I. CALL TO ORDER
Meeting called to order at 6:06 p.m.
II. ATTENDANCE
Present: Mary Moore Wallinger, Chair; Bradley Lewis, Vice Chair;
Randall Beach; Nicholas Petrillo; Jason Bogdanowicz-Wilson;
Dharam Hitlall; Colin M. Evers; Susan Nadler; Chris Marley,
Corporation Counsel; and Sylvia Jimison, Development Staff
Excused: Christine S. Primiano, Principal Planner
III. Conflict of Interest Check
Commissioners Beach and Lewis recused themselves from the
consideration of Items A and B, AIK Property Group, LLC.
IV. Approval of Minutes for June 15, 2022, motioned by Commissioner
Beach and seconded by Commissioner Hitlall. Motion carried
unanimously.
Commissioner Wallinger began the meeting by welcoming Susan Nadler as a
new commissioner to join the Planning Commission.
She reviewed the process for how projects should be presented and reviewed
and reminded the public to please sign in and address comments to the
Commission when speaking during public comment periods.
ZONING INTERPRETION: CRYSTAL JONES requests site plan approval pursuant to Section
264-90 G of a proposal to renovate the existing building for use as a private club and
business office at 2525 Broadway, tax parcel # 48.66-2-12 and 14.11 located in a “C-2”
Mixed Use Commercial District, and tax parcel #’s 48.66-2-10 and 14.2 located in an “R-
1” Single Family Residential District.
Before the project presentations began, the applicant’s representative, Luigi
Palleschi from ABD Engineers, requested the zoning interpretation to be
removed from the agenda to allow the applicant time to respond and
complete an application.
As per the Zoning Interpretation, the intended use is not permitted in the C-2
Mixed Used Commercial District. At the request of the applicant’s
representative, the Commission voted to table the project to allow the
applicant further time to respond and complete the application.
Motion to table made by Commissioner Wilson and seconded by Commissioner
Petrillo. Motion carried unanimously.
V. NEW BUSINESS
A. AIK PROPERTY GROUP, LLC requests site plan approval pursuant to Section 264-90
F of a proposal to construct a 16-unit residential building at 1052 -1062 Barrett
Street and 608 South Avenue, tax parcel #’s 39.65-2-33.1, 34.1, and 35.1, located
in a “C-4” Downtown Commercial District.
B. AIK PROPERTY GROUP, LLC requests site plan approval pursuant to Section 264-90
F of a proposal to construct a nine (9) unit residential building at 1101-1107
Barrett Street and 519 South Avenue, tax parcel #’s 39.57-4-29, 30 and 32,
located in a “C-4” Downtown Commercial District.
Ms. Pam Swanigan of AIK Property Group presented to the Commission
background information about AIK Property Group that they are a group with
compassion and heart in the community. Their goal is to strengthen
neighborhoods and to be a problem solver; more importantly create sustainable
and quality housing. She also stated that a community meeting was held at the
downtown library to discuss the development at Barrett Street with the
community and more than 16 residents attended. A PowerPoint presentation
was provided at the meeting, and she provided printed copies of the
community PowerPoint presentation to the commissioners.
Ms. Swanigan stated that 6 of the units on the first floor will be designated for
Living Resources consumers to occupy. These will be one-bedroom units.
Luigi Palleschi of ABD Engineers provided an overview of the entire
development project to the commissioners. He stated:
There will be three sites that are part of the project. Site one, that is first on the
agenda, is the 16-unit building. It is a 10,800+/- SF property. It consists of three
parcels and the three parcels will be combined into one to make way for a two-
story 16-unit multifamily project.
With the site plan, there will be an upgrade to the sidewalks along Barrett Street
and South Street and there will be some trees added. There are a couple of
existing trees on the street that will be preserved and provide a buffer to the
adjoining residential properties to the South and a commercial garage building.
