: (1) the original expenditure was
made not more than 60 days prior to the adoption of this bond ordinance, (2) the reimbursement
will be made within three years after the later of the date the original expenditure was paid or the
date the Purpose is placed in service or abandoned.
Section 9. This Ordinance shall be published in summary form by the City Clerk together
with a notice in substantially the form prescribed by Section 81.00 of the Local Finance Law, and
such publication shall be in each of the official newspapers of the City. The validity of the
Refunding Bonds may be contested only if such obligations are authorized for an object or purpose
for which the City is not authorized to expend money, or the provisions of law which should be
complied with at the date of publication of the summary of this Ordinance are not substantially
complied with, and an action, suit or proceeding contesting such validity is commenced within
twenty (20) days after the date of such publication; or if said obligations are authorized in violation
of the provisions of the Constitution.
Section 10. The faith and credit of the City are hereby and shall be irrevocably pledged for
the punctual payment of the principal of and interest on all obligations authorized and issued
pursuant to this bond ordinance as the same shall become due. An annual appropriation shall be
made in each year sufficient to pay the principal of and interest on such obligations becoming due
and payable in such year. There shall be levied annually on all taxable real property of said City,
a tax sufficient to pay the principal of and interest on such obligations as the same become due and
payable.
Section 11. The City intends to issue the obligations authorized by this bond ordinance to
finance the costs of the purposes described in Section 2 hereof. The City covenants for the benefit
of the holders of the obligations authorized herein that it will not make any use of the proceeds of
such obligations, any funds reasonably expected to be used to pay the principal of or interest on
such obligations, or any other funds of the City, and will not make any use of the facilities financed
with the proceeds of such obligations which would cause the interest on such obligations to become
subject to federal income taxation under the Internal Revenue Code of 1986, as amended (the
“Code”) or subject the City to any penalties under section 148 of the Code, and that it will not take
any action or omit to take any action with respect to such obligations, the proceeds thereof or any
facilities financed thereby if such action or omission would cause the interest on such obligations
to become subject to federal income taxation under the Code or subject the City to any penalties
under Section 148 of the Code.
23589041.1
Section 12. In connection with the financing of the Purpose, the City is hereby authorized
to participate in the Water Infrastructure Improvement Program (the “WIIA Program”)
administered by the New York State Environmental Facilities Corporation (“EFC”). The Director
of Finance of the City is hereby authorized to execute and deliver such documents as may be
necessary to effect the participation of the City in such WIIA Program.
Section 13. In connection with the financing of the Purpose, the City is hereby
authorized to participate in the Drinking Water State Revolving Fund program (the “DWSRF
Program”) administered by EFC. The Supervisor of the City is hereby authorized to execute and
deliver such documents as may be necessary to effect the participation of the City in such DWSRF
Program.
Section 14. The law firm of Barclay Damon LLP is hereby appointed to serve as bond
counsel to the City in connection with the issuance of the Bonds.
Section 15. This bond ordinance shall take effect immediately upon its adoption by the
City Council of the City.
The Motion having been duly seconded by _____________, it was adopted and the
following votes were cast:
AYES NAYS
23589041.1
STATE OF NEW YORK )
) SS.:
COUNTY OF SCHENECTADY )
I, the undersigned Clerk of the City of Schenectady, do hereby certify as follows:
1. A Regular Meeting of the City Council of the City of Schenectady, State of New
York, was duly held on November 22, 2021, and Minutes of said meeting have been duly recorded
in the Minute Book kept by me in accordance with law for the purpose of recording the Minutes
of meetings of said Council. I have compared the attached Extract with said Minutes so recorded
and said Extract is a true copy of said Minutes and of the whole thereof insofar as said Minutes
relate to matters referred to in said Extract.
2. Said Minutes correctly state the time when said meeting was convened and the
place where such meeting was held and the members of said Council who attended said meeting.
3. Public Notice of the time and place of said meeting was duly given to the public
and the news media in accordance with the Open Meetings Law, constituting Chapter 511 of the
Laws of 1976 of the State of New York, and that the members of said Council had due notice of
said meeting and that the meeting was in all respects duly held and a quorum was present and acted
throughout.
