Susanville Municipal Airport Commission
Regular MeetingSusanville, CA · April 28, 2022
Agenda
CITY OF SUSANVILLE
66 N. Lassen Street • Susanville CA
Robert Tyndall, Chair
Richard Hrezo, Vice Chair
Paul Clark • William Heyland • Dan Weaver
Susanville Municipal Airport Commission Special Meeting
Regular Susanville Municipal Airport Commission Meeting • City
Council Chambers, 66 North Lassen Street, Susanville, CA 96130
Thursday, April 28, 2022 – 3:00 PM
Call meeting to Order
Roll Call of Commissioners Present
1. AGENDA APPROVAL: (Additions and/or Deletions)
2. APPROVAL OF MINUTES:
2.A Approval of minutes from the February 24, 2022 meeting
3. CORRESPONDENCE/INFORMATION:
4. BUSINESS FROM THE FLOOR: Any person may address the Commission at this time upon any
subject not on the agenda within the jurisdiction of the Commission. However, any matter that
requires action will be referred to staff for a report and action at a subsequent
meeting. Presentations are subject to a five-minute limit.
5. PUBLIC COMMENT: Any person may address the Board at this time to comment on any subject
on or not on the agenda. However, the Board may not take action on an item not on the agenda
other than direct staff to agendize the matter at a future meeting.
6. NEW BUSINESS:
6.A Discussion regarding Airport Capital Improvement Plan (ACIP) 2022-2026
7. CONTINUING BUSINESS:
7.A Airport Budget Review
7.B Public Works Director Update
8. AIRPORT MANAGERS REPORT:
9. COMMISION ITEMS:
10. ADJOURN
Next meeting date to be held on May 12, 2022.
1
I, Jolene Arredondo, certify that I caused to be posted notice of the special meeting scheduled for
April 28, 2022 in the areas designated on April 26, 2022. The agenda has been distributed to the
following: Robert Tyndal, emailed; Richard Hrezo, emailed; Dan Weaver, emailed; Bill Heyland, emailed;
Paul Clark, emailed.
2
AGENDA ITEM NO. 2.A
Action Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION SPECIAL MEETING AGENDA ITEM
Submitted By: Jolene Arredondo, Administrative Services
Action Date: April 28, 2022
SUBJECT: Approval of minutes from the February 24, 2022 meeting
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: Attached for the Commission's review are the minutes from the
February 24, 2022 SMAC meeting.
FISCAL IMPACT: None.
ACTION REQUESTED: Motion to approve minutes from the February 24, 2022 SMAC
meeting
ATTACHMENTS:
20220224_SMAC Minutes.docx
3
SUSANVILLE MUNICIPAL AIRPORT COMMISSION SPECIAL MEETING
Regular Susanville Municipal Airport Commission Meeting Minutes
THURSDAY, FEBRUARY 24, 2022 – 3:00 PM
Roll Call of Councilmembers Present: Paul Clark, William Heyland, Robert Tyndall, Dan Weaver
Absent: Ross Stevenson
Chair Stevenson is no longer on Comission. In replacement alternate Richard Hrezo was in
attendance
Meeting was called to order at 3:02
1. AGENDA APPROVAL:
Moved by Dan Weaver; seconded by Robert Tyndall to Approve the Agenda.
Motion Carried: 4 - 0
Voting For: Paul Clark, William Heyland, Robert Tyndall, Dan Weaver, Richard Hrezo
Voting Against: None
2. APPROVAL OF MINUTES:
2.A Consider approval of the November 18, 2021 Airport Commission Meeting Minutes Motion to approve
the November 18, 2021 Airport Commission Meeting Minutes 20211118_SMAC Minutes.pdf
Moved by Dan Weaver; seconded by Robert Tyndall to Approve the minutes.
Motion Carried: 4- 0
Voting For: Paul Clark, William Heyland, Robert Tyndall, Dan Weaver, Richard Hrezo
Voting Against: None
3. CORRESPONDENCE/INFORMATION: None
4. BUSINESS FROM THE FLOOR: None
5. PUBLIC COMMENT: None
6. NEW BUSINESS:
6.A Consider appointment of Chair and Vice Chair for the 2022 Calendar Year Appoint Chair and Vice
Chair for the 2022 Calendar Year
Chair Paul Clark nominated Robert Tyndall for Chair, a second was received by Commissioner
Weaver
Chair Paul Clark nominated Richard Hrezo for Vice Chair, a second was received by Commissioner
Weaver
Moved by Dan Weaver; seconded by Paul Clark to Approve .