With some buffers, the applicant has decided to put the garbage totes on the
south end away from the residents. The west end of the building meets the site
setback requirements for current zoning for the building. The main entrance to
this building is off South Street. There are two entrances. It's a two-story building
and it's configured with 16 units and there's a mixture of one bedroom and two-
bedroom units.
The utility connections to the city for water and sewer, gas and electric are all
available on site and will be available across the street at the nine-unit building.
That parcel consists of three existing tax parcels. The applicant is going to
reconfigure the parcels into three separate lots. The building will contain nine
units, but each parcel will have three units. The units will be three stories high,
which will complement the townhouse building directly across the street.
Commissioner Wallinger asked if there will be three separate address numbers.
Mr. Palleschi stated that there will be three separate street numbers for the
properties. Mr. Palleschi added that there will be front scoops with improved
sidewalks and landscaping. There will be 10 parking spaces for a total of 25 units;
street parking and shared parking with Metroplex. He also stated that, in
addition, some residents will not need parking. Commissioner Wallinger
indicated to Mr. Palleschi that that Commission has encouraged bike parking to
be included in instances where parking is limited, and alternative modes of
transportation are anticipated. The applicant agreed to adding bike racks.
Commissioner Wallinger notes that many apartments include covered bike
parking, which is desirable to residents.
Mr. Palleschi stated he has submitted applications for area variances for onsite
parking for both proposals to the Board of Zoning Appeals and they will be
considered on August 3, 2022.
Commissioner Wallinger reminded AIK they will need to provide a lighting plan
and make sure that lights do not shine onto neighbors’ property. Commissioner
Petrillo, wanted to know if the city’s right of way would be impacted and Mr.
Palleschi said that it would not.
Overall Commissioner Wallinger said that she is excited about the project and
appreciated that the architectural rendering showed a lot of architectural
detail. She was thrilled to see so many trees and commended the applicant for
their efforts to preserve the existing street trees as urban trees can take several
years to grow that large and have such an important impact on the urban heat
island effect and residents’ quality of life. She suggested to the applicant that
they carefully prune the trees and keep them well watered during construction
to help ensure their success.
Commissioner Wallinger noted that all parking would require a minimum 4’
landscape buffer that needs to include trees and either fencing, landscaping,
or a combination of both.
Commissioner Wallinger opened the public hearing:
Commissioner Wallinger read a letter signed by Stephanie Medellin, Xavier
Medellin, and Zhenshi Shen.
Ray Gillen of Metroplex stated that the Barrett Street project is very important.
Barrett Street was really distressed until a group of investors built townhomes
there. The eyes of the State are on this project and the State wants to support
more minority developers and that Schenectady is fortunate to have this
development team. The project will be a great infill and will get more people to
the city. He stated that he likes the fact that Living Resources will be part of the
project and encouraged the commission to move forward on the project.
Commissioner Wallinger closed the public hearing.
Special Note: Neighbor to Barrett Street, there was a gentleman who spoke at
the end of the commission meeting and after the public hearing had been
closed about Barrett Street. He said he lived on Barrett Street and the sidewalks
are terrible, especially during the winter when it snows. He has lived on Barrett
Street for several years and is concerned about walking and parking.
The Commission discussed prior support of shared parking agreements and
reduced parking requirements in the downtown areas, particularly in cases
when residents are anticipated to have lower demands for parking. The
Commission agreed that they would like to send a letter in support of a parking
variance for these projects to the Zoning Board of Appeals.
Motion by Commissioner Hitlall and seconded by Commissioner Petrillo for Site
Plan Approval for 1052 -1062 Barrett Street and 608 South Avenue with the
following conditions:
1. The Landscaping Plan will be revised to include the following trees:
a. Shade trees in the areas where there are no overhead lines in place
of smaller trees
b. Smaller, flowering trees below utility lines
2. Bike Racks will be added to the site plan.
3. A landscape buffer will be added to the triangle shown between the
parking and the sidewalk to provide the required min. 4’ buffer between
the parking and public sidewalk.
