Public Works Committee (Meets 1st Thursday of each month at 5:00 p.m.)
Regular MeetingSuperior, WI · April 6, 2023
Minutes
PUBLIC WORKS COMMITTEE MINUTES
April 6, 2023 Regular Meeting
The meeting was called to order by Councilor Van Sickle at 5:00pm on April 6, 2023, in Government Center Room 204.
COMMITTEE MEMBERS: Jenny Van Sickle, Ruth Ludwig, Nick Ledin, Tylor Elm (alt)
1. ROLL CALL
Members Present: Jenny Van Sickle, Nick Ledin, Tylor Elm
Members Absent: Ruth Ludwig
City Staff Present: Todd Janigo, Chris Carlson, Jodi Saylor, Lee Sandok-Baker, Erin Abrahamson,
Michael Maruska, Darienne McNamara, Thor Trone
Others Present: Shelley Nelson, Eric Thomas, Dan Hinzmann*
2. APPROVAL OF MINUTES
2.1. Public Works Committee (Meeting held March 2, 2023)
MOTION by Ledin, second by Elm and carried to approve the minutes from March 2, 2023.
3. OLD BUSINESS
3.1. Discuss reducing snow abatement timeline from 48 hours to a shorter timeline.
Van Sickle reviewed discussion from last PW meeting.
The current timeline of 48 hours can make it stretch out if there are consecutive days of snowfall or
if the 48 hours end on a weekend. Changing the timeline to 24 hours will allow us to get the snow
removed more quickly.
MOTION By Ledin, second by Elm and carried to approve reducing the snow abatement
timeline from 48 hours to 24 hours.
Sandok-Baker left the meeting at 5:12pm.
3.2. Review No Mow May.
Director Cadotte spoke on the impact of No Mow May last year and said that overall, it opened
time for us to work on a few other projects like gardens. May is not an aggressive growing time in
this area, so the grass does not become too long. It did take a little longer for the first mowing as
some areas needed multiple passes and sweeping of the grass clippings. That will vary year to year
depending on weather and growth. The calls the Parks Department did receive were in favor of No
Mow May. Long term there are multiple areas in some of the bigger parks where we can look at
entire park spaces and enhance them with pollinator plants as well as be more intentional with what
we mow and nurture. The intention is to take some steps towards that slowly.
Maruska left the meeting at 5:19pm.
4. NEW BUSINESS
4.1. Request to approve the Landfill Consultant contract with SEH Inc. for 2023; not-to-exceed
$55,000.00.
PUBLIC WORKS COMMITTEE –4/6/2023 Meeting (Meets monthly on 1st Thursday at 5 p.m.) Page 1 of 6
*Attended virtually
This contract sets the language so that SEH can be utilized as a consultant as needed throughout the
year. They will support things like environmental monitoring, gas sampling, air permitting, etc. that
are required.
Motion by Ledin, second by Elm and carried to approve the Landfill Consultant contract
with SEH Inc. for 2023; not-to-exceed $55,000.00.
It was requested that a table of previous years contract costs be included in the minutes.
4.2. Request to approve the contract with O’Day Equipment, LLC for the Barker’s Island Marina
Fueling Facility.
Eric Thomas who runs the Marina recently found out that bid and quote given to him previously is
no longer valid. O’Day is unable to supply the needed equipment for at least a year and pricing for
that time is currently unknown. They had requested simple fuel dispensers to install at the Marina,
but they are no longer being made by anyone. They will repair the current pumps and continue to
service them until they are able to find another solution. The request for this contract was then
withdrawn by Thomas. Request withdrawn; no action taken
Thor Trone entered the meeting at 5:28pm
4.3. Request to approve the Belknap, Tower and Roundabout Maintenance Contract with EasyLiving
Services, LLC.
This contract has been separated out from the vegetation management and is only for garbage and
lighting. In looking at a side-by-side estimate of costs, this contract should be around $30K for their
services but will depend on what services are actually needed. Their costs were less this year as
they are now familiar with what is needed and can provide some services at a lower rate and more
affordably. The vegetation side of this should go out next week for bids. Director Cadotte
mentioned that this winter was rough on garbage cans, and we are now at end of our stockpile, so as
we remove and reconstruct, there may be a few less cans going out until the City decides on a
design going forward. Cans will be placed in concentrated areas such as by bus stops and other
busy areas. The hope is that when the bus shelter project is completed, the receptacles at those
locations will match or possibly be inside the shelter.
Motion by Elm, second by Ledin and carried to approve the Belknap, Tower and Roundabout
Maintenance Contract with EasyLiving Services, LLC.