Motion Carried: 4- 0
Voting For: Paul Clark, William Heyland, Robert Tyndall, Dan Weaver, Richard Hrezo
Voting Against: None
4
6.B Airport Financials Review
Information only
Public Works Director Bob Godman presented the Airport Financial Statements. Commissioner
Heyland inquired about where in the financial report the annual contribution of $15,000 for matching
funds is reflected in the financials. Mr. Godman noted he would bring a report of those accumulated
funds to a future meeting.
SMAC Financials.pdf
6.C Taxiway A Project Update
Information only
Public Works Director, Bob Godman presented an update on the Taxiway A project. Discussion occurred
about the status of the contract with Hat Creek and tentative start date in relation to weather and it was a
tentative start date of May. Discussion occurred about contract modification dates and project costs due
to increases in construction material costs.
Chair Tyndall mentioned that the airfare is scheduled for June and it might impede in the project
timeline. Mr. Datema noted that it would not interfere with the event.
Commissioner Weaver inquired if the grinding was included in the project.
Commissioner Clark requested a copy of the contract with Hat Creek to be presented at a future
meeting.
Discussion occurred about the re-striping. Mr. Godman noted that it would be a good idea to consider
obtaining a quote from the subcontractor and potentially complete re-striping in conjunction with the
Taxiway A project.
6.D CARES Act Report
Information Only
Public Works Director, Bob Godman presented the CARES act report, noting that there are Covid
related 3 grants that have been received for a total of $65,000. Money is currently being held in a
DELFI account for expending
Discussion occurred about needed updates to the bathroom/water closet at the airport facility.
Discussion occurred that this would be an approved expense and is a needed project.
Discussion occurred about hardening the FBO facility.
Commission Heyland inquired about the water facilities be an eligible expenditure and Mr. Godman
noted that he would look into if it would be an eligible expenditure project but did not think it would
be eligible.
CARES Act Grant Report.docx
7. CONTINUING BUSINESS: None
8. AIRPORT MANAGERS REPORT:
5
Mr. Datema provided an update to the commission that hangars 15 and 19 and half interest in hangar
11 are currently up for sale and will be going to City Council for first right of refusal. Discussion
occurred about interest of building new hangars, and Mr. Datema noted that there was not much
interest in building new hangars due to the firewall requirements tend to deter new buyers due to
price of materials and construction.
9. COMMISION ITEMS:
Chair Tyndall provided information that hangar 4 is clean for the most part and staff is working on
completing some electrical wiring.
Chair Tyndall provided information on the connection build that exists between hangar 3 and hangar
4, noting it is still needing to be discussed as to how that will be dealt with, and discussion occurred
about the restroom and which hangar (3 or 4) that would be connected to. Mr. Datema noted that
the septic might have ben permitted and he would look into that.
Chair Tyndall provided an update that Hangar 3 had been cleaned by American Legion, Crossroads,
Teen Challenge and city staff and all contributed to cleaning out the hangar. Most debris has been
removed and what remains is helicopter parts. The insulation needs to be replaced and there are
holes in the roof. The helicopter is scheduled to be cleaned and moved to hangar #6 upon approval
of the city.
Mr. Heyland inquired about who the owner of the helicopter is and what is the process for unclaimed
property. Mr. Godman noted that he would discuss that with the city attorney. Mr. Datema noted that
abandoned planes is a frequent problem airports experience. Mr. Tyndall noted that he knew who
the helicopter was registered to and the owner, and a bill of sale might be obtained if that is a legal
way of conducting such business.
Commissioner Heyland noted that we should begin work on the ACIP at the upcoming meeting for
review to see if there are any recommended changes.
10. ADJOURN
Moved by Dan Weaver; seconded by Paul Clark to Adjourn at 3:54.