4. The applicant will submit color and material samples to the City Planner
for final approval prior to the issuance of building permits.
Motion carried, with Commissioners Beach and Lewis abstaining.
Motion made by Commissioner Hitlall and seconded by Commissioner Petrillo,
to approve the Site Plan for 1101-1107 Barrett Street and 519 South Avenue with
the following conditions:
1. The Landscaping Plan will be revised to include the following trees:
(1) Shade trees in the areas where there are no overhead lines in place
of smaller trees
(2) Smaller, flowering trees below utility lines
(3) Landscaping and or a decorative fence will be added to the
triangle by parking spaces to provide screening behind the public
sidewalk and that the proper permits will be done for the city
regarding the residents and anything encroaching on the city right
away.
2. Bike Racks will be added to the site plan.
3. Notes will be added to the plan to protect existing trees during
construction
4. The applicant will obtain a revocable permit or license agreement with
the City for any stoops within the City right of way.
5. Submit colors and materials to City Planner for review and approval prior
to proceeding
Motion carried, with Commissioners Beach and Lewis abstaining.
A plan was submitted for parking that would serve the two facilities and be
located on 1063 & 1065 Barrett Street.
Commissioner Wallinger stated that since this project was not included on the
agenda that it would have to come back to the commission next month so that
the notices could be sent out. The Commission stated that the following would
be required:
1. Min. 4’ buffer between any parking and sidewalks with trees and
decorative fencing, shrubs or a combination of both.
2. 2 trees on Barrett Street
3. 2 trees on South Avenue
I. OLD BUSINESS
A. MITCHELL RAMSEY requests site plan approval pursuant to Section 264-90 M of a
proposal to operate a bar and music hall at 116 Jay Street, tax parcel # 39.72-2-
13, located in a “C-4” Downtown Commercial District.
Commissioner Evers stated for the record that he would be recusing himself due
to a conflict of interest.
Mitchell Ramsey stated that he is looking to do three 8’ decorative doors on the
front and that the middle one would include a door. It would be symmetrical.
He assured the commissioners that the door would remain unobstructed from
the inside so that, if there's an emergency, people can get out.
Commissioner Hitlall asked about garbage and Mr. Ramsey responded that the
enclosed dumpster across the street will be used for garbage.
Commissioner Wallinger asked if the applicant would prefer the front door be
located in one of the side garage panels to allow for more flexibility on the
inside. The applicant responded that he preferred it in the center and would
make sure it remained unobstructed. Commissioner Wallinger asked if the entry
on the side would be wide enough for a fully accessible entry and stated that
the fire department said there needs to be multiple doors, including a door on
the front.
Commissioner Wilson expressed concern about the possibility of drinks getting
knocked onto the public sidewalk and suggested that the fence be set back
from the face of the building. After discussion with the applicant, it was agreed
that the fence would be set back a minimum of 18” and that the rails would not
be wide enough for patrons to sit their drinks on them. The applicant stated that
he also plans to include planters in the area between the railing and the fence.
Commissioner Wallinger asked about materials for the roof kiosk. Mr. Mitchell
replied that the materials have not yet been determined, but that it may be a
shipping container or something similar to what is at Frog Alley. He also stated
that it would be toward the back and not visible from the street level. The
Commission agreed that any final materials shall be submitted to the City
Planner for review and approval prior to proceeding.
Commissioner Wallinger opened the public hearing:
Ray Gillen of Metroplex stated that 116 Jay Street has been empty since 2004
and he is often asked when something is going to be done with the building. He
went on to say that Mitchell is a great entrepreneur, and he knows that he will
do well. He urged the commission to move forward with this project and stated
that the building cannot remain vacant any longer.
Chris Sparagen who owns the property across from the Open Door Book Store
stated that he also supports the project and is excited to see more businesses
opening in the area.
Commissioner Wallinger closed the public hearing.
