Planning Commission
Regular MeetingSitka, AK · August 3, 2022
Minutes
CITY AND BOROUGH OF SITKA
Minutes - Final
Planning Commission
Wednesday, August 3, 2022 7:00 PM Harrigan Centennial Hall
I. CALL TO ORDER AND ROLL CALL
Present: Chris Spivey (Chair), Darrel Windsor, Stacy Mudry, Wendy Alderson, Katie
Riley (telephonic), Thor Christianson (Assembly Liaison)
Staff: Amy Ainslie, Kim Davis
Public: Sam Smith, Eric Calvin, Larry Calvin, Beverly Caldwell, Todd Fleming, Michael
Tisher, Margie Esquiro, Pete Esquiro, Ryan Herbert, Adam Chinalski, Noah Galarza,
Ariadne Will (Sitka Sentinel)
Chair Spivey called the meeting to order at 7:00 pm.
II. CONSIDERATION OF THE AGENDA
III. CONSIDERATION OF THE MINUTES
A PM 22-14 Approve the July 20, 2022 meeting minutes.
Attachments: 12-July 20 2022 DRAFT
M-Mudry/S-Alderson moved to approve the July 20, 2022 meeting minutes.
Motion passed 5-0 by voice vote.
IV. PERSONS TO BE HEARD
Stacy Mudry stated she had been contemplating the housing issues in town and was
aware of State of Alaska infrastructure funds, and would like to pursue the opening City
and Borough of Sitka lands. If CBS would develop an infrastructure plan to create roads
and LIDs on CBS owned property, they would be able to apply to these funds and
develop more land as a way to get affordable housing in town.
V. PLANNING DIRECTOR’S REPORT
Ainslie reported of the change to the Lincoln Street closure, which was that the
threshold would be based on passenger capacity instead of the actual passenger
count. The new closure threshold was when there were days with 5,000 or more total
passenger capacity. The closures would end on September 15. Visit Sitka kept a live
calendar with the cruise ship schedule and closure days. The cost allocation study
was underway to best identify the costs and impacts of tourism on city services and
infrastructure. This study would help the city reimburse passenger-related expenses
properly from the cruise ship passenger tax. The traffic study had begun as well, the
CITY AND BOROUGH OF SITKA Page 1
Planning Commission Minutes - Final August 3, 2022
consultants would be in town the following week to complete onsite observations. This
would support any necessary changes to Department of Transportation roads in Sitka.
CBS was funding the study. Commissioner Alderson would be absent at the August 17
meeting, and the September 7 meeting would be canceled as Ainslie would be absent.
Windsor asked if Mudry's comments from Persons To Be Heard could be added as a
discussion item on the next agenda, Ainslie confirmed.
VI. REPORTS
VII. THE EVENING BUSINESS
B VAR 22-14 Public hearing and consideration of a variance to reduce the front setback
from 14' to 0' at 1415 Davidoff Street in the R-1 single family and duplex
residential district. The property is also known as Lot 3, Clyde Franks
Subdivision. The request is field by Sam Smith. The owner of record is Hard
Rock Construction, LLC.
Attachments: V 22-14_Smith_1415 Davidoff_Setback_Staff Report
A_V 22-14_Smith_1415 Davidoff_Setback_Aerial
B_V 22-14_Smith_1415 Davidoff_Setback_Site Plan
C_V 22-14_Smith_1415 Davidoff_Setback_Elevation & Floor Plan
D_V 22-14_Smith_1415 Davidoff_Setback_1417 Davidoff As-built
E_V 22-14_Smith_1415 Davidoff_Setback_Photos
F_V 22-14_Smith_1415 Davidoff_Setback_Applicant Materials
G_V 22-14_Smith_1415 Davidoff_Setback_Public Comment
Staff report: Ainslie introduced the variance to reduce the front setback from 14 feet to
0 feet at 1415 Davidoff Street. The lot was currently undeveloped and was located along
the undeveloped portion of the Davidoff Street right-of-way (ROW). The section of the
ROW had very dense vegetation and uneven topography even for pedestrian use. The
ROW was platted as 60 feet wide. The applicant would like to construct a single-family
home on the property. The property had landslide history and steep topography
particularly towards the rear of the lot. The applicant had completed study work to
determine the best path forward and had concluded keeping the structure towards the
front of the lot was the best and safest option to complete construction. The site plan
shows the proposed boundary line adjustment from the Sitka Community Land Trust
subdivision; the ceded portion to 1415 Davidoff provided another 50 feet of frontage
along Davidoff Street, which created a larger setback to the common property line with
1417 Davidoff. It also allowed for more off-street parking on the property. The variance
itself would not increase traffic, density, or other impacts beyond regular residential
use under the R-1 zone. It was in line with the comprehensive plan objectives on
housing development and the topography challenges qualified as special circumstance
warranting a variance. Staff recommended approval. Alderson asked staff about the
current owner of the portion from the Sitka Community Land Trust Subdivision. Staff
responded the SCLT currently owned the portion, and the new boundary line would be
recorded on the final plat for the subdivision.
