City Council
Regular MeetingSteelton, PA · November 17, 2014
Minutes
Page |1
Borough of Steelton
Council Agenda
November 17, 2014
Call Meeting to Order: President Jeffery Wright
Pledge of Allegiance: President Jeffery Wright
Moment of Silence: Mayor Thomas F. Acri
There were no executive sessions held between meetings.
Approval of schedules of billing, requisitions and change order as present for: October 2014
Approval of Department Reports:
Fire and Ambulance
Police
Code Enforcement
NEDC Committee
Mayor’s Report
Public Works Report
Mayor’s Report
Borough Manager’s Report
Public Comment on Agenda Items Only
Presentations:
Matt Cichy Engineering Activities
(October 17 – November 14)
Communication:
2013 Audited Financial Statements and Management Representation Letter prepared by Zelenkofske Axelrod
(ZA)
Unfinished Business:
Mr. Wion Proposed changes to the Animal Ordinance
Page |2
Borough of Steelton
Council Agenda
November 17, 2014
New Business:
Mr. Wion Resolution to self report to the United States
Exchange Commission (SEC) through their voluntary
settlement program, Municipal Continuing Disclosure
Cooperation Imitative
Borough Manager Approval of the Disclosure Dissemination Agent
Agreement with Susquehanna Group Advisors
(SGA)
Donna Kreiser – McNees, Wallace & Nurick LLC Ordinance to (1) refinance the General Obligation
Bond Series of 2006 and (2) issuance of the 2014
General Obligation Bond for the Firehouse
Improvement Project and the Pine & Harrisburg
Street Utility Improvements Project
Audience Participation
Council Concerns
Executive Session
Other Business
Adjournment
Page 1
Steelton Borough
Council Meeting
November 17, 2014
The regular monthly meeting was called to order at 6:30 pm, by President, Jeffery Wright, with
the pledge of allegiance, followed by a moment of silence.
In Attendance:
Michael Albert
Maria Marcinko
Steve Shaver
Jeffery Wright
Mayor Thomas Acri
David A. Wion, Solicitor
Sara Gellatly, Borough Manager
Ken Klinepeter
John King, Police Chief
Sylvie Bmbacher
Absent:
Denae House
Brian Proctor
MaryJo Szada
APPROVAL OF SCHEDULES OF BILLINGS, REQUISITIONS AND CHANGE
ORDERS AS PRESENTED
A motion was made by Mr. Albert to approve the schedules, seconded by Mr. Shaver and
approved unanimously by all present.
APPROVAL OF DEPARTMENT REPORTS:
A motion was made by Mr. Albert to approve the department reports, seconded by Ms. Marcinko
and approved unanimously by all present.
Fire and Ambulance - No report
Police - Mr. Shaver reported that there were several trainings that the police undertook. A motion
was made by Mr. Shaver that those training certificates be added to the officers' personnel files,
seconded by Ms. Marcinko and approved unanimously by all present.
Code Enforcement - No report
NEDC - No report
Mayor's Report - Mr. Acri reported that December 2nd will be the tree lighting ceremony at
6:30 p.m. in front of the hall.
Public Works - Ms. Marcinko stated that the final walkthrough Street Scape II happened this
week. The Memorial Bricks are all back in place in front of the trees.
Page 2
Steelton Borough
Council Meeting
November 17, 2014
Mr. Klinepeter stated that they have developed and implemented a spill control procedure. We
continue to work at bringing the filtration plant up to spec and all four filters are operating as
designed and to spec.
Borough Manager's Report - None
PUBLIC COMMENT: AGENDA ITEMS ONLY
None
PRESENTATIONS:
Matt Cichy, HRG- Engineering Activities October 17, 2014 through November 14, 2014 Mr.
Cichy provided an overview of his report.
Project No. 1337.0032 (Engineering Retainer) HRG has assisted the Borough staff in
presentation of the Fire House Improvements Grant Application to the Dauphin County Gaming
Advisory Board. HRG will assist the Borough in making a presentation to the Dauphin County
Gaming Advisory Board on this application.