IN WITNESS WHEREOF, I have hereunto set my hand and have hereunto affixed the
corporate seal of the City of Schenectady this _____ day of November, 2021.
____________________________________
City Clerk
[SEAL]
23589041.1
LEGAL NOTICE
The Ordinance a summary of which is published herewith, has been adopted on the 22nd
day of November, 2021 and the validity of the obligations authorized by such resolution may be
hereafter contested only if such obligations were authorized for an object or purpose for which the
City of Schenectady is not authorized to expend money or if the provisions of law which should
have been complied with as of the date of publication of this notice were not substantially complied
with, and an action, suit or proceeding contesting such validity is commenced within twenty (20)
days after the date of publication of this notice, or such obligations were authorized in violation of
the provisions of the constitution.
A complete copy of the bond ordinance summarized herewith is available for public inspection
during regular business hours at the Office of the City Clerk of the City of Schenectady for a period
of twenty days from the date of publication of this Notice.
City Clerk
BOND ORDINANCE, DATED NOVEMBER 22, 2021
AUTHORIZING NOT TO EXCEED [$7,775,470] AGGREGATE
PRINCIPAL AMOUNT SERIAL BONDS GENERAL
OBLIGATIONS BONDS TO FINANCE THE COST OF
CONSTRUCTION, RECONSTRUCTION AND INSTALLATION OF
IMPROVEMENT AT AND IN CONNECTION WITH THE RICE
ROAD WATER TREATMENT PLANT IN THE CITY OF
SCHENECTADY, AT AN ESTIMATED MAXIMUM COST NOT TO
EXCEED [$7,775,470], LEVY OF TAX IN ANNUAL
INSTALLMENTS IN PAYMENT THEREOF, THE EXPENDITURE
OF SUCH SUM FOR SUCH PURPOSE AND DETERMINING
OTHER MATTERS IN CONNECTION THEREWITH.
Class of objects or purposes: construction, reconstruction and installation of
improvements at and in connection with the Rice Road water
treatment plant, acquisition of land or rights in land,
furnishings, equipment, machinery or apparatus and pay
incidental costs related thereto
Maximum Estimated Cost: [$7,775,470 ]
Period of probable usefulness: Forty (40) years
Amount of obligations to be issued: [$7,775,470]
23589041.1
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Finance Committee Date: Monday, November 15, 2021
From: Gary McCarthy
Subject Discussion - ARPA Survey
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
CITY OF SCHENECTADY
LEGISLATION REQUEST FORM
COMMITTEE ASSIGNMENT: DATE: October 28, 2021
TO: COUNCILMEMBERS
FROM: Assistant Chief Michael Seber
SUBJECT: FY2021 State Homeland Security Grant Program (SHSP)
TO BE PLACED ON COUNCIL AGENDA OF: November 15, 2021
Background Information:
The NYS Division of Homeland Security and Emergency Services (DHSES) provides
funding to municipalities through the State Homeland Security Grant Program (SHSP).
The grant application was prepared by the Capital District Urban Area Working Group
(UAWG) which represents Albany, Rensselaer, and Schenectady Cities and Counties.
The City of Schenectady Police Department is the recipient of a portion of the grant in
the amount of $203,670.00. These funds will be used towards the purchase as follows:
$26,200 on cybersecurity upgrades including police website, data backup, and
VPN licenses;
$48,200 for soft target protection & crowded places protection including Mobile
command post, EOC and SWAT truck upgrades;
$60,000 on intelligence sharing for projects including crime analyst training,
Cellebrite school & equipment for forensics investigations, and Street Smart
secure platform buildout among others;
$20,500 on projects for domestic violence terrorism which includes CLEAR
licensing for record searching, social media investigative training, and purchase of
computer hardware;
$15,000 on emerging threats including equipment and training related to CBRNE
and working with the community; and
$33,770 towards maintenance and equipment related to the new 800mh radio
system.
The funding period is 9/1/2021 through 8/31/2024.
There is no match required by the City.
Recommendation/Action
The Police Department recommends acceptance of this Homeland Security grant award.