4.4. Request to approve the 2023 Gravel and Sand proposals.
These proposals set the pricing for a list of materials that we may use during the year. We get per
ton pricing and then base that cost on where we are using it. Typically, we do not buy a lot from
this pricing as materials used for bigger projects are priced with the project.
Motion by Ledin, second by Elm and carried to approve the 2023 Gravel and Sand proposals.
4.5. Request to approve the 2023 Hot Mix Asphalt proposals.
We have two asphalt plants in our area. One in Superior and one in Duluth with different mixes of
PUBLIC WORKS COMMITTEE –4/6/2023 Meeting (Meets monthly on 1st Thursday at 5 p.m.) Page 2 of 6
*Attended virtually
asphalt. We get prices from both as different projects require different mixes. We will look at the
cost, amount needed and the location when deciding on where to purchase from. If we can’t get the
mix from Monarch, we may then balance where we are working so we are hauling less of a
distance.
Motion by Ledin, second by Elm and carried to approve the 2023 Hot Mix Asphalt proposals.
4.6. Request to approve the contract with Phoenix Gravel for landfill daily cover at a unit cost of $11.23
per ton.
Darienne McNamara shared that she and a couple of the landfill staff toured other landfills and
found that a lot of places are using coarse sand or aggregate for daily cover. This material allows
water through so you don’t get puddling and you can drive on it rather than sinking into soft sand.
We have now started to transition to using aggregate. Darienne put together a spec and it was sent
out for bids. The expectation is that we will use about 1,000 tons per month. The increased cover
cost was budgeted for. The usage will vary usage depending on need. Regular sand from local
gravel pits has a high clay content and is causing drainage issues which then perch liquid in the
landfill and create compliance issues and operational challenges. This contract was done to coincide
with when gravel and sand contracts go out to keep it simple for companies submitting bids for
similar materials each year.
Councilor Van Sickle requested to hold this item to request an opinion from City Attorney, giving
his blessing, to utilize Phoenix Gravel given the potential conflict of interest as a Street staff has
some ownership in the company. She also suggested we open it up for bid again every 6 months
with the expectation that the cost would come down. The letter of disclosure that was included is
one step in making sure we are protected, but she would like to see an official opinion on record
and would like the disclosure statement dated and tailored to this contract as well. There was some
concern that the landfill would need material before this could all happen. Director Janigo believes
that the amount of material needed would be well under any contracted amount so we could
purchase smaller amounts as needed until a contract is in place.
MOTION by Van Sickle, second by Ledin and carried to hold this item until the May 4, 2023,
Public Works Committee meeting.
Eric Thomas left the meeting at 5:49pm.
4.7. Request to approve contract with Nordic for the Girl Scout Point Shore Stabilization in the amount
of $99,070.00.
This area is the toe point of Girl Scout Point in Billings Park. Right above it is the stone circle and
firepit. There is significant erosion from the St. Louis River. Weyandt and our engineer techs came
up with a plan to stabilize the area. The concern is that if the erosion continues at the current pace,
the top could collapse. In many areas we are not doing anything about shore erosion, but in this
location, there are assets above that we want to protect.
People going to GSP are not in danger as we are getting ahead of it. If people were to start walking
down over that hill, there is potential to end up in a compromised situation and go into the river. If
they stay up top and utilize the park as designed, they should be fine. Director Cadotte feels
comfortable that we got ahead of any major damage or danger. This work will come from the Parks
PUBLIC WORKS COMMITTEE –4/6/2023 Meeting (Meets monthly on 1st Thursday at 5 p.m.) Page 3 of 6
*Attended virtually
Capital Improvement Program Budget.
MOTION by Ledin, second by Elm and carried to approve the contract with Nordic for the
Girl Scout Point Shore Stabilization in the amount of $99,070.00.
4.8. Request approval to sign a Letter of Intent with Vespene Energy, Inc. of Berkeley, CA to
investigate potential for a landfill gas-to-energy project.
We have looked at landfill gas-to-energy projects quite a few times at the landfill. Currently, we
flare off our gas to convert to CO2 and burn off methane. Methane can be converted to compressed
natural gas. In the past, when looking at this, the barriers have been first, that it is an isolated area
and long ways away from anybody that would use it and second, the equipment to do this is very
expensive. Vespene Energy, Inc. helps get around both of those issues. They use the gas to generate
electricity that can be used to power equipment on site and doesn’t have to get out to the grid. It is a
program geared for smaller landfills and looks like a good fit for our landfill in that way. It is also a
good fit because we don’t have to get energy out to other users, it can be used to power data centers
for data processing and crypto currency mining. The company makes money from that and would
share part of that money with the City. It helps pay for the initial kick-off of the project. Once they
were to get enough money built up. They would then try to connect to the grid. The City could
potentially earn a decent revenue eventually. Vespene has requested that we sign a letter of intent
that allows them to do due diligence to see if this is feasible in our landfill. The letter is non-binding
and there are no timelines. They laid out a process of the City signing the letter, they would then do
their due diligence and then come back to the City with contract details.
