Susanville Municipal Airport Commission
Regular MeetingSusanville, CA · July 14, 2022
Agenda
CITY OF SUSANVILLE
66 N. Lassen Street • Susanville CA
Robert Tyndall, Chair
Richard Hrezo, Vice Chair
Paul Clark • William Heyland • Dan Weaver
Susanville Municipal Airport Commission
Regular Susanville Municipal Airport Commission Meeting • City
Council Chambers
Thursday, July 14, 2022 – 3:00 PM
Call meeting to Order
Roll Call of Commissioners Present
1. AGENDA APPROVAL: (Additions and/or Deletions)
2. APPROVAL OF MINUTES:
2.A Consider approval of minutes from the June 9, 2022 Meeting
3. CORRESPONDENCE/INFORMATION:
4. BUSINESS FROM THE FLOOR: Any person may address the Commission at this time upon any
subject not on the agenda within the jurisdiction of the Commission. However, any matter that
requires action will be referred to staff for a report and action at a subsequent
meeting. Presentations are subject to a five-minute limit.
5. PUBLIC COMMENT: Any person may address the Board at this time to comment on any subject
on or not on the agenda. However, the Board may not take action on an item not on the agenda
other than direct staff to agendize the matter at a future meeting.
6. NEW BUSINESS:
6.A ACIP Discussion
7. CONTINUING BUSINESS:
7.A CARES Funding Update
7.B Taxiway A Project
8. AIRPORT MANAGERS REPORT:
9. COMMISION ITEM:
9.A Consider the following items for staff direction
1
10. ADJOURN
Next meeting date to be held on August 11, 2022 .
I, Marci Rojas, certify that I caused to be posted notice of the regular meeting scheduled for July
14, 2022 in the areas designated on July 11, 2022.
2
AGENDA ITEM NO. 2.A
Action Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION AGENDA ITEM
Submitted By: Jolene Arredondo, Administrative Services
Action Date: July 14, 2022
SUBJECT: Consider approval of minutes from the June 9, 2022 Meeting
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: Attached for the commission's review are the meeting minutes from
June 9, 2022.
FISCAL IMPACT: None
ACTION REQUESTED: Approve June 9, 2022 Meeting Minutes
ATTACHMENTS:
20220609_SMAC Minutes.docx
3
SUSANVILLE MUNICIPAL AIRPORT COMMISSION
Regular Susanville Municipal Airport Commission Meeting Minutes
THURSDAY, JUNE 9, 2022 – 3:00 PM
Roll Call of Councilmembers Present: Robert Tyndall, Richard Hrezo, William Heyland, Dan Weaver
Absent: Paul Clark
Commissioner Hrezo joined the meeting at 3:23pm
Call meeting to Order
Roll Call of Commissioners Present
1. AGENDA APPROVAL:
Moved by Dan Weaver; seconded by William Heyland to Approve
agenda. Motion Carried: 4 - 0
Voting For: Robert Tyndall, Richard Hrezo, William Heyland, Dan Weaver
Voting Against: None
2. APPROVAL OF MINUTES:
2.A Consider approval of Minutes from April 28, 2022 Special Meeting
Approve Minutes from April 28, 2022 Special Meeting
20220428_SMAC Minutes.docx
Moved by William Heyland; seconded by Dan Weaver to Approve motion to approve once
typo FFA to FAA is corrected..
Motion Carried: 0- 0
Voting For: None
Voting Against: None
3. CORRESPONDENCE/INFORMATION: None
4. BUSINESS FROM THE FLOOR: None
5. PUBLIC COMMENT: None
6. NEW BUSINESS:
6.A Airport Budget comparison from 2014-15 to present.
None, information only
Public Works Director Bob Godman presented the Airport Budget comparison spreadsheet.
Commissioner Weaver inquired into the deletions, Mr. Godman explained it is from grants and
Capitol Contributions. Chair Tyndall inquired why the Airport depreciates six figures yearly. Mr.