Motion made by Commissioner Beach and seconded by Commissioner Wilson
to approve the site plan with the following conditions:
1. Three doors would be included in the plans with at least one being
handicap accessible and one being located on the front facing Jay
Street
2. 18-inch clearance (setback) for the fence on the rooftop
3. Certificate of Use
4. Approval of all materials, including the roof kiosk, by the City Planner prior
to installation
Motion carried, with Commissioner Evers abstaining.
B. THOMAS LYNCH requests site plan approval pursuant to Section 264-90 L of a
proposal to operate a charter school, Destine Preparatory Charter School, at 530
Franklin Street, tax parcel #’s 39.80-1-1&2, located in a “C-4” Downtown Mixed-
Use Commercial District.
Luigi Palleschi of ABD Engineers stated he was representing the 530 Franklin
Street project and that he previously appeared before the Planning Commission
last month. He submitted a revised plan.
Mr. Palleschi stated the following:
“Mr. Lynch mentioned, the bus drop off area, the dumpster relocation, we're
relocating it on the other side of this AC unit, and will enclose it.
Similar to the closure of the AC unit. We've added shade trees and flowering
trees along Lafayette Street, we're removing two parking spaces to provide a
four-foot strip of mulch beds so that we can get the two trees in there. We'll also
remove a small panel of concrete in the city right away and adding a tree there
as well. We believe Lafayette Street is the main corridor. We're trying to beautify
the area.
Right across the street, you have the Great Flats, brewery, and they have some
good street improvements, street trees on that side as well. We're trying to
complement what was approved previously across the street with some
masonry planters have been added along Franklin Street, they'll be circular;
similar to what you see around in the city.
The flowers will be annual perennial in the planters and we're proposing one on
either side, the existing main entryway when you're facing Franklin Street.
Another thing that was asked about was this future bike path which we reached
out to Chris Wallin and have not heard back from him with the exact details.”
Commissioner Wallinger asked about the “secondary lot” that is accessed from
Lafayette Street and also from inside the “main parking area” via a striped aisle.
She stated that the Commission would want that coned off during drop-off and
pickup so that parents don’t try to use it as a drop-off point or a way to exit the
drop-off area as this would cause traffic issues on Lafeyette Street and also lead
to unsafe drop-off conditions. Commissioner Wallinger also asked how pickup
would work since it is much more complicated with dropoff since children have
to be reunited with caretakers as opposed to just being let out of the car in the
order of showing up.
Commissioner Nadler stated that she had read in the paper in March a goal
was to increase enrollment by 400 students by 2025 and noted that this would
have a major impact on site.
Mr. Palleschi stated the facility is for 120 students.
Re’Shawn Rogers (CEO of Charter School) stated that parents will have
designated times for pick-up to control the flow of parents and only 50% of kids
will ride the bus. By the sixth week of school there should be a good system in
place. Staff will be using walkie talkies.
Commissioner Wallinger continued to state that drop-off is a concern.
Commissioner Nadler inquired about the number of entrances for students, fire
drills, shooter drills, and stairwells for evacuation.
Mr. Rogers responded that the school is working on a district wide safety plan
and that policies are part of the plan and that feedback on the plan will be
made available to the public.
Commissioner Wallinger said she appreciated the buffers being added to the
Lafayette side of the parking area, but feels they are equally important on the
Barrett Street side to protect pedestrians and that she thought the Commission
would be open to a decorative fence as a buffer. She also noted the staff
comments that the double stacked cars are not compliant with the Zoning
Ordinance and that they need to be designed to meet the code or a variance
would be needed.
Mr. Palleschi cited City Code Chapter 264-40, Section C, which states:
“Preexisting off-street parking areas and lots which are nonconforming with
respect to any of the design standards specified in § 264-43 may be lawfully
continued, provided that such nonconforming parking area is not enlarged or
altered in a way which increases its nonconformity. Where the premises served
by such nonconforming parking area are substantially improved, the parking
area shall also be improved in compliance with the design standards specified
herein.” He then referenced Section 264-2 which defines Substantial
Improvements as “Any repair, reconstruction or improvement of a structure, the
cost of which equals or exceeds 50% of the market value of the structure either
before the improvement or repair is started or, if the structure has been
damaged and is being restored, before the damage occurred….”