Gas can still be generated even after the landfill closes. Energy would be minimal about 15 years
after closure. All the big landfills are already in the gas-to-energy business, but it becomes hard to
make it cost effective for a smaller landfill. Vespene has partnered with companies that have
engineered micro turbines and equipment. Using energy right on site also reduces cost. They
provided a list of six other landfills where they are up and running. The City will still maintain
carbon credits, so revenue for us will not go down. They are asking for six months to be exclusive
and to see if it is a viable option.
MOTION by Ledin, second by Elm and carried to approve signing a Letter of Intent with
Vespene Energy, Inc. of Berkeley, CA to investigate potential for a landfill gas-to-energy
project.
4.9. Request to purchase Landfill Compactor GPS System from RDO Integrated Controls in the amount
of in the amount of $57,807.50.
This was a budgeted item. There was no discussion. As the landfill gets full, GPS on multiple
machines will be important.
MOTION by Elm, second by Ledin and carried to approve the purchase of a Landfill
Compactor GPS System from RDO Integrated Controls in the amount of in the amount of
$57,807.50.
4.10. Request to approve the contract with Northland Constructors for the Lift Station 3 Improvements
Project in the amount of $2,429,700.00.
Erin Abrahamson with ESD explained that Lift Station 3 is critical infrastructure in the Billings
PUBLIC WORKS COMMITTEE –4/6/2023 Meeting (Meets monthly on 1st Thursday at 5 p.m.) Page 4 of 6
*Attended virtually
Park neighborhood. It conveys the flow of water to the wastewater treatment facility. This station
originated in 1939. SEH was hired to do engineering for the project and found that the best
alternative is to move the lift station to CSTP 6. This project is budgeted in the Wastewater
Enterprise fund and is also eligible for the Clean Water Fund.
Only one proposal was received. ESD has no concerns with Northland Constructors. They feel their
subcontractors are quality people, with which SEH concurs.
There will be minimal disruption to residents with some road closures and such, but service will not
be interrupted during this project. All the work will be completed this year.
MOTION by Ledin, second by Elm and carried to approve the contract with Northland
Constructors for the Lift Station 3 Improvements Project in the amount of $2,429,700.00.
4.11. Request to approve the State Municipal Agreement for STP-Urban funding for the reconstruction of
the Marina Drive causeway in 2026.
Director Janigo said there are concerns about having one way in and one way out locations. This
bridge is from 1959. The sheeting is showing section loss and getting thinner. We have applied for
and received Bipartisan Infrastructure Law (BIL) funding through the Surface Transportation
Program in the amount of $1.5M. Currently, there is a very preliminary plan. The plan is to have
the construction project take place in 2026.
MOTION by Ledin, second by Elm and carried to approve the State Municipal Agreement
for STP-Urban funding for the reconstruction of the Marina Drive causeway in 2026.
4.12. Request approval to award a professional services agreement with AMI Consulting Engineers.
This is a standard professional services agreement. It is helpful for when smaller things come up
and allows us not to have to go through contract negotiations. AMI is one of the leading
engineering firms working with living shorelines. They will be doing minor specs and plans with
the Marina to get to the next phase of the dock improvement.
MOTION by Ledin, second by Elm and carried to award a professional services agreement
with AMI Consulting Engineers.
4.13. Notice of Surplus Equipment auction sales. (no action required)
5. RECURRING BUSINESS
5.1. ESD Director’s Update Received and filed
5.2. Director’s Update
5.2.1. LHB will be working on the furnaces at Barkers Island Marina in the storage building. They
will go through a design process. Quotes were received and LHB was the lowest at $7,500.
5.2.2. Docks are spudded in place, those bend and wear out so another round of spuds are coming.
The lowest bid for those was Ogden Machine to produce 40 spuds.
5.2.3. The Sidewalk program is currently out for bids.
5.2.4. The Bardon Ave project is currently out for bids.
5.2.5. North 28th Street landscaping project – we are waiting to get some things ironed out before it
PUBLIC WORKS COMMITTEE –4/6/2023 Meeting (Meets monthly on 1st Thursday at 5 p.m.) Page 5 of 6
*Attended virtually
can go to bid.
5.2.6. The Public Works staff have a couple of ideas for dealing with potholes this summer.
5.3. Future Agenda Items
5.3.1. Contract with Phoenix Gravel for landfill daily cover at a unit cost of $11.23 per ton.
5.4. Confirm the next meeting date of May 4, 2023, at 5:00pm in Room 204 of the Government Center.
6. ADJOURNMENT
Councilor Van Sickle announced the meeting adjourned at 6:39pm.
