Plan Commission (Meets 2nd Tuesday of each month at 5:00 p.m.)
Regular MeetingSuperior, WI · January 17, 2024
Minutes
PLAN COMMISSION Minutes
January 17, 2024 Regular Meeting
The meeting was called to order by Chair Paine at 4:01 pm on January 17, 2024 in Government Center
Room 201.
1 ROLL CALL
PRESENT: Jim Paine, Brent Fennessey, Brian Finstad, Garner Moffat, Lindsey Graskey
VIRTUAL: Tyler Vandenberghe, Mike Bull, Erin Dukart, Pamela Guthman, Sarah
Mooradian, Lindsey Conley, Jared, Casey Werner (MP), Hudson Kingston, Brittany Keyes,
Geoff Tolley, Chris Rankila, Nate Boettcher, Taylor Pedersen, Lynn, Matt Ehrman, Becky
Kern, Councilors: Jenny Van Sickle, Nick Ledin, Mark Johnson
ABSENT: Anne Porter
CITY STAFF PRESENT: Director Jason Serck, Tech Stephanie Becken, Chief of Staff
Rebecca Scherf
OTHERS PRESENT: Jacob Ahrens Baldwin, Josh Skelton, Chris Tarpey, Dan
McCourtney, Mary McConnell, Mrk McConnell, Barb Hendrick, Brett Korte, Kevin Norbie,
Ron Franz, Gavin McCollam, William Volkman-Lien, Julie Pierce, Dan Olson, Brian
Hubbard, Kirk Ilenda, Pattie Soleday, Jennifer Kuklenski, Kyle Bukovich, Christine Martin,
Taylor Pedersen, Valeree Hubble for Bruce Doyle, Lisa Fitzpatrick, Lee Sandok Baker,
Mark Liebert, Councilors: Jack Sweeney, Tylor Elm, Ruth Ludwig, Mike Herrick
2 APPROVAL OF MINUTES
2.1 Plan Commission Minutes from December 20, 2023
MOTION to approve December 20, 2023, minutes by Commissioner Fennessey, seconded by
Commissioner Graskey. Carried.
3 OLD BUSINESS
4 NEW BUSINESS
4.1 Public Hearing for Special Use Permit Krisak
Director Serck explained the special use permit is rather standard for ice machines of this type already in
existence in Superior and recommended the Plan Commission recommend the application for approval
by Council.
MOTION to close public hearing and recommend the special use permit for approval by
Commissioner Fennessey, seconded by Commissioner Moffat. Carried.
4.2 CSM 24-01 for Bruce Doyle
Director Serck explained the CSM presented is meant to combine two side by side parcels that are on two
plat maps in order to unify the parcel for future residential building and noted it was straightforward,
easy to number, and recommended approval.
MOTION to approve the proposed CSM by Commissioner Graskey, seconded by
Commissioner Moffat. Carried.
PLAN COMMISSION MINUTES - 1/17/24 Mtg (Meets monthly on 3RD Wednesday of each month) Page 1 of 5
4.3 Nemadji Trail Energy Center Informational Presentation by Jennifer Cady: Vice President
of Regulatory and Legislative Affairs ALLETE/Minnesota Power
Chair Paine offered up an option for protocol for the meeting. Paine recommended the
Plan Commission listen to both presentations, and then public comment for 3 minutes each
where questions would be noted for when the commissioners were engaging directly with
the presenters at a later time in the meeting. Paine also noted City Councilors in
attendance and recommended they be able to offer questions and input after the public
comment time, as they customarily have some special privileges in commission meetings.
Then, after all outside comments, the Plan Commissioners would engage in discussion and
would ask their own questions and share their own thoughts while also asking the
questions that were brought up during public comment and Councilor comment. Chair
Paine reminded commissioners they could change the format at any time. Plan
Commissioners did not have alternative ideas on how the meeting should progress.