Motion Carried: 4 - 0
Voting For: Paul Clark, William Heyland, Robert Tyndall, Dan Weaver, Richard Hrezo
Voting Against: None
Approved By:
_________________________
SMAC President
Submitted By:
___________________________ Approved On:
SMAC Secretary
6
AGENDA ITEM NO. 6.A
Discussion Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION SPECIAL MEETING AGENDA ITEM
Submitted By: Jolene Arredondo, Administrative Services
Action Date: April 28, 2022
SUBJECT: Discussion regarding Airport Capital Improvement Plan (ACIP) 2022-
2026
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: As part of the ongoing project compliance and maintaining eligibility
for funding through the FAA, the City of Susanville is periodically
required to work with the FAA on the current ACIP to address
changes in project schedules and update the document to cover
future funding years, changes to and the completion of pending
projects and availability of non-entitlement funding. Staff is requesting
a discussion and recommendation(s) of potential future projects.
FISCAL IMPACT:
ACTION REQUESTED: Discussion only
ATTACHMENTS:
DRAFT ACIP 2023-2027 - SUSANVILLE.pdf
7
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
FY 2022 - 2026
11/30/2020
DATE:
Airport: Susanville Municipal Airport State: California NPIAS# 06-0251 LOCID SVE
Project Description & Year Federal Funds State Funds Local Total Environmental NPIAS Rating Start Date Comp. Date
2021
1 - Taxiway Rehabilitation, Phase I - Construction $ 666,000 $ 33,300 $ 40,700 $ 740,000 CATEX 2020 66 May 2021 May 2022
2 - Taxiway Rehabilitation, Phase I, Bid Alt. 1 - Construction $ 891,000 $ 44,550 $ 54,450 $ 990,000 CATEX 2020 66 May 2021 May 2022
TOTAL (FY 2021) $ 1,557,000 $ 77,850 $ 95,150 $ 1,730,000
2022
1 - Taxiway Rehabilitation, Phase II - Construction $ 234,900 $ 11,745 $ 14,355 $ 261,000 CATEX 2020 66 May 2022 May 2023
2 - Perimeter Fence - Design $ 108,000 $ 5,400 $ 6,600 $ 120,000 CATEX 2019 41 May 2021 December 2021
TOTAL (FY 2022) $ 342,900 $ 17,145 $ 20,955 $ 381,000
2023
1 - Perimeter Fence - Construction $ 382,500 $ 19,125 $ 23,375 $ 425,000 CATEX 2019 41 May 2023 December 2023
2 - Pavement Maintenance Management Plan $ 135,000 $ 6,750 $ 8,250 $ 150,000 Revalidate 2019 66 May 2023 May 2024
TOTAL (FY 2024) $ 517,500 $ 25,875 $ 31,625 $ 575,000
2024
1 - Apron Reconstruction, Phase II - Construction $ 1,012,500 $ 50,625 $ 61,875 $ 1,125,000 Revalidate 2022 60 May 2024 December 2024
TOTAL (FY 2024) $ 1,012,500 $ 50,625 $ 61,875 $ 1,125,000
2025
1 - Runway Sealcoat - Design $ 67,500 $ 3,375 $ 4,125 $ 75,000 CATEX 2023 70 May 2025 December 2025
TOTAL (FY 2025) $ 67,500 $ 3,375 $ 4,125 $ 75,000
2026
1 - Runway Sealcoat - Construction $ 225,000 $ 11,250 $ 13,750 $ 250,000 CATEX 2023 70 May 2026 September 2026
TOTAL (FY 2026) $ 225,000 $ 11,250 $ 13,750 $ 250,000
TOTALS $ 3,722,400 $ 186,120 $ 227,480 $ 4,136,000
1
8
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2021
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Taxiway Rehabilitation, Phase I - Construction $ 666,000 $ 40,700 $ 33,300 $ 740,000
Y D 2 - Taxiway Rehabilitation Phase I, Bid Alt. I - Construction $ 891,000 $ 54,450 $ 44,550 $ 990,000
TOTAL $ 1,557,000 $ 95,150 $ 77,850 $ 1,730,000
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - The existing taxiway pavement is in poor condition (7,2000 SY). A 2020 evaluation determined the pavement to have a PCI of 46. This project is
the Base Bid of Phase I of the pavement reconstruction project for the taxiway and apron; this portion will include reconstruction of taxiway alpha
pavement.