Respectfully submitted by Jodi Saylor.
PUBLIC WORKS COMMITTEE –4/6/2023 Meeting (Meets monthly on 1st Thursday at 5 p.m.) Page 6 of 6
*Attended virtually
Public Works - Landfill
15 Moccasin Mike Road, Superior, WI 54880
Phone: (715) 395-7506
Fax: (715) 395-7346
www.ci.superior.wi.us/landfill
DATE: March 7, 2023
TO: Public Works Committee; Superior Common Council
FROM: Todd Janigo, Public Works Director
Darienne McNamara, Environmental Regulatory Manager
RE: Landfill Consultant contract with SEH Inc. for 2023; not-to-exceed fifty-five thousand dollars ($55,000)
1. Overview
Because of the unique challenges involved with operating a modern solid waste landfill, and evolving regulatory
requirements, the City occasionally relies on the expertise of solid waste industry professionals to keep landfill
operations efficient and in compliance. SEH has been retained due to their extensive involvement at our facility,
and other public and private landfills in Wisconsin. In 2023, SEH will assist with: air permit compliance and
oversight; surveying, engineering and design services; one-time gas sampling; and general consulting as needed.
2. Background
Short Elliot Hendrickson, Inc. (SEH) has been contracted to provide landfill consulting services since 2004 under a
Master Agreement for Professional Services. The landfill contract grew to over $200,000/year from 2012-2014
when many essential functions were being outsourced. Following the addition of a new staff position and
modification of another position in 2016, many of these job duties are now being done by city employees. Over
the past three years this contract has averaged less than $55,000.
We anticipate the need for a Landfill Consultant for the remaining life of the landfill, which is expected to close
in 2026. The challenges at the facility are unique to the operation, and the City has very limited involvement in
this evolving and highly technical industry. However, the role of consultants at the City’s landfill has changed
from a de facto staff position to that of a true consultant, with experts called upon only when we require a
professional with broad experience and specific expertise.
3. Budget Source
This item is budgeted in the Landfill’s operating budget.
4. Summary
The Public Works Department recommends approval of the Landfill Consultant contract with SEH in 2022 for an
amount not-to-exceed fifty-five thousand dollars ($55,000).
Recommended:
Jim Paine, Mayor
Public Works Department
Phone: (715) 395-7334 Public Works Director
Fax: (715) 395-7346 Todd Janigo
E-mail: publicworks@ci.superior.wi.us 1316 N 14th Street, Suite 200
Website: www.ci.superior.wi.us Superior, WI 54880
MEMORANDUM
Date: March 29, 2023 Council Agenda Date: April 18, 2023
TO: Mayor Paine and the Common Council
FROM: Todd Janigo, Public Works Director
RE: 2023 Gravel and Sand Proposals
1. Introduction
On March 7, 2023, proposals were accepted by the Public Works Department for gravel and
sand supplies for the 2023 construction season.
2. Background
Each year the Public Works Department requests proposals from local suppliers for gravel and
sand for various projects. The general use of the proposals allows the City to purchase from any
of the suppliers based on a number of considerations, including the submitted price, availability
and location of the materials, proximity to the project, amount of material required, etc. The
City also uses these prices to determine the comparative costs for recycling the recovered
concrete and asphalt that is crushed and stored at the Garage.
Again this year we requested prices for screened 4-inch rock that is specified for certain projects
under the WISDOT guidelines, as well as rip rap for erosion control. We also asked for a price if
the City supplied the loader, the fuel and the labor to load materials for comparison purposes so
the City can evaluate the raw price for the materials. Vendors may submit proposals only for
those materials they can supply, thus there may be some companies who only submit the price
for one material.
3. Budget Source
Funds are budgeted annually within the various divisions for Public Works material needs.