Jennifer Cady introduced staff members working on the Nemadji Trail Energy Center Project
(NTEC) and shared the timeline of the project from purchase of land, initial vacating and rezoning
of part of the property, State and Federal level approvals, to current time as approvals continue to
finalize and more vacations and a rezone request will be made soon. (Handouts from this
presentation are included as exhibit 1 in minutes).
4.4. Clean Wisconsin Nemadji Trail Energy Center Presentation by Brett Korte: Staff Attorney for Clean
Wisconsin
Brett Korte shared a presentation on Clean Wisconsin’s concerns on building the proposed NTEC
plant in Superior along the Nemadji River. Korte shared different aspects of the possible
environmental impacts including local issues, water quality, air quality, and climate. He also
shared the places within the regulatory process that Clean Wisconsin is currently challenging in
the court systems. (Presentation is included as exhibit 2 in minutes).
Chair Paine opened public comment with a 3 minute limit to each speaker. He encouraged
speakers to share any questions they wanted the Plan Commission to ask during discussion. 18
citizens shared during public comment, including 2 online. City Councilors were invited to ask
questions. Online, Councilor Van Sickle shared her concerns and questions concerning the project.
Attending councilors were invited to share any other questions. Councilor Ludwig asked about
Superior residents existing need for power and would power generated at NTEC go to Superior
residents.
Chair Paine opened discussion for Plan Commissioners. Commissioner Fennessey asked for
clarification from Clean Wisconsin on the progress and results of their environmental challenges.
Korte shared that so far they are still working through some challenges and don’t have the end
result, and that some of the final documents from permitting entities are not complete. There are
cases, specifically for the air quality, actively in appellate court.
Commissioner Graskey asked if the potential vacations would block public access to the water.
Director Serck shared the streets are undeveloped and any vacations in this area would not block
PLAN COMMISSION MINUTES - 1/17/24 Mtg (Meets monthly on 3RD Wednesday of each month) Page 2 of 5
existing public access. Commissioner Graskey continued, asking who pays for the additional
wastewater infrastructure that will need to be added to accommodate the systems. Chair Paine
shared the City was responsible. Commissioner Graskey asked if households and other consumers
would be part of the line. Dan McCourtney, Manager of Strategic Environmental Initiatives with
Minnesota Power answered that yes, others would be part of the wastewater flow, but that MN
Power was working closely with the City to understand what quality the water will first need to be
before it can access the pipes. Commissioner Graskey asked why the plant was changed from
water cooling to air cooling. McCourtney shared there was a concern on water and water use and
the move to air cooling has been positive. Graskey asked for MN Power’s experience building in
clay. McCourtney said they’ve built in many different land quality situations and are prepared for
the uniqueness of the clay and mentioned the substantial retaining wall. Commissioner Graskey
asked how close the facility would be to the cemetery and what sort of lighting was planned.
McCourtney shared they were about 100-250 feet away from the property line and planned to use
lighting that would not be intrusive. Graskey asked about what sort of community engagement
had been pursued. McCourtney mentioned open houses in the past and named others coming in
the future. Graskey asked for clarification if vulnerable populations who may not be able to leave
their homes were consulted. McCourtney shared they had not and didn’t normally do door
knocking, but thought the previous and future opportunities brought many populations to the
table for input.
Graskey asked for a very simple definition of hydrogen power. McCourtney shared it was an
immature technology that splits water into parts, including hydrogen that can be burned for
power.
Graskey asked how close the nearest resident lived. McCourtney answered a quarter mile away.
Graskey followed up about how emissions impact the community. McCourtney shared that many
variables go into emissions impact including weather and the type of emission.
Commissioner Finstad asked about property use. Director Serck shared that if the rezone to M2 is
allowed, the changed area then is allowed to be used for any prescribed purpose as noted in the
code. Commissioner Finstad followed up about what sort of buffer would be required. Director
Serck noted that the abutting Suburban zone would make the new M2 area have to follow all
buffering rules that exist in code for manufacturing properties that are next to residential.