Tyndall asked what is the downside; Commissioner Heyland explained it is political. Mr. Tyndall
inquired what is the internal services line item on spreadsheet; Mr. Godman explained it is the
4
Admin cost, such as himself, Marci and Engineer cost, went into detail on how it is tracked. Mr.
Tyndall asked what is the airport receiving for the cost. Mr. Heyland inquired about the Bad Debt
Expenses; Mr. Godman explained it happens when someone hasn't paid their lease and the
$7,000.00 will be a written off; Mr. Heyland asked if that will hit the bottom line; Mr. Godman
confirmed. Commissioner Hrezo arrived to the meeting. Mr. Heyland asked if the next meeting
they can have the revenue added; Mr. Godman stated he will email it to them after this meeting.
Mr. Tyndall asked about Airport Manager Steve Datema contract and MOU; Mr. Godman stated
City Admin Dan Newton is working on this. Mr. Godman also stated for the 22/23 Budget that we
will be funding 30k into the Airports Cash Account for matching funds for the FAA Grant. Mr.
Heyland stated he was not told the truth from the last meeting; Mr. Godman stated we do have
funds there. Mr. Heyland went further into detail of why did we steal money out of one account to
go into the matching funds account. Mr. Godman explained the difference between the Cash
Fund and the CIP Fund.
6.B Update on Helipad landing lights
None, information only
Mr. Godman presented the City Council approved to move funds from the CIP fund for Helipad
Lights. Commissioner Weaver asked to the placement of the lights; Mr. Godman explained they
will be replacing the current ones; infrastructure is already there. Mr. Godman explained where
the electricity in the past was from Hangar 4, the city will no longer run it through Hangar 4 and
will run the electricity from a meter that is used for the helicopter display. Mr. Heyland asked
what type of lights were purchased; Mr. Godman stated he is unsure and will need to follow up
with Airport Manager Datema. Mr. Heyland asked when the lights will be put in; Mr. Godman
stated as soon as they come in but sometime this summer.
6.C Taxiway Project Update
None, Information only
Mr. Godman presented updated. Stated it is set to be complete next week. FAA approved the
gas increase. Mr. Tyndall asked if the striping will be completed as well. Mr. Godman stated it
will not. Mr. Godman is going to try and add the airport striping into the contract the City Streets
department will be seeking with the Striping company. Mr. Weaver asked what date
the taxiway will be complete, Mr. Godman said last communication shows Monday June
13, 2022 it should be completed.
7. CONTINUING BUSINESS: None
8. AIRPORT MANAGERS REPORT:
None provided.
9. COMMISION ITEMS:
Mr. Tyndall inquired about maintenance needed for the Airport and if there was ability to use
CARES funds; Mr. Godman responded that would need RFQ's to proceed. Mr. Tyndall then
listed several items that he would like to see repaired and improved. Bob Godman explained we
will need an estimate of items in order to go to City Council for approval of fund. Commissioners
5
will supply a list of priority items to be repaired at future meeting. Mr. Tyndall stated he can help
with getting the quotes needed.
Mr. Tyndall requested a new Master Plan; Mr. Godman stated he will look into the cost of getting
a new Master Plan with C & S Consulting. Mr. Tyndall stated the City has been in violation for
not having an Airport Planning Committee. Discussion occurred about Airport Planning
Committee. Mr. Tyndall asked about sending some commissioners to the Airport conference
held in South Lake Tahoe.
Mr. Weaver inquired into using ACIP monies for maintenance. Mr. Godman stated as long as it is
on the current plan then yes; which it is on the current plan. Mr. Weaver also inquired about the
150k cost for the fence. Mr. Godman explained the reason it has to be completed by an Engineer
is to follow the bid process for the FAA.
Mr. Heyland stated he would like to see ACIP updated on every agenda moving forward. He
also inquired about BILLS Grant money and Susanville Airport has been allotted $159k. Bob
Godman was unaware and will inquire; Mr. Tyndall would like to make the fence an agenda item
for the next meeting.