4. Conclusion
The bids received are as follows:
1) Charlie Allen Excavating & Trucking, LLC
Granular Backfill - delivered to landfill $ 8.74 per ton
Granular Backfill – picked up at Allen Pit $ 2.55 per ton
Granular Backfill - loaded by the City at Allen Pit $ 2.55 per ton
2) Udeen Trucking, Superior
Base Aggregate Dense 1 ¼”- picked up at Thunderhill Quarry $ 6.75 per ton
Base Aggregate Sense ¾” - picked up at Thunderhill Quarry $ 6.75 per ton
Select Crushed Material – picked up at Thunderhill Quarry $ 9.75 per ton
Light Rip Rap - picked up at Thunderhill Quarry $ 20.00 per ton
Medium Rip Rap - picked up at Thunderhill Quarry $ 20.00 per ton
Granular Backfill - delivered to landfill $ 7.30 per ton
4) Milestone Materials
Base Aggregate Dense 1 ¼”- loaded by the City at Kimmes Quarry $ 7.05 per ton
Base Aggregate Sense ¾” - loaded by the City at Kimmes Quarry $ 7.45 per ton
Breaker Run- loaded by the City at Kimmes Quarry $ 7.35 per ton
Select Crushed Material – loaded by the City at Kimmes Quarry $ 10.75 per ton
Light Rip Rap - loaded by the City at Kimmes Quarry $ 22.75 per ton
Medium Rip Rap - loaded by the City at Kimmes Quarry $ 21.35 per ton
5) Phoenix Gravel
Base Aggregate Dense 1 ¼”- delivered $ 13.60 per ton
Base Aggregate Dense 1 ¼”- delivered to the Landfill $ 11.00 per ton
Base Aggregate Dense 1 ¼”- picked up by the City at Stone Road $ 7.19 per ton
Base Aggregate Dense ¾”- delivered $ 13.66 per ton
Base Aggregate Dense ¾”- delivered to the Landfill $ 11.06 per ton
Base Aggregate Dense ¾”- picked up by the City at Stone Road $ 7.25 per ton
Breaker Run- delivered $ 14.16 per ton
Breaker Run- picked up by the City at Stone Road $ 7.75 per ton
Select Crushed Material – delivered $ 16.41 per ton
Select Crushed Material – picked up by the City at Stone Road $ 10.00 per ton
The Public Works Department may use products from any and all vendors listed above based on their
submitted prices and locations.
Recommended: ______________________________
Jim Paine, Mayor
DISCLOSURE LETTER FOR THE CITY OF SUPERIOR
ln the spirit of complete disclosure and to ensure municipal purchases in an
ethical manner, please know that l, Public Works Superintendent, Nathan
Johnstad, maintain an ownership interest in Phoenix Gravel, LLC which engages in
the sale of crushed aggregate and other products sometimes purchased by my
employerfor use in local projects. As a City of Superior employee, I shall not
engage in any decision, on behalf of the city, to purchgie any product from
Phoenix Gravel, LLC and shall defer, in all such instances, to others within our
department. I shall not use my position of employment within the city to affect,
direct, encourage or otherwise influence any purchase of product by the City of
Superior from Phoenix Gravel, LLC.
Nathan Johnstad
Public Works Department
Phone: (715) 395-7334 Public Works Director
Fax: (715) 395-7346 Todd Janigo
E-mail: publicworks@ci.superior.wi.us 1316 N 14th Street, Suite 200
Website: www.ci.superior.wi.us Superior, WI 54880
MEMORANDUM
Date: March 29, 2023 Council Agenda Date: April 18, 2023
TO: Mayor Paine and the Common Council
FROM: Todd Janigo, Public Works Director
RE: 2023 Hot Mix Asphalt Proposals
1. Introduction - On March 7, 2023 proposals for hot mix asphalt materials for the annual street maintenance
program were opened by the Public Works Department.
2. Background - Each spring the Public Works Department request proposals from local suppliers for hot mix
asphalt materials to be used on city projects. Specifications require submission of rates per ton for base
course materials, wear course materials, and filler materials. The location of the supplier’s plant is also
requested as travel distance is considered along with the cost of the materials. Suppliers must provide
materials that meet either the WisDOT OR MnDOT Standard Specifications for Highway and Structure
Construction.
Our general use of these proposals allows the city to purchase from any suppliers based on the submitted unit
prices. Choice of the supplier is based on availability of materials, location of the project relative to the
supplier’s facility, and the ability of the supplier to meet the required specifications.
3. Budget Source - Funds for road maintenance are budgeted annually within the CIP.
4. Conclusion - The bids received were as follows:
1) Northland Constructors, - Duluth, MN (plant location – Garfield Ave)
Wisc. Design Spec MN DOT Spec
Base Course No bid No bid
Wear Course No bid $84.00
Fine Mix No bid $84.00
2) Monarch Paving-Superior, WI (plant location-Albany Ave.)
Wisc. Design Spec MN DOT Spec
Base Course $68.65 No bid
Wear Course $69.25 No bid
Fine Mix $75.00 No bid
The Public Works Department may use products from the vendor based on their submitted price and plant location.