The applicant Sam Smith was present. He stated to keep the project safe and
CITY AND BOROUGH OF SITKA Page 2
Planning Commission Minutes - Final August 3, 2022
affordable, he would like to move the house forward towards Davidoff Street and away
from the steep hillside. The hillside had been reviewed by a local engineer, who
suggested that moving the house closer to Davidoff Street was the best option for
constructability. A mitigation study had been done by R&M engineering and provided
options to help mitigate possible landslide risk. A local engineer who was assisting
with the design had been adamant that the applicant drill into rock and not build on
ash. Drilling rebar into the bedrock and adding a retaining wall would shore up the
hillside. The footprint of the house was roughly 35 feet by 50 feet. The footprint included
the cantilever floor portion out from the foundation using steel beams. Smith stated it
was possible to build without a variance, but the house would be wider and not as
deep. He was asking for the consideration with the understanding Davidoff Street was
considered a dead-end. The height of the building was limited to 35 feet per the zoning
code. Smith also stated he believed other developments nearby had been granted the
0’ variance by the Commission and would like that to be considered.
Public comment: Eric Calvin, representing his father Larry Calvin, disagreed with the
findings of the area not being developed. E. Calvin stated the properties across the
street would be developed in the future. If granted the variance would create a parking
problem. He asked that the variance application be denied.
Ainslie read a letter objecting to the variance from Kris Calvin, Eric Calvin, Leif Calvin,
and Karen Calvin-Woodard on behalf of Larry Calvin (Calvin). Calvin owned four
neighboring properties; 210 and 214 Neva Street, 1410 Davidoff Street, and 1409
Edgecumbe Drive. The letter asserted that if granted, the variance would have a
detrimental effect on their surrounding properties and public safety in the area. They
also felt that the variance was not warranted because the issues regarding the
topography and buildability of the lot could be addressed with enough time and
financial resources, and that variances may not be granted solely to relieve financial
hardship or inconvenience. The detrimental effect to Calvin's property included a greater
view obstruction as the structure would be built on a higher elevation as a result of the
variance. Public safety considerations included soil disturbance and long-term erosion
in an already unstable landslide zone.
Ainslie read a letter from Beverly Caldwell. Caldwell resided at 1503 Halibut Point
Road. She stated she had concerns about potential landslides happening between
1511 and 1417 Halibut Point Road, particularly due to trees on the hillside that could
uproot.
Smith responded to public comment. Understands the concerns but even without the
variance he would be able to build a house on the property. Without the variance he
would have to make the house wider which would probably block the view more. He
stated landslides in the area were caused by the way the lots in the area were
developed. He would be de-loading the lot by pulling trees and stumps to make the
hillside stable for building. Geotechnical engineers have assessed the hillside and
provided ways to make it safer. He believes even without the variance view blocking
would occur.
Commission discussion: Windsor stated he felt the 0-foot variance would be safer for
preventing landslides, and there was a precedent with the Sitka Community Land Trust
property below being granting a 0-foot setback for those properties that abutted the
undeveloped portion of Davidoff Street, but he understood the neighbors point of view.