2 - The existing taxiway pavement is in poor condition (10,000 SY). A 2020 evaluation determined the pavement to have a PCI of 46. This project is
Bid Alternate 1 of Phase I of the pavement reconstruction project for the taxiway and apron; this portion will include reconstruction of the taxiway
pavement.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2021
1 - Anticipated Construction Schedule: September 2021 to December 2021
1 - Anticipated Grant Closeout: May 2022
2 - Anticipated Bid Opening: May 2021
2 - Anticipated Construction Schedule: September 2021 to December 2021
2 - Anticipated Grant Closeout: May 2022
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX revalidated in 2020
2 - CATEX revalidated in 2020
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
9
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2021
1 2
LEGEND
1 TAXIWAY REHABILITATION,(BASE BID) PHASE I -
CONSTRUCTION
2 TAXIWAY REHABILITATION (BID ALTERNATE) PHASE I -
CONSTRUCTION 10
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2022
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Taxiway Rehabilitation, Phase II - Construction $ 234,900 $ 14,355 $ 11,745 $ 261,000
Y D 2 - Perimeter Fence - Design $ 108,000 $ 6,600 $ 5,400 $ 120,000
TOTAL $ 234,900 $ 14,355 $ 11,745 $ 261,000
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - The existing taxiway pavement is in poor condition (3,300 SY). A 2020 evaluation determined the pavement to have a PCI of 24. This project is
Phase II of the pavement reconstruction project for the taxiway and apron; this portion will include reconstruction of taxiway bravo pavement.
2 - Design and Construct Perimeter Fence Installation (approximately 4,100 LF of 8' fence). There are areas on the airport with minimal fencing,
where wildlife can gain access to the airport and cause safety issues.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2022
1 - Anticipated Construction Schedule: September 2022 to December 2022
1 - Anticipated Grant Closeout: May 2023
2 - 100% Plans and Specifications to be submitted March 2021
2 - Anticipated Bid Opening: May 2021
2 - Anticipated Grant Closeout: December 2021
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX revalidated in 2020
2 - CATEX in 2019
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
11
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2022
2
1
LEGEND
1 TAXIWAY REHABILITATION,PHASE II - CONSTRUCTION
2 PERIMETER FENCE - DESIGN
12
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2023
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Perimeter Fence - Construction $ 382,500 $ 23,375 $ 19,125 $ 425,000
Y D 2 - Pavement Maintenance Management Plan $ 135,000 $ 8,250 $ 6,750 $ 150,000
TOTAL $ 517,500.00 $ 31,625.00 $ 25,875.00 $ 575,000.00
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - Design and Construct Perimeter Fence Installation (approximately 4,100 LF of 8' fence). There are areas on the airport with minimal fencing,
where wildlife can gain access to the airport and cause safety issues.
2 - Conduct an Airport Pavement Maintenance Management Plan. Accurate PCI data is needed to assess current and future pavement treatment
needs.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2023
1 - Anticipated Construction Schedule: September 2023 to December 2023
1 - Anticipated Grant Closeout: May 2024
2 - Anticipated Bid Opening: May 2023
2 - Anticipated Construction Schedule: September 2023 to December 2023
2 - Anticipated Grant Closeout: May 2024
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX in 2019
2 - Revalidate CATEX in 2019
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
13
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2023
1
2
LEGEND
1 PERIMETER FENCE - CONSTRUCTION
2 PAVEMENT MAINTENANCE MANAGEMENT PLAN
14
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2024
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Apron Reconstruction, Phase II - Construction $ 1,012,500 $ 61,875 $ 50,625 $ 1,125,000
TOTAL $ 1,012,500 $ 61,875 $ 50,625 $ 1,125,000