LEGISLATION WILL BE PREPARED BY: Assistant Chief Michael Seber
Legislative Request Form
DEPARTMENT OF ENGINEERING
CHRISTOPHER WALLIN, P.E., CITY ENGINEER
COMMITTEE ASSIGNMENT: DATE: November 15, 2021
TO: City Council
FROM: Christopher R. Wallin, P.E., City Engineer
SUBJECT: Supplemental Agreement #2, PIN 1760.62 (D035937) Nott Street (Rosa Road to
Wendell Avenue) Paving, City of Schenectady, Schenectady County
TO BE PLACED ON COUNCIL AGENDA OF: November 22, 2021
Background Information:
The City of Schenectady applied for an received Federal Funding to replace the existing traffic
signal at the Nott Street, Rosa Road and Wendell Avenue intersection. This includes the
modification of the existing intersection to increase pedestrian safety and reduce driver
confusion. This project was bid and awarded to Callanan for construction.
Evaluation/Analysis:
A supplemental agreement with the NYSDOT is necessary to receive reimbursement for
the project. This agreement is produced and disseminated by the DOT and allows the
City to receive Federal Funds for construction related activities.
Recommendation:
Enter into an agreement with the New York State Department of Transportation for Supplemental
Agreement #2 for the above referenced project to cover construction expenses.
LEGISLATION WILL BE PREPARED BY: Engineering
CRW: cd
1
November 15, 2021
Christopher Wallin
City of Schenectady
105 Jay Street
Schenectady, NY 12305
RE: Supplemental Agreement #2, PIN 1760.62, D035937,
Nott Street (Rosa Road to Wendell Avenue) Paving, City
of Schenectady, Schenectady County
Dear Chris,
Enclosed is the proposed Supplemental Agreement #2 and Resolution required for the above subject
project. These documents need to be enacted by the City Council in order for NYSDOT to provide
approved Federal funding reimbursements to the City of Schenectady for work to be accomplished on the
Construction/CI phase of your project.
(A) We have provided you with a single copy of the standardized Federal Local Agreement language
and relevant Schedule A and Schedule B. Please keep these documents for your records.
(B) We have provided you with a single copy of a draft resolution. The City should complete, enact
and certify the resolution. You may redraft your own resolutions, but they must contain all the
necessary clauses of the enclosed version. Please do not change the wording of the
resolution in any way without checking with this office first. Remember the resolution
must identify the source of the funding appropriation. Please return 3 (three) originals with
the required certificates. Also, as with the agreement, please keep an additional copy for your
records as you will not get a copy of the resolution returned to you.
(C) Because you have received this via email, we have provided you with 1 (one) copy of the
necessary signature page. Please make 5 (five) copies and return all 5 (five) copies, with original
signatures, to this office with the above resolutions. You will get a single original of this page
returned to you once the contract is executed by the necessary State officials.
If you have any questions concerning the procedures, please call me 518-485-1715.
Sincerely,
Lorenzo DiStefano, P.E.
Region One Regional Local Project Liaison
Program Development and Management
LD:bc
Enclosures
50 Wolf Road, Albany, NY 12232 │ www.dot.ny.gov
SUPPL (12/19) Supplemental Agreement Cover for Local Agreements
Sponsor:City of Schenectady
PIN: 1760.62 BIN:
Comptroller's Contract No. D035937
Supplemental Agreement No.2
Date Prepared:5/25/2021 By:BC
Press F1 for instructions in the blank fields: Initials
SUPPLEMENTAL AGREEMENT No. 2 to D035937 (Comptroller's Contract No.)
This Supplemental Agreement is by and between:
the New York State Department of Transportation ("NYSDOT"), having its principal office at 50
Wolf Road, Albany, NY 12232, on behalf of New York State (“State”);
and
City of Schenectady (the Sponsor)
Acting by and through the Mayor
with its office at City Hall, 105 Jay Street, Schenectady, NY 12305.