Riley was unsure given that there could be alternate building plans made, and
reinforced that variances were not granted solely due to inconvenience. Alderson had
questions and concerns regarding how the building plans could change after the
CITY AND BOROUGH OF SITKA Page 3
Planning Commission Minutes - Final August 3, 2022
variance was granted, but generally understood why it made sense to build that close
to Davidoff Street. Alderson also felt that with the additional 32 feet on the side
adjacent to 1417 Davidoff, and a two-car garage there seemed to be enough parking.
Ainslie clarified the building plans submitted under a building permit would need to be
consistent with those submitted in the variance application, and if plans changed too
much then it would come back to the commission for reconsideration. Spivey stated
the footprint had to stay the same, but the building design was able to change. Ainslie
reminded Commissioners they could add conditions if necessary. Spivey believed that
the development of this portion of the right-of-way undertaken by the applicant would
ultimately be a benefit to the property owners across the street. Spivey stated he did
not see a reason for denial, and they have set precedent of approving 0-foot setbacks
to this portion of the Davidoff Street right-of-way in the past.
M/Mudry–S/Windsor moved to approve the zoning variance for a reduction to
the front setback to 0' at 1415 Davidoff Street in the R-1 single family and
duplex residential district subject to the attached conditions of approval. The
property was also known as Lot 3, Clyde Franks Subdivision. The request was
filed by Sam Smith. The owner of record was Hard Rock Construction, LLC.
Motion passed 5-0 by voice vote.
M/Mudry–S/Windsor moved to adopt and approve the required findings for
variances involving major structures or expansions as listed in the staff report.
Motion passed 5-0 by voice vote.
C VAR 22-15 Public hearing and consideration of a platting variance to serve more than four
lots (eleven lots) via private utility easement for a subdivision of 300 Kramer
Avenue in the R-1 single family and duplex residential district. The property is
also known as Lot 3, West Woodbury Subdivision. The request is filed by
Todd Fleming. The owner of record is Sound Development, LLC.
Attachments: V 22-15_Sound Development_300 Kramer_Platting Variance_Staff
Memo
A_V 22-15_Sound Development_300 Kramer_Platting Variance_Aerial
B_V 22-15_Sound Development_300 Kramer_Platting
Variance_Preliminary Plat
C_V 22-15_Sound Development_300 Kramer_Platting
Variance_Neighboring Subdivision Plats
D_V 22-15_Sound Development_300 Kramer_Platting Variance_CBS
to DEC 6.21
E_V 22-15_Sound Development_300 Kramer_Platting
Variance_Applicant Materials
F_V 22-15_Sound Development_300 Kramer_Platting
Variance_Photos
Staff report: Ainslie introduced the consideration of a platting variance to serve more
than four lots (eleven lots) via private utility easement. The Sitka General Code
21.40.030 stated no more than four lots shall be served by a private utility easement.
The applicant was requesting approval to serve the resulting lots 1-3 of the subdivision
via a private sewer easement which currently had approval to serve eight lots. Ainslie
provided a brief history of the platting actions and approval for the eight lots approved to
use the sewer easement. There were three primary considerations made in coming to
a staff recommendation including operational and service issues for the sewer line, the
challenges that come in managing private utility services via easement and
maintenance agreements, and considerations for future growth and development in the
area. Staff recommended denial for five primary reasons; the system had been
CITY AND BOROUGH OF SITKA Page 4
Planning Commission Minutes - Final August 3, 2022
designed to serve a minimal number of lots and did not find expansion advisable, the
challenges managing the system carried risk for current and future property owners as
well as for CBS rate payers, future development of the area was not well accounted for
through this development plan, the granting of the variance would set a worrying
precedent that allowed developers to circumvent the major subdivision process, and
that the applicant had not met the burden of proof to show that the variance was
warranted. However, if the Commission was inclined to approve the platting variance,
staff had prepared a list of conditions that should be attached to an approval.