Mr. Palleschi then claimed that according to the City Zoning Ordinance, he did
not believe that mprovements to the parking area were required since his client
was not making Substantial Improvements to the building. He also stated that
the cars that were double stacked should be fine since they are used by people
who do not leave during the day.
Commissioner Wallinger stated that the reason the buffer is required is to protect
pedestrians and promote walkability in the downtown, which is needed to
attract and retain residents and for businesses to thrive. Commissioner Petrillo
stated that this was particularly important with so many children on the site and
was concerned about the parking lot being two way. Commissioner
Bogdanowicz-Wilson stated it would be up to staff to make sure that the parking
lot is used for dropoff and pickup only during those times and remains one way
as presented during those times. He also reiterated that the sidewalk buffers are
especially important given the situation and the added traffic that will occur
during dropoff and pickup. Commissioner Wilson also pointed out that the
Google aerial shows cars in the parking lot being partially parked on the
sidewalk and that this was one of the main reasons that the buffer is so
important in preventing such dangerous and illegal infringements on the public
right-of-way. Mr. Palleschi said that the buffers would interfere with plowing.
Commissioner Wallinger stated that the buffers were also important to keep
snow from parking lots from blocking the public sidewalks.
Commissioner Wilson also stated that the buses should not hold up traffic. The
school would need to make sure that the drivers only put the signs out during
the required times when students are loading and unloading and not when they
are just waiting for students to come out of the building as it would create
significant traffic problems in the downtown if this were to happen. He then
referenced the situation around Oneida Middle School where traffic is virtually
stopped in all directions for several blocks during the pickup and dropoff times.
Commissioner Wallinger stated that staff recommended that the parking lot be
made one way since many people use it as a shortcut. The Applicant
responded that it would be too difficult to police and that it is convenient to be
able to exit to either street since Barret is a one way street. The Commission felt
that having it 2-way added to the confusion, but agreed that policing it during
the whole day would be difficult. Commissioner Wallinger stressed that the one
way during dropoff and pickup would need to be enforced and that, while the
2-way during the rest of the day could stay for now, it may need to be
reevaluated and changed at a later date if problems arose after the school
opens.
Commissioner Wallinger opened the public hearing:
Ray Gillen of Metroplex stated that downtown has a lot of schools (Union
College, Clark College, and SCCC) and Proctors will be bringing students
downtown.
He went on to say, “we have Clarkson and we have the Community College
which has a major campus downtown. The Community College and the public
school system is just announced a major plan with Proctor's to bring hundreds of
students down to the Center City Building.
We have a student-oriented downtown, it will be very cool to have these
students in our downtown. In this building, Northeast Parent is shrinking their
presence in that building. The top floor is vacant. I won a $750,000 grant years
ago to transform the bottom floor of that building into a training center. Every
kid who dropped out of high school in the entire county used to get bused to
this building, to go to remedial classes in the basement of the building, so this is a
prominent building on Franklin Street.
Commissioner Wallinger closed the public hearing.
Mr. Gillen spoke again and said that “he keeps hearing the term municipal
parking, that there is no such thing, that it's Metroplex parking. We help
everyone that parks downtown in our system, we give them notifications, we
educate them, we have thousands of students come to shows and practice
every year downtown.
We will embrace this school and work with them and their employees to have
them come to our parking system. So, there's a sea of parking right across the
street from this building. In addition, Ortho New York is moving out of that
building over to State Street. There's a massive amount of parking right across
the street from Franklin to absorb future needs of the school.” He concluded by
asking the commission to move forward with the project.