This amends the existing Agreement between the parties in the following respects only (check
applicable categories):
Amends a previously adopted Schedule A by (check as applicable):
amending a project description
amending the contract end date
amending the scheduled funding by:
adding additional funding (check and enter the # phase(s) as applicable):
adding phase C/CI which covers eligible costs incurred on/after 6/3/2021
adding phase which covers eligible costs incurred on/after / /
increasing funding for a project phase(s)
adding a pin extension
change from Non-Marchiselli to Marchiselli
deleting/reducing funding for a project phase(s)
other ( )
Amends a previously adopted Schedule “B" (Phases, Sub-phase/Tasks, and Allocation of
Responsibility)
Amends a previously adopted Agreement by replacing the Appendix A dated January
2014 with the Appendix A dated October 2019
Amends the text of the Agreement as follows (insert text below):
1
SUPPL (12/19) Supplemental Agreement Cover for Local Agreements
Sponsor:City of Schenectady
PIN: 1760.62 BIN:
Comptroller's Contract No. D035937
Supplemental Agreement No.2
Date Prepared:5/25/2021 By:BC
Press F1 for instructions in the blank fields: Initials
IN WITNESS WHEREOF, the parties have caused this Agreement to be executed by their duly authorized
officials as of the date first above written.
SPONSOR: SPONSOR ATTORNEY:
By: _________________________________________ By: __________________________________________
Print Name: _________________________________ Print Name: __________________________________
Title: ________________________________________
STATE OF NEW YORK
)ss.:
COUNTY OF Schenectady
On this ______________ day of _______________________, 20___ before me personally came
_____________________________ to me known, who, being by me duly sworn did depose and say that he/she
resides at _________________________________; that he/she is the _________________________________ of the
Municipal/Sponsor Corporation described in and which executed the above instrument; (except New York
City) that it was executed by order of the ________________________ of said Municipal/Sponsor Corporation
pursuant to a resolution which was duly adopted on ______________________ and which a certified copy is
attached and made a part hereof; and that he/she signed his/her name thereto by like order.
__________________________________
Notary Public
APPROVED FOR NYSDOT: APPROVED AS TO FORM:
STATE OF NEW YORK ATTORNEY GENERAL
BY:____________________________________________
For Commissioner of Transportation
Agency Certification: In addition to the acceptance of this
contract I also certify that original copies of this signature
By: _________________________________
page will be attached to all other exact copies of this
contract. Assistant Attorney General
Date: ____________________________ COMPTROLLER'S APPROVAL:
By:__________________________________
For the New York State Comptroller
Pursuant to State Finance Law '112
2
Schedule A (5/18)
Press F1 to read instructions in blank fields Page 1 of 3
SCHEDULE A – Description of Project Phase, Funding and Deposit Requirements
NYSDOT/ State-Local Agreement - Schedule A for PIN 1760.62
OSC Municipal Contract #: Contract Start Date: 6/14/2018(mm/dd/yyyy) Contract End Date: 6/14/2028(mm/dd/yyyy)
D035937 Check, if date changed from the last Schedule A
Purpose: Original Standard Agreement Supplemental Schedule A No. 2
Agreement Locally Administered Municipality/Sponsor (Contract Payee): City of Schenectady
Type: Other Municipality/Sponsor (if applicable):
State Administered List participating Municipality(ies) and the % of cost share for each and indicate by checkbox which
Municipality this Schedule A applies.
Municipality: % of Cost share
Municipality: % of Cost share
Municipality: % of Cost share
Authorized Project Phase(s) to which this Schedule applies: PE/Design ROW Incidentals
ROW Acquisition Construction/CI/CS
Work Type: HWY RESURF County (If different from Municipality): County of Schenectady
Marchiselli Eligible Yes No (Check, if Project Description has changed from last Schedule A):
Project Description: Nott Street (Rosa Road to Wendell Avenue) Paving, City of Schenectady
Marchiselli Allocations Approved FOR All PHASES All totals will calculate automatically.
Check box to indicate Project Phase
change from last State Fiscal Year(s) TOTAL
Schedule A PE/Design ROW (RI & RA) Construction/CI/CS
Cumulative total for all prior SFYs $11,000.00 $0.00 $75,000.00 $86,000.00
Current SFY $0.00 $0.00 $0.00 $ 0.00
Authorized Allocations to Date $11,000.00 $ 0.00 $75,000.00 $86,000.00
A. Summary of allocated MARCHISELLI Program Costs FOR ALL PHASES For each PIN Fiscal Share below,
show current costs on the rows indicated as “Current.”. Show the old costs from the previous Schedule A on the row indicated as “Old.” All totals will calculate
automatically.