Chair Paine asked about the process for consulting with the different tribal entities. Jennifer Cady
noted the Federal Government was the entity that did the consultation, as was appropriate when
working with a Sovereign Nation. Chair Paine asked Councilor Van Sickle’s question about if the
Union representative, who claimed the exhaust was the equivalent of filtered steam was correct.
Dan McCourtney answered that the claim is incorrect and not the claim of Minnesota Power.
Chair Paine asked if the Union representative who claimed the tribes are only angry due to input
from Councilor Van Sickle was speaking on behalf of the NTEC project. Dan McCourtney offered
no comment.
Commissioner Fennessey noted the stormwater issues and the washed out burial grounds just
downstream of the site and asked if NTEC is worried about erosion. Dan McCourtney shared they
were working closely with the DNR to ensure they were following all guidelines to avoid and
prevent erosion in the future.
PLAN COMMISSION MINUTES - 1/17/24 Mtg (Meets monthly on 3RD Wednesday of each month) Page 3 of 5
Commissioner Graskey asked about different plants around the state that might be similar and
what sort of health plans were in place due to emissions. Jennifer Cady shared that each
community has a Community Advisory Panel, and she would anticipate doing the same in
Superior. Graskey asked about the newspaper article about a potential sale. Jennifer Cady said
the rumors are very common in their field and would not impact this project.
Chair Paine asked Councilor Ludwig’s question about if the power made at the plant will stay in
Superior. Julie Pierce, Vice President of Strategy and Planning for Minnesota Power shared the
power made at the NTEC plant would go into the power supply for the region that is used by
Superior Water Light and Power as well as other areas in Wisconsin and Northern Minnesota.
Chair Paine asked for clarification on what a merchant plant is. Pierce shared it meant in the state
of Wisconsin that the power goes directly to customers. Chair Paine asked for clarification on the
‘wholesale’ aspect. Pierce shared that some power generating plants generate power only to sell
to other providers, but the NTEC one will serve locals as well. Jennifer Cady clarified some
differences in Minesota and Wisconsin statutes on how power is sold so the classifications can be
confusing. MN Power has to have merchant classification because MN Power doesn’t have direct
Wisconsin customers—Superior Water Light and Power does and for Superior Water Light and
Power to buy the power from MN Power, the classification has to be there.
Chair Paine asked about Burns and McDonnell. Pierce shared they are national engineering,
design, and planning firm that often works with large utility projects. Chair Paine asked about
how the relationship with the DNR, Burns and McDonnell, and NTEC staff works. Dan McCourtney
stated in house staff works first with the DNR and brings in Burns and McDonnell for consulting as
needed. Chair Paine asked for clarification on the aquifer and well permit. Dan McCourtney
shared there was a difference in opinion with the DNR when that original plan was made, but the
pivot to air cooling is a positive one. Chair Paine asked for clarification on the FONSI process, as it
looked like the report was largely put together by the applicants and their consultants.
McCourtney shared the process did include the applicant doing a significant part of the work on
the application and then turning over their information to the RUS (Rural Utilities Service) at
which point the RUS digs in, challenges what they see fit, and finalizes it.
Chair Paine noted the public process portion seems limited and that the applicant and regulator
relationship seems close. McCourtney disagreed about closeness between applicant and
regulator, but noted there are cases where, to be in compliance in things like erosion control, they
work closely with bodies like the DNR to make sure they’re doing things correctly. Chair Paine
expressed that the current regulatory process in the Wisconsin is far from rigorous, siting City
disagreement with findings and lack of communications from the DNR and other regulatory
agencies when the City requested the findings reports. Chair Paine asked for clarification on the
economic development and jobs claims. Pierce noted the project has evolved over 7 years and the
design and needs have changed some as well as the technology. Chair Paine asked what else the
City could expect to evolve. Pierce shared that any significant changes would require a new
process for approval—so they won’t be making any significant changes. Chair Paine asked if it
could be expected that the jobs will be local. Pierce shared that effort will be made to use local
workers where practical. Chair Paine noted that a lot of money leaves the city when transient
workers are brought in and rental prices increase. Pierce replied that the trend is concerning and
one that local governments and broader regional planning may need to undertake seriously.