Project No. 1337.0229 (NDES Phase II MS4 Stormwater Requirements) - HRG will continue to
assist the Borough on the follow-up actions from the EPA audit.
Project No. 1337.0430 & 1337.0462 (Blueberry Alley Storm Sewer Replacement & Washington
Street Storm Sewer Replacement) - Borough staff completed the test holes on Washington Street
on the existing utilities needed for that project. HRG has input that data into the documents to
determine the location of the existing utilities and found that the proposed design as HRG
revised it, HRG can now avoid a conflict with UGI's existing gas line. Will work with Borough
staff to finalize design and bidding for this project.
Project No. 1337.0446 (Pump Station Sewage Grinder Improvement Project) - This project is
underway. HRGdid meet with the Public Works Department to visit the pump stations and review
the scope of work associated with this project. HRG will continue to move forward on design
purposes.
Project No. 1337.0456 (Mohn Street Recreational Project) - This project is out for bid on the
PennBID Program. Bidders are able to access the bid documents at no cost at www.PennBID.net.
Bids are due on December 8, 2014. It is intended that HRG will review the bids at the Council
meeting in December.
Page 3
Steelton Borough
Council Meeting
November 17, 2014
Project No. 1337.0460 (Street Scape phase 2) - Work on this project is nearing completion. The
contractor is working on minor items that remain. It is intended that those items will be
completed by the end ofthis month.
Project No. 1337.0467 (Adams Street Redevelopment Storm Sewer Improvements) - HRG
conducted a Preconstruction Conference for this project on October 28, 2014. The contractor
intends to start work on this project the week of December 15th.
Project No. _1337.0470 (Swatara Street Retaining Wall) - HRG worked with the Borough
Manager to order the survey targets that are to be installed on the wall. Once we get a delivery
date we will work with Borough staff to coordinate a schedule the actual installation and
investigation work
Project No. 0124.0432 (Harrisburg & Pine Streets Utility Improvements Project) - HRG has been
working on the survey efforts, designating the utilities and is moving forward in the design
efforts for this project. HRG did meet with PennDOT to review the project status and schedule.
PennDOT advised that they have revised their schedule and pushed back the date for submitting
final plans and specs from late January until March 2, 2015. Mr. Cichy requested an action item to
authorize the execution of all necessary documents relative to incorporation of the Borough's
sewer facility improvements into the PennDOT construction contract including the Consultant
Request form and the Cost Sharing Request form, resolution, and agreement. A motion was made
by Mr. Shaver to approve Resolution 2014-R-16, seconded by Mr. Albert and approved
unanimously by all present.
COMMUNICATION:
The Borough received the 2013 Audited Financial Statements and Management Representation
Letter prepared by Zelenkofske Axelrod (ZA).
UNFINISHED BUSINESS:
Mr. Wion, Proposed Changes to the Animal Ordinance No. 2014-6 - Mr. Wion stated that the
Borough is considering, tonight, Ordinance No. 2014-6, which is an Ordinance that amends the
Animal Ordinance Chapter and puts in its' place an entirely new Chapter dealing with animals. It
provides the definition for the ordinance, prohibits keeping of specified animals in the Borough,
regulates the control of dogs and other animals running at-large, provides for the seizure and
disposition of animals, the abandonment, mistreatment, or cruelty to animals, requires the
removal of waste, prohibits nuisances in the nature of noise, provides for quarantine of animals in
certain situations, prohibits hunting of animals, establishes the liability of the owner, requires the
licensing and vaccination of dogs, and establishes violations and penalties for the violation of the
Ordinance. A motion was made by Mr. Albert to approve Ordinance no. 2014-6, seconded by
Ms. Marcinko and approved unanimously by all present.