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - The asphalt concrete pavement on the existing apron is close to failing (18,500 SY). This project is to reconstruct the apron with a new asphalt
concrete structural section per FAA standards. This is the second construction phase of this project.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or
design, planning or environmental process)
1 - Anticipated Bid Opening: May 2024
1 - Anticipated Construction Schedule: September 2024 to December 2024
1 - Anticipated Grant Closeout: May 2025
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - Revalidate CATEX in 2022
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
15
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2024
1
LEGEND
1 APRON RECONSTRUCTION, PHASE II - CONSTRUCTION
16
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2025
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Runway Sealcoat - Design $ 67,500.00 $ 4,125.00 $ 3,375.00 $ 75,000.00
TOTAL $ 67,500.00 $ 4,125.00 $ 3,375.00 $ 75,000.00
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - Design: Apply a crack seal and seal coat, and re-apply pavement markings to Runway 11-29 (4,051' x 75') and Taxiway connectors.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - 100% Plans and Specifications to be submitted March 2025
1 - Anticipated Bid Opening: May 2025
1 - Anticipated Grant Closeout: December 2025
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX in 2023
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
17
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2025
1
LEGEND
1 RUNWAY SEALCOAT - DESIGN
18
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2026
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Runway Sealcoat - Construction $ 225,000.00 $ 13,750.00 $ 11,250.00 $ 250,000.00
TOTAL $ 225,000.00 $ 13,750.00 $ 11,250.00 $ 250,000.00
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - Design: Apply a crack seal and seal coat, and re-apply pavement markings to Runway 11-29 (4,051' x 75') and Taxiway connectors.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2026
1 - Anticipated Construction Schedule: September 2026 to September 2026
1 - Anticipated Grant Closeout: May 2027
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX in 2023
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
19
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2026
1
LEGEND
1 RUNWAY SEALCOAT - CONSTRUCTION
20
AGENDA ITEM NO. 7.A
Discussion Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION SPECIAL MEETING AGENDA ITEM
Submitted By: Jolene Arredondo, Administrative Services
Action Date: April 28, 2022
SUBJECT: Airport Budget Review
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: Review of the most recent airport revenues with comparison to
budget.
FISCAL IMPACT: None.
ACTION REQUESTED: Information
ATTACHMENTS:
22020426_Airport.pdf
21
CITY OF SUSANVILLE
INCOME STATEMENT
REVENUES WITH COMPARISON TO BUDGET
FOR THE 10 MONTHS ENDING APRIL 30, 2022
AIRPORT
BUDGET YTD ACTUAL ENCUMBRANCE % EARNED UNEARNED % UNEARNED
PUBLIC WORKS
AIRPORT-OPERATIONS
7201-430-81-3341 STATE OF CA - CALTRANS 10,000.00 .00 .00 .00 10,000.00 100.00
7201-430-81-3611 INTEREST REVENUE 10.00 .00 .00 .00 10.00 100.00
7201-430-81-3613 NET INCREASE(DECREASE) FMV .00 ( 2.46) .00 .00 2.46 .00
7201-430-81-3620 AIRPORT - LEASES 90,000.00 87,071.97 .00 96.75 2,928.03 3.25
7201-430-81-3701 AIRPORT - FLOWAGE FEES 14,000.00 8,291.90 .00 59.23 5,708.10 40.77
7201-430-81-3703 COMMERCIAL OPERATOR FEES 20,000.00 10,801.90 .00 54.01 9,198.10 45.99
TOTAL AIRPORT-OPERATIONS 134,010.00 106,163.31 .00 79.22 27,846.69 20.78
TOTAL PUBLIC WORKS 134,010.00 106,163.31 .00 79.22 27,846.69 20.78
TOTAL FUND REVENUE 134,010.00 106,163.31 .00 79.22 27,846.69 20.78
FOR ADMINISTRATION USE ONLY 83 % OF THE FISCAL YEAR HAS ELAPSED 04/26/2022 11:17AM PAGE: 1
22
CITY OF SUSANVILLE
INCOME STATEMENT
EXPENDITURES WITH COMPARISON TO BUDGET
FOR THE 10 MONTHS ENDING APRIL 30, 2022
AIRPORT
BUDGET YTD ACTUAL ENCUMBRANCE % EXPENDED UNEXPENDED % UNEXP.