PLAN COMMISSION MINUTES - 1/17/24 Mtg (Meets monthly on 3RD Wednesday of each month) Page 4 of 5
Chair Paine mentioned the EPA’s findings that show a potential 2 billion dollar negative
community impact on these types of projects. Paine asked if there’s a community that has shown
a measurable positive impact after a power plant like this was built. Pierce would like to know
how the commission looks at other industries with questions like that, so future discussion can
include the things the commission is considering. Chair Paine noted tax talk, and made it clear
Utility Aid is calculated by megawattage and is a fixed amount that most likely doesn’t change.
This is different than the local taxes that adjust based on value changes.
Chair Paine asked if the plant would burn diesel. Pierce said no, burning diesel is not the plan. Dan
McCourtney shared a 2-part answer. The plant will have diesel for backup generators, like most
large facilities of this nature. Burning diesel, while it is part of the application they submitted, is
not the active plan. Before the plant would move from natural gas to diesel, it would need to be
refitted and be up to the standard of whatever the regulations of that future might require. Pierce
noted historically, burning diesel has only been used in a state of emergency.
Chair Paine noted the neighborhood could be argued as walkable and asked NTEC to relabel the
site on their website correctly, as they have it labeled industrial. Chair Paine shared his thoughts
on the lack of input from local indigenous populations and the factual errors that were found in
the permits that weren’t corrected, even after tribal input was offered. The errors and lack of local
band member input, especially the input of those who have a burial so close, is egregious.
Commissioner Fennessey noted there’s reasonable argument that the area, while near some
residential, is markedly industrial in nature. Chair Paine agreed that’s a fair argument that could
be made and will come up in the future.
Chair Paine invited any other questions or comments from the Plan Commission and thanked
those in attendance.
5 ADJOURNMENT
Meeting adjourned at 6:41
Please find Exhibit 1 & 2 attached
A recording of the meeting can be found on the City of Superior Agenda Center
Respectfully submitted by Stephanie Becken.
PLAN COMMISSION MINUTES - 1/17/24 Mtg (Meets monthly on 3RD Wednesday of each month) Page 5 of 5
Exhibit 1
Exhibit 2
Nemadji Energy Trail Center:
A Bad Deal for Superior
City of Superior Planning Commission
January 17, 2024
Brett Korte, Staff Attorney
Clean Wisconsin
About Clean Wisconsin
• Founded in 1970
• Our mission is to combat climate change and pollution in our air,
water, and land, and ensure a healthy future for every Wisconsin
community.
• Over 30,000 members and supports across the state
• Scientific, policy, and legal expertise
v informs our advocacy
Overview of the Nemadji Trail Energy Center
• Proposed methane gas power plant
• Up to 625 megawatts
• To be built in Superior
• Along the Nemadji River
• Off 31st Ave. E
• Directly adjacent (SW) of the St. Francis Cemetery
• Proposed by Dairyland, ALLETE, and Basin Electric
• Anticipated to start operating in 2028
NTEC Proposed Location
Environmental Impacts: Local
• Located on a steep, 46-foot slope leading to the Nemadji River
• Heavy rains and highly erodible slop risk catastrophic failure leading to severe
water quality impacts to river
• Requires a large sheet pile retaining wall across 80% of the site, requiring 26,000
cubic yards of soil to be excavated for installation of, and another 80,000 cubic
yards of backfill
• Are prone to large, intense rainfalls—expected to continue in the future under
current climate predictions.