LOCAL
DEPOSIT
“Current” or FEDERAL STATE LOCAL
PIN Federal AMOUNT
“Old” entry Total Costs Participating MARCHISELLI Matching
Fiscal Share Funding (Required
indicator Share Match Share
only if State
Administered)
1760.62.121 Current STP $72,000.00 $57,600.00 $10,800.00 $3,600.00 $0.00
. Old STP $72,000.00 $57,600.00 $10,800.00 * $3,600.00 $0.00
1760.62.321 Current $487,000.00 $389,600.00 $73,050.00 $24,350.00 $0.00
. Old $ 0.00 $0.00 $0.00 $0.00 $0.00
. . Current $ 0.00 $0.00 $0.00 $0.00 $0.00
. Old $ 0.00 $0.00 $0.00 $0.00 $0.00
. . Current $ 0.00 $0.00 $0.00 $0.00 $0.00
Old $ 0.00 $0.00 $0.00 $0.00 $0.00
Current $ 0.00 $0.00 $0.00 $0.00 $0.00
. .
Old $ 0.00 $0.00 $0.00 $0.00 $0.00
Current $ 0.00 $0.00 $0.00 $0.00 $0.00
. .
Old $ 0.00 $. $0.00 $0.00 $0.00
TOTAL CURRENT COSTS: $559,000.00 $447,200.00 $83,850.00 $27,950.00 $ 0.00
Schedule A (5/18)
Press F1 to read instructions in blank fields Page 2 of 3
NYSDOT/State-Local Agreement – Schedule A
B. Summary of Other (including Non-allocated MARCHISELLI) Participating Costs FOR ALL
PHASES For each PIN Fiscal Share, show current costs on the rows indicated as “Current.”. Show the old costs from the previous Schedule A on the row
indicated as “Old.” All totals will calculate automatically.
‘Current’
Other
or ‘Old’
PIN Fiscal Funding Source TOTAL Other FEDERAL Other STATE Other LOCAL
entry
Shares
indicator
1760.62.NPS Current 100% Local $158,041.00 $0.00 $0.00 $158,041.00
. Old $ 0.00 $0.00 $0.00 $0.00
. . Current $ 0.00 $0.00 $0.00 $0.00
. Old $ 0.00 $0.00 $0.00 $0.00
. . Current $ 0.00 $0.00 $0.00 $0.00
. Old $ 0.00 $0.00 $0.00 $0.00
Current $ 0.00 $0.00 $0.00 $0.00
. .
Old $ 0.00 $0.00 $0.00 $0.00
Current $ 0.00 $0.00 $0.00 $0.00
. .
Old $ 0.00 $0.00 $0.00 $0.00
Current $ 0.00 $0.00 $0.00 $0.00
. .
Old $ 0.00 $0.00 $0.00 $0.00
Current $ 0.00 $0.00 $0.00 $0.00
. .
Old $ 0.00 $0.00 $0.00 $0.00
Current $ 0.00 $0.00 $0.00 $0.00
. .
Old $ 0.00 $0.00 $0.00 $0.00
TOTAL CURRENT COSTS: $158,041.00 $ 0.00 $ 0.00 $158,041.00
C. Local Deposit(s) from Section A: $ 0.00
Additional Local Deposit(s) $
Total Local Deposit(s) $ 0.00
D. Total Project Costs All totals will calculate automatically.
Total STATE Total
Total FEDERAL Total OTHER Total LOCAL
MARCHISELLI ALL SOURCES
Cost STATE Cost Cost
Cost Cost
$447,200.00 $83,850.00 $ 0.00 $185,991.00 $717,041.00
E. Point of Contact for Questions Regarding this Name: Bryan Cross
Schedule A (Must be completed) Phone No: 518-417-6595
See Agreement (or Supplemental Agreement Cover) for required contract signatures.
Schedule A (5/18)
Press F1 to read instructions in blank fields Page 3 of 3
NYSDOT/State-Local Agreement – Schedule A
Footnotes: (See LPB’s website for link to sample footnotes)
This Supplemental Agreement #2 adds the Construction and CI phases of the project. Construction =
$437,000.00, CI = $50,000.00. There is a Local 100% NPS Construction share of $158,041.00. Approved
Marchiselli funds for the Construction phase have been included.