Recommend _____________________
Mayor Jim Paine
DISCLOSURE LETTER FOR THE CITY OF SUPERIOR
ln the spirit of complete disclosure and to ensure municipal purchases in an
ethical manner, please know that l, Public Works Superintendent, Nathan
Johnstad, maintain an ownership interest in Phoenix Gravel, LLC which engages in
the sale of crushed aggregate and other products sometimes purchased by my
employerfor use in local projects. As a City of Superior employee, I shall not
engage in any decision, on behalf of the city, to purchgie any product from
Phoenix Gravel, LLC and shall defer, in all such instances, to others within our
department. I shall not use my position of employment within the city to affect,
direct, encourage or otherwise influence any purchase of product by the City of
Superior from Phoenix Gravel, LLC.
Nathan Johnstad
SEH Contract Costs
2012 - 2022
2012 $ 293,300
2013 $ 205,850
2014 $ 201,980
2015 $ 157,000
2016 $ 130,000 *
2017 $ 92,050
2018 $ 51,330
2019 $ 45,805
2020 $ 45,805
2021 $ 51,055
2022 $ 41,721
2023 $ 55,000 **
* Staffing was restructured in 2016, Landfill Manager role was assigned to Environmental Regulatory
Manager and a new Landfill Technician position was created to take over many job duties that were
formerly contracted out to consultants.
** Requesting approval up to $55,000, slightly higher than recent average because we’re installing new gas
wells in 2024 and have to pay for design (by SEH) in 2023
Parks, Recreation & Forestry
1316 North 14th Street, 2nd Floor Phone: (715) 395-7270
Superior, WI 54880 Fax: (715) 395-7346
Web site: www.ci.superior.wi.us TTY: (715) 395-7521
Public Works Committee: April 6, 2023
MEMORANDUM
Date: March 28, 2023
To: Public Works Committee, Mayor Jim Paine and Members of the City Council
From: Linda Cadotte, Director of Parks, Recreation and Forestry
RE: Girl Scout Point Shoreline Stabilization
1. Recommendation
Recommendation that the Public Works Committee approve the recommendation that the City
enter into an agreement with Nordic Underwater Services, Inc. for the Girl Scout Point
Shoreline Stabilization project in the amount of ninety-nine thousand, seventy dollars
($99,070.00).
2. Background
In many areas along the St Louis River there are slopes that are sluffing off into the river. One
of the primary reasons for this repair is that on top of the hill is Stone Circle on Girls Scout
Point in Billings Park. Over the past several years the City has invested in this area to restore
the area and enhance the image and access to the space. Reservations have increased for this
space and it has been deemed valuable enough to maintain the integrity of the hill in order to
prevent erosion from engulfing the assets that are on top of the hill into the river.
The work for this project consists of repairing a failing slope by installing large riprap to restore
the shoreline as well as installing a combination of Geocells and Geogrids used to stabilize the
failing slope from future erosion.
This project will be substantially complete by November 1, 2023.
A request for bids went out on February 3, 2023. The project was listed publicly on
DemandStar and at Minnesota and Wisconsin Builder’s Exchanges. Three contractors
submitted bids for the project as outlined in the plans and specifications.
Veit $203,438.55
Nordic $ 99,070.00
Wren Works $155,227.00
1|Page
3. Budget Source
This project was budgeted and will be paid for out of the Parks CIP.
4. Recommendation
Recommendation that the Public Works Committee approve the recommendation that the City
enter into an agreement with Nordic Underwater Services, Inc. for the Girl Scout Point
Shoreline Stabilization project in the amount of ninety-nine thousand, seventy dollars
($99,070.00).
Approved: ___________________________________ ________________
Jim Paine, Mayor Date
Denied: ______________________________________ ________________
Jim Paine, Mayor Date
2|Page
Public Works – Landfill
15 Moccasin Mike Road
Superior, WI 54880
Phone: (715) 398-7222
www.ci.superior.wi.us/landfill
DATE March 29, 2023
TO Public Works Committee; Superior Common Council
FROM Todd Janigo, Public Works Director
Darienne McNamara, Landfill Manager
RE Requesting approval to sign Letter of Intent with Vespene Energy, Inc. of Berkeley, CA to investigate
potential for a landfill gas-to-energy project
The Public Works Department is requesting approval to sign the attached Letter of Intent with Vespene
Energy, Inc. of Berkeley, CA. This letter is nonbinding and does not commit the City to any current or future
contract or expenditures. By signing, we would be indicating our intent to work with Vespene Energy on a gas-
to-energy project if, after further investigation, it is found to be in the financial interests of both parties.
The City has explored landfill gas-to-energy projects in the past, but all have shared common obstacles. The
landfill is over a mile from the nearest gas pipeline or shared power line, making it very expensive to get
energy to users. Another challenge is the upcoming landfill closure. The amount of gas being generated will
decline within 10-15 years after closure, so the payback period on a project is relatively short. Lastly, the cost
for equipment to convert gas to energy has been far beyond what the City could reasonably afford.