• Stormwater pond at the top of the slope
Environmental Impacts: Local
• Neighbors exposed to safety hazards associated with truck traffic and
construction, dust, and noise
• Use of 31st Avenue E. as the access haul road, with an increase of
200-260 vehicles per day
• After construction, increased air emissions, fog/ice/condensation,
visual impacts, employee traffic, lights, possible stormwater changes
• an increased safety hazard in a neighborhood that already suffered a
major industrial accident at the Husky refinery
Environmental Impacts: Water
• At least 4.36 acres of permanent wetland fill and 14.8 acres of temporary impact
on the staging area that may last up to 3.5 years
• Incorrect characterization of the wetlands leading to undervaluing the ecosystem
services provided and the amount of mitigation required
• Wetland impacts likely to reduce water retention ability
• Many of the wetlands contain diverse native plants, and likely large numbers of
rare plants species
Environmental Impacts: Air
Environmental Impacts: Air
• DNR found the total impact from NTEC plus background pollution would cause
air pollution concentrations equaling:
• 97.4 % of the ambient air standard for NOx (Nitrogen Oxides)
• 80.9% of the ambient standard for PM2.5 (particulate matter)
• Ozone cause headaches, coughing, dry throat, shortness of breath, a heavy feeling
in chest, and fluid in the lungs
• Chronic exposure can cause asthma
• PM exposure can have cardiovascular effects (ardiac arrhythmias and heart
attacks) and respiratory effects (asthma and bronchitis)
• Risk compounds for at-risk individuals
Environmental Impacts: Climate
• Would add over 2.7 million tons of CO2e per year
• 4% of Wisconsin’s total GHG emission (2021)
• Projected lifespan of 40 years
• 109 million tons of CO2e total
• Not counting emissions from extracting methane, including leakage
• Inconsistent with Gov. Evers’ 100% carbon-free electricity standard,
national climate commitments, and limiting warming to 1.5° C by
2050
Regulatory Process
• Public Service Commission of Wisconsin
• Wisconsin Department of Natural Resources
• Wetland/waterway permits
• Air pollution permits
• Local permits
• Army Corps of Engineers Wetland permit
• USDA Rural Utilities Service Loan
A Changing Landscape
• Subsidizing gas inconsistent with current state and federal priority of
transitioning to renewable energy
• New opportunities through the federal Inflation Reduction Act
• tax credits
• $9.7 billion in funding for rural electric cooperatives to transition to
renewable generation
• New proposed EPA regulations that would require NTEC to achieve
30% hydrogen co-firing just 4 years after it begins operation.
• Costs of renewables continue to drop
• Availability of battery storage
Questions?
Agenda
PLAN COMMISSION Agenda
WEDNESDAY, January 17, 2024–4:00 p.m.
Government Center Room 201
Microsoft Teams Meeting ID: 223 069 663 551 Passcode: 6oWwZY
Direct Link: LINK TO MEETING
Or call in (audio only) 1-872-242-8028
Phone Conference ID: 472 210 618#
MISSION STATEMENT: To guide and coordinate development including harbor related issues in
accordance with existing and future needs. City Code 98-2.
COMMITTEE MEMBERS: Jim Paine (chair), Brent Fennessey (vice-chair), Lindsey Graskey, Brian Finstad,
Garner Moffat, Anne Porter
1 ROLL CALL
2 APPROVAL OF MINUTES
2.1 Plan Commission Minutes (December 20, 2023)
3 OLD BUSINESS
4 NEW BUSINESS
4.1 Public Hearing for Special Use Permit Krisak
4.2 CSM 24-01 for Doyle
4.3 Nemadji Trail Energy Center Informational Presentation
Jennifer Cady; Vice President of Regulatory and Legislative Affairs ALLETE/Minnesota Power
4.4 Clean Wisconsin Nemadji Trail Energy Center Presentation
Brett Korte; Staff Attorney for Clean Wisconsin
5 ADJOURNMENT
Notice is hereby given that a majority of the members of the Common Council may be present at the meeting, and
although this may constitute a quorum of the Common Council, the Council will not take any action at this meeting.