Commissioner Wallinger stated that it is not so much the parking that is a
concern, but the nature of the drop-off and pickup of the students and that
elementary school parents have a history of parking wherever they like,
including in the street and in private parking lots and spaces, and illegal spaces,
in order to be able to walk their child(ren) to the door. The commission is trying
to do its due diligence and wants to make sure the project is a success.
Commissioner Hitlall added that safety for the kids is a concern and that the
parking mentioned is on the opposite side of Franklin Street where cars are
moving back and forth.
Commissioner Wilson wanted to know where things stood with requiring the
buffer.
Commissioner Wallinger stated that an interpretation would be needed from
the City’s Zoning Officer on whether the additional buffers would be required
and that until then, the Commission could issue a Conditional Site Plan approval
with the requirement that the buffers would need to be added by the opening
of the School if the Zoning Officer rules that they are required or if the Applicant
does not provide the required proof of exemption prior to the opening of the
school.
Motion for Conditional Site Plan Approval with the following Conditions made by
Commissioner Evers and seconded by Commissioner Beach to approve the site
plan with the following conditions:
1. Cones shall be placed a minimum of 15 minutes prior to the start of
dropoff / pickup until a minimum of 15 minutes after the scheduled times
to block both the Lafayette entrance to the smaller section of the parking
lot and also access to this section from the larger section where the
dropoff and pickup will occur.
2. The landscape buffer to the parking lot on the Lafayette Street side shall
be installed prior to the start of school and, unless ruled otherwise by the
Zoning Officer with the necessary proof being provided by the Applicant
prior to the opening of the school, landscape buffers will be required on
all sections of the parking lot bordering public sidewalks. If required, these
will be installed prior to the start of school.
3. The Applicant shall return to the Planning Commission at the October
meeting to review how the dropoff and pickup strategies are working and
to provide the opportunity for changes to be made if the situation proves
problematic to adjacent streets and businesses. If there are no
complications, the Applicant may request not to attend and City Staff
can make a determination.
4. The Applicant shall return to the Planning Commission to review the
parking and dropoff and pickup accommodations and revisit the
requirements if the number of students is increased.
5. Unless ruled otherwise by the Zoning Officer with the necessary proof
being provided by the Applicant prior to the opening of the school, the
parking lot will be revised to comply with City parking requirements and
the double-parked spaces will be eliminated.
6. Buses will drop off and pick up as proposed on Lafayette Street and the
stop signs will only be out during the times required by law and during
times of waiting for pickup and dropoff to start.
Motion carried unanimously.
C. AMSLER AUTO SALES requests site plan approval pursuant to Section 264-90 I and
K of a proposal to construct a 3,120 SF addition to the existing building at 1545
Broadway, tax parcel # 49.37-1-21, located in a “C-2” Mixed Use Commercial
District.
Luigi Palleschi of ABD Engineers stated he was present to address all the
concerns Mr. Paul Lafond had about the water separator. He stated there are
three options available:
1) Leave it the way it is (as approved in other municipalities)
2) Remove the well
3) Connect to city system (an additional cost)
He went on to say that they have done it in other municipalities where it goes
through an oil water separator, and removes the oil and it's just rainwater that
goes into the ground, similar to the way a septic system works. He said that this
sight is all sand and that the ground could certainly absorb the water.
The second option would be to remove the well and just have the oil water
separator and then the owner would just have to vacuum it out periodically. The
third option would be to connect to the city system. They would have to put a
pump in there and pump it back into the street. Mr. Palleschi stated that there's
no sense of ripping up all the pavement and going into the city streets if not
necessary. They would pump it up through the building, which would be possible
but an added cost. He proposed working it out with City Engineering.“
Commissioner Wallinger, stated that she likes option 2 because it would require
regular maintenance whereas, with the first option, the maintenance could be
forgotten or neglected, which could result in oil making its way into the ground.
