EOC
Regular MeetingSwansboro, NC · November 9, 2022
Minutes
Town of Swansboro
Emergency Operations Center Committee
November 9, 2022, Regular Meeting
In attendance: Paula Webb, David Degnan, Dwayne Taylor, Brenda Pugliese, Andrea Correll,
Commissioner Larry Philpott, Commissioner Jeff Conaway, Roy Herrick, Ed McHale, and
Junior Freeman. Jonathan McDaniel Laurent Meilleur, and Dusty Rhodes were absent.
**********************************
Call to Order
The meeting was called to order at 3:00 pm.
Minute Adoption
On a motion by Mr. Herrick seconded by Mr. Taylor the minutes for July 27, 2022, Regular
Meeting and July 27, 2022, Closed Session were adopted unanimously.
Public Safety Building/Emergency Operations Center Consultant
Commissioner Philpott reviewed that the Committee recommended Becker Morgan as its top
selection for the PSB/EOC Consultant at its October 26, 2022, meeting. In addition, the
committee asked staff to inquire further into consultant costs.
In conversation with all three firms, all three firms are fully aware of the $6 million dollar
budget. Although trends indicate that construction costs may be coming down, the current
construction costs is $425 – 450/sq ft. All have experience in conducting feasibility studies
and/or developing master plans.
Becker Morgan’s feasibility cost are typically $15-25K, dependent on a few things
• whether we already have a property survey and which budget pays for it,
• whether we have any tricky or complex site matters – DOT, Duke, regional stormwater,
zoning irregularities, etc. The more players we need to engage the higher the fee.
• the number of options needing study.
Becker Morgan further indicated they could complete a feasibility study in 30-45 days and
project design costs were then ranging from 7-9% of the estimated construction costs.
Davis Kane’s feasibility costs were typically $12,000 - 15,000, generally based on the estimated
effort they anticipate a project taking to complete, and not so much a percentage of construction
cost. They estimate the feasibility study taking up to 6 weeks. Project design costs ranged
from 8-10% of the estimated construction costs.
Oakley Collier shared that they typically wrap the feasibility costs into the 10% estimated
construction cost and estimate a 12-week turn around for the study.
On a motion by Commissioner Conaway, seconded by Mr. Degnan, Becker Morgan was
reaffirmed as the consultant for the PSB/EOC Project completing one of the committee’s tasks
Page 1 of 2
to provide a consultant recommendation as provided for in the Emergency Management
Committee Action Plan.
Board Comments
Several board members agreed that this project would exceed the budgeted $6 million and that
grants should be considered for additional funds.
The next regular meeting for November 23, 2022 was cancelled, as there would be no further
business to address until Becker Morgan was approved by the Board of Commissioners as
consultant.
Adjournment
The meeting adjourned at 3:22 pm.