Page 4
Steelton Borough
Council Meeting
November 17,2014
NEW BUSINESS:
Mr. Wion - Resolution to self-report to the United States Exchange Commission (SEC)
through their voluntary settlement program, Municipal Continuing Disclosure Cooperation
Initiative - Mr. Wion explained that Resolution 2014-R-16 deals with the fact that some of the
financial institutions who have been dealing with the bond issues on behalf of the Borough and
the Borough issuer, as well as some of the other entities that deal with the bonds have been
required to indicate that their statements and past issues have either contained the appropriate
information, or to some extent, have not contained the materials which the SEC requires to be in
them. The resolution authorizes the Borough to file a self-report in a timely fashion. A motion was
made by Mr. Albert to approve Resolution 2014-R-16, seconded by Mr. Shaver and approved
unanimously by all present.
Ms. Gellatly - Approval of the Disclosure Dissemination Agent Agreement with
Susquehanna Group Advisors (SGA) - Ms. Gellatly explained that this Agreement goes along
with Resolution 2014-R-16 that was just passed. This Agreement authorizes Susquehanna Group
Advisors to take care of uploading the necessary required documents annually, as well as, assisting
the Borough catching up with what is currently missing for an annual fee of $1,500.00. A motion
was made by Mr. Albert to approve the Agreement, seconded by Ms. Marcinko and approved
unanimously by all present.
Ms. Donna Kreiser, McNees, Wallace & Nurick LLC -- Ordinance to (1) refmance the
General Obligation Bond Series of 2006 and (2) issuance of the 2014 General Obligation
Bond for the Firehouse Improvement Project and the Pine & Harrisburg Street Utility
Improvements Project - Ms. Kreiser reviewed the Ordinance that authorizes the Borough to
issue $8,000,000 in maximum amount of bonds to finance a variety of projects. Those projects
include capital projects of the Borough, projects to be undertaken on behalf of the Borough's
sewer system, projects to be undertaken in connection with the water system owned by the
Borough Authority, and also to undertaken the refunding of outstanding 2006 Bonds. SGA has
been working with the Borough to define the project and get the project ready to be financed
through bonds to be issued by the Borough. This Ordinance authorizes the issuance of the bonds
and the Borough's pledge of the full faith credit and taxing power to secure those bonds. It
otherwise authorizes the Borough and its consultant, bond counsel and other involved parties to
proceed with all other action that is needed in order to issue those bonds and finance the project. A
motion was made by Mr. Shaver to approve the Ordinance, seconded by Ms. Marcinko and
approved unanimous!y by all present.
AUDIENCE PARTICIPATION:
Mr. Powell, 321 Lebanon Street
Mr. Powell expressed concerns about no parking during the Adams Street Redevelopment
Stormwater Project.
Page 5
Steelton Borough
Council Meeting
November 17,2014
COUNCIL'S CONCERNS:
Mr. Shaver - reminded everyone about the Christmas Tree lighting on December 2'd at 6:30 p.m.
Mr. Shaver thanked staff for all the work they did in regards to the budget. We did not have to raise
taxes.
Mr. Albert - reported that the Steelton Peewees won the Superbowl this year. Mr. Albert
congratulated the team. Mr. Albert wished everyone a Happy Thanksgiving.
Mr. Acri - wished everyone a Happy Thanksgiving and congratulated the Steelton Peewees.
Ms. Marcinko - thanked the staff for all they did in regards to the budget. Ms. Marcinko stated
that long time member of the fire department Mr. Dale Novachak passed away last week.
Mr. Wright - thanked the staff for all they did in regards to the budget. Wished everyone a
Happy Thanksgiving. Mr. Wright expressed sympathy to Ms. Szada on the passing of her mother.
ADJOURNMENT:
There being no other business before Council, on a motion made by Mr. Shaver, seconded by Mr.
Albert, the meeting adjourned at 7:07 pm.
Respectively Submitted:
Sara Gellatly
Borough Secretary
14008-001/FL*43839