Commissioner Wallinger reminded Mr. Palleschi of the Commission’s previous
requirement that there be a landscape buffer between the parking and the
sidewalk and that street trees need to be included. At the suggestion of
Commissioner Wilson, Mr. Palleschi agreed that the parking space on the far
right, when looking from the street, would be rotated to allow for a wider
planting area between the Amsler property and the neighboring property and
would include a shade tree. This planting buffer will be L-shaped and shrubs will
also be included in the area between the sidewalk and the parking. The storm
infrastructure shown in what should have been the planting buffer will be moved
the parking area to allow for the landscape buffer. Mr. Palleschi also agreed
that a planting island with shrubs and a flowering tree would be added in the
triangular space to the left or west of the sign.
Commissioner Wallinger opened the public hearing.
Commissioner Wallinger closed the public hearing.
A motion was made for Site Plan Approval with the following conditions:
The final plan for the oil and water separator shall be approved by the
City Engineer.
A revised landscaping plan that includes the widened landscape buffers
and two additional beds with trees will be submitted to the City Planner
for review and approval prior to proceeding.
Striping shall be added as per direction provided in previous Staff
Comments.
Motion made by Commissioner Wilson seconded by Commissioner Petrillo.
Motion carried unanimously.
Motion made to adjourn the meeting made by Commissioner Hitlall and
seconded by Commissioner Nadler. Meeting adjourned at 8:20 p.m.
Agenda
City of Schenectady
NEW YORK
CITY PLANNING COMMISSION
Room 206, City Hall, Jay Street
Schenectady, NY 12305-1938
NOTICE IS HEREBY GIVEN THAT the City of Schenectady Planning Commission will
conduct a regularly scheduled meeting at 6:00 PM on Wednesday July 13, 2022 in
City Hall, Room 110, 105 Jay Street, Schenectady NY 12305.
Masks are optional. If you would like to email comments for the public hearing, please send
prior to the meeting and include your name and address, to cprimiano@schenectadyny.gov
I. NEW BUSINESS
A. AIK PROPERTY GROUP, LLC requests site plan approval pursuant to Section 264-90 F of a
proposal to construct a 16-unit residential building at 1052 -1062 Barrett Street and 608
South Avenue, tax parcel #’s 39.65-2-33.1, 34.1, and 35.1, located in a “C-4” Downtown
Commercial District.
B. AIK PROPERTY GROUP, LLC requests site plan approval pursuant to Section 264-90 F of a
proposal to construct a nine (9) unit residential building at 1101-1107 Barrett Street and
519 South Avenue, tax parcel #’s 39.57-4-29, 30 and 32, located in a “C-4” Downtown
Commercial District.
II. OLD BUSINESS
A. MITCHELL RAMSEY requests site plan approval pursuant to Section 264-90 M of a
proposal to operate a bar and music hall at 116 Jay Street, tax parcel # 39.72-2-13,
located in a “C-4” Downtown Commercial District.
B. THOMAS LYNCH requests site plan approval pursuant to Section 264-90 L of a proposal
to operate a charter school, Destine Preparatory Charter School, at 530 Franklin Street,
tax parcel #’s 39.80-1-1&2, located in a “C-4” Downtown Mixed-Use Commercial
District.
C. AMSLER AUTO SALES requests site plan approval pursuant to Section 264-90 I and K of a
proposal to construct a 3,120 SF addition to the existing building at 1545 Broadway, tax
parcel # 49.37-1-21, located in a “C-2” Mixed Use Commercial District.
D. ZONING INTERPRETION: CRYSTAL JONES requests site plan approval pursuant to Section
264-90 G of a proposal to renovate the existing building for use as a private club and
business office at 2525 Broadway, tax parcel # 48.66-2-12 and 14.11 located in a “C-2”
Mixed Use Commercial District, and tax parcel #’s 48.66-2-10 and 14.2 located in an “R-
1” Single Family Residential District.
III. MISCELLANEOUS
IV. ADJOURN
Page 1 of 1