10. ADJOURN
Approved By:_____________________________________
Approved On:
Submitted By:_____________________________________
Marci Rojas, SMAC Secretary
6
AGENDA ITEM NO. 6.A
Discussion Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION AGENDA ITEM
Submitted By: Bob Godman, Public Works
Action Date: July 14, 2022
SUBJECT: ACIP Discussion
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: We will review the ACIP for direction when meeting with C&S the
consulting firm that is preparing our current ACIP.
FISCAL IMPACT: None
ACTION REQUESTED: Direction to Staff
ATTACHMENTS:
DRAFT ACIP 2023-2027 - SUSANVILLE.pdf
7
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
FY 2022 - 2026
11/30/2020
DATE:
Airport: Susanville Municipal Airport State: California NPIAS# 06-0251 LOCID SVE
Project Description & Year Federal Funds State Funds Local Total Environmental NPIAS Rating Start Date Comp. Date
2021
1 - Taxiway Rehabilitation, Phase I - Construction $ 666,000 $ 33,300 $ 40,700 $ 740,000 CATEX 2020 66 May 2021 May 2022
2 - Taxiway Rehabilitation, Phase I, Bid Alt. 1 - Construction $ 891,000 $ 44,550 $ 54,450 $ 990,000 CATEX 2020 66 May 2021 May 2022
TOTAL (FY 2021) $ 1,557,000 $ 77,850 $ 95,150 $ 1,730,000
2022
1 - Taxiway Rehabilitation, Phase II - Construction $ 234,900 $ 11,745 $ 14,355 $ 261,000 CATEX 2020 66 May 2022 May 2023
2 - Perimeter Fence - Design $ 108,000 $ 5,400 $ 6,600 $ 120,000 CATEX 2019 41 May 2021 December 2021
TOTAL (FY 2022) $ 342,900 $ 17,145 $ 20,955 $ 381,000
2023
1 - Perimeter Fence - Construction $ 382,500 $ 19,125 $ 23,375 $ 425,000 CATEX 2019 41 May 2023 December 2023
2 - Pavement Maintenance Management Plan $ 135,000 $ 6,750 $ 8,250 $ 150,000 Revalidate 2019 66 May 2023 May 2024
TOTAL (FY 2024) $ 517,500 $ 25,875 $ 31,625 $ 575,000
2024
1 - Apron Reconstruction, Phase II - Construction $ 1,012,500 $ 50,625 $ 61,875 $ 1,125,000 Revalidate 2022 60 May 2024 December 2024
TOTAL (FY 2024) $ 1,012,500 $ 50,625 $ 61,875 $ 1,125,000
2025
1 - Runway Sealcoat - Design $ 67,500 $ 3,375 $ 4,125 $ 75,000 CATEX 2023 70 May 2025 December 2025
TOTAL (FY 2025) $ 67,500 $ 3,375 $ 4,125 $ 75,000
2026
1 - Runway Sealcoat - Construction $ 225,000 $ 11,250 $ 13,750 $ 250,000 CATEX 2023 70 May 2026 September 2026
TOTAL (FY 2026) $ 225,000 $ 11,250 $ 13,750 $ 250,000
TOTALS $ 3,722,400 $ 186,120 $ 227,480 $ 4,136,000
1
8
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2021
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Taxiway Rehabilitation, Phase I - Construction $ 666,000 $ 40,700 $ 33,300 $ 740,000
Y D 2 - Taxiway Rehabilitation Phase I, Bid Alt. I - Construction $ 891,000 $ 54,450 $ 44,550 $ 990,000
TOTAL $ 1,557,000 $ 95,150 $ 77,850 $ 1,730,000
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - The existing taxiway pavement is in poor condition (7,2000 SY). A 2020 evaluation determined the pavement to have a PCI of 46. This project is
the Base Bid of Phase I of the pavement reconstruction project for the taxiway and apron; this portion will include reconstruction of taxiway alpha
pavement.