PUBLIC WORKS
AIRPORT-OPERATIONS
7201-430-81-4101 4% VACANCY RATE ( 1,089.00) .00 .00 .00 ( 1,089.00) ( 100.00)
7201-430-81-4120 TEMPORARY EMPLOYEES 24,415.00 19,735.14 .00 80.83 4,679.86 19.17
7201-430-81-4221 SOCIAL SECURITY CONTRIBUTIONS 1,514.00 1,261.40 .00 83.32 252.60 16.68
7201-430-81-4222 MEDICARE 354.00 295.00 .00 83.33 59.00 16.67
7201-430-81-4260 WORKERS' COMPENSATION 732.00 610.40 .00 83.39 121.60 16.61
7201-430-81-4293 STATE UNEMPLOYMENT 220.00 .00 .00 .00 220.00 100.00
7201-430-81-4340 TECHNICAL SVCS 7,676.00 5,839.06 1,800.00 99.52 36.94 .48
7201-430-81-4431 REPAIR AND MAINTENANCE-MISC 1,900.00 1,891.37 .00 99.55 8.63 .45
7201-430-81-4434 REPAIR AND MAINTENANCE-FACILIT 1,223.00 667.76 .00 54.60 555.24 45.40
7201-430-81-4510 INSURANCE AIRPORT HANGARS 4,337.00 3,610.00 .00 83.24 727.00 16.76
7201-430-81-4511 INSUR.AIRPORT OWNER OPER. LIAB 4,147.00 3,460.00 .00 83.43 687.00 16.57
7201-430-81-4512 INSUR.AIRPORT AIR SHOW LIAB 442.00 370.00 .00 83.71 72.00 16.29
7201-430-81-4524 INTERNAL SVCS ADMIN 48,280.00 40,230.00 .00 83.33 8,050.00 16.67
7201-430-81-4525 INTERNAL SVC PW/ENG 10,604.00 8,840.00 .00 83.36 1,764.00 16.64
7201-430-81-4530 COMMUNICATIONS 640.00 529.37 .00 82.71 110.63 17.29
7201-430-81-4610 SUPPLIES - GENERAL 140.00 32.96 .00 23.54 107.04 76.46
7201-430-81-4622 ELECTRICITY 6,600.00 4,175.38 .00 63.26 2,424.62 36.74
7201-430-81-4623 PROPANE 3,500.00 3,025.13 .00 86.43 474.87 13.57
7201-430-81-4641 POSTAGE 81.00 .00 .00 .00 81.00 100.00
7201-430-81-4770 DEPRECIATION EXPENSE 157,898.00 131,580.00 .00 83.33 26,318.00 16.67
7201-430-81-4810 TAXES, FEES, PERMITS & CHARGES 2,349.00 2,348.90 .00 100.00 .10 .00
7201-430-81-4852 INTEREST .00 ( 62.20) .00 .00 62.20 .00
TOTAL AIRPORT-OPERATIONS 275,963.00 228,439.67 1,800.00 83.43 45,723.33 16.57
TOTAL PUBLIC WORKS 275,963.00 228,439.67 1,800.00 83.43 45,723.33 16.57
TOTAL FUND EXPENDITURES 275,963.00 228,439.67 1,800.00 83.43 45,723.33 16.57
REVENUE OVER (UNDER) EXPENDITURES ( 141,953.00) ( 122,276.36) ( 1,800.00) ( 87.41) ( 17,876.64) ( 12.59)
FOR ADMINISTRATION USE ONLY 83 % OF THE FISCAL YEAR HAS ELAPSED 04/26/2022 11:17AM PAGE: 2
23
CITY OF SUSANVILLE
INCOME STATEMENT
REVENUES WITH COMPARISON TO BUDGET
FOR THE 10 MONTHS ENDING APRIL 30, 2022
AIRPORT CIP FUND
BUDGET YTD ACTUAL ENCUMBRANCE % EARNED UNEARNED % UNEARNED
AIRPORT CIP
7202-430-81-3611 INTEREST .00 63.77 .00 .00 ( 63.77) .00
7202-430-81-3613 NET INCREASE (DECREASE) FMV .00 ( 4.08) .00 .00 4.08 .00
TOTAL DIVISION 81 .00 59.69 .00 .00 ( 59.69) .00
AIRPORT-TAXIWAY RECONSTRUCTION
7202-430-85-3301 US DEPT OF TRANS - FAA 1,289,905.00 .00 .00 .00 1,289,905.00 100.00
TOTAL AIRPORT-TAXIWAY RECONSTRUC 1,289,905.00 .00 .00 .00 1,289,905.00 100.00
TOTAL AIRPORT CIP 1,289,905.00 59.69 .00 .00 1,289,845.31 100.00
TOTAL FUND REVENUE 1,289,905.00 59.69 .00 .00 1,289,845.31 100.00
FOR ADMINISTRATION USE ONLY 83 % OF THE FISCAL YEAR HAS ELAPSED 04/26/2022 11:17AM PAGE: 3
24
CITY OF SUSANVILLE
INCOME STATEMENT
EXPENDITURES WITH COMPARISON TO BUDGET
FOR THE 10 MONTHS ENDING APRIL 30, 2022
AIRPORT CIP FUND
BUDGET YTD ACTUAL ENCUMBRANCE % EXPENDED UNEXPENDED % UNEXP.