Vespene Energy has a unique model that appears to get around these issues. Rather than the City purchasing
the equipment, the company owns and maintains all of the equipment. Rather than selling electricity or gas to
the grid, electricity is used on site (at least initially), avoiding the need for expensive powerlines or pipelines.
Based on their preliminary analysis, the quantity and quality of gas at the City’s landfill is sufficient to make a
project economically viable even with the upcoming closure.
Vespene Energy’s model uses custom-designed “self-sustaining microgrids” to generate power for data
centers at the landfill. Data centers are then used for online data processing and/or cryptocurrency mining,
which generates revenue for the company. Vespene shares a portion of their revenue with the City. They have
done this successfully on several sites in the U.S. Based on their initial evaluation, they see potential for a gas-
to-energy project at the City’s landfill. However, before expending any more resources on further
investigation, they have asked that we sign the attached nonbinding Letter of Interest.
Mayor Jim Paine
Public Works – Landfill
15 Moccasin Mike Road
Superior, WI 54880
Phone: (715) 398-7222
www.ci.superior.wi.us/landfill
March 29, 2023
TO: Public Works Committee; Superior Common Council
FROM: Todd Janigo, Public Works Director
Darienne McNamara, Landfill Manager
RE: Request to purchase Landfill Compactor GPS System from RDO Integrated Controls
The Public Works Department is requesting that the Common Council waive the formal bidding procedures
and approve the purchase of a GPS system and additional wiring harness from RDO Integrated Controls in the
amount of $57,807.50 (fifty-seven thousand, eight hundred and seven dollars and fifty cents).
The City purchased a similar GPS system for its primary compactor in 2019. The GPS system guides the
operator as they move about the landfill. It shows where garbage is needed to achieve target elevations, alerts
the operator if more compaction is needed, lets operators mark hazards (ex. gas wells) from the safety of the
cab, and has reporting capabilities that help predict when the landfill will reach capacity.
Since 2019 we have had one machine equipped with GPS. This purchase will equip the backup compactor with
the necessary wiring so the existing GPS unit can be swapped between the two compactors, which is
important if the primary machine is down for service. We will also purchase a second GPS system for a
bulldozer, which is used to spread cover over the waste. The bulldozer is often working on outer slopes where
target elevations are critical – waste cannot be piled higher than approved limits, but under-filling would
waste precious air space and is costly to fix. The bulldozer is often the last machine to traverse the waste
before final cover is placed so having GPS capability on that machine is important. Without it, we have to hire
surveyors to stake the waste, and often re-stake if waste elevations are too high/low.
GPS systems are common at modern landfills. Benefits include:
▪ save on survey costs – surveys by third-party consultants cost the City an average of $10,000 annually;
construction staking, surveys to determine remaining landfill capacity, ensuring that we adhere to
approved slopes, and to locate hazards
▪ improved safety – points can be mapped from inside heavy equipment rather than traversing the
waste on foot while carrying expensive surveying equipment; system can also alert operators to
hazards through “avoidance zones” pre-programmed into the unit (ex. gas wells)
▪ higher compaction – system tells operator if waste is being compacted or has reached maximum
density; this ensures the most waste is packed into all available space, which translates to maximum
revenue
▪ smaller working face – use GPS to define work areas each day, keep it small to minimize daily cover
needed and save money on cover material
▪ more efficiency – system tells operator when they have achieved maximum compaction or design
elevations; eliminates unnecessary fuel consumption, wear and tear on machines
▪ timely progress and compliance reports – real-time data to accurately predict landfill closure, better
information for City budgeting and planning, compile reports without relying on consultants, online
portal for real-time observation of waste placement, machine down-time, etc.
Budget Source
This item is budgeted in the landfill’s 2023 capital equipment budget. The budgeted amount is $50,000. The
difference will be absorbed in the landfill’s 2023 operating budget.
Summary
The Public Works Department is requesting that the Common Council waive the formal bidding procedures
and approve the purchase of a GPS system for the landfill’s backup compactor and bulldozer. The system
would be purchased from RDO Integrated Controls in the amount of $57,807.50 (fifty-seven thousand, eight
hundred and seven dollars and fifty cents).
Mayor Jim Paine
Public Works Department
1316 North 14th Street, 2nd Floor Phone: 715-395-7334
Superior, WI 54880 Fax: 715-395-7346
Web site: www.ci.superior.wi.us TTY: 715-395-7521
MEMORANDUM
DATE: March 29, 2023 Council Agenda Date: April 18, 2023
TO: Mayor Jim Paine and the Common Council
FROM: Todd Janigo, Public Works Director
RE: State Municipal Agreement for STP-Urban funding for the reconstruction of the Marina Drive
causeway in 2026.