Supplemental Agreement #1 added approved Marchiselli funds to the Design phase of the project
The Master Agreement was for the Design Phase of the project. Preliminary Design = $49,789.00, Detailed
Design = $22,211.00
SCHEDULE B: Phases, Sub-phase/Tasks, and Allocation of Responsibility
Instructions: Identify the responsibility for each applicable Sub-phase task by entering X in
either the NYSDOT column to allocate the task to State labor forces or a State Contract, or in
the Sponsor column indicating non-State labor forces or a locally administered contract.
A1. Preliminary Engineering (“PE”) Phase
Phase/Sub-phase/Task Responsibility: NYSDOT Sponsor
1. Scoping: Prepare and distribute all required project reports, including an
Expanded Project Proposal (EPP) or Scoping Summary Memorandum
(SSM), as appropriate.
2. Perform data collection and analysis for design, including traffic counts
and forecasts, accident data, Smart Growth checklist, land use and
development analysis and forecasts.
3. Smart Growth Attestation (NYSDOT ONLY).
4. Preliminary Design: Prepare and distribute Design Report/Design
Approval Document (DAD), including environmental
analysis/assessments, and other reports required to demonstrate the
completion of specific design sub-phases or tasks and/or to secure the
approval/authorization to proceed.
5. Review and Circulate all project reports, plans, and other project data to
obtain the necessary review, approval, and/or other input and actions
required of other NYSDOT units and external agencies.
6. Obtain aerial photography and photogrammetric mapping.
7. Perform all surveys for mapping and design.
8. Detailed Design: Perform all project design, including preparation of
plan sheets, cross-sections, profiles, detail sheets, specialty items,
shop drawings, and other items required in accordance with the
Highway Design Manual, including all Highway Design, including
pavement evaluations, including taking and analyzing cores; design of
Pavement mixes and applications procedures; preparation of bridge site
data package, if necessary, and all Structural Design, including
hydraulic analyses, if necessary, foundation design, and all design of
highway appurtenances and systems [e.g., Signals, Intelligent
Transportation System (ITS) facilities], and maintenance protection of
traffic plans. Federal Railroad Administration (FRA) criteria will apply to
rail work.
9. Perform landscape design (including erosion control).
10. Design environmental mitigation, where appropriate, in connection with:
Noise readings, projections, air quality monitoring, emissions
projections, hazardous waste, asbestos, determination of need of
cultural resources survey.
Phase/Sub-phase/Task Responsibility: NYSDOT Sponsor
11. Prepare demolition contracts, utility relocation plans/contracts, and any
other plans and/or contract documents required to advance, separate,
any portions of the project which may be more appropriately progressed
separately and independently.
12. Compile PS&E package, including all plans, proposals, specifications,
estimates, notes, special contract requirements, and any other contract
documents necessary to advance the project to construction.
13. Conduct any required soils and other geological investigations.
14. Obtain utility information, including identifying the locations and types of
utilities within the project area, the ownership of these utilities, and
prepare utility relocations plans and agreements, including completion
of Form HC-140, titled Preliminary Utility Work Agreement.
15. Determine the need and apply for any required permits, including U.S.
Coast Guard, U.S. Army Corps of Engineers, Wetlands (including
identification and delineation of wetlands), SPDES, NYSDOT Highway
Work Permits, and any permits or other approvals required to comply
with local laws, such as zoning ordinances, historic districts, tax
assessment and special districts.
16. Prepare and execute any required agreements, including:
- Railroad force account
- Maintenance agreements for sidewalks, lighting, signals, betterments
- Betterment Agreements
- Utility Work Agreements for any necessary Utility Relocations of
Privately owned Utilities
17. Provide overall supervision/oversight of design to assure conformity
with Federal and State design standards or conditions, including final
approval of PS&E (Contract Bid Documents) by NYSDOT.
A2. Right-of-Way (ROW) Incidentals
Phase/Sub-phase/Task Responsibility: NYSDOT Sponsor
1. Prepare ARM or other mapping, showing preliminary taking lines.
2. ROW mapping and any necessary ROW relocation plans.
3. Obtain abstracts of title and certify those having an interest in ROW to
be acquired.