2 - The existing taxiway pavement is in poor condition (10,000 SY). A 2020 evaluation determined the pavement to have a PCI of 46. This project is
Bid Alternate 1 of Phase I of the pavement reconstruction project for the taxiway and apron; this portion will include reconstruction of the taxiway
pavement.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2021
1 - Anticipated Construction Schedule: September 2021 to December 2021
1 - Anticipated Grant Closeout: May 2022
2 - Anticipated Bid Opening: May 2021
2 - Anticipated Construction Schedule: September 2021 to December 2021
2 - Anticipated Grant Closeout: May 2022
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX revalidated in 2020
2 - CATEX revalidated in 2020
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
9
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2021
1 2
LEGEND
1 TAXIWAY REHABILITATION,(BASE BID) PHASE I -
CONSTRUCTION
2 TAXIWAY REHABILITATION (BID ALTERNATE) PHASE I -
CONSTRUCTION 10
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2022
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Taxiway Rehabilitation, Phase II - Construction $ 234,900 $ 14,355 $ 11,745 $ 261,000
Y D 2 - Perimeter Fence - Design $ 108,000 $ 6,600 $ 5,400 $ 120,000
TOTAL $ 234,900 $ 14,355 $ 11,745 $ 261,000
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - The existing taxiway pavement is in poor condition (3,300 SY). A 2020 evaluation determined the pavement to have a PCI of 24. This project is
Phase II of the pavement reconstruction project for the taxiway and apron; this portion will include reconstruction of taxiway bravo pavement.
2 - Design and Construct Perimeter Fence Installation (approximately 4,100 LF of 8' fence). There are areas on the airport with minimal fencing,
where wildlife can gain access to the airport and cause safety issues.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2022
1 - Anticipated Construction Schedule: September 2022 to December 2022
1 - Anticipated Grant Closeout: May 2023
2 - 100% Plans and Specifications to be submitted March 2021
2 - Anticipated Bid Opening: May 2021
2 - Anticipated Grant Closeout: December 2021
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX revalidated in 2020
2 - CATEX in 2019
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
11
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2022
2
1
LEGEND
1 TAXIWAY REHABILITATION,PHASE II - CONSTRUCTION
2 PERIMETER FENCE - DESIGN
12
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2023
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Perimeter Fence - Construction $ 382,500 $ 23,375 $ 19,125 $ 425,000
Y D 2 - Pavement Maintenance Management Plan $ 135,000 $ 8,250 $ 6,750 $ 150,000
TOTAL $ 517,500.00 $ 31,625.00 $ 25,875.00 $ 575,000.00
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - Design and Construct Perimeter Fence Installation (approximately 4,100 LF of 8' fence). There are areas on the airport with minimal fencing,
where wildlife can gain access to the airport and cause safety issues.
2 - Conduct an Airport Pavement Maintenance Management Plan. Accurate PCI data is needed to assess current and future pavement treatment
needs.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2023
1 - Anticipated Construction Schedule: September 2023 to December 2023
1 - Anticipated Grant Closeout: May 2024
2 - Anticipated Bid Opening: May 2023
2 - Anticipated Construction Schedule: September 2023 to December 2023
2 - Anticipated Grant Closeout: May 2024
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX in 2019
2 - Revalidate CATEX in 2019
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
13
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2023
1
2
LEGEND
1 PERIMETER FENCE - CONSTRUCTION
2 PAVEMENT MAINTENANCE MANAGEMENT PLAN
14
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2024
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Apron Reconstruction, Phase II - Construction $ 1,012,500 $ 61,875 $ 50,625 $ 1,125,000
TOTAL $ 1,012,500 $ 61,875 $ 50,625 $ 1,125,000
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - The asphalt concrete pavement on the existing apron is close to failing (18,500 SY). This project is to reconstruct the apron with a new asphalt
concrete structural section per FAA standards. This is the second construction phase of this project.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or