Pursuant to the Americans with Disabilities Act of 1990, if you are in need of an accommodation to participate in
the public meeting process, please call (715) 395-7200 by 4:30 p.m. on the day prior to the scheduled meeting date
(OR dial 711 for Telecommunications Relay Service). The City will attempt to accommodate any request depending
on the amount of notice received.
In compliance with Wisconsin Open Meetings Law, this agenda was posted on 1/10/2024 at the following locations: Superior Government
Center, Douglas County Courthouse, Superior Public Library, and online at https://www.ci.superior.wi.us/agendacenter. It was also emailed the
Superior Telegram.
PLAN COMMISSION AGENDA – 1/17/2024 Mtg (Meets monthly on 3RD Wednesday at 4:00pm.) Page 1 of 1
PLAN COMMISSION Minutes
December 20, 2023 Regular Meeting
The meeting was called to order by Chair Paine at 4:00 pm on September 20, 2023 in Government Center
Room 270.
1 ROLL CALL
PRESENT: Jim Paine, Brent Fennessey, Laura Gapske, Brian Finstad, Anne Porter,
Garner Moffat
VIRTUAL:
ABSENT: Lindsey Graskey
CITY STAFF PRESENT: Director Serck, Tech Becken, Chief of Staff Scherf
OTHERS PRESENT: Shelly Nelson, Lori Ronchi, Kelly Keller, Cory Gatzke, Kimber
Johnson
2 APPROVAL OF MINUTES
2.1 Plan Commission Minutes from September 20, 2023
MOTION to approve September 20, 2023, minutes by Commissioner Fennessey, seconded by
Commissioner Porter. Carried.
3 OLD BUSINESS
4 NEW BUSINESS
Chair Paine asked the commission to take business out of order to allow more time for late coming Small
Business Grant applicants. Commission agreed.
4.1 Review and approve proposed changes to Certificate of Appropriateness Process
Chair Paine asked Jeff Skrenes to introduce the Historic Preservation process. Commissioner
Fennessey asked for clarification on what CLG status means. Skrenes explained the designation
means a community has met state criteria and therefore allows participants to be eligible for
more tax credits.
Commissioner Fennessey asked if historical properties qualify for those things regardless of the
CLG status. Commissioner Finstad explained that grant eligibility expands through the
Historical Society and shared from the Historical Society website. Commissioner Paine asked
for clarification on what sort of code standards may be offered. Director Serck shared it meant
that the historical homes could potentially ask to make updates to their home under older codes
that may allow for less structural damage in updating something like electrical.
Commissioner Finstad shared that by and large, his experience with criteria like this have been
positive, as the interaction with homeowners tend to be positive as it’s a chance for the historical
team to help find solutions with the homeowner rather than just offering negative directives.
PLAN COMMISSION MINUTES - 12/20/23 Mtg (Meets monthly on 3RD Wednesday of each month) Page 1 of 3
Chair Paine asked if CLG gives the city enforcement ability. Skrenes clarified that the CLG
status allows the city to have clarity on what it can and can’t do when it comes to historically
designated properties that are part of the local historical designation program.
Commissioner Moffat asked for clarity on what ‘alter’ means in the new language, specifically
citing a situation where someone with a brick historical building might want to paint it all black.
Chair Paine shared thought structure was actually the structure, not necessarily paint.
Commissioner Finstad shared that paint could be tricky, but with brick or stone, paint could be
structural change. Moffat agreed that it could be a very dynamic change. Director Serck shared
that paint is not generally a change that requires a permit.
Commissioner Moffat asked for clarification on if decorative elements would be considered
structural and named ones that are often associated with period architecture. Chair Paine
shared that being too specific allows for unnamed potential elements to be exempt.