4. Secure Appraisals.
5. Perform Appraisal Review and establish an amount representing just
compensation.
Phase/Sub-phase/Task Responsibility: NYSDOT Sponsor
6. Determination of exemption from public hearing that is otherwise
required by the Eminent Domain Procedure Law, including de minimis
determination, as may be applicable. If NYSDOT is responsible for
acquiring the right-of-way, this determination may be performed
by NYSDOT only if NYSDOT is responsible for the Preliminary
Engineering Phase under Phase A1 of this Schedule B.
7. Conduct any public hearings and/or informational meetings as may be
required by the Eminent Domain Procedures Law, including the
provision of stenographic services, preparation and distribution of
transcripts, and response to issues raised at such meetings.
B. Right-of-Way (ROW) Acquisition
Phase/Sub-phase/Task Responsibility: NYSDOT Sponsor
1. Perform all Right-of-Way (ROW) Acquisition work, including
negotiations with property owners, acquisition of properties and
accompanying legal work, payments to and/or deposits on behalf of
property owners; Prepare, publish, and pay for any required legal
notices; and all other actions necessary to secure title to, possession of,
and entry to required properties. If NYSDOT is to acquire property,
including property described as an uneconomic remainder, on
behalf of the Municipality/Sponsor, the Municipality/Sponsor
agrees to accept and take title to any and all permanent property
rights so acquired which form a part of the completed Project.
2. Provide required relocation assistance, including payment of moving
expenses, replacement supplements, mortgage interest differentials,
closing costs, mortgage prepayment fees.
3. Conduct eminent domain proceedings, court and any other legal
actions required to acquire properties.
4. Monitor all ROW Acquisition work and activities, including review and
processing of payments of property owners.
5. Provide official certification that all right-of-way required for the
construction has been acquired in compliance with applicable Federal,
State or Local requirements and is available for use and/or making
projections of when such property(ies) will be available if such
properties are not in hand at the time of contract award.
6. Conduct any property management activities, including establishment
and collecting rents, building maintenance and repairs, and any other
activities necessary to sustain properties and/or tenants until the sites
are vacated, demolished, or otherwise used for the construction project.
7. Subsequent to completion of the Project, conduct ongoing property
management activities in a manner consistent with applicable Federal,
State and Local requirements including, as applicable, the development
of any ancillary uses, establishment and collection of rent, property
maintenance and any other related activities.
C. Construction, Construction Support (C/S) and Construction Inspection (C/I) Phase
Phase/Sub-phase/Task Responsibility: NYSDOT Sponsor
1. Advertise contract lettings and distribute contract documents to
prospective bidders.
2. Conduct all contract lettings, including receipt, opening, and analysis of
bids, evaluation/certification of bidders, notification of rejected
bids/bidders, and awarding of the construction contract(s).
3. Receive and process bid deposits and verify any bidder’s insurance and
bond coverage that may be required.
4. Compile and submit Contract Award Documentation Package.
5. Review/approve any proposed subcontractors, vendors, or suppliers.
6. Conduct and control all construction activities in accordance with the
plans and proposal for the project. Maintain accurate, up-to-date project
records and files, including all diaries and logs, to provide a detailed
chronology of project construction activities. Procure or provide all
materials, supplies and labor for the performance of the work on the
project, and insure that the proper materials, equipment, human
resources, methods and procedures are used.
7a. For non-NHS or non-State Highway System Projects: Test and accept
materials, including review and approval for any requests for
substitutions.
7b. For NHS or State Highway System Projects: Inspection and approval of
materials such as bituminous concrete, Portland cement concrete,
structural steel, concrete structural elements and/or their components to
be used in a federal aid project will be performed by, and according to
the requirements of NYSDOT. The Municipality/Sponsor shall make or
require provision for such materials inspection in any contract or
subcontract that includes materials that are subject to inspection and
approval in accordance with the applicable NYSDOT design and
construction standards associated with the federal aid project.
7c. For projects that fall under both 7a and 7b above, check boxes for
each.
8. Design and/or re-design the project or any portion of the project that
may be required because of conditions encountered during
construction.