design, planning or environmental process)
1 - Anticipated Bid Opening: May 2024
1 - Anticipated Construction Schedule: September 2024 to December 2024
1 - Anticipated Grant Closeout: May 2025
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - Revalidate CATEX in 2022
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
15
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2024
1
LEGEND
1 APRON RECONSTRUCTION, PHASE II - CONSTRUCTION
16
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2025
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Runway Sealcoat - Design $ 67,500.00 $ 4,125.00 $ 3,375.00 $ 75,000.00
TOTAL $ 67,500.00 $ 4,125.00 $ 3,375.00 $ 75,000.00
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - Design: Apply a crack seal and seal coat, and re-apply pavement markings to Runway 11-29 (4,051' x 75') and Taxiway connectors.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - 100% Plans and Specifications to be submitted March 2025
1 - Anticipated Bid Opening: May 2025
1 - Anticipated Grant Closeout: December 2025
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX in 2023
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
17
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2025
1
LEGEND
1 RUNWAY SEALCOAT - DESIGN
18
SUSANVILLE MUNICIPAL AIRPORT ACIP DATA SHEET
Airport Name Susanville Municipal Airport Fiscal Year 2026
Shown On Project Federal
ALP Type* Project Description Share Local Share State Share Total
Y D 1 - Runway Sealcoat - Construction $ 225,000.00 $ 13,750.00 $ 11,250.00 $ 250,000.00
TOTAL $ 225,000.00 $ 13,750.00 $ 11,250.00 $ 250,000.00
* D - Development; P - Planning; E - Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS
Detail Project Description (Square/Lineal Footage or Length/Width)
1 - Design: Apply a crack seal and seal coat, and re-apply pavement markings to Runway 11-29 (4,051' x 75') and Taxiway connectors.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction
or design, planning or environmental process)
1 - Anticipated Bid Opening: May 2026
1 - Anticipated Construction Schedule: September 2026 to September 2026
1 - Anticipated Grant Closeout: May 2027
NEPA Environmental Status (Date of FONSI or CATEX Approval)
1 - CATEX in 2023
Land Title Status & Date of Exhibit "A" Status Date
Owned by the City of Susanville Fee Simple August 1999
Open AIP Funded Projects Expected Close-out Date
No open grants
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly
authorized by the Sponsor.
Dan Newton, Public Works Director
Name and Title of Authorized Representative (Print or Type) Contact Name and Title (Print or Type)
1/13/2021 (530) 257-1045
Signature Date Contact Phone (Print or Type)
19
SUSANVILLE MUNICIPAL AIRPORT
AIRPORT CAPITAL IMPROVEMENT PROGRAM
ACIP FY 2026
1
LEGEND
1 RUNWAY SEALCOAT - CONSTRUCTION
20
AGENDA ITEM NO. 7.A
Discussion Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION AGENDA ITEM
Submitted By: Bob Godman, Public Works
Action Date: July 14, 2022
SUBJECT: CARES Funding Update
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: Report on where the CARES act grant money is being allocated.
Current projects:
1) Well pump and pressure tank rehab
2) Bathroom remodel
Both of these projects are being added to the upcoming City of
Susanville budget, so will be able to move forward on them soon.
FISCAL IMPACT: none
ACTION REQUESTED: Report from staff and direction from Commission if needed.
ATTACHMENTS:
21
AGENDA ITEM NO. 7.B
Discussion Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION AGENDA ITEM
Submitted By: Bob Godman, Public Works
Action Date: July 14, 2022
SUBJECT: Taxiway A Project
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: Taxiway A Project is complete.
FISCAL IMPACT: none
ACTION REQUESTED: None Informational Item
ATTACHMENTS:
22
AGENDA ITEM NO. 9.A
Discussion Item
SUSANVILLE MUNICIPAL AIRPORT COMMISSION AGENDA ITEM
Submitted By: Bob Godman, Public Works
Action Date: July 14, 2022
SUBJECT: Consider the following items for staff direction
PRESENTED BY: Bob Godman, Public Works Director
SUMMARY: Provide direction on the following:
1) Moving meeting times from 3pm to 5pm
2) Add December and January to the Meeting Calendar
3) Initiate a new Airport Master Plan
4) Create and Prioritize an Airports Project List
FISCAL IMPACT:
ACTION REQUESTED: Direct Staff
ATTACHMENTS:
23