Commissioner Gapske added that keeping it broader might put those questions in the hands of
the Historical Preservation Committee to be able to discern as questions rise. Commissioner
Finstad added if there’s not a direct list, people will ask. Skrenes said there is an area for
definitions earlier in the code area, so potential for adding more clarity. Fennessey noted that
vague could be helpful as noted earlier.
Commissioner Gapske asked if clarification could be added in earlier definition and be brought
back to the Plan Commission for further consideration.
MOTION to approve the proposed changes to certificate of appropriateness process by
Commissioner Fennessey, seconded by Commissioner Gapske. Carried.
Skrenes shared that the Historical Preservation Committee would be looking at the definitions at their
January meeting and he would return to the Plan Commission in the future to discuss again and make
further recommendations.
4.2 Small Business Grant Application Q4 Review & Recommendation
a. Bird’s Bar
b. Strength Factory
c. Yes, Cheese
d. Lori Ronchi Agency Inc
Tech Becken introduced the four grant applications and shared representatives were online and available
for questions. Director Serck reminded the commission that the Small Business Grant process would be
up for review at the January meeting, so actual process comments and changes anyone had in mind
would be a topic for January.
Chair Paine shared three were very obviously building related, where one was more equipment based
and asked if there were any questions for Kelly Keller who had to leave early. Commissioner Fennessey
agreed that one grant was more focused on equipment. Chair Paine if there was a recommendation for
all four to be approved.
PLAN COMMISSION MINUTES - 12/20/23 Mtg (Meets monthly on 3RD Wednesday of each month) Page 2 of 3
MOTION to approve all applications and recommend to the City Council by Commissioner
Moffatt, seconded by Commissioner Finstad. Carried.
5 ADJOURNMENT
Meeting adjourned at 4:30
Respectfully submitted by Stephanie Becken.
PLAN COMMISSION MINUTES - 12/20/23 Mtg (Meets monthly on 3RD Wednesday of each month) Page 3 of 3
N 57TH ST N 57TH ST
DUNCAN
5702 BANKS AVE
088080513600
WHITETAIL INVESTMENTS INC
5710 BANKS AVE
088080513500
SUTHERLAND SOUTHSIDE LLC
5701 TOWER AVE
088080511100
Proposed location of
¬
«35
free standing ice machine
DAVIS
5712 BANKS AVE
088080513400
CITY OF SUPERIOR
VACANT
088080511000
NELSON
5716 BANKS AVE
088080513300
BUHR
5719 TOWER AVE
088080511800
VACATED ALLEY-e
BUHR BUHR
1807 N 58TH ST 5729 TOWER AVE
088080512100 088080511900
µ
Krisak Special Use Permit
5701 Tower Avenue
Portable Ice Machine
10 feet x 12 feet x 17 feet tall (including sign)
20 feet setback from Tower Ave Parcel line
126 feet setback from alley parcel line
22 feet from neighboring property line
Proposed location in red
FAXON ST FAXON ST
diagram1-e
FAXON STREET LLC PATNAUDE LUNDBERG HOMES, LLC NUMMI
1224 FAXON ST 1218 FAXON ST 1210 FAXON ST 1204 FAXON ST
058050259600 058050126000 058050126200 058050423800
LIGMAN PROPERTIES LLC
1220 FAXON ST
058050259300
TOLLERS
1301 N 23RD ST
058050259400
PEARTHREE DOYLE DOYLE PENNINGTON LARSON LARSON
1223 N 23RD ST VACANT VACANT 1211 N 23RD ST VACANT 1205 N 23RD ST
058050259402 058050259401 058050127000 058050126300 058050126400 058050423900
N 23RD ST N 23RD ST
CUMMING AV
SCHOOL DISTRICT OF SUPERIOR
VACANT
SCHOOL DISTRICT OF SUPERIOR 058050259700
VACANT
058050130900
Proposed CSM 24-01
1200 Block of N 23rd Street
µ