Commissioner discussion: Spivey asked for clarification on the maintenance of the
sewer line; it was his understanding that it would be the responsibility of the property
owners and did not understand what risk there was to the municipality that would
result. Ainslie explained staff's experience in older subdivisions in which urgent or
catastrophic failures of private amenities such as roads or utilities occurred, and the
resulting pressure for the municipality to respond in those cases, incurring added costs
to the ratepayers broadly. Christianson added the perspective of an Assembly
member, stating it was not uncommon for these types of issues to come forward to the
Assembly; when 30 years or more pass from the time of original development and
initial property owners, it was hard to say no to city-action when a citizen was without
water or sewer. Spivey asked about the dimension of the sewer line, and if an 8-inch
line was required for a major subdivision. Ainslie stated that an 8-inch sewer line was
generally standard, but was evaluated on a case-by-case basis for each subdivision
based on the number of properties that would be served. Windsor asked for clarification
between repair or maintenance on a sewer line.
The applicant, Todd Fleming representing Sound Development, was present. Fleming
passed out paperwork to the Commissioners not included in the applicant materials.
He stated they were working on developing properties for people to build houses on.
There was no sewer service in Kramer Avenue adjacent to the proposed lots 1-3, and a
gravity sewer was not feasible without private properties utilizing pumps which he did
not think was ideal for property owners. The sewer line in Kramer Avenue was a
12-inch pipe. The 8" line developed for the Tisher Subdivision was designed by an
engineer, and they would be putting in two or three manholes to serve the line. The
private utility system was approved by both CBS and the State of Alaska DEC for
construction. He was confused about the recommendation of denial, as he asserted it
had already been approved by both CBS and DEC. Spivey stated one of the staff
concerns was the possibility of further development in the area which might also use
the sewer line. Fleming said he had been working on a major subdivision plan in 2014,
but that it was still under city review. He also stated he did intend to continue with
minor subdivisions of the properties and felt the private line had adequate capacity to
handle more lots. Spivey asked if there was a drainage report, and Fleming reported it
would be submitted under the minor subdivision.
Public comment: Michael Tisher was in support of the variance. He did not agree with
the staff recommendation of denial, and he believed adding a few more connections
would help with the maintenance of the line. He stated this was one of the best sewer
lines he had ever put into a development, and it had passed inspection by CBS. He
stated DEC had a maintenance provision that every few years the line had to be
flushed. Ainslie read a letter from Jill Hirai, who was disheartened about the
recommendation of denial for both the variance and the subdivision. She was
concerned about the housing situation in Sitka, and she believed the infrastructure
developed by Mr. Tisher was well within the existing standards for developments.
Commission discussion: Windsor believed it was important to listen to the experts and
CITY AND BOROUGH OF SITKA Page 5
Planning Commission Minutes - Final August 3, 2022
he had reviewed the letter from the city for the approval from June 24, 2021 on the
sewer line connection. He also stated the sewer line was built well and trusted the
developers who installed it, Mudry agreed with his opinion. Alderson does not like
going against staff recommendations, but Jill’s letter resonated with her. Riley agreed
with Alderson and staff’s assessment. She was concerned about the precedent that
would be set regarding subdivision developments. She asked if the major subdivision
was moving forward, Spivey responded it was in limbo since the landslides. He
respected the staff decision but was conflicted given the paperwork from CBS
approving the utility. He also suggested a signed maintenance agreement between
property owners would help with the maintenance of the sewer line. Ainslie stated
these documents regarding CBS approval of the line were not provided in the applicant
materials. She noted the signed approval was only for lot three as a singular lot and not
for any additional subdivided properties. Her concern was not with the integrity or size
of the sewer line but with the number of connections. It was a question of whether it
was advisable to do so from both a management perspective and the matter of
precedent set. With no clear standard for how many more lots could connect to a
private utility system, it would create a path forward for circumvention of the major
subdivision process by approving minor after minor subdivision. She also wanted to
note that even though CBS approved and inspected the utility as a private line, it did
not make the line a good candidate to be owned and maintained by CBS. Staff
recommended postponement due to the materials provided by Mr. Fleming which
warranted further review. Riley was in favor of postponement since she had also not
seen the documents provided and the public had not been able to review those
documents as well. Applicant was asked if the postponement would be a problem, he
would rather not be delayed but understood the need for staff review.
M/Alderson–S/Mudry moved to postpone until September 21, 2022. Motion
passed by a 3-2 by voice vote.
D P 22- 07 Public hearing and consideration of a preliminary plat for a minor subdivision
to result in four lots at 300 Kramer Avenue in the R-1 single family and duplex
residential district. The property is also known as Lot 3, West Woodbury
Subdivision. The request is filed by Todd Fleming. The owner of record is
Sound Development, LLC.