9. Administer construction contract, including the review and approval of
all contactor requests for payment, orders-on-contract, force account
work, extensions of time, exceptions to the plans and specifications,
substitutions or equivalents, and special specifications.
10. Review and approve all shop drawings, fabrication details, and other
details of structural work.
11. Administer all construction contract claims, disputes or litigation.
Phase/Sub-phase/Task Responsibility: NYSDOT Sponsor
12. Perform final inspection of the complete work to determine and verify
final quantities, prices, and compliance with plans specifications, and
such other construction engineering supervision and inspection work
necessary to conform to Municipal, State and FHWA requirements,
including the final acceptance of the project by NYSDOT.
13. Pursuant to Federal Regulation 49 CFR 18.42(e)(1) The awarding
agency and the Comptroller General of the United States, or any of
their authorized representatives, shall have the right of access to any
pertinent books, documents, papers, or other records of grantees and
subgrantees which are pertinent to the grant, in order to make audits,
examinations, excerpts, and transcripts.
Legislative Request Form
DEPARTMENT OF ENGINEERING
CHRISTOPHER WALLIN, P.E., CITY ENGINEER
COMMITTEE ASSIGNMENT: DATE: November 15, 2021
TO: City Council
FROM: Christopher R. Wallin, P.E., City Engineer
SUBJECT: Supplemental Agreement #2, PIN 1760.62 (D035937) Nott Street (Rosa Road to
Wendell Avenue) Paving, City of Schenectady, Schenectady County
TO BE PLACED ON COUNCIL AGENDA OF: November 22, 2021
Background Information:
The City of Schenectady applied for an received Federal Funding to replace the existing traffic
signal at the Nott Street, Rosa Road and Wendell Avenue intersection. This includes the
modification of the existing intersection to increase pedestrian safety and reduce driver
confusion. This project was bid and awarded to Callanan for construction.
Evaluation/Analysis:
A supplemental agreement with the NYSDOT is necessary to receive reimbursement for
the project. This agreement is produced and disseminated by the DOT and allows the
City to receive Federal Funds for construction related activities.
Recommendation:
Enter into an agreement with the New York State Department of Transportation for Supplemental
Agreement #2 for the above referenced project to cover construction expenses.
LEGISLATION WILL BE PREPARED BY: Engineering
CRW: cd
1
CITY OF SCHENECTADY
LEGISLATIVE REQUEST FORM
COMMITTEE ASSIGNMENT: Health and Recreation DATE: November 15, 2021
FROM: Councilwoman Marion Porterfield
SUBJECT: Schenectady Belmont Pop Warner
Backqround Information:
Schenectady Belmont Pop Warner won the local Superbowl for the second consecutive
year and are now in Regional competition.
Evaluation/Analysis:
Recommendation:
Present the players and cheer team with a Ceremonial Resolution
LEGISLATION WILL BE PREPARED by
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Government Operations Committee Date: Monday, November 15, 2021
From: John Polimeni
Subject Discussion - OSM Broadcast of City Council and Committee Meetings
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Government Operations Committee Date: Monday, November 15, 2021
From: Marion Porterfield / John Mo
Subject Discussion - Calling for a Public Hearing to Amend Chapter 87-11 of the Code of the City of
Schenectady regarding Holidays (Follow-up from 06-21-2021)
Background Info:
Evaluation/Analysis
Recommendation
Adding Juneteenth to the City of Schenectady 87-11 Ordinance regarding Holidays.
Friday, November 12, 2021
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Government Operations Committee Date: Monday, November 15, 2021
From: John Mootooveren
Subject Discussion - Seating New Council Members for Vacant Council Seats
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Claims Committee Date: Monday, November 15, 2021
From: Andrew Koldin
Subject James Gulneck v. City of Schenectady
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Claims Committee Date: Monday, November 15, 2021
From: Andrew Koldin
Subject Edward Ritz v. City of Schenectady
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
SCHENECTADY CITY COUNCIL
Legislative Request Form
Committee: Claims Committee Date: Monday, November 15, 2021
From: Andrew Koldin
Subject Lisa Williams v. City of Schenectady
Background Info:
Evaluation/Analysis
Recommendation
Friday, November 12, 2021
Get email alerts for Schenectady