1. CALL TO ORDER/ROLL CALL
2. PUBLIC COMMENT*
3. ITEM(S) FOR DISCUSSION
3.1 19-5687 DISCUSSION AND CONSIDERATION OF THE SUSTAINABLE
GROUNDWATER MANAGEMENT ACT (SGMA) GROUNDWATER
SUSTAINABILITY PLAN UPDATE/ADOPTION SCHEDULE
Recommended Action: RECOMMENDATION
It is recommended that the Council Water Committee approve the
Sustainable Groundwater Management Act (SGMA) Groundwater
Sustainability Plan Update/Adoption Schedule.
Department: Municipal Utilities
Attachments: PPT - SGMA Update July 2019
3.2 19-5690 CONSIDERATION OF DRAFT STAFF REPORT - APPROVE
CONTRACT CHANGE ORDER NO. 2 WITH ROBERTSON-BRYAN,
INC. FOR PROJECT MANAGER SERVICES FOR THE REGIONAL
WASTEWATER CONTROL FACILITY MODIFICATIONS PROJECT;
AND FORWARD A RECOMMENDATION TO THE CITY COUNCIL
Recommended Action: RECOMMENDATION
It is recommended that the Council Water Committee consider the Draft
Staff Report - Approve Contract Change Order No. 2 with Robertson-Bryan,
Inc. for Project Manager Services for the Regional Wastewater Control
Facility Modifications Project; and forward a recommendation to the City
Council for consideration and approval.
All draft documents are subject to change.
Department: Municipal Utilities
City of Stockton Page 1 Printed on 7/8/2019
Council Water Committee Meeting Agenda - Final July 11, 2019
Attachments: Draft Staff Report - Contract Change Order No 2
Draft Attachment A - Contract Change Order No 2
Draft Attachment B - Professional Services Contract
Draft Attachment C - Contract Change Order No 1
3.3 19-5693 CONSIDERATION OF DRAFT STAFF REPORT - AWARD A
PROFESSIONAL SERVICES CONTRACT FOR CONSTRUCTION
REPRESENTATIVE FOR THE REGIONAL WASTEWATER
CONTROL FACILITY MODIFICATIONS PROJECT, AND FORWARD
A RECOMMENDATION TO THE CITY COUNCIL
Recommended Action: RECOMMENDATION
It is recommended that the Council Water Committee consider the Draft
Staff Report - Award a Professional Services Contract for Construction
Representative for the Regional Wastewater Control Facility Modifications
Project, and forward a recommendation to the City Council for
consideration and approval.
All draft documents are subject to change.
Department: Municipal Utilities
Attachments: Draft Staff Report - Construction Rep Contract
Attachment A - Draft Professional Services Contract
3.4 19-5692 CONSIDERATION OF DRAFT STAFF REPORT - REIMBURSE THE
CITY’S CAPITAL EXPENDITURES PAID PRIOR TO THE STATE
WATER BOARD APPROVAL OF THE REGIONAL WASTEWATER
CONTROL FACILITY MODIFICATIONS PROJECT FUNDS, AND
FORWARD A RECOMMENDATION TO THE CITY COUNCIL
Recommended Action: RECOMMENDATION
It is recommended that the Council Water Committee consider the Draft
Staff Report - Reimburse the City's Capital Expenditures Paid Prior to the
State Water Board Approval of the Regional Wastewater Control Facility
Modifications Project Funds, and forward a recommendation to City
Council consideration and approval.
All draft documents are subject to change.
Department: Municipal Utilities
Attachments: Draft Staff Report - Reimburse Capital Expenditures
Draft Proposed Resolution - Reimburse Capital Expenditures
3.5 19-5691 CONSIDERATION OF DRAFT STAFF REPORT - AUTHORIZE THE
ISSUANCE AND SALE OF WASTEWATER BOND ANTICIPATION
NOTES, SERIES 2019, IN AN AGGREGATE PRINCIPAL AMOUNT
NOT TO EXCEED $125,000,000; APPROVING AS TO FORM THE
VARIOUS FINANCING DOCUMENTS AND AUTHORIZE THE
TAKING OF CERTAIN ACTIONS IN CONNECTION THEREWITH,
City of Stockton Page 2 Printed on 7/8/2019
Council Water Committee Meeting Agenda - Final July 11, 2019
AND FORWARD A RECOMMENDATION TO THE CITY COUNCIL
Recommended Action: RECOMMENDATION
It is recommended that the Council Water Committee consider the Draft
Staff Report - Authorize the Issuance and Sale of Wastewater Bond
Anticipation Notes, Series 2019, in an Aggregate Principal Amount Not to
Exceed $125,000,000, Approving as to Form the Various Financing
Documents and Authorize the Taking of Certain Actions in Connection
Therewith; and forward a recommendation to the City Council for
consideration and approval.
All draft documents are subject to change.