It is my recommendation to approve the State Municipal Agreement (SMA) with the Wisconsin Department of
Transportation (WISDOT) for the STP-Urban funding portion of the reconstruction of the Marina Drive Causeway
scheduled for the 2026 construction season.
1. Introduction
The City of Superior is receiving $1.5M in BIL STP-Urban funding administered by the Wisconsin DOT for the
design and construction of the Marina Drive Causeway replacement. Due to expected permitting challenges,
design needs to begin as soon as possible.
2. Background
The Marina Drive or Barkers Island causeway bridge was constructed in about 1959 with tied back steel sheet pile
abutments, timber girders, and timber decking with an asphalt surface. While the decking has been replaced
approximately 3 times since construction, the remaining structure is original and deteriorating. The existing
roadway is narrow with minimal shoulder width and steep slopes.
Preliminary design of the new bridge and causeway widens the roadway by 10 feet, creates a more gradual slope
and includes curb and gutter as well as a 6 foot sidewalk.
The City of Superior applied for BIL STP-Urban funds for the Marina Drive causeway reconstruction in June of last
year and was awarded $1,507,615.78 in Federal Funds for the project. These funds are currently scheduled for
construction in 2026 and require a 20% City match plus the balance of the construction costs.
3. Budget Source
BIL STP-Urban funding for this project is capped at $1,507,615.78. The current and preliminary estimate for the
project design and construction including delivery is $2,548,731.00 leaving the City responsible for the remaining
estimated cost of $1,041,115.22. Project construction costs have been budgeted in the 2026 Major Street
Projects CIP at $700k for a total budgeted project cost of $2.2M. Based on these preliminary estimates,
additional funds may need to be budgeted in the 2026 Major Street Projects CIP.
4. Recommendation
It is my recommendation to approve the State Municipal Agreement (SMA) with the Wisconsin Department of
Transportation (WISDOT) for the STP-Urban funding portion of the reconstruction of the Marina Drive Causeway
scheduled for the 2026 construction season.
Recommended: _________________________________
Jim Paine, Mayor
Parks, Recreation & Forestry
1316 North 14th Street, 2nd Floor Phone: (715) 395-7270
Superior, WI 54880 Fax: (715) 395-7346
Web site: www.ci.superior.wi.us TTY: (715) 395-7521
Public Works Committee: February 2, 2023
MEMORANDUM
Date: March 29, 2023
To: Public Works Committee, Mayor Jim Paine and Members of the City Council
From: Linda M Cadotte, Director of Parks, Recreation and Forestry
RE: Professional Services Agreement with AMI
Introduction
Parks, Recreation and Forestry Director is requesting the Public Works Committee recommend
that the City Council award a professional services agreement with AMI Consulting Engineers
(AMI).
Background
The City has a frequent need for professional engineering services and consultation support.
These services may be requested for small, low-cost tasks that would not be subject to
bidding/proposal threshold or requested in emergency situations where the time needed to
advertise for proposals would subject the city to significant risk of liability or result in a public
safety danger. Approval of this agreement allows the City to seek ‘as-needed’ services from
AMI under a signed contract that defines terms, liability, and sets a predetermined rate schedule.
AMI is an engineering firm with offices in Superior, WI, St Paul, MN, and Pensacola, FL. AMI
has worked on a number of City projects including projects at Barker’s Island Marina, Barker’s
Island Beach, Pokegama Landing, and Woodstock Bay. Under this agreement, as-needed
services provided by AMI would include:
• Architectural and landscape consultation design and renderings
• Concept Designs for Projects to Define Direction Scope and Budget
• Shoreline Stabilization, Rehabilitation and Restoration resiliency design and related
services
• Waterfront and Marina related design, review, and consultation
• Inspection Services
1|Page
• Internal and External Project Team Development for Project Delivery
• Project Management Support for Design and Construction
• Condition Assessments for Infrastructure
• Coordination on Design and Construction Projects
• Estimating
• Bidding Support
• Project Management and Construction Administration Oversight
• Other Tasks as Determined by the City of Superior
Budget Source
Funds for work performed under this agreement would be under the $25k bid threshold. The
services would be allocated from the Parks, Recreation and Forestry professional services
account within the area where work is performed. Typical areas would include estimating,
schematic layout, civil engineering, shoreline, beach, marina or other waterfront related or
general engineering specifications.
Recommendation
Parks, Recreation and Forestry Director is requesting the Public Works Committee recommend
that the City Council award a professional services agreement with AMI Consulting Engineers
(AMI).
Approved:____________________________________ Date:__________________
Mayor Jim Paine
Denied:______________________________________ Date:__________________
Mayor Jim Paine
2|Page