Attachments: P 22-07_Sound Development_300 Kramer_Minor Sub_Staff Report
A_P 22-07_Sound Development_300 Kramer_Minor Sub_Aerial
B_P 22-07_Sound Development_300 Kramer_Minor Sub_Current Plat
C_P 22-07_Sound Development_300 Kramer_Minor Sub_Preliminary
Plat
D_P 22-07_Sound Development_300 Kramer_Minor Sub_Neighboring
Subdivision Plats
E_P 22-07_Sound Development_300 Kramer_Minor Sub_Photos
F_P 22-07_Sound Development_300 Kramer_Minor Sub_Applicant
Materials
G_P 22-07_Sound Development_300 Kramer_Minor Sub_Public
Comment
Staff report: Ainslie stated the preliminary plat was contingent on approval of V 22-15
CITY AND BOROUGH OF SITKA Page 6
Planning Commission Minutes - Final August 3, 2022
and recommended postponement. The applicant asked to move forward regardless.
Ainslie stated the plan and plat submitted had to address the plans for utilities. As the
subdivision code stated that no more than four lots could connect to a private utility
easement, and the platting variance to waive this subdivision requirement had not been
granted, the plat was not compliant with the subdivision code and therefore staff
recommended denial on that basis. In concept, the subdivision itself was
straightforward; all the lots met minimum size requirements, and all were accessed via
Kramer Avenue which was a municipally maintained right-of-way. The waterline in
Kramer Avenue had been extended by Tisher for the Tisher and JPJL Subdivisions from
its previous termination point near Emmons Street. It was an 8-inch line that connected
to a 6-inch line in the subdivision. CBS would consider adopting the waterline as
public, which would be a good opportunity to work with the applicant to get a waterline
to serve the entire area. The front of the lot was flat, but the topography varies
throughout the middle and there may be wetlands to be aware of. The comprehensive
plan encouraged residential development, but also aimed to have a fair share of costs
be borne by developers to account for the public costs of private development. Staff
recommended denial, but had prepared conditions that should be attached to an
approval if granted. Spivey asked staff if sewer utilities as shown on the preliminary plat
could be changed on the final plat. Ainslie responded that while there were times in
which minor modifications were made to plats between preliminary and final, but
something as substantial as the utility plan would be inconsistent with the general
platting process. The larger issue was that without an approved platting variance, the
preliminary plat did not the meet the subdivision code requirement.
The applicant, Todd Fleming representing Sound Development, came forward. Fleming
had a drainage report he provided to Commissioners and staff. He stated he did not
agree with staff on the requirement of providing utilities on the preliminary plat. Windsor
asked what size the lots would be, Fleming stated approximately 9,500 square feet.
Alderson asked about the drainage plan, as it did not show any significant changes.
Fleming stated the engineer he had hired to complete the report did not see the need
for any substantial changes to drainage flow in the area.
Public comment: Margie Esquiro was concerned with drainage, as the water goes
downhill towards her property on Sand Dollar Drive. There had been landslides in the
area and when it rained, there was a lot of groundwater. She also stated there were
some wetlands in the area behind her house where lot four was located.
Commission discussion: Windsor had a question for staff about building a subdivision
off-grid and if there was a requirement to connect it to a utility. Ainslie clarified a minor
subdivision did not require the developer to install utilities to the lots. The materials as
submitted had easements located on the plat to connect to a private utility, and it did
not meet the code requirement of no more than four lots connecting to a private utility
easement.
M/Windsor–S/Alderson moved to postpone to September 21, 2022. Motion
passed by 5-0 by voice vote.
VIII. ADJOURNMENT
Seeing no objections, Chair Spivey adjourned the meeting at 9:25 pm.
CITY AND BOROUGH OF SITKA Page 7
Agenda
CITY AND BOROUGH OF SITKA
Meeting Agenda - Final
Planning Commission
Wednesday, August 3, 2022 7:00 PM Harrigan Centennial Hall
I. CALL TO ORDER AND ROLL CALL
II. CONSIDERATION OF THE AGENDA
III. CONSIDERATION OF THE MINUTES
A PM 22-14 Approve the July 20, 2022 meeting minutes.