Department: Municipal Utilities
Attachments: Draft Staff Report
Draft Attachment A - Pro Forma
Draft Attachment B - BANs Schedules
Draft Attachment C - Estimated Total Debt Service
Draft Attachment D - Plan of Finance
Draft Proposed Resolution
Draft Proposed Authority Resolution
Draft Exhibit 1 - Indenture
Draft Exhibit 2 - Installment Purchase Agreement
Draft Exhibit 3 - Note Purchase Contract
Draft Exhibit 4 - Preliminary Offering Memorandum
Wastewater BANs Presentation CWC
3.6 19-5689 CONSIDERATION OF DRAFT STAFF REPORT - AUTHORIZE THE
CITY MANAGER TO APPLY TO THE U.S. ENVIRONMENTAL
PROTECTION AGENCY (EPA) FOR A LOW INTEREST WATER
INFRASTRUCTURE FINANCE AND INNOVATION ACT (WIFIA)
LOAN TO REDUCE FINANCING COSTS FOR THE REGIONAL
WASTEWATER CONTROL FACILITY (RWCF) MODIFICATIONS
PROJECT, EXECUTE A WIFIA LOAN AGREEMENT FOR THE
PLANNING, DESIGN, AND CONSTRUCTION OF THE RWCF
MODIFICATIONS PROJECT, PLEDGE REVENUES AS SECURITY
FOR PAYMENT OF THE WIFIA LOAN AGREEMENT, AND
REIMBURSEMENT OF CITY’S EXPENDITURES PAID PRIOR TO
THE LOAN AGREEMENT; AND FORWARD A RECOMMENDATION
TO THE CITY COUNCIL
City of Stockton Page 3 Printed on 7/8/2019
Council Water Committee Meeting Agenda - Final July 11, 2019
Recommended Action: RECOMMENDATION
It is recommended that the Council Water Committee consider the Draft
Staff Report - Authorize the City Manager to Apply to the U.S.
Environmental Protection Agency for a Low Interest Water Infrastructure
Finance and Innovation Act Loan to Reduce Financing Costs for the
Regional Wastewater Control Facility Modifications Project, Execute the
WIFIA Loan Agreement for the Planning, Designm and Construction of the
RWCF Modifications Project, Pledge Revenues as Security for Payment of
the WIFIA Loan Agreement, and Reimbursement of City's Expenditures
Paid Prior to the Loan Agreement; and forward a recommendation to the
City Council for consideration and approval.
All draft documents are subject to change.
Department: Municipal Utilities
Attachments: Draft Staff Report - WIFIA Loan
Draft Proposed Resolution - Authorize WIFIA Loan
Draft Proposed Resolution - WIFIA Loan Pledge
Draft Proposed Resolution - WIFIA Reimburserment
WIFIA CWC Presentation
3.7 19-5688 CONSIDERATION OF DRAFT STAFF REPORT - AWARD PHASE
2B OF THE PROGRESSIVE DESIGN-BUILD CONTRACT FOR THE
REGIONAL WASTEWATER CONTROL FACILITY (RWCF)
MODIFICATIONS PROJECT; AND FORWARD A
RECOMMENDATION TO THE CITY COUNCIL
Recommended Action: RECOMMENDATION
It is recommended that the Council Water Committee consider the Draft
Staff Report - Award Phase 2B of the Progressive Design-Build Contract for
the Regional Wastewater Control Facility (RWCF) Modifications Project;
and forward a recommendation to the City Council for consideration and
approval.
All draft documents are subject to change.
Department: Municipal Utilities
Attachments: Draft Staff Report - Award Phase 2B
Draft Proposed Resolution - Award Phase 2B
Draft Exhibit 1 - Contract Amendment
Phase 2B CWC Presentation
4. FUTURE ITEMS/COMMITTEE MEMBER COMMENTS
5. ADJOURNMENT
City of Stockton Page 4 Printed on 7/8/2019
Council Water Committee Meeting Agenda - Final July 11, 2019
CERTIFICATE OF POSTING
I declare, under penalty of perjury, that I am employed by the City of Stockton and
that I caused this agenda to be posted in the City Hall notice case on July 8, 2019, in
compliance with the Brown Act.
Eliza R. Garza, CMC
City Clerk
By: ________________________________
Deputy
All proceedings are conducted in English. The City of Stockton does not furnish language interpreters and, if one
is needed, it shall be the responsibility of the person needing one.
In accordance with the Americans With Disabilities Act and California Law, it is the policy of the City of Stockton to
offer its public programs, services and meetings in a manner that is readily accessible to everyone, including those
with disabilities. If you are disabled and require a copy of a public hearing notice, or an agenda and/or agenda
packet in an appropriate alternative format; or if you require other accommodation, please contact the Office of the
City Clerk located at 425 North El Dorado Street, Stockton, California 95202 during normal business hours or by
calling (209) 937-8459, at least 5 days in advance of the hearing/meeting. Advance notification within this guideline
will enable the City/Agency to make reasonable arrangements to ensure accessibility.
Any writings or documents provided to a majority of this meeting body regarding any item on this agenda will be
made available for public inspection at the Office of the City Clerk located at 425 North El Dorado Street,
Stockton, California 95202 during normal business hours or by calling (209) 937-8459. The Agenda is available on
the City of Stockton Website: www.stocktongov.com.
City of Stockton Page 5 Printed on 7/8/2019
Get email alerts for Stockton
A daily email when new agendas and minutes are posted.