AIRPORT CIP
AIRPORT-HANGAR 3&4 ELECTRICAL
7202-430-84-4100 REGULAR EMPLOYEES 2,000.00 1,668.17 .00 83.41 331.83 16.59
7202-430-84-4221 SOCIAL SECURITY .00 103.44 .00 .00 ( 103.44) .00
7202-430-84-4222 MEDICARE .00 24.18 .00 .00 ( 24.18) .00
7202-430-84-4230 PERS .00 254.40 .00 .00 ( 254.40) .00
7202-430-84-4260 WORKER'S COMPENSATION .00 316.95 .00 .00 ( 316.95) .00
7202-430-84-4293 STATE UNEMPLOYMENT .00 15.02 .00 .00 ( 15.02) .00
7202-430-84-4610 SUPPLIES - GENERAL 2,642.00 1,081.15 .00 40.92 1,560.85 59.08
TOTAL AIRPORT-HANGAR 3&4 ELECTRICAL 4,642.00 3,463.31 .00 74.61 1,178.69 25.39
AIRPORT-TAXIWAY RECONSTRUCTION
7202-430-85-4100 REGULAR EMPLOYEES 17,000.00 540.47 .00 3.18 16,459.53 96.82
7202-430-85-4120 GROUP LIFE INSURANCE 500.00 .00 .00 .00 500.00 100.00
7202-430-85-4221 SOCIAL SECURITY 500.00 33.35 .00 6.67 466.65 93.33
7202-430-85-4222 MEDICARE 500.00 7.79 .00 1.56 492.21 98.44
7202-430-85-4230 PERS 500.00 125.24 .00 25.05 374.76 74.95
7202-430-85-4260 WORKERS COMPENSATION 500.00 16.40 .00 3.28 483.60 96.72
7202-430-85-4292 STATE DISABILITY 500.00 6.30 .00 1.26 493.70 98.74
7202-430-85-4293 STATE UNEMPLOYMENT 500.00 4.78 .00 .96 495.22 99.04
7202-430-85-4330 PROFESSIONAL SVCS 120,285.00 .00 .00 .00 120,285.00 100.00
7202-430-85-4450 CONSTRUCTION SERVICES 1,149,120.00 .00 .00 .00 1,149,120.00 100.00
TOTAL AIRPORT-TAXIWAY RECONSTRUCTIO 1,289,905.00 734.33 .00 .06 1,289,170.67 99.94
TOTAL AIRPORT CIP 1,294,547.00 4,197.64 .00 .32 1,290,349.36 99.68
TOTAL FUND EXPENDITURES 1,294,547.00 4,197.64 .00 .32 1,290,349.36 99.68
REVENUE OVER (UNDER) EXPENDITURES ( 4,642.00) ( 4,137.95) .00 ( 89.14) ( 504.05) ( 10.86)
GRAND TOTAL REVENUE 1,423,915.00 106,223.00 .00 7.46 1,317,692.00 92.54
GRAND TOTAL EXPENDITURES ( 1,570,510.00) ( 232,637.31) ( 1,800.00) ( 14.93) ( 1,336,072.69) ( 85.07)
TOTAL NET REVENUE(EXPENDITURES) ( 146,595.00) ( 126,414.31) ( 1,800.00) ( 87.46) ( 18,380.69) ( 12.54)
FOR ADMINISTRATION USE ONLY 83 % OF THE FISCAL YEAR HAS ELAPSED 04/26/2022 11:17AM PAGE: 4
25
AGENDA ITEM NO. 7.B
Discussion Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION SPECIAL MEETING AGENDA ITEM
Submitted By: Jolene Arredondo, Administrative Services
Action Date: April 28, 2022
SUBJECT: Public Works Director Update
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: Public Works Director, Bob Godman will provide an update on the
Taxiway A Project and various operational updates to the
Commssion.
FISCAL IMPACT: None.
ACTION REQUESTED: Information Only
ATTACHMENTS:
26