Attachments: 12-July 20 2022 DRAFT
IV. PERSONS TO BE HEARD
(Public participation on any item off the agenda. All public testimony is not to exceed 3
minutes for any individual, unless the Chair imposes other time constraints at the
beginning of the agenda item.)
V. PLANNING DIRECTOR’S REPORT
VI. REPORTS
VII. THE EVENING BUSINESS
B VAR 22-14 Public hearing and consideration of a variance to reduce the front setback
from 14' to 0' at 1415 Davidoff Street in the R-1 single family and duplex
residential district. The property is also known as Lot 3, Clyde Franks
Subdivision. The request is field by Sam Smith. The owner of record is
Hard Rock Construction, LLC.
Attachments: V 22-14_Smith_1415 Davidoff_Setback_Staff Report
A_V 22-14_Smith_1415 Davidoff_Setback_Aerial
B_V 22-14_Smith_1415 Davidoff_Setback_Site Plan
C_V 22-14_Smith_1415 Davidoff_Setback_Elevation & Floor Plan
D_V 22-14_Smith_1415 Davidoff_Setback_1417 Davidoff As-built
E_V 22-14_Smith_1415 Davidoff_Setback_Photos
F_V 22-14_Smith_1415 Davidoff_Setback_Applicant Materials
G_V 22-14_Smith_1415 Davidoff_Setback_Public Comment
CITY AND BOROUGH OF SITKA Page 1 Printed on 7/29/2022
Planning Commission Meeting Agenda - Final August 3, 2022
C VAR 22-15 Public hearing and consideration of a platting variance to serve more than
four lots (eleven lots) via private utility easement for a subdivision of 300
Kramer Avenue in the R-1 single family and duplex residential district. The
property is also known as Lot 3, West Woodbury Subdivision. The request
is filed by Todd Fleming. The owner of record is Sound Development, LLC.
Attachments: V 22-15_Sound Development_300 Kramer_Platting Variance_Staff Memo
A_V 22-15_Sound Development_300 Kramer_Platting Variance_Aerial
B_V 22-15_Sound Development_300 Kramer_Platting Variance_Preliminary Plat
C_V 22-15_Sound Development_300 Kramer_Platting Variance_Neighboring Subdivision Plats
D_V 22-15_Sound Development_300 Kramer_Platting Variance_Photos
E_V 22-15_Sound Development_300 Kramer_Platting Variance_Applicant Materials
D P 22- 07 Public hearing and consideration of a preliminary plat for a minor
subdivision to result in four lots at 300 Kramer Avenue in the R-1 single
family and duplex residential district. The property is also known as Lot 3,
West Woodbury Subdivision. The request is filed by Todd Fleming. The
owner of record is Sound Development, LLC.
Attachments: P 22-07_Sound Development_300 Kramer_Minor Sub_Staff Report
A_P 22-07_Sound Development_300 Kramer_Minor Sub_Aerial
B_P 22-07_Sound Development_300 Kramer_Minor Sub_Current Plat
C_P 22-07_Sound Development_300 Kramer_Minor Sub_Preliminary Plat
D_P 22-07_Sound Development_300 Kramer_Minor Sub_Neighboring Subdivision Plats
E_P 22-07_Sound Development_300 Kramer_Minor Sub_Photos
F_P 22-07_Sound Development_300 Kramer_Minor Sub_Applicant Materials
G_P 22-07_Sound Development_300 Kramer_Minor Sub_Public Comment
VIII. ADJOURNMENT
NOTE: More information on these agenda items can be found at
https://sitka.legistar.com/Calendar.aspx or by contacting the Planning Office at 100
Lincoln Street. Individuals having concerns or comments on any item are encouraged to
provide written comments to the Planning Office or make comments at the Planning
Commission meeting. Written comments may be dropped off at the Planning Office in
City Hall or emailed to planning@cityofsitka.org. Those with questions may call (907)
747-1814.
Publish:
CITY AND BOROUGH OF SITKA Page 2 Printed on 7/29/2022
Get email alerts for Sitka